CN219491463U - Solid waste-based cementing material cement wallboard - Google Patents
Solid waste-based cementing material cement wallboard Download PDFInfo
- Publication number
- CN219491463U CN219491463U CN202320599654.5U CN202320599654U CN219491463U CN 219491463 U CN219491463 U CN 219491463U CN 202320599654 U CN202320599654 U CN 202320599654U CN 219491463 U CN219491463 U CN 219491463U
- Authority
- CN
- China
- Prior art keywords
- wire netting
- wallboard
- solid waste
- cement
- wire
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Panels For Use In Building Construction (AREA)
Abstract
The application discloses a cement wallboard made of solid waste-based cementing material, which relates to the technical field of cement wallboards, and comprises a wallboard body, a wire netting and a woven net; the wire netting and the woven net are both arranged in the wallboard body, and the wallboard body is formed by mixing, pouring and solidifying solid waste-based cementing materials and cement; the two wire meshes are wavy and are symmetrically arranged; the woven mesh is located one side that two wire netting kept away from each other, and is by wire netting butt on the die cavity inner wall. The method has the effect of improving the quality of the solid waste-based cementing material cement wallboard.
Description
Technical Field
The application relates to the technical field of cement wallboards, in particular to a solid waste-based cementing material cement wallboard.
Background
Cement wallboard is a common pre-supporting wallboard, and is divided into a plurality of types, and is widely used and built along with the development of assembly type buildings.
The cement wallboard internal material generally contains an iron wire net, plays a role in internal reinforcement, and is generally produced by placing the iron wire net at a corresponding position in a die cavity and then pouring the cement material.
The solid waste-based cementing material is a recycling material formed by mixing construction waste after being crushed with cementing materials such as cement and lime, has the advantage of low cost compared with cement, but has poor self-coagulability, after the solid waste-based cementing material is adopted for pouring the wallboard, the produced cement wallboard is uneven in internal stress due to different position distribution of the wire netting, and the produced cement wallboard is easy to crack at the position without the wire netting in the middle part, so that the service life of the solid waste-based cementing material cement wallboard is reduced, the quality of the cement wallboard is reduced, and the safety of a building is further influenced.
Disclosure of Invention
The utility model provides a solid waste-based cementing material cement wallboard, which aims to solve the problem that the service life of the cement wallboard is reduced because the cement wallboard is cracked at a position without a wire netting due to uneven internal stress.
The application provides a solid waste based cementing material cement wallboard adopts following technical scheme:
a cement wallboard of solid waste based cementing material comprises a wallboard body, an iron wire net and a woven net;
the wire netting and the woven net are both arranged in the wallboard body, and the wallboard body is formed by mixing, pouring and solidifying solid waste-based cementing materials and cement;
the two wire meshes are wavy and are symmetrically arranged;
the woven mesh is located one side that two wire netting kept away from each other, and is by wire netting butt on the die cavity inner wall.
Through adopting above-mentioned technical scheme, two wavy wire netting sets up relatively, can effectually carry out effectual support to cement wallboard inside to can tightly push up the mesh grid to the die cavity inner wall, and then realize the fixed to the mesh grid before pouring, the setting of wire netting makes each part atress more balanced in the cement wallboard of solid useless base cementing material, reduces the fracture probability of solid useless base cementing material cement wallboard, improves cement wallboard's life.
Alternatively, the opposite wavy protrusions on one side of the two wires are mutually abutted.
Through adopting above-mentioned technical scheme, the protruding department of two opposite sides of wire netting butt each other, can effectually improve the stability of pouring in-process wire netting position.
Optionally, the vertical bars of the wire netting are wavy, and the transverse bars are positioned at wavy turning points of the vertical bars of the wire netting.
Through adopting above-mentioned technical scheme, the position setting of horizontal muscle can effectually reduce the resistance that the castable passed through, and then improves the inside filling rate of cement wallboard, improves the quality of solid useless base cementing material cement wallboard.
Optionally, a fixing rib is inserted between the two wires, and the fixing rib crosses and bypasses the transverse rib at the abutting part of the two wires and abuts against the transverse ribs of the two wires in sequence.
Through adopting above-mentioned technical scheme, the interlude setting of horizontal muscle can be effectual with two wire netting mutual fixation together, and then improves the bulk strength of pouring back cement wallboard, reduces the probability of the inside fracture of solid useless base cementing material cement wallboard.
Optionally, the wire netting is fixedly provided with hooks near the transverse ribs of the woven net, and the woven net is hung on the hooks.
Through adopting above-mentioned technical scheme, the mesh grid can be through the hook hanging on the wire netting, and then improves the stability of mesh grid position in the pouring process.
Optionally, the hooks are further fixedly arranged on transverse ribs at the topmost end and bottommost end of the wire netting and used for attaching and hanging the top and bottom of the woven net with the wire netting.
Through adopting above-mentioned technical scheme, couple setting of wire netting top and bottom also can be attached to the wire netting with the top and the bottom of woven wire netting, and then reduces the probability that the woven wire netting top and bottom are turned over out and are leaked in the pouring process, improves the quality of the cement wallboard of production.
In summary, the present application includes at least one of the following beneficial technical effects:
the quantity, shape and position of the wire meshes inside the wallboard body can effectively support the interior of the wallboard body, meanwhile, supporting points can be provided for the woven mesh, the uniformity of stress inside the wallboard body is effectively improved, and the cracking probability of the cement wallboard made of the solid waste-based cementing material is reduced;
the two wire meshes can be effectively fixed together by the arrangement of the fixing ribs, so that the quality of the wallboard body is effectively improved;
the woven mesh is hung on the wire netting through the hooks, and the top and the bottom of the woven mesh can be hung on the hooks at the top and the bottom of the wire netting, so that the probability of misplacement of the woven mesh due to casting materials in the casting process is reduced, and the quality of the cement wallboard is improved.
Drawings
FIG. 1 is a schematic diagram of an embodiment of the present application;
fig. 2 is a schematic view showing the structure of the wire netting;
fig. 3 is a partial schematic view showing the fixing rib.
In the figure, 1, a wallboard body; 2. a wire netting; 21. a hook; 3. a woven mesh; 4. and fixing the ribs.
Detailed Description
The present application is described in further detail below in conjunction with figures 1-3.
The embodiment of the application discloses a solid waste-based cementing material cement wallboard.
Referring to fig. 1 and 2, the solid waste-based cementing material cement wallboard comprises a wallboard body 1, wherein the wallboard body 1 is formed by solidifying solid waste-based cementing material and cement after mixing and pouring. The wallboard body 1 is internally provided with an iron wire netting 2 for internal support and a woven net 3 for improving the surface tensile capacity. Wherein, wire netting 2 is two, is located wallboard body 1 inside intermediate position, and woven wire 3 is two, is located wallboard body 1's lateral wall part.
Inside cement wallboard, the skeleton that is as wallboard body 1 through wire netting 2 is internal support, improves the homogeneity of the inside atress of wallboard body 1, and the effectual probability that reduces solid useless base cementing material cement wallboard production fracture of cooperation net 3 improves cement wallboard's life.
Referring to fig. 2 and 3, the wire netting 2 is wave-shaped, the wire netting 2 is formed by welding a plurality of transverse ribs and vertical ribs, the vertical ribs of the wire netting 2 are wave-shaped, and the transverse ribs of the wire netting 2 are positioned at turning points of the waves of the vertical ribs. The two wire netting 2 are mutually symmetrically arranged, namely the wavy bulge parts on the opposite sides of the two wire netting 2 can mutually abut. A fixing rib 4 is inserted between the two wire netting 2, the fixing rib 4 crosses and bypasses the transverse rib at the abutting part of the two wire netting 2 and abuts against the transverse ribs of the two wire netting 2 in sequence, and then the two wire netting 2 abuts against each other and abuts against the fixing rib 4. After the two wire netting 2 are put into the die cavity, the woven net 3 can be abutted against the inner wall of the die cavity.
The wavy shape of wire netting 2 sets up can effectually carry out even distribution in wallboard body 1 inside, and then makes the inside atress of wallboard body 1 more even. The horizontal rib position of the wire netting 2 is provided with resistance capable of reducing downward flow of pouring materials in the vertical direction, so that the pouring and filling efficiency of solid waste base cementing materials is improved. The setting of fixed muscle 4 can make two wire netting 2 mutually jack-up fixed, and then improves the intensity of the useless base cementing material cement wallboard of solid of formation of pouring, reduces the probability of useless base cementing material cement wallboard fracture admittedly.
Referring to fig. 2 and 3, hooks 21 are fixedly arranged on the transverse ribs on one side, away from each other, of the two wire netting 2, the hooks 21 are further fixedly arranged on the transverse ribs on the top end and the bottom end of the wire netting 2, the woven net 3 can be hung on the transverse ribs of the wire netting 2 to be spread, a plurality of open holes through which common casting materials pass are formed in the top end and the bottom end of the woven net 3, the top and the bottom of the woven net 3 can be attached to the wire netting 2 through the hooks 21 on the upper end and the lower end of the wire netting 2, the woven net 3 is further fixed, dislocation of the woven net 3 is reduced in the casting process, and then the quality of the wallboard body 1 is improved.
The implementation principle of the cement wallboard made of the solid waste-based cementing material provided by the embodiment of the application is as follows: the wire netting 2 that sets up wavy and symmetry in through wallboard body 1 carries out even support to wallboard body 1 inside, and through the position of horizontal muscle being provided with the effectual efficiency that has improved pouring material flow, improves wallboard body 1 shaping efficiency to through the fixed mode to woven mesh 3 improves the adhesive strength of woven mesh 3, and then improves the intensity of solid useless base cementing material cement wallboard, has reduced the probability of surface cracking, improves the quality of solid useless base cementing material cement wallboard.
The embodiments of the present utility model are all preferred embodiments of the present application, and are not intended to limit the scope of the present application in this way, therefore: all equivalent changes in structure, shape and principle of this application should be covered in the protection scope of this application.
Claims (6)
1. The utility model provides a solid useless base cementing material cement wallboard which characterized in that: comprises a wallboard body (1), an iron wire net (2) and a woven net (3);
the wire netting (2) and the woven net (3) are both arranged inside the wallboard body (1), and the wallboard body (1) is formed by mixing, pouring and solidifying solid waste-based cementing materials and cement;
the two wire netting (2) are wavy and are symmetrically arranged;
the woven mesh (3) is positioned at one side of the two wire meshes (2) which are far away from each other, and is abutted on the inner wall of the die cavity by the wire meshes (2).
2. The solid waste-based cementitious material cement wallboard of claim 1, wherein: the opposite wavy bulges on one side of the two wire netting (2) are mutually abutted.
3. The solid waste-based cementitious material cement wallboard of claim 1, wherein: the vertical bars of the wire netting (2) are wavy, and the transverse bars are positioned at wavy turning points of the vertical bars of the wire netting (2).
4. A solid waste-based cementitious material cement wallboard as defined in claim 3, wherein: a fixing rib (4) is inserted between the two wire netting (2), and the fixing rib (4) is crossed and bypasses the transverse rib at the abutting part of the two wire netting (2) and is abutted with the transverse ribs of the two wire netting (2) in sequence.
5. The solid waste-based cementitious material cement wallboard of claim 1, wherein: the wire netting (2) is close to the transverse ribs of the woven net (3) and is fixedly provided with hooks (21), and the woven net (3) is hung on the hooks (21).
6. The solid waste-based cement wallboard of claim 5, wherein: the hooks (21) are also fixedly arranged on transverse ribs at the topmost end and bottommost end of the wire netting (2) and are used for attaching and hanging the tops and bottoms of the woven mesh (3) and the wire netting (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202320599654.5U CN219491463U (en) | 2023-03-24 | 2023-03-24 | Solid waste-based cementing material cement wallboard |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202320599654.5U CN219491463U (en) | 2023-03-24 | 2023-03-24 | Solid waste-based cementing material cement wallboard |
Publications (1)
Publication Number | Publication Date |
---|---|
CN219491463U true CN219491463U (en) | 2023-08-08 |
Family
ID=87476803
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202320599654.5U Active CN219491463U (en) | 2023-03-24 | 2023-03-24 | Solid waste-based cementing material cement wallboard |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN219491463U (en) |
-
2023
- 2023-03-24 CN CN202320599654.5U patent/CN219491463U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105421652B (en) | A kind of composite thermo-insulating wall board | |
CN207959612U (en) | A kind of frame, shear wall cast-in-place structural fill wall with assembled light | |
CN108457421A (en) | A kind of assembled steel reinforced Concrete U Vierendeel girder and its construction method | |
CN208430661U (en) | A kind of vertical piece construction of line-styled self-heat conserving overlapped shear wall | |
CN204386018U (en) | Autoclaved aerated concrete slabs steel sheet arrangement of reinforcement | |
CN110130534A (en) | A kind of novel energy-consumption precast shear wall and its processing installation method | |
CN219491463U (en) | Solid waste-based cementing material cement wallboard | |
CN207331394U (en) | Embedded prefabricated road plate of corner protection assembled | |
CN108729545A (en) | The connecting joint structure and construction method of circular steel tube concrete column and reinforced beam | |
CN205804745U (en) | A kind of precast concrete shear wall component | |
CN201649639U (en) | Supporting system of post-pouring belt template on foundation soleplate | |
CN213390660U (en) | One shot forming's secret close rib structure light weight wallboard | |
CN208685652U (en) | Anchor bolt preformed hole scale mold | |
CN208167766U (en) | A kind of simple and fast connection precast concrete plate fetal membrane | |
CN206667546U (en) | Add floor construction after a kind of steel reinforced concrete | |
CN212534786U (en) | High-strength autoclaved aerated concrete slab | |
CN205804387U (en) | Building ring group structure parting seam jigsaw formwork system | |
CN205713449U (en) | A kind of detachable enclosure wall of fast stacking | |
CN208563972U (en) | Vertical post-cast strip cover plate and building wall | |
CN209509611U (en) | With the assembly concrete silo for pouring channel | |
CN216689994U (en) | Prefabricated light floor structure | |
CN109505422A (en) | A kind of reinforcement means of ancient architecture wall | |
CN216552450U (en) | Reinforced connecting device of concrete structure and section steel | |
CN212742843U (en) | Integral prefabricated sump pit | |
CN216664732U (en) | Bucket-shaped molding column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |