CN220099754U - Portable positioning mechanism for construction of steel pipe guardrail - Google Patents

Portable positioning mechanism for construction of steel pipe guardrail Download PDF

Info

Publication number
CN220099754U
CN220099754U CN202320106982.7U CN202320106982U CN220099754U CN 220099754 U CN220099754 U CN 220099754U CN 202320106982 U CN202320106982 U CN 202320106982U CN 220099754 U CN220099754 U CN 220099754U
Authority
CN
China
Prior art keywords
guardrail
steel pipe
main beam
beam body
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320106982.7U
Other languages
Chinese (zh)
Inventor
朱文杰
于谦
陈煜�
程丽丽
徐勤光
班洪富
刘建鲁
滕飞廷
孔晓婷
鲁统伟
李玉亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Linyi Municipal Group Co Ltd
Original Assignee
Linyi Municipal Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Linyi Municipal Group Co Ltd filed Critical Linyi Municipal Group Co Ltd
Priority to CN202320106982.7U priority Critical patent/CN220099754U/en
Application granted granted Critical
Publication of CN220099754U publication Critical patent/CN220099754U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a convenient positioning mechanism for steel pipe guardrail construction, which comprises a main beam body, wherein the main beam body is fixedly attached to the side part of a guardrail upright post; a top cross rod perpendicular to the main beam body is arranged at one end of the main beam body, and the top cross rod is lapped on the top of the guardrail upright post; the lateral part of the girder body is evenly provided with a plurality of transverse brackets, and each transverse bracket is in vertical relation with the girder body and the top cross rod. In practical application, the two positioning mechanisms are respectively fixed on the outer sides of the two guardrail posts at the two ends of the guardrail, and the two opposite transverse pushing mechanisms on the two positioning mechanisms are respectively supported at the two ends of the steel pipe guardrail, so that the steel pipe guardrail and the guardrail posts are accurately positioned, and the steel pipe is welded after being attached to the buckles on the guardrail posts by manual adjustment. The labor intensity of workers and the investment of engineering machinery are reduced, the engineering construction efficiency is improved, and the overall appearance quality of the guardrail is guaranteed.

Description

Portable positioning mechanism for construction of steel pipe guardrail
Technical Field
The utility model relates to the technical field of guardrail construction auxiliary tools, in particular to a portable positioning mechanism for steel pipe guardrail construction.
Background
Municipal guardrail is in the work progress, generally with guardrail stand fixed buries subaerial earlier, then is fixed in between a plurality of guardrail stands with horizontal steel pipe guardrail again. In the installation and construction of the steel pipe guardrail at the present stage, most of the traditional construction modes of mechanical hoisting and manual fixing and welding are adopted. In hoisting construction, accurate positioning cannot be realized, and displacement is easy to generate during manual fixing welding; the traditional construction mode increases the workload of workers, causes the waste of engineering machinery and reduces the engineering construction efficiency; affecting the overall appearance quality of the guardrail.
Disclosure of Invention
The utility model aims to provide a convenient positioning mechanism for construction of a steel pipe guardrail, which solves the technical problems mentioned in the background art.
In order to solve the technical problems, the utility model adopts the following technical scheme:
the utility model relates to a portable positioning mechanism for steel pipe guardrail construction, which comprises a main beam body, wherein the main beam body is fixedly attached to the side part of a guardrail upright post; a top cross rod perpendicular to the main beam body is arranged at one end of the main beam body, and the top cross rod is lapped on the top of the guardrail upright post; the lateral part of the girder body is evenly provided with a plurality of transverse brackets, and each transverse bracket is in vertical relation with the girder body and the top cross rod.
Further, the main beam body is fixedly provided with a reinforcing sheet fixedly connected with the guardrail upright post.
Further, the reinforcing sheet is fixedly arranged at the position of two thirds of the upper part of the main beam body.
Further, the reinforcing sheet is fixedly connected with the guardrail upright post through the locking pliers.
Compared with the prior art, the utility model has the beneficial technical effects that:
in practical application, the two positioning mechanisms are respectively fixed on the outer sides of the two guardrail posts at the two ends of the guardrail, and the two opposite transverse pushing mechanisms on the two positioning mechanisms are respectively supported at the two ends of the steel pipe guardrail, so that the steel pipe guardrail and the guardrail posts are accurately positioned, and the steel pipe is welded after being attached to the buckles on the guardrail posts by manual adjustment. The labor intensity of workers and the investment of engineering machinery are reduced, the engineering construction efficiency is improved, and the overall appearance quality of the guardrail is guaranteed.
Drawings
The utility model is further described with reference to the following description of the drawings.
FIG. 1 is a schematic perspective view of the present utility model;
FIG. 2 is a schematic view of the construction state of the present utility model;
reference numerals illustrate: 1. a main beam body; 2. guard bar upright posts; 3. a top rail; 4. a transverse support; 5. a reinforcing sheet; 6. a steel pipe guardrail.
Detailed Description
As shown in fig. 1-2, the portable positioning mechanism for the construction of the steel pipe guardrail comprises a main beam body 1, wherein the main beam body 1 is fixedly attached to the side part of a guardrail upright post 2. One end of the main beam body 1 is fixedly provided with a top cross rod 3 perpendicular to the main beam body in a welding mode, and the top cross rod 3 is lapped on the top of the guardrail upright 2. The side part of the main beam body 1 is uniformly and fixedly provided with a plurality of transverse supports 4 in a welding mode, each transverse support 4 is in vertical relation with the main beam body 1 and the top cross rod 2, and the distance between every two adjacent transverse supports 4 is equal to the design distance of the steel pipe guardrail 6 on the steel pipe upright post 2.
In addition, in this embodiment, the main beam body 1 is further fixedly provided with a reinforcing sheet 5 fixedly connected with the guardrail posts 2 by means of welding. Specifically, the reinforcing sheet 5 is fixedly arranged at the two-thirds position of the upper part of the main beam body 1 and is fixedly connected with the guardrail upright post 2 through a locking pliers.
In practical application, as shown in fig. 2, two positioning mechanisms are respectively fixed at the outer sides of two guardrail posts at two ends of a guardrail, a main beam body 1 is attached to the side part of the guardrail post 2, a top cross rod 3 is attached to the top of the guardrail post 2, and then a reinforcing sheet 5 and the guardrail post 2 are fixedly reinforced by using a locking pliers so as to ensure that the positioning mechanisms do not deviate when the steel pipe guardrail is installed, and after the positioning mechanisms are installed, whether the distance between the top of a transverse support 4 at the bottom and an asphalt pavement is the same as the design requirement distance between the steel pipe guardrail and the asphalt pavement is measured. Then, the pipe hanging construction of the steel pipe guardrail can be carried out, two opposite transverse pushing mechanisms on the two positioning mechanisms are respectively supported at two ends of the steel pipe guardrail, so that the steel pipe guardrail and the guardrail upright post are accurately positioned, and the welding operation is carried out after the buckles on the steel pipe guardrail and the guardrail upright post are attached by manual adjustment.
The above embodiments are only illustrative of the preferred embodiments of the present utility model and are not intended to limit the scope of the present utility model, and various modifications and improvements made by those skilled in the art to the technical solutions of the present utility model should fall within the protection scope defined by the claims of the present utility model without departing from the design spirit of the present utility model.

Claims (4)

1. The utility model provides a convenient positioning mechanism is used in construction of steel pipe guardrail which characterized in that: the guardrail comprises a main beam body, wherein the main beam body is fixedly attached to the side part of the upright post of the guardrail; a top cross rod perpendicular to the main beam body is arranged at one end of the main beam body, and the top cross rod is lapped on the top of the guardrail upright post; the lateral part of the girder body is evenly provided with a plurality of transverse brackets, and each transverse bracket is in vertical relation with the girder body and the top cross rod.
2. The portable positioning mechanism for construction of steel pipe guardrails according to claim 1, wherein: and the main beam body is also fixedly provided with a reinforcing sheet which is fixedly connected with the guardrail upright post.
3. The portable positioning mechanism for construction of steel pipe guardrails according to claim 2, characterized in that: the reinforcing sheet is fixedly arranged at the two-thirds position of the upper part of the main beam body.
4. The portable positioning mechanism for construction of steel pipe guardrails according to claim 2, characterized in that: the reinforcing sheet is fixedly connected with the guardrail upright post through the locking pliers.
CN202320106982.7U 2023-02-03 2023-02-03 Portable positioning mechanism for construction of steel pipe guardrail Active CN220099754U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320106982.7U CN220099754U (en) 2023-02-03 2023-02-03 Portable positioning mechanism for construction of steel pipe guardrail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320106982.7U CN220099754U (en) 2023-02-03 2023-02-03 Portable positioning mechanism for construction of steel pipe guardrail

Publications (1)

Publication Number Publication Date
CN220099754U true CN220099754U (en) 2023-11-28

Family

ID=88872720

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320106982.7U Active CN220099754U (en) 2023-02-03 2023-02-03 Portable positioning mechanism for construction of steel pipe guardrail

Country Status (1)

Country Link
CN (1) CN220099754U (en)

Similar Documents

Publication Publication Date Title
CN215104737U (en) A assembled support for bridge construction
CN212534174U (en) Raft foundation steel bar supporting tool
CN204703500U (en) Assembled architecture construction novel support system
CN111364757A (en) Supporting structure of steel bar truss floor bearing plate
CN220099754U (en) Portable positioning mechanism for construction of steel pipe guardrail
CN103866692A (en) Novel assembling method for bent cap bearing frame
CN110670873B (en) Support system of steel formwork of ultrahigh large-section concrete column and construction method
JP3238640U (en) Temporary underpinning steel support structure applied to demolition and remodeling work
CN202766974U (en) Bent cap bearing frame without full framing
CN216586226U (en) Large-scale concrete drainage box culvert roof suspension type template support
CN202689585U (en) Ground fitting up assembly mould of large steel truss
CN213563427U (en) Precast beam removes stretch-draw rack
CN214170072U (en) Steel construction factory building structure based on exposed foundation
CN212688718U (en) Bent cap reinforcement bed-jig structure
CN213297136U (en) Assembled steel construction house steel bar truss building carrier plate bearing structure
CN211006352U (en) Pier stud template reinforced structure
CN208304249U (en) Framework of steel reinforcement piece welds positioning clamping fixture
CN218504850U (en) Simple device for mounting and tensioning protection of precast beam jack
CN212507075U (en) Tool type steel bar support frame for mass concrete in super high-rise core barrel
CN218264956U (en) Tool type auxiliary support for square and round buckles
CN217580198U (en) Concrete structure unilateral template structure with narrow distance from support pile
CN216238167U (en) Variable cross-section steel box arch tower supporting jig frame for municipal construction
CN217204223U (en) Retaining wall unilateral founds mould and supports reinforcement assembly
CN221297595U (en) Bent cap construction operation platform with bailey beam as support girder
CN211689958U (en) Cast-in-place pier construction platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant