CN219809525U - Underground utility tunnel control box installation gallows device - Google Patents

Underground utility tunnel control box installation gallows device Download PDF

Info

Publication number
CN219809525U
CN219809525U CN202321341128.5U CN202321341128U CN219809525U CN 219809525 U CN219809525 U CN 219809525U CN 202321341128 U CN202321341128 U CN 202321341128U CN 219809525 U CN219809525 U CN 219809525U
Authority
CN
China
Prior art keywords
control box
angle steel
steel
box body
threading
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321341128.5U
Other languages
Chinese (zh)
Inventor
吕仁俊
董海洋
刘即勇
潘洋洋
胡标
肖继宗
刘洪�
徐思
刘楠
邓国强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Electrification Engineering Co Ltd of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Electrification Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Electrification Engineering Co Ltd of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN202321341128.5U priority Critical patent/CN219809525U/en
Application granted granted Critical
Publication of CN219809525U publication Critical patent/CN219809525U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses an underground comprehensive pipe gallery control box mounting hanging bracket device which comprises a first angle steel and a bracket mechanism arranged at the lower end of the first angle steel, wherein the upper end of the first angle steel is fixedly connected with the top wall of a pipe gallery, a control box body is arranged on the bracket mechanism, and a pipeline mechanism is fixedly arranged at the upper end of the control box body. The utility model has simple structure, the hanging bracket device is fixed on the top wall of the underground comprehensive pipe rack, and the control box is arranged on the hanging bracket device, so that the traditional installation mode of the control box is changed from the traditional wall-attached installation, vertical installation, end installation and the like to the hanging installation of the rack top, the arrangement paths of the threading steel pipes and the threading cables are changed, the material cost is saved, the construction difficulty is reduced, the construction period is shortened, the shielding problem of the subsequent pipeline entering the rack is avoided, the length of the pipeline arrangement path and the bending quantity are reduced, and the space of the cabin can be fully utilized.

Description

Underground utility tunnel control box installation gallows device
Technical Field
The utility model relates to the technical field of installation of underground comprehensive pipe rack control boxes, in particular to an installation hanging bracket device of an underground comprehensive pipe rack control box.
Background
The urban underground comprehensive pipe gallery is used as a national important civil engineering, and the construction of the pipe gallery plays an important role in improving urban functions and improving urban comprehensive bearing capacity, so that the urban comprehensive pipe gallery is highly valued by the country. In the electromechanical installation engineering of the urban underground comprehensive pipe rack, a plurality of various control boxes (such as an industrial overhaul socket box, a drainage pump control box and the like) are often required to be installed in the pipe rack so as to meet the operation and maintenance requirements of the later pipe rack, and after the control boxes are put into use, powerful protection is provided for the inspection and overhaul in the operation stage, because after the pipe rack enters the operation stage, a plurality of operations in the rack are completed by providing kinetic energy through the control boxes, otherwise, the reliable operation of the pipe rack is directly influenced.
At present, the underground comprehensive pipe rack control box is installed by adopting the modes of adherence, independent bracket vertical installation, pipe rack end installation and the like, but in actual construction, if the arrangement mode is adopted, the material usage amount of the steel pipes and the cables is increased firstly; secondly, the construction difficulty is increased; thirdly, the cabin space is occupied, and therefore the underground comprehensive pipe gallery control box hanging bracket device is provided.
Disclosure of Invention
The utility model aims to provide an installation hanging bracket device for an underground comprehensive pipe rack control box, which aims to solve the problems that the underground comprehensive pipe rack control box is high in material usage amount of steel pipes and cables, high in construction difficulty and large in cabin space occupation during assembly.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides an underground utility tunnel control box installation gallows device, includes first angle steel and installs the bracket mechanism at first angle steel lower extreme, the upper end of first angle steel is connected fixedly with the roof of piping lane, install the control box body on the bracket mechanism, the upper end of control box body is equipped with pipeline mechanism.
As a further scheme of the utility model: the support mechanism comprises two telescopic parts arranged at the lower end of the first angle steel, the two telescopic parts are fixedly connected through a connecting part, and the control box body is arranged on the connecting part.
As a further scheme of the utility model: the telescopic part comprises a second angle steel arranged at the lower end of the first angle steel, a telescopic part is arranged at the end part of the second angle steel, which is far away from the first angle steel, and a third angle steel is arranged at the end part of the telescopic part, which is far away from the second angle steel.
As a further scheme of the utility model: the connecting portion comprises two first flat steels arranged between two third flat steels, a second flat steel arranged above the first flat steels is arranged between the two third flat steels, two cross grooves are formed in the first flat steels, and an adjusting bolt penetrating through the cross grooves and connected with the control box body is arranged on the first flat steels.
As a further scheme of the utility model: the pipeline mechanism comprises a threading steel pipe arranged at the upper end of the control box body, and a threading cable arranged in the threading steel pipe is arranged at the upper end of the control box body.
As a further scheme of the utility model: the outer peripheral surface of the threading steel pipe is provided with a clamping ring for fixing the threading steel pipe on the second flat steel.
As a further scheme of the utility model: the snap ring is U-shaped, and the inner arc of the snap ring is matched with the outer arc of the threading steel pipe.
As a further scheme of the utility model: two mounting holes close to the end are formed in the upper end of the first angle steel, and the mounting holes are far away from each other.
Compared with the prior art, the utility model has the beneficial effects that: the utility model has novel structure, the hanging bracket device is fixed on the top wall of the underground comprehensive pipe rack, and the control box is arranged on the hanging bracket device, so that the traditional installation mode of the control box is changed from the traditional wall-attached installation, vertical installation, end installation and the like to the hanging installation of the rack top, the arrangement paths of the threading steel pipes and the threading cables are changed, the material cost is saved, the construction difficulty is reduced, the construction period is shortened, the shielding problem of the subsequent pipeline entering the rack is avoided, the length of the pipeline arrangement path and the bending quantity are reduced, and the space of the cabin can be fully utilized.
Drawings
FIG. 1 is a schematic view of a hanger apparatus of the present utility model;
FIG. 2 is a rear schematic view of the hanger apparatus of the present utility model;
FIG. 3 is a schematic view of a first flat steel according to the present utility model;
FIG. 4 is a schematic view of another embodiment of a snap ring connection of the present utility model;
in the figure: 1. a first angle steel; 2. a second angle steel; 3. a telescoping member; 4. a third angle steel; 5. a first flat steel; 6. a second flat steel; 7. a cross groove; 8. a control box body; 9. an adjusting bolt; 10. threading the steel pipe; 11. threading the cable; 12. a clasp; 13. and (5) mounting holes.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-4, in an embodiment of the present utility model, an installation hanger device for an underground utility tunnel control box includes a first angle steel 1 and a bracket mechanism installed at the lower end of the first angle steel 1, wherein the upper end of the first angle steel 1 is fixedly connected with the top wall of the pipe tunnel, a control box body 8 is installed on the bracket mechanism, and a pipeline mechanism is fixed at the upper end of the control box body 8.
During the use, through fixing the support mechanism of first angle steel 1 lower extreme in the top of utility tunnel, the effectual consumption that reduces pipeline mechanism reduces the construction degree of difficulty, promotes the work efficiency, has effectively avoided the risk that is blocked when follow-up various income corridor cable lays simultaneously, makes equipment reach best service condition.
Referring to fig. 1, in one embodiment, in order to facilitate adjusting the height of the control box body 8, in this embodiment, preferably, the bracket mechanism includes two telescopic parts installed at the lower end of the first angle steel 1, the two telescopic parts are connected and fixed through a connecting part, and the control box body 8 is installed on the connecting part.
When the control box is used, the position of the control box body 8 is conveniently fixed under the action of the connecting part, and meanwhile, the height of the control box body 8 is adjusted under the action of the telescopic part.
Referring to fig. 1, in one embodiment, in order to facilitate adjusting the height of the control box body 8, in this embodiment, preferably, the telescopic portion includes a second angle steel 2 installed at the lower end of the first angle steel 1, a telescopic member 3 is installed at the end of the second angle steel 2 away from the first angle steel 1, and a third angle steel 4 is installed at the end of the telescopic member 3 away from the second angle steel 2.
When the novel clothes hanger is used, a worker pulls the third angle steel 4, so that the total length of the second angle steel 2, the telescopic piece 3 and the third angle steel 4 is changed, when the third angle steel 4 is pulled downwards, the total length of the second angle steel 2, the telescopic piece 3 and the third angle steel 4 is prolonged, the height of the control box body 8 is reduced, when the third angle steel 4 is pushed upwards, the total length of the second angle steel 2, the telescopic piece 3 and the third angle steel 4 is shortened, the locking sleeve on the telescopic piece 3 is rotated, the fixing and adjusting of the second angle steel 2 and the third angle steel 4 in the telescopic piece 3 can be realized (the fixing and adjusting principle of the telescopic piece 3 is the same as that of a telescopic clothes hanger in the prior art, and excessive redundant description is not made here), and the height of the control box body 8 is increased.
Referring to fig. 2, in one embodiment, in order to facilitate fixing the position of the control box body 8, in this embodiment, preferably, the connection portion includes two first flat steels 5 installed between two third flat steels 4, a second flat steel 6 located above the first flat steels 5 is disposed between the two third flat steels 4, two cross grooves 7 are formed on the two first flat steels 5, and an adjusting bolt 9 penetrating through the cross grooves 7 and connected with the control box body 8 is disposed on the first flat steel 5.
When the control box is used, the two first flat steels 5 and the second flat steels 6 can be connected with the two third flat steels 4 together, then the adjusting bolts 9 penetrate through the cross grooves 7 on the first flat steels 5 and are connected with the control box body 8, fine adjustment and correction can be carried out on the position of the control box body 8, the adjusting bolts 9 are screwed down to ensure that the control box body 8 is stably mounted on the first flat steels 5, and the control box body 8 is fixed after accurate positioning so as to ensure that the mounted control box body 8 is in the standard allowable mounting deviation range.
Referring to fig. 2, in one embodiment, the pipeline mechanism preferably includes a threading steel pipe 10 mounted at the upper end of the control box body 8, and a threading cable 11 located in the threading steel pipe 10 is mounted at the upper end of the control box body 8.
During the use, can be located its inside threading cable 11 under the effect of threading steel pipe 10 and protect, avoid threading cable 11 can receive outside influence for threading cable 11 possesses better protective effect under the effect of threading steel pipe 10.
Referring to fig. 1, in an embodiment, in order to reinforce the position of the threading steel pipe 10, in this embodiment, preferably, the outer circumferential surface of the threading steel pipe 10 is provided with a clamping ring 12 for fixing the threading steel pipe on the second flat steel 6, the clamping ring 12 is U-shaped, the inner arc of the clamping ring 12 is matched with the outer arc of the threading steel pipe 10, the connection mode between the second flat steel 6 and the clamping ring 12 is not limited, in this embodiment, preferably, a welding mode can be adopted between the clamping ring 12 and the second flat steel 6, so that the stability of the threading steel pipe 10 can be ensured, and the threading steel pipe 10 is prevented from being deviated when being impacted.
Referring to fig. 4, in another embodiment, in order to facilitate the repeated use of the bracket mechanism, in this embodiment, preferably, the second flat steel 6 and the snap ring 12 are connected by a detachable bolt, so that the subsequent detachment of the snap ring 12 on the second flat steel 6 is facilitated, and multiple applications of the snap ring 12 are facilitated.
Referring to fig. 2, in an embodiment, in order to facilitate the installation of the first angle steel 1 on the top wall of the utility tunnel, in this embodiment, preferably, two mounting holes 13 near the ends are formed at the upper end of the first angle steel 1, and the mounting holes 13 are far away from each other.
When the underground comprehensive pipe rack is used, holes are punched in the top wall of the underground comprehensive pipe rack firstly, then the mounting holes 13 in the first angle steel 1 are aligned with holes in the underground comprehensive pipe rack, and then the end parts of expansion bolts penetrate through the mounting holes 13 in the first angle steel 1 and are driven into the holes in the underground comprehensive pipe rack by constructors, so that the first angle steel 1 is stably mounted at the top of the underground comprehensive pipe rack.
The working principle and the using flow of the utility model are as follows: firstly, fixing a first angle steel 1 on a hanger device at the top of a pipe gallery through an expansion bolt, paying attention to the position of the hanger device, which is positioned outside a cable support and is close to a personnel passage, determining the height of the hanger device according to the design requirement, and adjusting the hanger device through the mutual coordination among a second angle steel 2, a telescopic piece 3 and a third angle steel 4 after the assembly is completed; then, fixing the control box body 8 on the first flat steel 5 on the hanger device through the adjusting bolt 9; finally, firstly, one end of the threading steel pipe 10 and the threading cable 11 are inserted into the inner side of the reserved opening of the bridge frame to be fixed, and then the other end of the threading steel pipe 10 and the threading cable 11 are inserted into the threading opening of the control box body 8 to be fixed.
Although the present disclosure describes embodiments, not every embodiment is described in terms of a single embodiment, and such description is for clarity only, and one skilled in the art will recognize that the embodiments described in the disclosure as a whole may be combined appropriately to form other embodiments that will be apparent to those skilled in the art.
Therefore, the above description is not intended to limit the scope of the utility model; all changes which come within the meaning and range of equivalency of the claims are to be embraced within their scope.

Claims (8)

1. The utility model provides an underground utility tunnel control box installation gallows device, includes first angle steel (1) and installs the bracket mechanism at first angle steel (1) lower extreme, its characterized in that, the upper end of first angle steel (1) is connected fixedly with the roof of piping lane, install control box body (8) on the bracket mechanism, the upper end of control box body (8) has set firmly pipeline mechanism.
2. The underground utility tunnel control box installation hanger device of claim 1, wherein the bracket mechanism comprises two telescopic parts installed at the lower end of the first angle steel (1), the two telescopic parts are fixedly connected through a connecting part, and the control box body (8) is installed on the connecting part.
3. The underground utility tunnel control box installation hanger device of claim 2, wherein the telescoping portion comprises a second angle steel (2) installed at the lower end of the first angle steel (1), the end part of the second angle steel (2) far away from the first angle steel (1) is provided with a telescoping piece (3), and the end part of the telescoping piece (3) far away from the second angle steel (2) is provided with a third angle steel (4).
4. The underground utility tunnel control box installation hanger device according to claim 3, wherein the connecting portion comprises two first flat steels (5) installed between two third angle steels (4), a second flat steel (6) located above the first flat steels (5) is arranged between the two third angle steels (4), two cross grooves (7) are formed in the two first flat steels (5), and an adjusting bolt (9) penetrating through the cross grooves (7) and connected with the control box body (8) is arranged on the first flat steels (5).
5. The underground utility tunnel control box installation hanger device of claim 4, wherein the pipeline mechanism comprises a threading steel pipe (10) installed at the upper end of the control box body (8), and a threading cable (11) located in the threading steel pipe (10) is installed at the upper end of the control box body (8).
6. The underground utility tunnel control box installation hanger device of claim 5, wherein the outer circumferential surface of the threading steel pipe (10) is provided with a snap ring (12) which fixes the threading steel pipe on the second flat steel (6).
7. The underground utility tunnel control box installation hanger device of claim 6, wherein the snap ring (12) is U-shaped and the inner arc of the snap ring (12) is matched with the outer arc of the threaded steel pipe (10).
8. The underground utility tunnel control box installation hanger device of claim 1, wherein the upper end of the first angle steel (1) is provided with two installation holes (13) close to the end, and the installation holes (13) are far away from each other.
CN202321341128.5U 2023-05-29 2023-05-29 Underground utility tunnel control box installation gallows device Active CN219809525U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321341128.5U CN219809525U (en) 2023-05-29 2023-05-29 Underground utility tunnel control box installation gallows device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321341128.5U CN219809525U (en) 2023-05-29 2023-05-29 Underground utility tunnel control box installation gallows device

Publications (1)

Publication Number Publication Date
CN219809525U true CN219809525U (en) 2023-10-10

Family

ID=88216372

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321341128.5U Active CN219809525U (en) 2023-05-29 2023-05-29 Underground utility tunnel control box installation gallows device

Country Status (1)

Country Link
CN (1) CN219809525U (en)

Similar Documents

Publication Publication Date Title
CN205424196U (en) Shaft wind pipe connection
CN204696583U (en) Fire-proof cable bridge rack
CN105819353A (en) Split combined type tower crane wall attaching frame and installation method thereof
CN219809525U (en) Underground utility tunnel control box installation gallows device
CN105781131A (en) Assembled building wall plate mounting support system and construction method thereof
CN205857693U (en) A kind of canalization template being applied to movement joint both sides shear wall synchronous construction
CN104627849B (en) Hoisting equipment and hoisting method for hoisting inner courtyard pipeline
CN105804417A (en) Sway brace for installation of assembly type building wallboard and using method thereof
CN215479321U (en) Tower crane that can have enough to meet need use attaches wall auxiliary fixture
CN219045733U (en) Approach lamp integrated with isolation transformer
CN217539902U (en) Large-span straight pipeline mounting structure
CN214793345U (en) Gas metering cabinet
CN212908898U (en) Piping lane support with adjustable
CN219697114U (en) Tail cable pipeline laying device for coal face
CN215009543U (en) Arc-shaped cable support
CN218667537U (en) Quick connecting device of concrete pump truck and open cut foundation pit comprehensive operation platform
CN220890405U (en) Construction operation hoisting platform
CN205479753U (en) Pipeline combination gallows
CN211556817U (en) Electric power tunnel support
CN217398221U (en) Auxiliary tool for hoisting large flue in limited space
CN219242815U (en) Pipeline installation structure
CN204678270U (en) For the stationary fixture that steel-structure factory building ceiling lighting is installed
CN219015516U (en) Tunnel steel support axial force detection device
CN215172775U (en) Rainwater pipe mounting structure of factory building
CN211698329U (en) Support for installing OPPC optical cable junction box

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant