CN220016662U - Detachable measuring instrument mounting platform for rapid installation of steel tower construction - Google Patents

Detachable measuring instrument mounting platform for rapid installation of steel tower construction Download PDF

Info

Publication number
CN220016662U
CN220016662U CN202320960189.3U CN202320960189U CN220016662U CN 220016662 U CN220016662 U CN 220016662U CN 202320960189 U CN202320960189 U CN 202320960189U CN 220016662 U CN220016662 U CN 220016662U
Authority
CN
China
Prior art keywords
steel tower
centering
measuring instrument
plate
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320960189.3U
Other languages
Chinese (zh)
Inventor
黄新伟
蒲冬哓
向小苗
汪子鹏
杨洋
吴兴富
赵志磊
胡玉花
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangmen Jianghe Expressway Co ltd
9th Engineering Co Ltd of MBEC
Original Assignee
Jiangmen Jianghe Expressway Co ltd
9th Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangmen Jianghe Expressway Co ltd, 9th Engineering Co Ltd of MBEC filed Critical Jiangmen Jianghe Expressway Co ltd
Priority to CN202320960189.3U priority Critical patent/CN220016662U/en
Application granted granted Critical
Publication of CN220016662U publication Critical patent/CN220016662U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A be used for steel tower construction to install detachable measuring instrument mounting platform fast relates to bridge steel tower construction field, sets up on the steel tower, including dismantling the mounting panel of fixing steel tower lateral part, the horizontal level in mounting panel upper portion is fixed with centering dish, centering dish top center is vertical upwards to be provided with centering screw, centering screw be used for with measuring instrument base centering fixed connection, the mounting panel with be provided with supporting mechanism between the centering dish distal end. The utility model has simple structure, utilizes the high-strength bolt hole on the L-shaped steel plate to effectively fix the platform by utilizing the high-strength bolt on the steel tower, has simple operation and convenient installation and disassembly, and improves the construction measurement precision of the steel tower and the assembly efficiency of the steel tower.

Description

Detachable measuring instrument mounting platform for rapid installation of steel tower construction
Technical Field
The utility model relates to the field of bridge steel tower construction, in particular to a detachable measuring instrument mounting platform for rapid installation of steel tower construction.
Background
In the previous steel tower splicing construction measurement process, related measurement instruments such as a total station and the like are required to be used for measurement and positioning. And the erection of the total station generally adopts a traditional tripod support as a mounting platform of the measuring instrument. However, due to the specificity of the steel tower material, the friction coefficient of the contact surface between the metal surface and the support bottom of the traditional tripod is low, so that the stability of instrument erection is seriously influenced, the probability of instrument sliding in the measuring process is extremely high, and the measuring precision is influenced. Meanwhile, the total height of each section of steel tower and the inner and outer partition plates exceeds 2m, the traditional tripod has the telescopic length of only 1.8m, and the section of steel tower and the inner and outer partition plates are required to be separately hoisted and spliced due to the limitation of the height of the sight line, so that the inner and outer partition plates can be hoisted after the measurement and positioning of the section of steel tower are completed, and the assembling efficiency of the steel tower is seriously influenced.
Because the measuring instrument erection method has obvious defects in the steel tower construction measuring link, the erection difficulty is high, the stability after the instrument is erected is poor, the instrument is damaged under severe conditions, and the hoisting efficiency of the field section steel tower is influenced.
Disclosure of Invention
The utility model aims to solve the defects and the shortcomings in the prior art, and provides a mounting platform for erecting measuring instruments such as total stations and the like in the construction and measurement process of a steel tower.
In order to solve the technical problems, the utility model adopts the following technical scheme:
a be used for steel tower construction to install detachable measuring instrument mounting platform fast sets up on the steel tower, including dismantling the mounting panel of fixing the steel tower lateral part, mounting panel upper portion transversely horizontally is fixed with centering dish, centering dish top center is vertical upwards to be provided with the centering screw, the centering screw be used for with measuring instrument base centering fixed connection, the mounting panel with be provided with supporting mechanism between the centering dish distal end.
Further, the mounting plate comprises a vertical plate and a transverse plate transversely arranged at the lower end of the vertical plate, and an L-shaped structure is arranged between the vertical plate and the transverse plate.
Further, the supporting mechanism comprises a vertical diagonal bracing, the upper end of the vertical diagonal bracing is fixedly connected with the bottom of the far end of the centering disc, and the lower end of the vertical diagonal bracing is fixedly connected with the top of the far end of the transverse plate.
Further, a supporting steel plate is obliquely fixed on the upper part of the vertical plate and the near end of the centering disc.
Further, a plurality of bolt fixing holes are formed in the vertical plate in an array mode, and the mounting plate is fixed to the steel tower through the mounting bolt and the bolt fixing holes.
Further, the mounting plate is made of steel plates.
Compared with the prior art, the utility model has the following beneficial effects:
the utility model has simple structure, utilizes the high-strength bolt hole on the L-shaped steel plate to effectively fix the platform by utilizing the high-strength bolt on the steel tower, has simple operation and convenient installation and disassembly, and improves the construction measurement precision of the steel tower and the assembly efficiency of the steel tower.
Drawings
In order to more clearly illustrate the embodiments of the utility model or the technical solutions of the prior art, the drawings which are used in the description of the embodiments or the prior art will be briefly described, it being obvious that the drawings in the description below are only some embodiments of the utility model, and that other drawings can be obtained according to these drawings without inventive faculty for a person skilled in the art.
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic view of a mounting plate according to the present utility model;
FIG. 3 is a schematic view of the riser structure of the present utility model.
In the figure: 1. steel tower, 2 centering disc, 3 centering screw, 4 measuring instrument base, 5 mounting panel, 51 riser, 52 diaphragm, 6 bolt fastening hole, 7 mounting bolt, 8 vertical diagonal bracing, 9 supporting steel plate.
Detailed Description
The features of the present utility model and other related features are described in further detail below in conjunction with the drawings in embodiments of the utility model, so that those skilled in the art will readily appreciate that the embodiments described are merely some, but not all, embodiments of the utility model. All other embodiments, based on the embodiments of the present utility model, which are within the scope of the present utility model as defined by the claims, will be within the scope of the present utility model as defined by the appended claims.
Terms of orientation such as up, down, left, right, front, rear, front, back, top, bottom, etc. mentioned or possible to be mentioned in the present specification are defined with respect to their construction, and they are relative concepts. Therefore, these and other directional terms should not be interpreted as display terms, since they may be changed according to different positions and different use states.
As shown in fig. 1-3, a quick-mounting detachable measuring instrument mounting platform for steel tower construction is arranged on a steel tower 1, and comprises a mounting plate 5 detachably fixed on the side part of the steel tower 1, a centering disc 2 is horizontally and transversely fixed on the upper part of the mounting plate 5, a centering screw 3 is vertically and upwards arranged at the center of the top of the centering disc 2, the centering screw 3 is used for being fixedly connected with a measuring instrument base 4 in a centering manner, and a supporting mechanism is arranged between the mounting plate 5 and the far end of the centering disc 2.
The device for measuring the rapid bracket instrument in the steel tower construction in the embodiment directly erects the total station on the vertical surface of the steel tower through the device and ensures the erection stability of measuring instruments such as the total station. As shown in the figure I, a supporting steel plate 9 is arranged at the welding position of the square homing disc and the mounting plate, symmetrical vertical diagonal braces 8 are arranged at two ends of the square homing disc, the strength and stability of the whole device are guaranteed, and a supporting plane for erecting measuring instruments such as a total station is further formed.
Specifically, as shown in the figure, the mounting plate 5 includes a riser 51, and a transverse plate 52 transversely disposed at the lower end of the riser 51, and an L-shaped structure is formed between the riser 51 and the transverse plate 52.
Specifically, as shown in the figure, the supporting mechanism includes a vertical diagonal brace 8, the upper end of the vertical diagonal brace 8 is fixedly connected with the bottom of the distal end of the centering disc 2, and the lower end of the vertical diagonal brace 8 is fixedly connected with the top of the distal end of the transverse plate 52.
Specifically, as shown in the figure, a supporting steel plate 9 is obliquely fixed to the upper portion of the riser 51 and the proximal end of the centering plate 2.
Specifically, as shown in the figure, a plurality of bolt fixing holes 6 are formed in the vertical plate 51 in an array manner, and the mounting plate 5 is fixed on the steel tower 1 through the mounting bolts 7 and the bolt fixing holes 6. As shown in the third drawing, nine high-strength bolt holes are formed in one surface of the long side of the L-shaped steel plate, and the device and the steel tower can be effectively connected and fixedly connected by utilizing different positions and different numbers of bolt holes according to requirements. The specification of the fixing bolt hole is matched with a bolt on the steel tower, so that the feasibility and the stability of the installation of the device are ensured. Meanwhile, in order to ensure the stability and the operation efficiency of the platform, the inner and outer partition plates of the segmental steel tower, which are fixed on one side of the platform device during measurement, are fixedly connected with the high-strength bolts of the steel tower.
Specifically, as shown in the figure, the mounting plate 5 is made of steel plate.
Specifically, the method comprises the following specific installation steps:
1. in the construction measurement process of the steel tower segment, selecting a proper position and height for installing the device according to the limit of the field environment;
2. nine high-strength bolt heads at the positions where the device is installed are taken down, nine high-strength bolt holes on the device are sleeved on high-strength bolts of an inner partition plate and an outer partition plate of a steel tower, the bolts are screwed at the points needing to be fixed, and the fixed points are at least five and uniformly distributed in order to ensure the stability of the platform.
3. And finally, placing the related measuring instruments such as the total station on a square centering disc, fastening the related measuring instruments such as the total station with the device through centering screws, and then adjusting the instruments to a horizontal state by utilizing the horizontal adjusting device of the instruments so as to perform construction measurement operation of the steel tower.
The foregoing description of the preferred embodiments of the utility model is not intended to be limiting, but rather is intended to cover all modifications, equivalents, alternatives, and improvements that fall within the spirit and scope of the utility model.
Furthermore, it should be understood that although the present disclosure describes embodiments, not every embodiment is provided with a separate embodiment, and that this description is provided for clarity only, and that the disclosure is not limited to the embodiments described in detail below, and that the embodiments described in the examples may be combined as appropriate to form other embodiments that will be apparent to those skilled in the art.

Claims (6)

1. A be used for steel tower construction to install detachable measuring instrument mounting platform fast sets up on steel tower (1), its characterized in that is including dismantling fixing mounting panel (5) of steel tower (1) lateral part, mounting panel (5) upper portion transversely horizontally is fixed with centering dish (2), centering dish (2) top center is vertical upwards to be provided with centering screw (3), centering screw (3) are used for with measuring instrument base (4) centering fixed connection, mounting panel (5) with be provided with supporting mechanism between centering dish (2) distal end.
2. The rapid-installation detachable measuring instrument installation platform for steel tower construction according to claim 1, wherein the installation plate (5) comprises a vertical plate (51) and a transverse plate (52) transversely arranged at the lower end of the vertical plate (51), and an L-shaped structure is formed between the vertical plate (51) and the transverse plate (52).
3. The rapid-installation detachable measuring instrument installation platform for steel tower construction according to claim 2, wherein the supporting mechanism comprises a vertical diagonal brace (8), the upper end of the vertical diagonal brace (8) is fixedly connected with the bottom of the far end of the centering disc (2), and the lower end of the vertical diagonal brace (8) is fixedly connected with the top of the far end of the transverse plate (52).
4. A rapid-installation detachable measuring instrument mounting platform for steel tower construction according to claim 3, characterized in that the upper part of the riser (51) and the proximal end of the centering disc (2) are obliquely fixed with a supporting steel plate (9).
5. The rapid-installation detachable measuring instrument installation platform for steel tower construction according to claim 4, wherein a plurality of bolt fixing holes (6) are formed in the vertical plate (51) in an array mode, and the installation plate (5) is fixed on the steel tower (1) through installation bolts (7) and the bolt fixing holes (6).
6. A rapid installable removable measuring instrument mounting platform for steel tower construction according to claim 5, wherein the mounting plate (5) is made of steel plate.
CN202320960189.3U 2023-04-25 2023-04-25 Detachable measuring instrument mounting platform for rapid installation of steel tower construction Active CN220016662U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320960189.3U CN220016662U (en) 2023-04-25 2023-04-25 Detachable measuring instrument mounting platform for rapid installation of steel tower construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320960189.3U CN220016662U (en) 2023-04-25 2023-04-25 Detachable measuring instrument mounting platform for rapid installation of steel tower construction

Publications (1)

Publication Number Publication Date
CN220016662U true CN220016662U (en) 2023-11-14

Family

ID=88683832

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320960189.3U Active CN220016662U (en) 2023-04-25 2023-04-25 Detachable measuring instrument mounting platform for rapid installation of steel tower construction

Country Status (1)

Country Link
CN (1) CN220016662U (en)

Similar Documents

Publication Publication Date Title
BRPI1105516A2 (en) Anchor cage installation method and installation method for industrial equipment
CN101705693A (en) Method for integrally fixing and installing foundation bolts with large diameter
CN211899725U (en) Vertical prefabricated component auxiliary installation equipment
CN103061524B (en) Movable copying positioning frame of steel structure complex joint
CN220016662U (en) Detachable measuring instrument mounting platform for rapid installation of steel tower construction
CN212452310U (en) First section steel anchor box positioning accuracy adjusting device of cable-stay bridge
CN110748156B (en) Sliding positioning top supporting structure of large silo and construction method thereof
CN219298471U (en) Connection structure of assembled steel structure post
CN112320580B (en) Method for mounting workshop crane beam
CN210089699U (en) Forced centering device and forced centering assembly
CN107860376B (en) Measuring and positioning method for tripod of large-scale intercooling tower cone section
CN217870977U (en) Adjustable supporting device for assembling net rack on ground
CN111058642A (en) Vertical prefabricated part auxiliary installation equipment and use method thereof
CN219757373U (en) Frame convenient for adjusting position of measuring equipment
CN219910180U (en) Counter type landscape PC component for architectural decoration
CN216809669U (en) Warning device for building engineering
CN215374033U (en) Attached measuring support for super high-rise steel column
CN216109628U (en) Quick mounting platform in narrow and small space of extensible
CN215182455U (en) High-stability signal lamp pole
CN218931504U (en) Steel tower column segment adjusting and positioning tool
CN219866625U (en) Floor inclined pipeline fixing device
CN219772734U (en) Positioning assembly for assembling arch ribs
CN219061115U (en) Upright post for heliostat
CN220807264U (en) Communication equipment is convenient for install and detects platform
CN219432874U (en) Liftable formula total powerstation measures support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Huang Xinwei

Inventor after: Pu Dongxiao

Inventor after: Xiang Xiaomiao

Inventor after: Wang Zipeng

Inventor after: Yang Yang

Inventor after: Wu Xingfu

Inventor after: Zhao Zhilei

Inventor after: Hu Yuhua

Inventor before: Huang Xinwei

Inventor before: Pu Dongxiao

Inventor before: Xiang Xiaomiao

Inventor before: Wang Zipeng

Inventor before: Yang Yang

Inventor before: Wu Xingfu

Inventor before: Zhao Zhilei

Inventor before: Hu Yuhua

CB03 Change of inventor or designer information