CN220117405U - Steel-concrete composite beam connection structure - Google Patents

Steel-concrete composite beam connection structure Download PDF

Info

Publication number
CN220117405U
CN220117405U CN202320592353.XU CN202320592353U CN220117405U CN 220117405 U CN220117405 U CN 220117405U CN 202320592353 U CN202320592353 U CN 202320592353U CN 220117405 U CN220117405 U CN 220117405U
Authority
CN
China
Prior art keywords
beams
vertical
threaded connection
composite
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320592353.XU
Other languages
Chinese (zh)
Inventor
宁红辉
邓海
谭庆俭
付朝晖
齐利华
杨炯
李登海
熊祖平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Institute Of Urban Planning & Design
Cccc Shanghai Airlines South China Municipal Engineering Co ltd
Original Assignee
Zhuhai Institute Of Urban Planning & Design
Cccc Shanghai Airlines South China Municipal Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Institute Of Urban Planning & Design, Cccc Shanghai Airlines South China Municipal Engineering Co ltd filed Critical Zhuhai Institute Of Urban Planning & Design
Priority to CN202320592353.XU priority Critical patent/CN220117405U/en
Application granted granted Critical
Publication of CN220117405U publication Critical patent/CN220117405U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a steel-concrete composite beam connecting structure which comprises a plurality of vertical limit composite beams arranged at the periphery of the bottom of a pipe well, wherein the vertical limit composite beams and the bottom of the pipe well are in a pre-buried fixed state, a plurality of threaded connection composite sections are arranged at one side of each vertical limit composite beam from top to bottom, the vertical limit composite beams are used for supporting, the steel structure retaining wall is temporarily fixed through the threaded connection composite sections, the stability of connection is enhanced, meanwhile, the connection is convenient, the threaded connection composite sections comprise connection support vertical beams, and two symmetrically arranged I-beams are fixedly connected at one side of each connection support vertical beam close to each vertical limit composite beam. According to the utility model, the detachable threaded connection combination joint is arranged, and the stress generated by the well descending is uniformly distributed through the threaded connection combination joint arranged in a combined mode, so that the threaded connection combination joint has stronger and more stable bearing capacity, is convenient to detach, can be repeatedly used, saves materials, and reduces cost.

Description

Steel-concrete composite beam connection structure
Technical Field
The utility model relates to the technical field of water supply and drainage, in particular to a steel-concrete composite beam connecting structure.
Background
The municipal water supply and drainage engineering top pipe well has circular, elliptic, rectangular, diamond and other structures. The main structural materials are reinforced concrete. The conventional working well with the diameter smaller than phi 1.5m can be directly used as a later-stage inspection well, but the working well with the diameter larger than phi 1.5m can be used as a later-stage inspection well by arranging a well-in-well (arranging a steel structure guard wall in a large well).
In coastal areas, the reinforced concrete materials of the water supply and drainage engineering operation well are extremely lack, the cost is high, the use function of the operation well as a temporary structure at the later stage is of no use value, the operation well cannot be reused after being disassembled, the cost of the disassembly is increased, and the material waste is avoided due to the disassembly.
Disclosure of Invention
The utility model aims to solve the technical problems that in coastal areas, the reinforced concrete material of the water supply and drainage engineering operation well is extremely lack, the cost and the manufacturing cost are high, the operation function of the operation well as a temporary structure in the later period is of no use value, and the steel beam structure at the well wall position cannot be disassembled and is wasted.
In order to solve the technical problems, the utility model adopts a technical scheme that: the utility model provides a steel and concrete composite beam connection structure, including setting up a plurality of vertical spacing composite beams in tube well bottom position all around, vertical spacing composite beam is pre-buried fixed state with tube well bottom, a plurality of vertical spacing composite beam one side position top-down is provided with a plurality of threaded connection combination festival.
Through above-mentioned technical scheme, support through vertical spacing combination roof beam, rethread threaded connection combination festival carries out temporary fixation to steel construction dado, strengthens the stability of connection, convenient dismantlement simultaneously.
The utility model further provides that the threaded connection combination sections comprise connection support vertical beams, two symmetrically arranged I-beams are fixedly connected to one side of each connection support vertical beam close to each vertical limit combination beam, and a vertical support beam is fixedly connected between the two I-beams.
Through above-mentioned technical scheme, support the vertical beam and can support the connection, have the effect of transfer, I-beam and vertical supporting beam have good supporting role, play the effect of strengthening stability.
The utility model is further characterized in that the triangular connecting seats are fixedly connected to the two ends of the connecting support vertical beam, and the triangular connecting seats at the bottommost position and the triangular connecting seats of the two adjacent connecting support vertical beams are provided with fixed connecting bolts in a penetrating way.
Through the technical scheme, the adjacent triangular connecting seats can be fixed by the fixed connecting bolts, so that the adjacent threaded connection combined sections are fixed.
The utility model is further characterized in that two clamping nuts which are symmetrically arranged are connected at two sides of the fixed connecting bolt positioned at the two adjacent triangular connecting seats through threads, and the two adjacent triangular connecting seats are fixedly connected with the fixed connecting bolt through the clamping nuts.
The triangular connecting seat at the lowest position is fixedly connected with the bottom of the pipe well through the corresponding clamping nuts and the corresponding fixed connecting bolts.
The beneficial effects of the utility model are as follows:
according to the utility model, the detachable threaded connection combination joint is arranged, and the stress generated by the well descending is uniformly distributed through the threaded connection combination joint arranged in a combined mode, so that the threaded connection combination joint has stronger and more stable bearing capacity, is convenient to detach, can be repeatedly used, saves materials, and reduces cost.
Drawings
FIG. 1 is a schematic view of a part of a steel-concrete composite girder connecting structure according to the present utility model;
fig. 2 is an enlarged view at a in fig. 1.
In the figure: 1. the bottom of the pipe well; 2. a vertical limit combined beam; 3. the combined section is connected through threads; 30. a vertical support beam; 31. fixing a connecting bolt; 32. clamping a nut; 33. a triangular connecting seat; 34. an I-beam; 35. and supporting the vertical beam.
Detailed Description
The preferred embodiments of the present utility model will be described in detail below with reference to the accompanying drawings so that the advantages and features of the present utility model can be more easily understood by those skilled in the art, thereby making clear and defining the scope of the present utility model.
Referring to fig. 1 and 2, a steel-concrete composite beam connecting structure comprises a plurality of vertical limiting composite beams 2 arranged at the periphery of a bottom 1 of a pipe well, wherein the vertical limiting composite beams 2 and the bottom 1 of the pipe well are in a pre-buried fixed state, and a plurality of threaded connection composite sections 3 are arranged at one side of each vertical limiting composite beam 2 from top to bottom.
The plurality of threaded connection combination sections 3 comprise connection support vertical beams 35, triangular connection seats 33 are fixedly connected to the two ends of the connection support vertical beams 35, and the triangular connection seats 33 located at the lowest position are fixedly connected with the bottom of the bottom 1 of the pipe well through corresponding clamping nuts 32 and fixed connection bolts 31.
Two symmetrically arranged clamping nuts 32 are penetrated and screwed at two sides of the fixed connecting bolt 31 positioned at the two adjacent triangular connecting seats 33, and the two adjacent triangular connecting seats 33 are fixedly connected with the fixed connecting bolt 31 through the clamping nuts 32.
The triangular connecting seat 33 positioned at the bottommost position and the triangular connecting seats 33 of two adjacent connecting support vertical beams 35 are provided with fixed connecting bolts 31 in a penetrating way, two symmetrically arranged I-beams 34 are fixedly connected to one side of the connecting support vertical beams 35 close to the vertical limiting combination beam 2, and a vertical supporting beam 30 is fixedly connected between the two I-beams 34.
When the vertical limiting combined beam 2 is used, the vertical limiting combined beam 2 is pre-buried at the bottom position of the bottom 1 of the pipe well, the threaded connection combined section 3 at the bottom position is fixed at the bottom of the bottom 1 of the pipe well through the triangular connecting seat 33, the fixed connecting bolt 31 and the clamping nut 32, then the adjacent threaded connection combined sections 3 are in threaded connection through the triangular connecting seat 33, the fixed connecting bolt 31 and the clamping nut 32, and then the steel structure retaining wall is fixed at the outer side position of the supporting vertical beam 35.
The foregoing description is only illustrative of the present utility model and is not intended to limit the scope of the utility model, and all equivalent structures or equivalent processes or direct or indirect application in other related technical fields are included in the scope of the present utility model.

Claims (1)

1. The utility model provides a steel and concrete composite beam connection structure, includes a plurality of vertical spacing composite beams (2) of setting in tube well bottom (1) position all around, its characterized in that: the vertical limiting combined beams (2) and the bottom (1) of the pipe well are in a pre-buried fixed state, and a plurality of threaded connection combined joints (3) are arranged at one side of each vertical limiting combined beam (2) from top to bottom;
the plurality of threaded connection combination sections (3) comprise connection support vertical beams (35), two symmetrically arranged I-beams (34) are fixedly connected to one side of the connection support vertical beams (35) close to the vertical limit combination beams (2), and a vertical support beam (30) is fixedly connected between the two I-beams (34);
the two ends of the connecting support vertical beam (35) are fixedly connected with triangular connecting seats (33), and the triangular connecting seats (33) at the bottommost position and the triangular connecting seats (33) of two adjacent connecting support vertical beams (35) are provided with fixed connecting bolts (31) in a penetrating way;
two symmetrically arranged clamping nuts (32) are connected at two sides of a fixed connecting bolt (31) positioned at two adjacent triangular connecting seats (33) in a penetrating threaded manner, and the two adjacent triangular connecting seats (33) are fixedly connected with the fixed connecting bolt (31) through the clamping nuts (32);
the triangular connecting seat (33) positioned at the lowest position is fixedly connected with the bottom of the bottom (1) of the pipe well through the corresponding clamping nut (32) and the fixed connecting bolt (31).
CN202320592353.XU 2023-03-23 2023-03-23 Steel-concrete composite beam connection structure Active CN220117405U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320592353.XU CN220117405U (en) 2023-03-23 2023-03-23 Steel-concrete composite beam connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320592353.XU CN220117405U (en) 2023-03-23 2023-03-23 Steel-concrete composite beam connection structure

Publications (1)

Publication Number Publication Date
CN220117405U true CN220117405U (en) 2023-12-01

Family

ID=88889772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320592353.XU Active CN220117405U (en) 2023-03-23 2023-03-23 Steel-concrete composite beam connection structure

Country Status (1)

Country Link
CN (1) CN220117405U (en)

Similar Documents

Publication Publication Date Title
CN109914244B (en) Weak bracket system suitable for high-tower reinforced concrete combined beam steel structure installation and bottom and top plate concrete pouring and operation method thereof
CN110004832B (en) Large-span cantilever truss type bent cap bracket system and construction method
CN2818421Y (en) Upper bearing frame for laminated floorslab construction
CN111663449A (en) Combined cast-in-place box girder support system and construction method
CN103321155B (en) Viaduct pier operation platform system and build this system and pour into a mould the method for bridge pier
CN102261043B (en) Assembled steel pipe upright post system
CN202039377U (en) Prestressed steel stranded wire-combined anchor bolt
CN220117405U (en) Steel-concrete composite beam connection structure
CN108204039A (en) A kind of assembled architecture truss structure
CN207905104U (en) A kind of assembled architecture truss structure
CN209585609U (en) Late poured band support structure
CN208440996U (en) A kind of novel inlet pipe
CN111188278A (en) Jig frame structure, jig frame assembly and construction method
CN202152442U (en) Assembling type steel tube-vertical post system
CN215331674U (en) Interim bearing structure of steel bar truss building carrier plate
CN215906796U (en) Hollow interlayer concrete filled steel tube subway foundation pit support long support with flange nodes
CN216586226U (en) Large-scale concrete drainage box culvert roof suspension type template support
CN210439163U (en) Diagonal joist supporting structure applicable to assembly and disassembly of continuous beam
CN112962427A (en) Off-standard span cast-in-place beam support across valley and construction method
CN112878508A (en) Repairable assembly type reinforced concrete column-steel beam column joint and construction method thereof
CN111519949A (en) Convenient ann tears assembled steel construction reinforcing bar processing protection canopy open
CN210316212U (en) Large-span factory shed ceiling supporting beam
CN217839670U (en) Upper chord reinforced combined steel truss structure
CN210105088U (en) Full-bolt connection node of H-shaped steel beam and floor bearing plate in fabricated building
CN219219375U (en) Component based on assembled building floor and crossbeam welding

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant