CN219898794U - Gluing equipment for cable bridge processing - Google Patents

Gluing equipment for cable bridge processing Download PDF

Info

Publication number
CN219898794U
CN219898794U CN202321099165.XU CN202321099165U CN219898794U CN 219898794 U CN219898794 U CN 219898794U CN 202321099165 U CN202321099165 U CN 202321099165U CN 219898794 U CN219898794 U CN 219898794U
Authority
CN
China
Prior art keywords
gluing
glue
cable bridge
box
fixedly installed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321099165.XU
Other languages
Chinese (zh)
Inventor
胡利萍
张家运
张进铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Hengsitai Electric Co ltd
Original Assignee
Wuhan Hengsitai Electric Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Hengsitai Electric Co ltd filed Critical Wuhan Hengsitai Electric Co ltd
Priority to CN202321099165.XU priority Critical patent/CN219898794U/en
Application granted granted Critical
Publication of CN219898794U publication Critical patent/CN219898794U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/10Greenhouse gas [GHG] capture, material saving, heat recovery or other energy efficient measures, e.g. motor control, characterised by manufacturing processes, e.g. for rolling metal or metal working

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a gluing device for processing a cable bridge. The gluing equipment for processing the cable bridge comprises: the automatic glue filling machine comprises a workbench, wherein a first through hole is formed in the workbench, two connecting rods are fixedly arranged at the bottom of the workbench, a glue filling box is fixedly arranged at the bottom end of each connecting rod, a second through hole is formed in the top of the glue filling box, a rotating roller is arranged in the glue filling box in a rotating mode, one end of the rotating roller extends out of the glue filling box, a glue coating cloth is fixedly sleeved on the rotating roller, a rotating motor is fixedly arranged on the outer wall of one side of the glue filling box, and an output shaft of the rotating motor is fixedly connected with one end of the rotating roller, which is located outside the glue filling box. The gluing equipment for processing the cable bridge has the advantages of being convenient to use, simple to operate, capable of preventing glue from dripping and preventing glue from being solidified due to waste.

Description

Gluing equipment for cable bridge processing
Technical Field
The utility model relates to the technical field of cable bridges, in particular to a gluing device for processing a cable bridge.
Background
The cable bridge is widely applied to the electrical construction process, and can be roughly divided into: hot galvanizing, aluminum alloy, stainless steel, glass steel, plastic package steel, polymer bridge and the like, wherein in the processing process of the polymer cable bridge, a plurality of bottom plates can be arranged into a double-layer structure, and the two layers are supported by a row of clamping plates, so that gluing equipment is required to be used for gluing when the cable bridge is produced, and the service life of the cable bridge is prolonged.
However, when the existing gluing equipment is used for gluing the cable bridge, the existing part of glue material is frequently dripped onto the ground from the cable bridge, so that glue material is wasted, economic loss is caused, and if the internal glue material of the existing gluing equipment is not used for a long time, the solidification phenomenon of the glue material is easily caused, so that people cannot uniformly paint the glue material on the cable bridge, and the service life of the cable bridge is affected.
Therefore, it is necessary to provide a new gluing device for processing the cable bridge to solve the above technical problems.
Disclosure of Invention
The utility model solves the technical problem of providing the gluing equipment for processing the cable bridge, which is convenient to use, simple to operate, capable of preventing glue from dripping and wasting and preventing the glue from solidifying.
In order to solve the technical problems, the gluing device for processing a cable bridge, provided by the utility model, comprises: the automatic glue applying device comprises a workbench, wherein a first through hole is formed in the workbench, two connecting rods are fixedly arranged at the bottom of the workbench, a glue mounting box is fixedly arranged at the bottom end of the connecting rods, a second through hole is formed in the top of the glue mounting box, a rotating roller is rotatably arranged in the glue mounting box, one end of the rotating roller extends out of the glue mounting box, a glue applying cloth is fixedly sleeved on the rotating roller, a rotating motor is fixedly arranged on the outer wall of one side of the glue mounting box, an output shaft of the rotating motor is fixedly connected with one end of the rotating roller, which is positioned outside the glue mounting box, two propellers are rotatably arranged in the glue mounting box, the bottom ends of the propellers are all extended to the lower side of the glue mounting box, a double-shaft motor is fixedly arranged below the glue mounting box, two output shafts of the double-shaft motor are respectively fixedly provided with rotating rods, one ends, which are far away from each other, of the rotating rods are respectively fixedly provided with a first bevel gear, the bottom ends of the two propellers are respectively and fixedly provided with second bevel gears, and the two bevel gears are respectively meshed with the second bevel gears correspondingly.
Preferably, a plurality of rolling balls are arranged on the workbench in a rolling way.
Preferably, a fixed pipe is fixedly installed in the first through hole, a plurality of air outlet covers are fixedly installed on the fixed pipe, an air heater is installed at the top of the glue loading box, an air outlet pipe is fixedly installed at the air outlet of the air heater, and one end, far away from the air heater, of the air outlet pipe is fixedly connected with the fixed pipe.
Preferably, a protective cover is fixedly arranged on the outer wall of one side of the glue filling box, and the rotating motor is positioned in the protective cover.
Preferably, a protective box is fixedly arranged at the bottom of the glue filling box, and the double-shaft motor, the first bevel gear and the second bevel gear are all positioned in the protective box.
Preferably, a heat dissipation opening is formed in the bottom of the protection box, and a dust screen is fixedly installed in the heat dissipation opening.
Preferably, four fixing plates are fixedly arranged at the bottom of the glue filling box, through holes are respectively formed in the four fixing plates, bearings are respectively and fixedly arranged in the four through holes, and the two rotating rods respectively penetrate through the corresponding two bearings and are fixedly connected with the inner walls of the corresponding bearings.
Compared with the related art, the gluing equipment for processing the cable bridge has the following beneficial effects:
the utility model provides glue coating equipment for processing a cable bridge, which is characterized in that a cable bridge is placed on a workbench to move and contact glue coating cloth, glue in a glue loading box is driven to be coated on the cable bridge through rotation of a rotating motor, excessive glue can drop into the glue loading box under the action of gravity, glue waste is prevented, high-temperature hot air generated by a hot air blower is sprayed onto the cable bridge from an air outlet cover through a fixed pipe and an air outlet pipe, the cable bridge coated with the glue is dried rapidly, the working efficiency is improved, and a screw is driven to rotate through rotation of a double-shaft motor, so that the glue in the glue loading box is always in a flowing state, and the phenomenon of solidification of the glue is prevented from occurring, and unnecessary troubles are prevented.
Drawings
FIG. 1 is a schematic diagram of a gluing device for cable bridge processing according to a preferred embodiment of the present utility model;
FIG. 2 is an enlarged schematic view of portion A shown in FIG. 1;
FIG. 3 is an enlarged schematic view of portion B shown in FIG. 1;
fig. 4 is a top view of the table shown in fig. 1.
Reference numerals in the drawings: 1. a work table; 2. a connecting rod; 3. filling a glue box; 4. a propeller; 5. a biaxial motor; 6. a rotating roller; 7. coating adhesive tape; 8. a rotating lever; 9. a first bevel gear; 10. a second bevel gear; 11. an air heater; 12. a fixed tube; 13. an air outlet pipe; 14. an air outlet cover; 15. rolling the ball; 16. and rotating the motor.
Description of the embodiments
The utility model will be further described with reference to the drawings and embodiments.
Referring to fig. 1 to fig. 4 in combination, fig. 1 is a schematic structural diagram of a preferred embodiment of a gluing device for processing a cable bridge according to the present utility model; FIG. 2 is an enlarged schematic view of portion A shown in FIG. 1; FIG. 3 is an enlarged schematic view of portion B shown in FIG. 1; fig. 4 is a top view of the table shown in fig. 1. The gluing equipment for processing the cable bridge comprises: in order to enable people to move a cable bridge on the workbench 1 more effort-saving, a plurality of rolling round beads 15 are arranged on the workbench 1 in a rolling way, a first through hole is formed in the workbench 1, two connecting rods 2 are fixedly arranged at the bottom of the workbench 1, a glue containing box 3 is fixedly arranged at the bottom ends of the two connecting rods 2, a second through hole is formed in the top of the glue containing box 3, a rotating roller 6 is rotatably arranged in the glue containing box 3, one end of the rotating roller 6 extends out of the glue containing box 3, a rubberizing fabric 7 is fixedly sleeved on the rotating roller 6, the rotating roller 6 is driven to rotate through rotation of a rotating motor 16, glue in the glue containing box 3 is smeared on the cable bridge by rotation of the rotating roller 6, when more glue is smeared on the cable bridge, redundant glue can drop into the glue containing box 3 under the action of gravity, the fact that the glue is wasted is prevented from being fixedly arranged on the outer wall of one side of the glue containing box 3, the output shaft of the rotating motor 16 is fixedly connected with one end of the rotating roller 6 positioned outside the glue box 3, in order to protect the rotating motor 16 and prevent external objects from impacting the rotating motor 16, the damage of the rotating motor 16 is caused, the service life is influenced, a protective cover is fixedly arranged on the outer wall of one side of the glue box 3, the rotating motor 16 is positioned in the protective cover, two propellers 4 are rotatably arranged in the glue box 3, the bottom ends of the two propellers 4 extend to the lower side of the glue box 3, a double-shaft motor 5 is fixedly arranged below the glue box 3, rotating rods 8 are respectively fixedly arranged on the two output shafts of the double-shaft motor 5, one ends, far away from each other, of the two rotating rods 8 are respectively fixedly provided with a first conical gear 9, the bottom ends of the two propellers 4 are respectively fixedly provided with a second conical gear 10, and two second bevel gears 10 mesh with corresponding first bevel gears 9 respectively, rotate through biax motor 5 and drive dwang 8 rotation, dwang 8 rotates and drives first bevel gear 9 rotation, and first bevel gear 9 rotates and drives second bevel gear 10 rotation, and second bevel gear 10 rotates and drives screw 4 rotation, makes the sizing material in the dress glue case 3 be in the state of flowing all the time through screw 4 rotation, prevents that the sizing material from taking place the solidification phenomenon.
In order to carry out quick drying to the cable bridge frame coated with sizing material, improve work efficiency, fixed pipe 12 is fixedly installed in the first through hole, fixed pipe 12 is last to be fixedly installed with a plurality of air-out cover 14, air heater 11 is installed at the top of dress gluey case 3, air outlet department fixed mounting of air heater 11 has air-out pipe 13, and air-out pipe 13 keeps away from air heater 11's one end and fixed pipe 12 fixed connection, through fixed pipe 12, air-out pipe 13 with the high temperature steam that air heater 11 produced from air-out cover 14 blowout to the cable bridge frame on, carry out quick drying to the cable bridge frame coated with sizing material.
In order to protect biax motor 5, first conical gear 9 and second conical gear 10, prevent that external object from bumping on biax motor 5, first conical gear 9 and the second conical gear 10, influence life, the bottom fixed mounting of dress gum case 3 has the protective housing, and biax motor 5, first conical gear 9, second conical gear 10 all are located the protective housing, in order to make the quick giving off to the external world of heat that biax motor 5 during operation produced, the thermovent has been seted up to the bottom of protective housing, and fixed mounting has the dust screen in the thermovent, prevent through the dust screen that external dust from getting into the protective housing in adhesion on first conical gear 9 and second conical gear 10, influence life.
In order to make the rotation of the rotating rod 8 more stable, four fixing plates are fixedly arranged at the bottom of the glue box 3, through holes are respectively formed in the four fixing plates, bearings are respectively and fixedly arranged in the four through holes, and the two rotating rods 8 respectively penetrate through the corresponding two bearings and are fixedly connected with the inner walls of the corresponding bearings.
The utility model provides a gluing device for cable bridge processing, which has the following working principle: when the device is needed to be used, a cable bridge is placed on a workbench 1, the cable bridge is moved to be in contact with a rubberized fabric 7, a rotating motor 16 is started, the rotating motor 16 rotates to drive a rotating roller 6 to rotate, the rotating roller 6 rotates to smear the rubberized fabric in the rubberized fabric box 3 on the cable bridge, when more rubberized fabric is smeared on the cable bridge, excessive rubberized fabric can drop into the rubberized fabric box 3 under the action of gravity, an air heater 11 is started, high-temperature hot air generated by the air heater 11 is sprayed onto the cable bridge from an air outlet cover 14 through a fixed pipe 12 and an air outlet pipe 13, the cable bridge smeared with the rubberized fabric is quickly dried, the working efficiency is improved, a double-shaft motor 5 is started, the rotating shaft motor 5 rotates to drive a rotating rod 8 to rotate, the rotating rod 8 rotates to drive a first conical gear 9 to rotate, the first conical gear 9 rotates to drive a second conical gear 10 to rotate, the second conical gear 10 rotates to drive a propeller 4, the rubberized fabric in the rubberized fabric box 3 is always in a flowing state through the rotation of the propeller 4, and the rubberized fabric is prevented from being solidified.
Compared with the related art, the gluing equipment for processing the cable bridge has the following beneficial effects:
the utility model provides glue coating equipment for processing a cable bridge, which is characterized in that a cable bridge is placed on a workbench 1 to move and contact glue coating cloth 7, glue in a glue containing box 3 is driven to be coated on the cable bridge by rotation of a rotating motor 16, excessive glue can drop into the glue containing box 3 under the action of gravity, glue waste is prevented from being caused, high-temperature hot air generated by an air heater 11 is sprayed onto the cable bridge from an air outlet cover 14 through a fixed pipe 12 and an air outlet pipe 13, the cable bridge coated with the glue is dried rapidly, the working efficiency is improved, and the screw 4 is driven to rotate by rotation of a double-shaft motor 5, so that the glue in the glue containing box 3 is always in a flowing state, and solidification of the glue is prevented.
The foregoing description is only illustrative of the present utility model and is not intended to limit the scope of the utility model, and all equivalent structures or equivalent processes or direct or indirect application in other related technical fields are included in the scope of the present utility model.

Claims (7)

1. The utility model provides a cable testing bridge processing is with rubber coating equipment, includes workstation, its characterized in that: the utility model provides a first through-hole has been seted up on the workstation, the bottom fixed mounting of workstation has two linking rods, two the bottom fixed mounting of linking rod has the installation case of gluing, just the second through-hole has been seted up at the top of installation case of gluing, install the rotor roll in the case of gluing, just the one end of rotor roll extends to outside the installation case of gluing, fixed cover is equipped with the rubberizing cloth on the rotor roll, fixed mounting has rotating electrical machines on one side outer wall of installation case of gluing, just rotating electrical machines's output shaft with the rotor roll is located the one end fixed connection outside the installation case of gluing, install two propellers in the installation case of gluing, and two the bottom of propellers all extends to the below of installation case of gluing, the below fixed mounting biax motor of installation case of gluing, just respectively fixed mounting has the rotor bar on two the output shafts of biax motor, two the one end that the rotor bar kept away from each other is fixed mounting has first bevel gear respectively, two the bottom fixed mounting has the second bevel gear respectively, and two bevel gears respectively mesh mutually corresponding with the second bevel gear.
2. The gluing device for cable bridge processing according to claim 1, wherein a plurality of rolling beads are mounted on the workbench in a rolling manner.
3. The gluing device for cable bridge processing according to claim 1, wherein a fixed pipe is fixedly installed in the first through hole, a plurality of air outlet covers are fixedly installed on the fixed pipe, a hot air blower is installed at the top of the glue loading box, an air outlet pipe is fixedly installed at an air outlet of the hot air blower, and one end, far away from the hot air blower, of the air outlet pipe is fixedly connected with the fixed pipe.
4. A gluing device for processing a cable bridge according to claim 3, wherein a protective cover is fixedly installed on the outer wall of one side of the glue box, and the rotating motor is located in the protective cover.
5. The gluing device for cable bridge processing according to claim 1, wherein a protective box is fixedly installed at the bottom of the glue box, and the double-shaft motor, the first bevel gear and the second bevel gear are all located in the protective box.
6. The gluing device for cable bridge processing according to claim 5, wherein a heat dissipation opening is formed in the bottom of the protective box, and a dust screen is fixedly installed in the heat dissipation opening.
7. The gluing device for cable bridge processing according to claim 5, wherein four fixing plates are fixedly installed at the bottom of the glue box, through holes are respectively formed in the four fixing plates, bearings are respectively fixedly installed in the four through holes, and two rotating rods respectively penetrate through the corresponding two bearings and are fixedly connected with the inner walls of the corresponding bearings.
CN202321099165.XU 2023-05-09 2023-05-09 Gluing equipment for cable bridge processing Active CN219898794U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321099165.XU CN219898794U (en) 2023-05-09 2023-05-09 Gluing equipment for cable bridge processing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321099165.XU CN219898794U (en) 2023-05-09 2023-05-09 Gluing equipment for cable bridge processing

Publications (1)

Publication Number Publication Date
CN219898794U true CN219898794U (en) 2023-10-27

Family

ID=88465848

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321099165.XU Active CN219898794U (en) 2023-05-09 2023-05-09 Gluing equipment for cable bridge processing

Country Status (1)

Country Link
CN (1) CN219898794U (en)

Similar Documents

Publication Publication Date Title
CN111532909B (en) Winding processing machine for heat preservation belt of petroleum conveying pipeline
CN112502404B (en) Processing system is used in construction of building outer wall heat insulation wall structure
CN219898794U (en) Gluing equipment for cable bridge processing
CN113620099B (en) Electrician's insulating tape rolling lapping machine
US20240085308A1 (en) Rain erosion test device and system
CN110743759A (en) Adhesive tape production and preparation process
CN112742673A (en) Efficient gumming device is used in former cloth processing
CN112002662A (en) High-speed multifunctional automatic chip mounter for semiconductor production
CN213845868U (en) Switch board with dehumidification is removed dust
CN111250346A (en) Fastener dip coating device with drying function
CN211390586U (en) Plastic film drying equipment
CN111715483A (en) Ink coating device and ink coating method
CN209866496U (en) Coating device with environmental protection performance for steel plate processing
CN215030707U (en) Be used for sensor processing to use silica gel coating device
CN205966344U (en) Automatic glue coater of excircle
CN212434588U (en) Silicon wafer etching device
CN110920246B (en) Oil passing process and equipment for leaflet production
CN209303117U (en) A kind of semi-automatic painting thermal grease device
CN219604784U (en) Trowelling mechanism for wallpaper paint
CN111910890A (en) High-efficient 2D wall paint spraying apparatus for building
CN216544949U (en) Paste firm packing printing with sticking with paste box machine
CN114538308B (en) Tower crane rotation transmission mechanism, rotation control device and tower crane
CN220532053U (en) Full static pressure clean optical film coating machine
CN213982944U (en) Machine part cleaning equipment
CN114392891B (en) Coating device for release film and convenient to change coating head based on PLC control

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant