CN220058088U - Pipe gallery pipeline assembling structure - Google Patents

Pipe gallery pipeline assembling structure Download PDF

Info

Publication number
CN220058088U
CN220058088U CN202321501772.4U CN202321501772U CN220058088U CN 220058088 U CN220058088 U CN 220058088U CN 202321501772 U CN202321501772 U CN 202321501772U CN 220058088 U CN220058088 U CN 220058088U
Authority
CN
China
Prior art keywords
pipe
ring
fixedly connected
groove
drainage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321501772.4U
Other languages
Chinese (zh)
Inventor
张宝香
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Dongjiakou Chemical Park Public Pipe Corridor Co ltd
Original Assignee
Qingdao Dongjiakou Chemical Park Public Pipe Corridor Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Dongjiakou Chemical Park Public Pipe Corridor Co ltd filed Critical Qingdao Dongjiakou Chemical Park Public Pipe Corridor Co ltd
Priority to CN202321501772.4U priority Critical patent/CN220058088U/en
Application granted granted Critical
Publication of CN220058088U publication Critical patent/CN220058088U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model belongs to the technical field of pipe gallery construction, and particularly relates to a pipe gallery pipeline assembling structure, which comprises a pipe culvert body, wherein a connecting ring is fixedly connected to the inner side of one end of the pipe culvert body, a connecting groove is formed in the side face of the connecting ring, a binding ring is fixedly connected to the inner side of the other end of the pipe culvert body, a fastening ring is connected to the inner side of the binding ring in a sliding manner, a drainage groove is formed in the inner side of the fastening ring, an annular pipe is arranged on the other side of the binding ring, a drainage tube is fixedly connected to one side of the annular pipe, the drainage tube is connected to the inner side of the drainage groove in a sliding manner, and an injection pipe is fixedly connected to the other side of the annular pipe; after the splicing of the pipe culverts is completed, workers can directly fill glue into the pipe joints through the injection pipe, waterproof materials can be continuously injected into the gap between the two pipe culvert bodies through the groove formed in one end of the drainage pipe until the pipe joints are filled, the workers do not need to go up to the top ends of the pipe culverts to fill glue, labor intensity of the workers is reduced, and construction efficiency is improved.

Description

Pipe gallery pipeline assembling structure
Technical Field
The utility model belongs to the technical field of pipe gallery construction, and particularly relates to a pipe gallery pipeline assembling structure.
Background
The utility model provides a pipe gallery, also called precast concrete box structure, is a common structural style in modern urban underground engineering, at present, generally adopt assembly type technology to carry out the construction in pipe gallery construction, namely whole pipe gallery is divided into a plurality of pipe culvert according to the section, adopt concrete prefabrication's mode to carry out processing at the mill with the pipe culvert, then after transporting to the job site, carry out the operation of assembling through hoisting machinery at the job site, the pipe culvert can exist the gap after accomplishing the concatenation, consequently, fill sealing material to realize waterproof function between the pipe seam, at present, usually need the workman to hold specialized tool to fill the glue operation to the pipe seam when filling sealing material, because circular pipe culvert top operation area is limited, and receive high restriction, the workman can have very big inconvenience when carrying out the construction operation to circular pipe culvert, in addition, because the whole construction length of pipe gallery is longer, the work load of filling the glue can also increase thereupon, can make workman intensity of labour higher, result in the efficiency of construction is low.
Disclosure of Invention
The utility model provides a pipe gallery pipeline assembling structure, which has the characteristic of being convenient for workers to fill waterproof materials into pipe seams.
The utility model provides the following technical scheme: including the pipe culvert body, the inboard fixedly connected with go-between of pipe culvert body one end, the spread groove has been seted up to the go-between side, the inboard fixedly connected with laminating ring of pipe culvert body other end, the inside sliding connection of laminating ring has the holding ring, the drainage groove has been seted up to the holding ring inside, the laminating ring opposite side is provided with the ring pipe, ring pipe one side fixedly connected with drainage tube, drainage tube sliding connection in inside the drainage groove, ring pipe opposite side fixedly connected with injection tube.
The mounting seat is detachably connected to the side face of the laminating ring and fixedly connected with the annular tube.
The inner wall of the connecting groove is fixedly connected with a sealing layer, a sliding groove is formed in the inner portion of the attaching ring, and the fastening ring is in sliding connection with the inner portion of the attaching ring through the sliding groove.
The side face of the fastening ring is fixedly connected with a threaded rod.
Wherein, the communication port has been seted up to drainage tube one end.
The beneficial effects of the utility model are as follows: through the cooperation of spread groove and fastening ring for the workman can directly fill out the glue operation to the pipe joint through the injection pipe after the pipe culvert is accomplished the concatenation, and waterproof material can be through the slot that drainage tube one end was seted up constantly inject into in the gap between two pipe culvert bodies, until filling up the pipe joint, the workman need not go up to the pipe culvert top and fill out the glue operation, thereby reduced workman's intensity of labour, and then promoted the efficiency of construction.
None of the parts of the device are the same as or can be implemented using prior art.
Drawings
FIG. 1 is a schematic cross-sectional view of the present utility model;
FIG. 2 is a schematic diagram of the connection state of the present utility model;
FIG. 3 is an enlarged schematic view of FIG. 1 at A;
fig. 4 is an enlarged schematic view at B in fig. 2.
In the figure: 1. a pipe culvert body; 11. a connecting ring; 12. a connecting groove; 121. a sealing layer; 2. a laminating ring; 21. a fastening ring; 211. a sliding groove; 212. a threaded rod; 22. drainage grooves; 23. a mounting base; 3. an annular tube; 31. a drainage tube; 311. a communication port; 32. an injection tube.
Detailed Description
Referring to fig. 1-4, the present utility model provides the following technical solutions: including the pipe culvert body 1, the inboard fixedly connected with go-between 11 of pipe culvert body 1 one end, go-between 12 have been seted up to the go-between 11 sides, the inboard fixedly connected with laminating ring 2 of the inboard fixedly connected with of the other end of pipe culvert body 1, the inside sliding connection of laminating ring 2 has the fastening ring 21, the drainage groove 22 has been seted up to the inside of fastening ring 21, the laminating ring 2 opposite side is provided with annular pipe 3, annular pipe 3 one side fixedly connected with drainage tube 31, drainage tube 31 sliding connection is inside drainage groove 22, annular pipe 3 opposite side fixedly connected with injection tube 32.
In this embodiment: the connecting ring 11 and the attaching ring 2 which are fixedly connected with the inner side of the pipe culvert body 1 are of annular structures, the connecting ring 11 and the attaching ring 2 are respectively and fixedly connected with the left end and the right end of the inner side of the pipe culvert body 1, when one end of the pipe culvert body 1 is inserted into the other end of the adjacent pipe culvert body 1 during assembly, the connecting groove 12 on the pipe culvert body 1 can be attached with the attaching ring 2 on the adjacent pipe culvert body 1, then workers can fix the connecting groove 12 and the attaching ring 2 in a bolt-nut or welding mode, assembly connection between the two pipe culvert bodies 1 can be completed, the size of the connecting groove 12 which is formed by the fastening ring 21 which is in sliding connection with the inner side of the attaching ring 2 is consistent with that of the connecting ring 11, the fastening ring 21 is used for being inserted into the connecting groove 12, the fastening ring 21 can be attached with a sealing part which is arranged on the inner wall of the connecting groove 12, the connecting groove 12 and the fastening ring 21 cooperate to prevent the waterproof material from leaking downwards through the gap between the connecting groove 12 and the fastening ring 21 when the worker fills glue, so as to avoid the occurrence of the condition of unsatisfactory filling effect, the drainage groove 22 is used for guiding the waterproof material into the inside of the pipe seam between the two pipe culvert bodies 1, the drainage tube 31 slides in the drainage groove 22, when the drainage tube 31 horizontally slides to the leftmost side of the drainage groove 22, the groove formed at one end of the drainage tube 31 is communicated with the drainage groove 22, at the moment, the worker is connected with an external filling pump through the injection pipe 32 to inject the waterproof material into the annular pipe 3, the waterproof material can be injected between the pipe seams of the two pipe culvert bodies 1 through the drainage groove 22, so that the pipe culvert bodies 1 can be firstly lifted by a lifting machine and one end is inserted into the other end of the adjacent pipe culvert bodies 1 when the pipe culvert is used, make the attachment ring 2 on the attachment ring 2 and the attachment ring 12 on the attachment ring 1 counterpoint laminating, the spread ring 21 can insert inside the attachment ring 12, and under the limiting effect of attachment ring 12 inner wall, slide along the inside groove of seting up of attachment ring 2, the drainage tube 31 of annular tube 3 one side fixed connection can gradually carry out horizontal slip in drainage groove 22 inside this moment, when the inside slip of solid ring 21 to attachment ring 2 to the terminal point, the groove of seting up of drainage tube 31 one end can move to between the gap of go-between 11 and attachment ring 2 just, then the workman can adopt bolt and nut or welded mode to fix attachment groove 12 and attachment ring 2, accomplish the assembly between two attachment ring bodies 1, the fastener that rethread fastener that fastener ring 21 side set up is to the spread ring 21 fastens, make the fastener 21 that fastener ring 21 can be inseparable with the sealing member that the inner wall of attachment groove 12 set up, alright connect injection pipe 32 with outside filling pump delivery port, and control outside filling pump to the inside injection into of tube 3, because fastener ring 21 slides to the inside the attachment ring 2, the gap between two ends of pipe 31 can be directly filled up the gap through the sealing member that fastener 21 and the pipe 1 are cut-off, can be directly to the gap through the joint material through setting up between two sealing member that fastener ring 21, the pipe 31 can be filled up the gap between the two ends through the pipe joint ring 1, the material through the sealing member that the gap between the two attachment ring 1, the pipe joint ring 1 and the pipe gap can be completed, the gap can be filled up through the sealing member that the joint gap between the pipe joint hole between the pipe 1 and the pipe joint hole 31, and the pipe joint hole is filled up between the sealing member through the sealing member that the sealing member is filled up between the sealing ring 31 and the sealing ring 31, until the pipe joints are filled, workers do not need to go up to the top ends of the pipe culverts to carry out glue filling operation, so that the labor intensity of the workers is reduced, and the construction efficiency is improved.
The side surface of the attaching ring 2 is detachably connected with a mounting seat 23, and the mounting seat 23 is fixedly connected with the annular tube 3; the annular pipe 3 is installed in one side of laminating ring 2 through mount pad 23, and mount pad 23 is used for providing support for annular pipe 3, and when the waterproof material of filling between the pipe seam solidifies, workman's accessible is released mount pad 23 and laminating ring 2 and is connected and demolish annular pipe 3 to install to need carry out the operation region of filling, strengthen annular pipe 3 flexibility of using, also reduced cost and extravagant simultaneously.
The inner wall of the connecting groove 12 is fixedly connected with a sealing layer 121, a sliding groove 211 is formed in the laminating ring 2, and the fastening ring 21 is connected in a sliding manner in the laminating ring 2 through the sliding groove 211; the sealing layer 121 has elasticity, and sealing layer 121 is used for laminating with the side of fastening ring 21, and spread groove 12 and fastening ring 21 cooperation can prevent that the workman from being in the time of filling glue, and waterproof material can leak downwards through the gap between spread groove 12 and the fastening ring 21 to avoid filling the condition emergence of effect non-ideal.
The side surface of the fastening ring 21 is fixedly connected with a threaded rod 212; the inside through-hole that corresponds with threaded rod 212 position that is provided with of go-between 11, consequently accomplish the counterpoint concatenation between two pipe culvert bodies 1, threaded rod 212 can insert the inside through-hole that sets up of go-between 11, workman's accessible is fastened fastening ring 21 with threaded rod 212 size anastomotic nut, make fastening ring 21 can with the inseparable laminating of spread groove 12 inner wall fixed connection, spread groove 12 and fastening ring 21 cooperation can prevent that the workman from being in the time of filling glue, waterproof material can leak downwards through the gap between spread groove 12 and the fastening ring 21, thereby avoid filling the condition emergence of effect inequality.
One end of the drainage tube 31 is provided with a communication port 311; the communication port 311 is used for injecting the waterproof material inside the drainage tube 31 into the pipe seam between the two pipe culvert bodies 1, the connecting groove 12 is inserted into the connecting groove 12 in the process of laminating the connecting groove 12 and the fastening ring 21 slides along the groove formed inside the laminating ring 2 under the limiting effect of the inner wall of the connecting groove 12, the drainage tube 31 fixedly connected with one side of the annular tube 3 gradually slides horizontally inside the drainage groove 22, when the fastening ring 21 slides to the end point inside the laminating ring 2, the communication port 311 just moves to the position of the pipe seam between the connecting ring 11 and the laminating ring 2 to complete communication, and then a worker can inject the waterproof material into the pipe seam between the two pipe culvert bodies 1 through the injection pipe 32 to complete filling operation between the pipe seam.
The working principle and the using flow of the utility model are as follows: when in use, the pipe culvert body 1 can be lifted by a lifting machine and one end of the pipe culvert body is inserted into the other end of the adjacent pipe culvert body 1, so that the connecting groove 12 on the pipe culvert body 1 is aligned and attached to the attaching ring 2 on the adjacent pipe culvert body 1, in the attaching process of the connecting groove 12 and the attaching ring 2, the fastening ring 21 can be inserted into the connecting groove 12 and slide along the groove formed in the attaching ring 2 under the limit effect of the inner wall of the connecting groove 12, at the moment, the drainage tube 31 fixedly connected with one side of the annular pipe 3 can gradually slide horizontally in the drainage groove 22, when the fastening ring 21 slides to the end point in the attaching ring 2, the communicating opening 311 formed at one end of the drainage tube 31 just moves between the gap of the connecting ring 11 and the attaching ring 2, then a worker can fix the connecting groove 12 and the attaching ring 2 in a bolt-nut or welding mode to complete the assembly between the two pipe culvert bodies 1, the fastening ring 21 is fastened by the nut which is matched with the threaded rod 212 in size, so that the fastening ring 21 can be tightly attached to the sealing layer 121 fixedly connected with the inner wall of the connecting groove 12, at the moment, the injection pipe 32 can be connected with the output port of the external filling pump, the external filling pump is controlled to inject glue into the annular pipe 3, because the fastening ring 21 and the attaching ring 2 are of annular structures, and the fastening ring 21 is tightly attached to the sealing part arranged on the inner wall of the connecting groove 12 by the fastening part, the waterproof material can be continuously injected into the gap between the two pipe culvert bodies 1 by the groove arranged at one end of the drainage pipe 31 until the waterproof material fills up the pipe gap, thereby completing the glue filling operation on the pipe gap, and after the splicing of the pipe culvert is completed by workers, the glue filling operation can be directly carried out on the pipe gap by the injection pipe 32 by the cooperation of the connecting groove 12 and the fastening ring 21, waterproof material can be constantly poured into the gap between two pipe culvert bodies 1 through the groove that drainage tube 31 one end was seted up, until the pipe joint is filled, the workman need not go up to the pipe culvert top and carry out the packing operation to reduce workman's intensity of labour, and then promoted the efficiency of construction.

Claims (5)

1. The utility model provides a structure is assembled to piping lane pipeline, includes pipe culvert body (1), its characterized in that: the utility model discloses a pipe culvert body, including pipe culvert body (1), connecting ring (11), connecting groove (12) have been seted up to connecting ring (11) side, pipe culvert body (1) other end inboard fixedly connected with laminating ring (2), inside sliding connection of laminating ring (2) has fastening ring (21), drainage groove (22) have been seted up to fastening ring (21) inside, laminating ring (2) opposite side is provided with annular pipe (3), annular pipe (3) one side fixedly connected with drainage tube (31), drainage tube (31) sliding connection in inside drainage groove (22), annular pipe (3) opposite side fixedly connected with injection tube (32).
2. A piping lane pipeline assembly structure as claimed in claim 1, wherein: the side face of the laminating ring (2) is detachably connected with a mounting seat (23), and the mounting seat (23) is fixedly connected with the annular tube (3).
3. A piping lane pipeline assembly structure as claimed in claim 1, wherein: the inner wall of the connecting groove (12) is fixedly connected with a sealing layer (121), a sliding groove (211) is formed in the laminating ring (2), and the fastening ring (21) is connected to the inside of the laminating ring (2) in a sliding manner through the sliding groove (211).
4. A piping lane pipeline assembly structure as claimed in claim 1, wherein: the side surface of the fastening ring (21) is fixedly connected with a threaded rod (212).
5. A piping lane pipeline assembly structure as claimed in claim 1, wherein: one end of the drainage tube (31) is provided with a communication port (311).
CN202321501772.4U 2023-06-13 2023-06-13 Pipe gallery pipeline assembling structure Active CN220058088U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321501772.4U CN220058088U (en) 2023-06-13 2023-06-13 Pipe gallery pipeline assembling structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321501772.4U CN220058088U (en) 2023-06-13 2023-06-13 Pipe gallery pipeline assembling structure

Publications (1)

Publication Number Publication Date
CN220058088U true CN220058088U (en) 2023-11-21

Family

ID=88763772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321501772.4U Active CN220058088U (en) 2023-06-13 2023-06-13 Pipe gallery pipeline assembling structure

Country Status (1)

Country Link
CN (1) CN220058088U (en)

Similar Documents

Publication Publication Date Title
CN111576403B (en) Pile splicing structure and bearing platform anchoring structure using PHC tubular pile
CN220058088U (en) Pipe gallery pipeline assembling structure
CN113605331A (en) Modular quick-assembly water retaining cofferdam for flood discharge runner maintenance and application method thereof
CN113293933B (en) Grouting device and grouting method for grouting sleeve
CN204919546U (en) But recovery type soil nail
CN111322075B (en) Backfill slip casting system behind wall for shaft boring machine
CN205857182U (en) A kind of end-protecting device for steel-pipe pile construction
CN110924990A (en) Advanced supporting structure assembled by corrugated steel pipe sheets and supporting method
CN208219638U (en) A kind of deep foundation pit precast stake
CN202302366U (en) Prestressed steel cylinder concrete jacking pipe
CN217328627U (en) Check valve for grouting pipe
CN211286302U (en) Inner cavity convex multi-point distributed grouting sleeve
CN213682083U (en) Upper section tubular pile of spliced prefabricated tubular pile
CN1274060A (en) Expansion shaped insertion-type steel tubes for both flexible and rigid joining and its manufacture technology
CN111577333B (en) Shield tunnel compaction grouting structure
CN210500792U (en) Double-tube type steel bar connecting structure between precast concrete components
CN210439568U (en) A grout sleeve for steel bar connection
CN209227902U (en) Prefabricated concrete structure column steel pipe socket shell ring point
CN212744003U (en) Hydraulic mould and automatic molding system for traction connection of cement pipeline
CN209308068U (en) A kind of underground pipe arragement construction
CN219711537U (en) Mortar reinforcing device and mortar reinforcing system of shield tunnel
CN211144521U (en) Advance support structure assembled by corrugated steel pipe sheets
CN211735814U (en) Prefabricated shear wall connection structure
CN211948273U (en) Reverse formwork system of modularization is pour to ditch that can have enough to meet need
CN110629876A (en) Installation and construction method of pipe truss structure system connection truss

Legal Events