CN220267176U - Suspension operation platform - Google Patents

Suspension operation platform Download PDF

Info

Publication number
CN220267176U
CN220267176U CN202321755985.XU CN202321755985U CN220267176U CN 220267176 U CN220267176 U CN 220267176U CN 202321755985 U CN202321755985 U CN 202321755985U CN 220267176 U CN220267176 U CN 220267176U
Authority
CN
China
Prior art keywords
platform
connecting plate
vertical
horizontal
hook
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321755985.XU
Other languages
Chinese (zh)
Inventor
唐旭
于雷
李帅
陈杰
李崇尔
郭栋才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Urban Construction No7 Engineering Co Ltd
Original Assignee
Beijing Urban Construction No7 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Urban Construction No7 Engineering Co Ltd filed Critical Beijing Urban Construction No7 Engineering Co Ltd
Priority to CN202321755985.XU priority Critical patent/CN220267176U/en
Application granted granted Critical
Publication of CN220267176U publication Critical patent/CN220267176U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ladders (AREA)

Abstract

The application discloses a suspension operation platform, which relates to the technical field of construction equipment and comprises a suspension structure and an operation platform, wherein the suspension structure is used for being clamped on a wall body, and the operation platform is detachably connected with the suspension structure; the operation platform comprises a vertical platform and a horizontal platform which are mutually vertical, and the vertical platform is hinged with the horizontal platform; and the end that vertical platform was kept away from to horizontal platform can dismantle and be provided with the diagonal draw bar, and the one end that horizontal platform was kept away from to the diagonal draw bar can dismantle with suspended structure and be connected, this application has the inconvenient effect of maintenance construction of high-rise resident air conditioner outer machine.

Description

Suspension operation platform
Technical Field
The application relates to the technical field of construction equipment, in particular to a suspension operation platform.
Background
When the high-rise householder changes the air conditioner external unit or maintains the air conditioner external unit, an operator usually does not have a standing position, so that maintenance and construction are inconvenient. Usually, mechanical equipment such as a hanging basket and the like for aerial operation is used for auxiliary construction, but related equipment is large in size and difficult to carry, so that maintenance cost of an air conditioner external unit becomes high. In addition, the process of installing the hanging basket is complicated, and the working efficiency of air conditioner maintenance is reduced.
Disclosure of Invention
In order to solve the problem that maintenance and construction of an air conditioner outdoor unit of a high-rise resident are inconvenient, the application provides a hanging operation platform.
The application provides a suspension operation platform, adopts following technical scheme:
the hanging operation platform comprises a hanging structure and an operation platform, wherein the hanging structure is used for being clamped on a wall body, and the operation platform is detachably connected with the hanging structure;
the operation platform comprises a vertical platform and a horizontal platform which are mutually perpendicular, and the vertical platform is hinged with the horizontal platform; and the end of the horizontal platform far away from the vertical platform can be detachably provided with an inclined pull rod, and one end of the inclined pull rod far away from the horizontal platform is detachably connected with the hanging structure.
Through adopting above-mentioned technical scheme, when maintaining the outer machine of air conditioner on high-rise, with this application operation platform through the suspension structure joint on building wall, vertical platform and horizontal platform set up outside the wall body this moment, and suspension structure and wall body drawknot, diagonal draw bar are with vertical platform and horizontal platform tie each other, and vertical platform is connected with suspension structure simultaneously, can realize the fixed of horizontal platform position, and the constructor who ties and has the safety rope can stand on horizontal platform and maintain the operation to the air conditioner.
After construction of constructors is completed, the connection between the diagonal draw bars and the hanging structure is released, the horizontal platform and the vertical platform can be folded by pulling the diagonal draw bars, and in addition, the hanging structure, the vertical platform and the diagonal draw bars can be detachably connected, so that the operation platform is convenient to carry and store; the operation platform has a simple structure, is convenient to assemble and is also convenient to tie with the building wall.
Optionally, the hanging structure includes two sets of draw-in groove structures that are parallel to each other the interval sets up, the draw-in groove structure is including symmetrical first pothook and the second pothook that sets up and can slide relatively, is provided with the mounting that is used for locking both relative positions between first pothook and the second pothook.
Through adopting above-mentioned technical scheme, to the wall body of different thickness, can make the wall body phase-match of suspended structure and different thickness through the relative position of adjustment first pothook and second pothook, adjust the back of accomplishing, through the relative position of mounting locking first pothook and second for this application operation platform can be applicable to the wall body of different thickness, and the suitability is stronger.
Optionally, the first pothook and the second pothook all include mobile jib and coupler body, be equipped with a plurality of first fixed orificess along length direction interval on the mobile jib of first pothook, the second fixed orificess has been seted up on the mobile jib of second pothook, the mounting passes first fixed orificess and second fixed orificess simultaneously.
Through adopting above-mentioned technical scheme, slide the relative position of first pothook and second pothook to realize the preliminary regulation of draw-in groove structure length, adjust to approximately match with wall thickness when the draw-in groove structure, and after first fixed orifices and second fixed orifices align, utilize the mounting to realize the connection and the position locking of first pothook and second pothook.
Optionally, the coupler body is fixed on the lateral wall of mobile jib, and two coupler bodies are used for respectively with the inside and outside wall of wall body offsets, can set up the regulating part between coupler body and the wall body.
Through adopting above-mentioned technical scheme, after carrying out preliminary regulation of first pothook and second pothook position, if the coupler body of second pothook supports when tight with the outer wall of building wall, the coupler body of first pothook does not support with the inner wall of building wall, and when there is the space, can insert the regulating part in the space for hang stable joint of structure on building wall.
Optionally, the hook body includes vertical portion and horizontal part, vertical portion perpendicular to mobile jib length direction sets up, horizontal portion with vertical portion is perpendicular and with vertical portion keep away from the one end of mobile jib fixed, the regulating part grafting is between mobile jib and horizontal portion.
Through adopting above-mentioned technical scheme, set up vertical portion for the pothook can with wall body inner wall looks butt, thereby realize fixing this application operation platform's function on the wall body, set up the horizontal portion and make the mounting can peg graft between mobile jib and horizontal portion, reduce the possibility that the plug connector breaks away from the coupler body.
Optionally, a plurality of buckles are arranged at the hinged end of the horizontal platform, and the buckles penetrate through the horizontal platform and the vertical platform at the same time.
Through adopting above-mentioned technical scheme for horizontal platform and vertical platform can realize articulated, and connect through the latch closure, strengthen the intensity of latch closure can strengthen horizontal platform and vertical platform's joint strength promptly.
Optionally, the one end that vertical platform was kept away from to the horizontal platform is fixed with first connecting plate, the one end that vertical platform kept away from the horizontal platform is fixed with the second connecting plate, diagonal draw bar both ends are fixed with respectively be used for with the third connecting plate that first connecting plate and second connecting plate are connected.
Through adopting above-mentioned technical scheme, set up first connecting plate, second connecting plate and third connecting plate to realize articulated and can dismantle the connection between diagonal draw bar and horizontal platform, the vertical platform, be convenient for dismantle horizontal platform, vertical platform and diagonal draw bar and accomodate.
Optionally, a fourth connecting plate is welded on the end surface of the clamping groove structure, which is close to the vertical platform, and the fourth connecting plate is connected with the second connecting plate and the third connecting plate at the same time.
Through adopting above-mentioned technical scheme, set up the fourth connecting plate on suspended structure for can fix each other between vertical platform, suspended structure and the diagonal draw bar, realize the drawknot, thereby make the application operation platform use that can be safe.
Optionally, the first connecting plate, the second connecting plate, the third connecting plate and the fourth connecting plate all comprise main steel plates, through holes are formed in the main steel plates in a penetrating mode, and connecting pieces are arranged in the through holes.
By adopting the technical scheme, when the vertical platform, the hanging structure and the diagonal draw bar are connected, the connecting pieces penetrate through the perforations of the second connecting plate, the third connecting plate and the fourth connecting plate at the same time, so that the three can be hinged; when connecting diagonal draw bar and horizontal platform, only need pass the connecting piece in the perforation of first connecting plate and third connecting plate, can realize the articulated of horizontal platform and diagonal draw bar, easy operation is convenient, and connects firmly.
Optionally, the horizontal platform includes many parallel interval setting's square steel, and the both ends of square steel are fixed with the connecting rod that is used for connecting many square steels, and are provided with the flitch on many square steels.
Through adopting above-mentioned technical scheme, the bearing capacity of horizontal platform can be strengthened to the square steel for constructor is safer when working on this application operation platform, sets up the flitch, and the constructor of being convenient for stands and operates.
In summary, the present application includes at least one of the following beneficial effects:
1. the horizontal platform, the vertical platform, the suspension structure and the diagonal draw bars are hinged with each other, the suspension structure is detachably connected with the vertical platform, and the diagonal draw bars are simultaneously detachably connected with the horizontal platform and the suspension structure, so that the operation platform is convenient to install, detach and store, and the operation platform is convenient to transport;
2. the operation platform is firmly tied with the building wall through the hanging structure, so that the safety is high, and the installation is simple and quick;
3. set up the draw-in groove structure for this application operation platform can adapt to the wall body of different thickness, thereby improves this application operation platform's suitability.
Drawings
Fig. 1 is a schematic diagram of an overall structure of an operation platform according to an embodiment of the present application mounted on a wall.
Reference numerals illustrate: 1. a hanging structure; 11. a first hook; 111. a main rod; 1111. a first fixing hole; 112. a hook body; 1121. a vertical portion; 1122. a horizontal portion; 12. a second hook; 121. a second fixing hole; 13. a fixing member; 14. an adjusting member; 15. a fourth connecting plate; 2. a vertical platform; 21. a second connecting plate; 22. a transverse square steel pipe; 23. a vertical square steel pipe; 3. a horizontal platform; 31. square steel; 32. a connecting rod; 33. a tread plate; 34. a first connection plate; 4. a diagonal draw bar; 41. a third connection plate 411, a main steel plate; 412. perforating; 5. and (5) a ring buckle.
Detailed Description
The present application is described in further detail below in conjunction with fig. 1.
The embodiment of the application discloses a hang operation platform, refer to fig. 1, a hang operation platform includes suspended structure 1 and operation platform, operation platform includes vertical platform 2, horizontal platform 3 and diagonal draw bar 4, vertical platform 2 and horizontal platform 3 are articulated each other, diagonal draw bar 4 both ends can dismantle with vertical platform 2, horizontal platform 3 respectively and be connected, suspended structure 1 can dismantle with vertical platform 2 and be connected, and suspended structure 1 is used for drawknot with building wall. When the operation platform is used, the vertical platform 2 and the horizontal platform 3 are positioned outside the building wall body, planes where the vertical platform 2 and the horizontal platform 3 are positioned are mutually perpendicular, and the whole operation platform can be fixed with the building wall body through the drawknot of the hanging structure 1, so that constructors can stand on the horizontal platform 3 to maintain.
Referring to fig. 1, a hanging structure 1 includes two sets of clamping groove structures clamped on a building wall, and the two clamping groove structures are detachably connected with two ends of a vertical platform 2 respectively. Each clamping groove structure comprises a first clamping hook 11 and a second clamping hook 12, and when the clamping groove structure is clamped on a building wall, the side walls of the first clamping hook 11 and the second clamping hook 12 are mutually attached and fixed in position. Specifically, the first hook 11 and the second hook 12 each include a main rod 111 and a hook body 112, the hook body 112 is fixed on a side wall at one end of the main rod 111, a plurality of first fixing holes 1111 are spaced apart from each other along a length direction of the main rod 111 of the first hook 11, and a second fixing hole 121 is formed in the main rod 111 of the second hook 12. When the first hook 11 and the second hook 12 are attached, the first fixing hole 1111 and the second fixing hole 121 are aligned, and a fixing piece 13 for locking the relative positions of the first hook 11 and the second hook 12 is inserted into the first fixing hole 1111 and the second fixing hole 121, and the fixing piece 13 is specifically a bolt and a nut screwed on the bolt; in addition, the first hook 11 and the second hook 12 are symmetrically arranged along the center line of the wall thickness, and the hook bodies 112 of the first hook 11 and the second hook 12 are respectively used for being abutted against the inner side wall and the outer side wall of the building wall.
Referring to fig. 1, the hook 112 includes a vertical portion 1121 and a horizontal portion 1122, the vertical portion 1121 is fixed on a side wall of the main lever 111, the vertical portion 1121 is perpendicular to a length direction of the main lever 111, the horizontal portion 1122 is perpendicular to the vertical portion 1121 and fixed to an end of the vertical portion 1121 away from the main lever 111, and the adjusting member 14 can be inserted between the horizontal portion 1122 and the main lever 111.
Referring to fig. 1, the thickness of the wall of each household is different due to different decoration modes, and when the clamping groove structure is installed on the wall, the installation mode is specifically as follows: firstly, the hook body 112 of the second hook 12 is abutted against the outer wall of the building wall, then the first hook 11 and the second hook 12 are attached and placed, and the first hook 11 is relatively slipped, so that one of the first fixing holes 1111 is aligned with the second fixing hole 121, and the fixing piece 13 is arranged in the first fixing hole 1111 and the second fixing hole 121, so that the fixing of the positions of the first hook 11 and the second hook 12 is realized. At this time, the hook body 112 of the first hook 11 does not necessarily abut against the inner wall of the building wall, and the adjusting member 14 is installed between the horizontal portion 1122 of the first hook 11 and the main rod 111 to abut against the inside of the building wall, and the adjusting member 14 may be a steel block or other hard object matched according to the gap between the first hook 11 and the inner wall of the building.
Referring to fig. 1, the vertical platform 2 includes a plurality of horizontal square steel pipes 22 arranged at intervals, vertical square steel pipes 23 are arranged at two ends of the horizontal square steel pipes 22, and two end heads of the plurality of horizontal square steel pipes 22 are welded and fixed with side walls of the vertical square steel pipes 23; the horizontal platform 3 also comprises a plurality of square steels 31 which are arranged at intervals in parallel, connecting rods 32 are arranged at two ends of the square steels 31, two end heads of the square steels 31 are welded and fixed with the side walls of the connecting rods 32, the horizontal platform 3 also comprises a tread plate 33 fixed on the square steels 31, and the tread plate 33 can be a tread plate 33 silk screen with the thickness of 3.5 mm.
Referring to fig. 1, a vertical platform 2 is hinged to a horizontal platform 3, and a plurality of buckles 5 are arranged between the horizontal platform 3 and the vertical platform 2, wherein the buckles 5 penetrate through the horizontal platform 3 and the vertical platform 2 at the same time, so that the horizontal platform 3 and the vertical platform 2 are kept connected and can rotate with each other.
Referring to fig. 1, two first connection plates 34 are fixed on a square steel 31 at one end of a horizontal platform 3 far from a vertical platform 2, and the two first connection plates 34 are arranged at positions close to two ends of the square steel 31; the side walls of the two vertical square steel pipes 23 far away from the horizontal platform 3 are respectively fixed with a second connecting plate 21; two diagonal draw bars 4 are arranged, and the two ends of each diagonal draw bar 4 are fixedly provided with a third connecting plate 41. The first connecting plate 34, the second connecting plate 21 and the third connecting plate 41 all comprise a main steel plate 411, through holes 412 are formed in the main steel plate 411, when the diagonal draw bar 4 and the horizontal platform 3 are connected, the through holes 412 in the first connecting plate 34 and the third connecting plate 41 are aligned, connecting pieces, particularly high-strength bolts and nuts matched with the high-strength bolts, are inserted into the through holes 412, and the connecting pieces are not shown in the figure; when connecting the diagonal draw bar 4 and the vertical platform 2, the through holes 412 in the third connecting plate 41 and the second connecting plate 21 are aligned, and the connectors are installed in the through holes 412. The stable connection of the diagonal draw bar 4 with the vertical platform 2 and the horizontal platform 3 is realized through the connecting piece, and the aperture of the through hole 412 can be larger than the diameter of the connecting piece, so that the two ends of the diagonal draw bar 4 are kept in rotary connection.
Referring to fig. 1, a fourth connection plate 15 is structurally fixed to the clamping groove, the fourth connection plate 15 also includes a main steel plate 411 and a through hole 412 formed in the main steel plate 411, and after the diagonal draw bar 4 and the horizontal platform 3 are fixed, the through holes 412 formed in the second connection plate 21, the third connection plate 41 and the fourth connection plate 15 are aligned, and a connection member is installed therein to achieve stable connection among the suspension structure 1, the vertical platform 2 and the diagonal draw bar 4. At this time, the hanging structure 1 is clamped on the building wall, the vertical platform 2 is attached to the outer wall of the building wall, and constructors can stand on the horizontal platform 3 to perform maintenance operation.
The implementation principle of the suspension operation platform in the embodiment of the application is as follows: when this application operation platform daily accomodates, can unpack apart vertical platform 2, diagonal draw bar 4 and suspended structure 1 and place, and vertical platform 2 and horizontal platform 3 can fold for occupation space is little when this application operation platform accomodates, and the transport of being convenient for.
When the platform is operated, firstly, the horizontal platform 3 and the diagonal draw bar 4 are connected and fixed in a room through a connecting piece; then the vertical platform 2, the diagonal draw bar 4 and the hanging structure 1 are connected and fixed through a connecting piece; then, according to the approximate thickness of the building wall, the positions of the first clamping hook 11 and the second clamping hook 12 are preliminarily adjusted, and the positions of the first clamping hook 11 and the second clamping hook 12 are fixed through the fixing piece 13; the assembled operation platform is carried out of the building wall, the hanging structure 1 is clamped on the building wall, when the hanging structure 1 is clamped, the hook 112 of the second clamping hook 12 is abutted against the outer wall of the building wall, at the moment, if the hook 112 of the first clamping hook 11 is not abutted against the inner wall of the building wall, the adjusting piece 14 can be inserted between the first clamping hook 11 and the building wall, the first clamping hook 11 and the building wall can be abutted tightly, so that the installation strength of the hanging structure 1 is improved, and an operator can stand on the horizontal platform 3 to perform construction operation. The adjusting member 14 is shown, and the adjusting member 14 is disposed between the second hook 12 and the outer wall of the building wall.
The foregoing are all preferred embodiments of the present application, and are not intended to limit the scope of the present application in any way, therefore: all equivalent changes in structure, shape and principle of this application should be covered in the protection scope of this application.

Claims (10)

1. The hanging operation platform is characterized by comprising a hanging structure (1) which is used for being clamped on a wall body and an operation platform which is detachably connected with the hanging structure (1);
the operation platform comprises a vertical platform (2) and a horizontal platform (3) which are mutually vertical, and the vertical platform (2) is hinged with the horizontal platform (3); and the end of the horizontal platform (3) far away from the vertical platform (2) can be detachably provided with a diagonal draw bar (4), and one end of the diagonal draw bar (4) far away from the horizontal platform (3) is detachably connected with the hanging structure (1).
2. A suspended operational platform according to claim 1, wherein: the hanging structure (1) comprises two groups of clamping groove structures which are arranged in parallel at intervals, the clamping groove structures comprise a first clamping hook (11) and a second clamping hook (12) which are symmetrically arranged and can slide relatively, and a fixing piece (13) used for locking the relative positions of the first clamping hook (11) and the second clamping hook (12) is arranged between the first clamping hook and the second clamping hook.
3. A suspended operational platform according to claim 2, characterized in that: the first clamping hooks (11) and the second clamping hooks (12) comprise a main rod (111) and a hook body (112), a plurality of first fixing holes (1111) are formed in the main rod (111) of the first clamping hooks (11) at intervals along the length direction, second fixing holes (121) are formed in the main rod (111) of the second clamping hooks (12), and the fixing piece (13) simultaneously penetrates through the first fixing holes (1111) and the second fixing holes (121).
4. A suspended operational platform according to claim 3, characterized in that: the hook bodies (112) are fixed on the side wall of the main rod (111), the two hook bodies (112) are respectively used for being abutted to the inner wall and the outer wall of the wall body, and the adjusting piece (14) can be arranged between the hook bodies (112) and the wall body.
5. A suspension operating platform as claimed in claim 4, wherein: the hook body (112) comprises a vertical portion (1121) and a horizontal portion (1122), the vertical portion (1121) is perpendicular to the length direction of the main rod (111), the horizontal portion (1122) is perpendicular to the vertical portion (1121) and fixed to one end, far away from the main rod (111), of the vertical portion (1121), and the adjusting piece (14) is inserted between the main rod (111) and the horizontal portion (1122).
6. A suspended operational platform as set forth in claim 5, wherein: the hinge end of the horizontal platform (3) is provided with a plurality of buckles (5), and the buckles (5) penetrate through the horizontal platform (3) and the vertical platform (2) simultaneously.
7. A suspended operational platform as set forth in claim 6, wherein: the one end that vertical platform (2) was kept away from to horizontal platform (3) is fixed with first connecting plate (34), the one end that horizontal platform (3) was kept away from to vertical platform (2) is fixed with second connecting plate (21), diagonal draw bar (4) both ends are fixed with respectively be used for with third connecting plate (41) that first connecting plate (34) and second connecting plate (21) are connected.
8. A suspended operational platform according to claim 7, wherein: the clamping groove structure is close to the end face of the vertical platform (2), a fourth connecting plate (15) is welded on the end face of the clamping groove structure, and the fourth connecting plate (15) is connected with the second connecting plate (21) and the third connecting plate (41) at the same time.
9. A suspended operational platform according to claim 8, wherein: the first connecting plate (34), the second connecting plate (21), the third connecting plate (41) and the fourth connecting plate (15) all comprise a main steel plate (411), a through hole (412) is formed in the main steel plate (411) in a penetrating mode, and a connecting piece is arranged in the through hole (412).
10. A suspended operational platform according to claim 7, wherein: the horizontal platform (3) comprises a plurality of square steels (31) which are arranged at intervals in parallel, connecting rods (32) used for connecting the square steels (31) are fixed at two ends of the square steels (31), and stepping plates (33) are arranged on the square steels (31).
CN202321755985.XU 2023-07-05 2023-07-05 Suspension operation platform Active CN220267176U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321755985.XU CN220267176U (en) 2023-07-05 2023-07-05 Suspension operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321755985.XU CN220267176U (en) 2023-07-05 2023-07-05 Suspension operation platform

Publications (1)

Publication Number Publication Date
CN220267176U true CN220267176U (en) 2023-12-29

Family

ID=89319604

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321755985.XU Active CN220267176U (en) 2023-07-05 2023-07-05 Suspension operation platform

Country Status (1)

Country Link
CN (1) CN220267176U (en)

Similar Documents

Publication Publication Date Title
US9157245B2 (en) Scaffold mount bracket
CN112431399A (en) Hanging basket for building outer wall and mounting method thereof
CN211736298U (en) Double-rod diagonal cantilever scaffold
CN220267176U (en) Suspension operation platform
CN108390291B (en) Special gallows of outdoor voltage transformer overhauls
CN208644462U (en) Pipeline welds lift hanger
CN110778009A (en) Suspended ceiling structure
CN210105234U (en) Trolley for ceiling construction
CN210619988U (en) Hoisting device of building module unit
CN114221260A (en) Insulator maintenance frame of electric power pylon
CN207513184U (en) A kind of casket shell type bracket device having enough to meet the need
CN218815121U (en) Safety hanging basket for decoration of curtain wall in constructional engineering
CN220705245U (en) A safety protection canopy for curtain installation
CN112324130B (en) Wall connecting piece device
CN210918143U (en) Assembled engineering scaffold
CN109774885B (en) A fast loading and unloading scaffold device for FSRU
CN218294742U (en) Pipeline hoisting support frame for fire-fighting equipment engineering
CN105944256A (en) Safety belt hanger
CN217353462U (en) Double-seat operating platform for high-altitude truss
CN211850689U (en) Scaffold with bracing
CN219678005U (en) Electric power bridge
CN217974077U (en) A assembled mounting platform for bridge rigidity jib
CN205163994U (en) Fire hose spreads and send car
CN209397900U (en) A kind of lifting device for scaffold for building
CN217076789U (en) Hanging operation platform under tower crane attached installation