CN219637814U - Large-scale template running gear of concrete link plate straight wall - Google Patents

Large-scale template running gear of concrete link plate straight wall Download PDF

Info

Publication number
CN219637814U
CN219637814U CN202320624668.8U CN202320624668U CN219637814U CN 219637814 U CN219637814 U CN 219637814U CN 202320624668 U CN202320624668 U CN 202320624668U CN 219637814 U CN219637814 U CN 219637814U
Authority
CN
China
Prior art keywords
straight wall
template
running gear
scale
link
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320624668.8U
Other languages
Chinese (zh)
Inventor
南铁雷
刘江
暴坡
赵旺锋
李建英
衡银课
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Corp Engineering Bureau 15 Co Ltd
Original Assignee
Sinohydro Corp Engineering Bureau 15 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Corp Engineering Bureau 15 Co Ltd filed Critical Sinohydro Corp Engineering Bureau 15 Co Ltd
Priority to CN202320624668.8U priority Critical patent/CN219637814U/en
Application granted granted Critical
Publication of CN219637814U publication Critical patent/CN219637814U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a large-scale template running gear of concrete link up board straight wall, includes large-scale template of link up board straight wall and hat beam template, and the device includes lower part running gear, elevating system, upper portion running gear, traction mechanism, lower part running gear and elevating system set up large-scale template bottom of link up board straight wall, traction mechanism sets up on the large-scale template direction of advance of link up with large-scale template of link up board straight wall, upper portion running gear sets up large-scale template top of link up board straight wall, upper portion running gear includes U-shaped connecting piece, branch, walking wheel, and one side wall of the U-shaped connecting piece of inversion links to each other with large-scale template of link up board straight wall, the inboard of another lateral wall transversely is provided with branch, and the tip of branch is provided with the walking wheel, and the walking wheel walks on hat beam template. The utility model can finish the turnover of the large template of the hanging plate straight wall in a short time, has convenient turnover, simple operation and gentle and stable moving process, reduces the deformation of the template and ensures the engineering quality.

Description

Large-scale template running gear of concrete link plate straight wall
Technical Field
The utility model belongs to the technical field of walls, and particularly relates to a concrete hanging plate straight wall template traveling device.
Background
In a certain project, the existing traffic trunk lines (large river and riverbank) along the river are on two sides of the river, residential areas are dense, and in order to meet the width of the channel and avoid damaging the existing municipal facilities, the concrete filling pile hanging plate straight wall structure is designed to protect the walls. The cast-in-situ reinforced concrete hanging plate straight wall with the diameter of 1.0m and 1.2m, the pile length of 16.1m and 17.1m, the pile spacing of 1.2m and 1.4m, the crown beam (cap beam) arranged at the pile top, the size of 1.5m multiplied by 0.8m (width multiplied by height), the design thickness of the continuous wall upstream surface of the cast-in-situ reinforced concrete hanging plate straight wall with the height of 5.5m and the single bin length of 22.4m is adopted as the cast-in-situ pile to form a clear water platform.
The clear water platform has higher requirements on appearance quality, in view of the above conditions, the concrete templates of the vertical wall hanging plate adopt steel templates, the single block size is 5.5m high by 1.5m wide, the single block weight is about 1.822 tons, 15 templates are total for each concrete bin, the total length is 22.7m, and the total weight is about 27.3t. Through field test, adopt monolithic template dismantlement and crane hoist and mount scheme, whole storehouse is installed and is torn open the template duration longer, and dismantles repeatedly and lead to template and template seam to destroy seriously, causes the template life to shorten, construction cost is high, restriction construction progress, be unfavorable for quality control and potential safety hazard great. In the continuous theoretical research and the field trial process, steel templates required by each concrete cabin are reinforced and connected into a whole by using profile steel, repeated disassembly is not needed after one-step forming, but the total weight of the whole single template is about 30 tons, the existing field cannot meet the hoisting requirement, and the template turnover cannot be completed through hoisting by a crane, so that a travelling device for moving a high and large template is urgently needed at present.
Disclosure of Invention
The technical problem to be solved by the utility model is to provide the large-scale formwork walking device for the concrete hanging plate straight wall, which has the advantages of reasonable design, simplicity in operation, low construction cost and high construction efficiency.
The technical scheme adopted for solving the technical problems is as follows: the utility model provides a large-scale template running gear of concrete link up board straight wall, includes large-scale template of link up board straight wall and hat beam template, and the device includes lower part running gear, elevating system, upper portion running gear, traction mechanism, lower part running gear and elevating system set up large-scale template bottom of link up board straight wall, traction mechanism sets up on the large-scale template direction of advance of link up with large-scale template of link up board straight wall, upper portion running gear sets up large-scale template top of link up board straight wall, upper portion running gear includes U-shaped connecting piece, branch, walking wheel, and one side wall of the U-shaped connecting piece of inversion links to each other with large-scale template of link up board straight wall, the inboard of another lateral wall transversely is provided with branch, and the tip of branch is provided with the walking wheel, and the walking wheel walks on hat beam template.
As a preferable technical scheme, the upper travelling mechanism further comprises a groove-shaped guide rail matched with the travelling wheel, the groove-shaped guide rail is arranged on the crown beam template, and the travelling wheel is positioned in the groove-shaped guide rail.
As a preferable technical scheme, the lower traveling mechanism is composed of at least 2 tank trucks.
As a preferred technical solution, the lifting mechanism consists of at least 2 hydraulic jacks.
As a preferable technical scheme, the traction mechanism is a winch.
As an optimal technical scheme, the large-scale formwork of the hanging plate straight wall is formed by connecting a plurality of steel formwork units into a whole, and the sizes of the steel formwork units are 5.5m multiplied by 1.5m.
The beneficial effects of the utility model are as follows:
the lower travelling mechanism, the lifting mechanism, the upper travelling mechanism and the traction mechanism form the travelling system of the large formwork of the hanging plate straight wall, the turnover of the large formwork of the hanging plate straight wall can be completed in a short time, the turnover is convenient, the operation is simple, compared with the traditional hoisting technology, the related cost of matching a crane and a digging machine is removed, the construction cost is greatly saved, the moving process is gentle and stable, the deformation of the formwork is reduced, and the engineering quality is ensured.
Drawings
Fig. 1 is a schematic structural view of the present utility model.
Fig. 2 is an enlarged schematic view of a portion a of fig. 1.
Fig. 3 is a right side view of fig. 1.
Fig. 4 is an enlarged schematic view of a portion B of fig. 3.
Wherein: the large-scale template of link plate straight wall 1, tank carrier 2, crown beam template 3, U-shaped connecting piece 4, branch 5, walking wheel 6, groove-shaped guide rail 7, hoist engine 8, hydraulic jack 9.
Detailed Description
The present utility model will be described in further detail with reference to the drawings and examples, but the present utility model is not limited to the following embodiments.
In fig. 1, 2, 3 and 4, the running gear of the large concrete vertical wall formwork 1 of this embodiment includes large vertical wall formwork 1 and crown beam formwork 3, large vertical wall formwork 1 is formed by fifteen steel formwork units connected as a whole, the shape of large vertical wall formwork 1 is the same as the shape of the casting bin surface, the size of the steel formwork unit is 5.5mx1.5 m, the weight of the single steel formwork unit is about 1.822 tons, tank trucks 2 of 1 18T are respectively installed at the front end and the rear end of the bottom of large vertical wall formwork 1 for assisting the movement of large vertical wall formwork 1, 2 hydraulic jacks 9 are installed between the two tank trucks 2 at the position close to the bottom of the side of large vertical wall formwork 1 for vertically lifting and adjusting the large vertical wall formwork 1, a winch 8 is fixedly installed on a cushion layer positioned at the side of the pouring pile in the advancing direction of the large vertical wall formwork 1, a steel wire rope of the winch 8 is fixedly connected with the large vertical wall formwork 1, and a large vertical wall formwork 1 is fixedly connected with a screw thread tightening mechanism for the large vertical wall formwork 1, and the running gear of the large vertical wall formwork 1 is provided with a large vertical wall formwork 1 in the running gear.
The upper travelling mechanism of the embodiment comprises a U-shaped connecting piece 4, a supporting rod 5 and travelling wheels 6, wherein one side wall of the inverted U-shaped connecting piece 4 is fixedly connected with a hanging plate straight wall large-scale formwork 1 through a threaded fastener, the supporting rod 5 is transversely and fixedly arranged on the inner side of the other side wall, the travelling wheels 6 are arranged at the end parts of the supporting rods 5, the trough-shaped guide rail 7 is arranged on the back water side of the installed crown beam formwork 3, and the travelling wheels 6 are positioned in the trough-shaped guide rail 7.
The working principle of the utility model is as follows:
the method comprises the steps of finishing pouring of one bin surface of a vertical wall of a hanging plate, removing head templates on two sides of the upstream and downstream, installing a crown beam template 3 on the back surface of a next to-be-poured bin, installing groove-shaped guide rails 7 on the crown beam template 3, removing anchors of upper and lower conical wire sleeves for fixing the vertical wall large template 1, loosening but not removing counter anchor bolts of the top of the vertical wall large template 1 and the crown beam template 3 of the poured bin, preventing the vertical wall large template 1 from being overturned, lifting the vertical wall large template 1 by 2 hydraulic jacks 9 with steps, respectively placing the two tank carriers 2 at three points of the length of the whole set of templates when the lifting height reaches the height of the tank carrier 2, adjusting the direction of the tank carrier 2 to be parallel to the moving direction of the templates, and enabling the whole vertical wall large template 1 to be placed on the tank carrier 2 by hydraulic jacks 9, and enabling the traveling wheels to move from the top of the vertical wall large template 1 to form a self-moving system to the top of the tank carrier 1, and the running wheels to be mounted on the top of the tank carrier 2, and the running system is arranged in the top of the tank carrier 1 is moved to the top of the tank carrier 2, and the running system is moved to the top of the tank carrier 2 is correspondingly to the top of the tank carrier 3 is moved to form a large template 1, and the running system is moved to be mounted to the top of the tank carrier is slowly moves to the top of the roof template 3 is mounted on the top of the top template is mounted on the top of the tank template is mounted and is mounted on the top of the tank template is mounted. After the large-scale template 1 of link plate straight wall moves in place, firstly installing the opposite-pull anchor rods of the top of the large-scale template 1 of link plate straight wall and the crown beam template 3 of the to-be-poured warehouse, after ensuring that the large-scale template 1 of link plate straight wall cannot be overturned, dismantling an upper travelling system, slowly jacking up the large-scale template 1 of link plate straight wall by using a hydraulic jack 9, after moving out of the tank carrier 2, unloading the force of the hydraulic jack 9 to enable the large-scale template 1 of whole link plate straight wall to be in place, and reinforcing the template for concrete pouring after local fine tuning.

Claims (6)

1. The utility model provides a large-scale template running gear of concrete link plate straight wall, includes large-scale template of link plate straight wall and crown beam template, its characterized in that: the device comprises a lower travelling mechanism, a lifting mechanism, an upper travelling mechanism and a traction mechanism, wherein the lower travelling mechanism and the lifting mechanism are arranged at the bottom of a large hanging plate straight wall formwork, the traction mechanism is arranged on the advancing direction of the large hanging plate straight wall formwork and is connected with the large hanging plate straight wall formwork, the upper travelling mechanism is arranged at the top of the large hanging plate straight wall formwork and comprises a U-shaped connecting piece, a supporting rod and travelling wheels, one side wall of the inverted U-shaped connecting piece is connected with the large hanging plate straight wall formwork, the supporting rod is transversely arranged at the inner side of the other side wall, the travelling wheels are arranged at the end parts of the supporting rod, and the travelling wheels travel on the crown beam formwork.
2. The running gear of a concrete cladding straight wall large-scale form according to claim 1, wherein: the upper travelling mechanism further comprises a groove-shaped guide rail matched with the travelling wheels, the groove-shaped guide rail is arranged on the crown beam template, and the travelling wheels are positioned in the groove-shaped guide rail.
3. The running gear of a concrete cladding straight wall large-scale form according to claim 1, wherein: the lower travelling mechanism consists of at least 2 tank trucks.
4. The running gear of a concrete cladding straight wall large-scale form according to claim 1, wherein: the lifting mechanism consists of at least 2 hydraulic jacks.
5. The running gear of a concrete cladding straight wall large-scale form according to claim 1, wherein: the traction mechanism is a winch.
6. The running gear of a concrete cladding straight wall large-scale form according to claim 1, wherein: the large-scale template of the hanging plate straight wall is formed by connecting a plurality of steel template units into a whole, and the sizes of the steel template units are 5.5m multiplied by 1.5m.
CN202320624668.8U 2023-03-27 2023-03-27 Large-scale template running gear of concrete link plate straight wall Active CN219637814U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320624668.8U CN219637814U (en) 2023-03-27 2023-03-27 Large-scale template running gear of concrete link plate straight wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320624668.8U CN219637814U (en) 2023-03-27 2023-03-27 Large-scale template running gear of concrete link plate straight wall

Publications (1)

Publication Number Publication Date
CN219637814U true CN219637814U (en) 2023-09-05

Family

ID=87808512

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320624668.8U Active CN219637814U (en) 2023-03-27 2023-03-27 Large-scale template running gear of concrete link plate straight wall

Country Status (1)

Country Link
CN (1) CN219637814U (en)

Similar Documents

Publication Publication Date Title
CN101586330B (en) Receding construction method of cradle of continuous girder bridge made of prestressing concrete
CN101260650B (en) 50m/1430t double width integral box girder construction process
CN201003145Y (en) Upward and self-walking type mobile die carrier
CN201065511Y (en) Mobile die carrier bridge fabrication machine for thin wall high frusta
CN208815424U (en) A kind of bridge descending hanging basket
CN109653105B (en) Main truss system of box girder bridge cantilever construction hanging basket and use method thereof
CN103669215B (en) Vertical-horizontal overall-sliding type side mold of fulcrum-few support
CN101250854B (en) Large span double-linear-box beam bunching-frame method construction bridging machine
CN206800212U (en) The Bridge Erector constructed by cross for precast segmental beam
CN202991063U (en) Large-section tunnel hydraulic trolley
CN215252400U (en) Self-supporting synchronous hanger system for corrugated steel web construction
CN207987749U (en) Ride cable-styled erection crane
CN202417519U (en) Synchronous trolley
CN109577303A (en) A kind of mobile formwork system and its working method for Shiplock Culvert
CN219637814U (en) Large-scale template running gear of concrete link plate straight wall
CN209652772U (en) Box girder bridge cantilever construction main truss cradle system
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
CN205975365U (en) Cast -in -situ box girder combined type moving die carrier
CN217327341U (en) Self-propelled long-span variable cross-section hydraulic formwork trolley
CN113152309A (en) Self-supporting synchronous hanging bracket system for corrugated steel web construction and construction method
CN206034300U (en) Move liangping car and with moving large -tonnage precast beam sideslip device that liangping car was made
CN113322819B (en) Method for erecting first-span T beam at tunnel outlet
CN204919341U (en) Installing the system of prefabricated decking of dysmorphism on uncovered lattice formula girder steel of arched bridge
CN209443464U (en) Stake top walking Pile Installation Platform
CN209260561U (en) A kind of integration Bridge Erector

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant