CN219931616U - Building templates connects steelframe - Google Patents

Building templates connects steelframe Download PDF

Info

Publication number
CN219931616U
CN219931616U CN202320851756.1U CN202320851756U CN219931616U CN 219931616 U CN219931616 U CN 219931616U CN 202320851756 U CN202320851756 U CN 202320851756U CN 219931616 U CN219931616 U CN 219931616U
Authority
CN
China
Prior art keywords
steel frame
connecting steel
connection
steelframe
building templates
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320851756.1U
Other languages
Chinese (zh)
Inventor
徐淑玮
陈曦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN202320851756.1U priority Critical patent/CN219931616U/en
Application granted granted Critical
Publication of CN219931616U publication Critical patent/CN219931616U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a building template connecting steel frame, which is characterized in that when concrete pouring is carried out, building templates are spliced and placed to a designated position, then a first connecting steel frame and a second connecting steel frame are turned over and opened and sleeved on the surface of the building templates, and then the building templates are combined, wherein clamping plates in the inner walls of the first connecting steel frame and the second connecting steel frame have a certain buffering effect on the expansion force in the later concrete pouring process under the action of elastic potential energy of a tension spring, the phenomenon that the building templates are expanded under the tension force is avoided, the first connecting steel frame and the second connecting steel frame are mutually attached under the action of a positioning component, a plurality of clamping plates attached to the surface of the building templates on the inner walls of the first connecting steel frame and the second connecting steel frame are limited, and the rectangular frame formed by the first connecting steel frame and the second connecting steel frame is enabled to be more stable, and the phenomenon that gaps are easily expanded is not easy to occur.

Description

Building templates connects steelframe
Technical Field
The utility model relates to the technical field of connection steel frame auxiliary devices for civil engineering, in particular to a building template connection steel frame.
Background
Civil engineering is a generic term of science and technology for constructing various land engineering facilities, which refers to both applied materials and equipment and technical activities such as survey, design, construction, maintenance, repair and the like performed, and also refers to engineering construction objects, namely various engineering facilities which are constructed on the ground or underground and land and serve for human life, production, military and scientific research, such as houses, roads, railways, pipelines, tunnels, bridges, canals, dykes, ports, power stations, airports, ocean platforms, water supply and drainage, protection engineering and the like, and civil engineering refers to engineering entities which are completed by various technical works such as investigation, planning, design, construction, installation and maintenance performed for buildings, structures, related supporting facilities and the like of new, reconstructed or expanded projects, in addition to house construction.
The construction template is a temporary supporting structure, is manufactured according to design requirements, enables concrete structures and components to be formed according to specified positions and geometric dimensions, keeps the correct positions, bears the self weight of the construction template and external loads acting on the self weight of the construction template, and performs template engineering, so that the quality and construction safety of the concrete engineering are guaranteed, the construction progress is quickened, the engineering cost is reduced, when a connecting steel frame is connected on the used construction template, a constructor needs to use a connecting structure to connect the connecting steel frame at a plurality of positions, the connecting steel frame is troublesome, gaps can be formed in the construction template due to the expansion force during concrete pouring after connection, the concrete is promoted to leak, the working efficiency is required to be finished again, and the connecting steel frame of the construction template is greatly reduced.
Disclosure of Invention
1. Technical problem to be solved
The utility model aims to solve the problems in the prior art, and provides a building template connecting steel frame.
2. Technical proposal
In order to solve the problems, the utility model adopts the following technical scheme.
The utility model provides a building templates connects steelframe, includes building templates, building templates's outer pot head is equipped with first connection steelframe and second connection steelframe, the pivot is installed to the linking department of first connection steelframe, second connection steelframe, locating component is installed to the outer end of first connection steelframe, second connection steelframe, be equipped with four equiangular distribution's grip block between the inner wall of first connection steelframe, second connection steelframe, four fixedly connected with extension spring between grip block and the inner wall of first connection steelframe, second connection steelframe.
Further, the locating component comprises a limiting hook which is rotationally connected with the outer end of the first connecting steel frame, the outer end of the second connecting steel frame is fixedly connected with a base, a pin shaft is inserted between the inner walls of the base, the outer end of the pin shaft is rotationally connected with a connecting plate, and the side end of the connecting plate is rotationally connected with a limiting collar.
Furthermore, a protective pad is adhered to the inner wall of the clamping plate, and the protective pad is made of nylon materials.
Further, the right end of the connecting plate is fixedly connected with a pulling handle, and anti-skidding lines are formed in the inner wall of the pulling handle.
Furthermore, the first connecting steel frame and the second connecting steel frame are made of stainless steel materials, and antirust paint is coated on the surfaces of the first connecting steel frame and the second connecting steel frame.
3. Advantageous effects
Compared with the prior art, the utility model has the following beneficial effects:
this scheme is when carrying out concrete placement, at first place building templates concatenation to the assigned position, then turn over first connection steelframe, the second connection steelframe is opened, the cover is established to the building templates surface, later merge, wherein, first connection steelframe, grip block in the second connection steelframe inner wall, because under the effect of extension spring elastic potential energy, can have certain cushioning effect to the tensile force when later stage concrete placement, avoid building templates to receive the phenomenon emergence that the tension is expanded, then under the effect through locating component, make first connection steelframe, the second connection steelframe laminate each other, inject a plurality of grip blocks of its inner wall laminating building templates surface, and make the rectangular frame that first connection steelframe, second connection steelframe formed more stable, the phenomenon emergence of difficult emergence expansion emergence gap.
Drawings
FIG. 1 is a schematic view of the overall structure of the present utility model;
FIG. 2 is a schematic view of a partial enlarged structure of the portion A in FIG. 1 according to the present utility model;
FIG. 3 is a schematic diagram of the structure of the present utility model.
The reference numerals in the figures illustrate:
the building template comprises a building template 1, a first connecting steel frame 2, a second connecting steel frame 3, a positioning component 4, a limiting hook 41, a base 42, a pin shaft 43, a connecting plate 44, a limiting collar 45, a pulling handle 46, a tension spring 5, a clamping plate 6 and a protective pad 61.
Detailed Description
The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model; it is apparent that the described embodiments are only some embodiments of the present utility model, not all embodiments, and that all other embodiments obtained by persons of ordinary skill in the art without making creative efforts based on the embodiments in the present utility model are within the protection scope of the present utility model.
Examples:
referring to fig. 1-3, a building template connecting steel frame comprises a building template 1, a first connecting steel frame 2 and a second connecting steel frame 3 are sleeved at the outer end of the building template 1, a rotating shaft is arranged at the joint of the first connecting steel frame 2 and the second connecting steel frame 3, a positioning component 4 is arranged at the outer ends of the first connecting steel frame 2 and the second connecting steel frame 3, four clamping plates 6 distributed at equal angles are arranged between the inner walls of the first connecting steel frame 2 and the second connecting steel frame 3, and a plurality of extension springs 5 are fixedly connected between the four clamping plates 6 and the inner walls of the first connecting steel frame 2 and the second connecting steel frame 3.
This scheme is in the use, in order to avoid the step that the connection steelframe that uses among the prior art need use the connection structure of a plurality of positions just can carry out the linking, and when concrete placement, its tension promotes the building templates who makes the connection steelframe centre gripping and appears the gap, cause the phenomenon of seepage to take place, in this embodiment, when carrying out concrete placement, at first, splice building templates 1 and place to the assigned position, then at the upset of connecting steelframe 2, second connection steelframe 3 is opened, the cover is established to building templates 1 surface, later merge, wherein, the clamping plate 6 in the steelframe 3 inner wall is connected to first connection steelframe 2, the second, because under the effect of extension spring 5 elastic potential energy, can have certain cushioning effect to the tensile force when concrete placement in later stage, avoid building templates 1 to receive the phenomenon emergence of expanding, then under the effect through locating component 4, make first connection steelframe 2, second connection steelframe 3 laminate each other, inject a plurality of clamping plates 6 on its inner wall 1 surface, and make first connection steelframe 2, the phenomenon that the second connection rectangle forms the frame emergence of the gap more stable phenomenon of expanding, the phenomenon emergence of the phenomenon of the frame that does not take place.
Referring to fig. 1-3, the positioning assembly 4 includes a limiting hook 41 rotatably connected to the outer end of the first connecting steel frame 2, a base 42 fixedly connected to the outer end of the second connecting steel frame 3, a pin 43 interposed between the inner walls of the base 42, a connecting plate 44 rotatably connected to the outer end of the pin 43, and a limiting collar 45 rotatably connected to the side end of the connecting plate 44.
In the use of this scheme, when needs link up locking with building templates 1, it is under the conflict through grip block 6 to and combine under first connection steelframe 2, second connection steelframe 3 and wrap up building templates 1, then rotate spacing hook 41 to base 42 one side, and rotate the joint board 44 thereupon, make spacing lantern ring 45 can place in spacing hook 41 arcwall face, later press joint board 44 to second connection steelframe 3 one side, make under the effect of tensile force, cause first connection steelframe 2, the position between the second connection steelframe 3 is prescribe a limit to, avoid the later stage to appear expanding and appear the phenomenon of gap, also avoided among the prior art simultaneously, need use the step that just can link up of the connection structure of a plurality of positions, in order to improve installation effectiveness.
Referring to fig. 2-3, a protective pad 61 is adhered to the inner wall of the clamping plate 6, and the protective pad 61 is made of nylon material.
In the use process of the scheme, the protection pad 61 made of the bonding nylon material can greatly reduce the damage between the clamping plate 6 and the building template 1, avoid the phenomenon of excessive abrasion caused by friction and prolong the service life of the protection pad.
Referring to fig. 1-2, a pulling handle 46 is fixedly connected to the right end of the engagement plate 44, and anti-slip patterns are formed on the inner wall of the pulling handle 46.
This scheme has been through fixed connection pulling handle 46 and set up anti-skidding line at its surface in the use, can make the staff can be more convenient when rotating the joint board 44, and the difficult phenomenon of pulling out the hand and being difficult to the knot takes place.
Referring to fig. 1 and 3, the first connection steel frame 2 and the second connection steel frame 3 are made of stainless steel materials, and the surfaces of the first connection steel frame and the second connection steel frame are coated with antirust paint.
According to the scheme, in the use process, the first connecting steel frame (2) and the second connecting steel frame (3) which are made of stainless steel materials can be used, so that the phenomena of rust on the first connecting steel frame (2) and the second connecting steel frame (3) caused by air erosion can be greatly reduced in daily use, and the service life of the stainless steel connecting steel frame is prolonged.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a building templates connects steelframe, includes building templates (1), its characterized in that: the outer pot head of building templates (1) is equipped with first connection steelframe (2) and second connection steelframe (3), the pivot is installed in the linking department of first connection steelframe (2), second connection steelframe (3), locating component (4) are installed to the outer end of first connection steelframe (2), second connection steelframe (3), be equipped with clamping plate (6) of four equiangular distributions between the inner wall of first connection steelframe (2), second connection steelframe (3), four fixedly connected with extension spring (5) between clamping plate (6) and the inner wall of first connection steelframe (2), second connection steelframe (3).
2. The building form connection steel frame according to claim 1, wherein: the locating component (4) comprises a limiting hook (41) which is connected with the outer end of the first connecting steel frame (2) in a rotating mode, a base (42) is fixedly connected with the outer end of the second connecting steel frame (3), a pin shaft (43) is inserted between the inner walls of the base (42), a connecting plate (44) is connected with the outer end of the pin shaft (43) in a rotating mode, and a limiting lantern ring (45) is connected with the side end of the connecting plate (44) in a rotating mode.
3. The building form connection steel frame according to claim 1, wherein: the inner wall of the clamping plate (6) is adhered with a protective pad (61), and the protective pad (61) is made of nylon materials.
4. A building form connection steel frame according to claim 2, wherein: the right end of the connecting plate (44) is fixedly connected with a pulling handle (46), and anti-skidding lines are formed in the inner wall of the pulling handle (46).
5. The building form connection steel frame according to claim 1, wherein: the first connecting steel frame (2) and the second connecting steel frame (3) are made of stainless steel materials, and antirust paint is coated on the surfaces of the first connecting steel frame and the second connecting steel frame.
CN202320851756.1U 2023-04-17 2023-04-17 Building templates connects steelframe Active CN219931616U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320851756.1U CN219931616U (en) 2023-04-17 2023-04-17 Building templates connects steelframe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320851756.1U CN219931616U (en) 2023-04-17 2023-04-17 Building templates connects steelframe

Publications (1)

Publication Number Publication Date
CN219931616U true CN219931616U (en) 2023-10-31

Family

ID=88500999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320851756.1U Active CN219931616U (en) 2023-04-17 2023-04-17 Building templates connects steelframe

Country Status (1)

Country Link
CN (1) CN219931616U (en)

Similar Documents

Publication Publication Date Title
CN103982045A (en) Installation construction method of roof lattice shell structure without supports and cantilevers
CN219931616U (en) Building templates connects steelframe
CN111042619A (en) Make things convenient for salvage wire pole of dismouting
CN108166481A (en) Civil engineering pile foundation fixing device
CN110397302A (en) A kind of hoop reinforcement of weld method of round tube steel structure member
CN103806373B (en) Oblique pull assembly type steel bridge on highway suspension cable anchor system
CN216578465U (en) Quick curing means of concrete pointed pile
CN105019557A (en) Flying-wing-type formwork space truss structure and construction method thereof
CN214302749U (en) Civil engineering construction support
CN213829521U (en) Integral telescopic core mould device for highway prefabricated box girder
CN211201161U (en) Building templates link for civil engineering
CN215334872U (en) Pipeline positioning device for municipal works
CN215803112U (en) Wall painting adjustable support for building civil engineering
CN217760046U (en) Building templates connects steelframe for civil engineering
CN213572900U (en) Civil engineering safety scaffold
CN204876064U (en) All -wing aircraft section mould shell space truss structure
CN209104768U (en) A kind of novel multifunctional cable bracket
CN211340455U (en) Bridge building templates link for civil engineering
CN218267626U (en) Platform railing fixing device
CN216737196U (en) Civil engineering pipeline handling device
CN113478622B (en) City piping lane integration pouring device
CN220537366U (en) Hoisting equipment for wind power tower
CN212670555U (en) Combined pile for civil engineering convenient to adjust
CN211872620U (en) Guardrail is used in civil engineering's bridge construction
CN218667589U (en) Splicing protective net for mountain ecological restoration

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant