CN219033752U CN202223429214.XU CN202223429214U CN219033752U CN 219033752 U CN219033752 U CN 219033752U CN 202223429214 U CN202223429214 U CN 202223429214U CN 219033752 U CN219033752 U CN 219033752U
Authority
CN
China
Prior art keywords
keel
light steel
installation
keel frame
mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223429214.XU
Other languages
Chinese (zh)
Inventor
朱迎华
滕启飞
彭秋瑞
王诚成
钟勇翔
秦真武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Dwelling New Building Materials Co ltd
Original Assignee
Xuzhou Dwelling New Building Materials Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou Dwelling New Building Materials Co ltd filed Critical Xuzhou Dwelling New Building Materials Co ltd
Priority to CN202223429214.XU priority Critical patent/CN219033752U/en
Application granted granted Critical
Publication of CN219033752U publication Critical patent/CN219033752U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a light steel assembled keel frame, which relates to the technical field of light steel keel frames and comprises a main framework and lifting mechanisms, wherein installation mechanisms for installation and fixation are installed in the middle parts of two sides of the main framework, the lifting mechanisms for inclination adjustment are arranged in the middle part above the installation mechanisms, and an assembly mechanism for assembly and installation is installed in the middle part below the main framework. This light steel assembled keel frame compares with current device, through fixing bolt, regulation hole and mounting hole, can be in the same place between installation cover and the main skeleton to hoist whole keel frame under hoisting mechanism's cooperation, through the adapter sleeve, it can twist with connecting screw and lift by crane between the screw rod and stretch out and draw back, under the running fit of movable joint through connecting screw and lift by crane screw rod tip, can take place the slope after whole hoist and the unilateral interval need be adjusted carries out independent screwing the adjustment, thereby more convenient and fast when making the operation.

Description

Light steel assembled keel frame
Technical Field
The utility model relates to the technical field of light steel keel frames, in particular to a light steel assembled keel frame.
Background
The light steel joist is a novel building material, and along with the development of modern construction in China, the light steel joist is widely used in places such as hotels, terminal buildings, bus stations, amusement parks, shops, factories, office buildings, old building reconstruction, indoor decoration arrangement, ceilings and the like, and in the prior art, the light steel joist is installed and assembled by adopting a self structure.
The utility model provides an assembled light steel keel frame for furred ceiling, this case fixed roof is inside to be offered the hoist and mount groove, and hoist and mount groove and strengthening rib phase-match, the strengthening rib runs through the hoist and mount groove and is connected with fixed roof, the strengthening rib runs through fixed roof and can hang fixing base and auxiliary joist through the anti-bending jib to this alleviates the bearing of auxiliary joist, slows down the auxiliary joist and appears crookedly, however this case still exists when using: the angle is comparatively fixed after the installation, when crooked or the installation face is different at ordinary times, is difficult to timely adjust to can bring certain trouble for subsequent skeleton adjustment.
Accordingly, in view of the above, research and improvement are made on the existing structure and the existing defects, and a light steel assembled keel frame is provided so as to achieve the purpose of higher practical value.
Disclosure of Invention
The utility model aims to provide a light steel assembled keel frame for solving the problems in the background technology.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a light steel assembled dragon skeleton, includes main skeleton and hoisting mechanism, the both sides mid-mounting of main skeleton has the installation mechanism that is used for installing fixedly for inclination adjustment hoisting mechanism sets up in the top middle part of installation mechanism, the below mid-mounting of main skeleton has the assembly mechanism that is used for the assembly to install, installation mechanism includes installation cover, fixing bolt and regulation hole, and the surface middle part of installation cover has seted up the mounting hole to the mid-mounting of mounting hole has fixing bolt, the regulation hole has been seted up on the surface of main skeleton, hoisting mechanism includes swing joint, connecting screw, adapter sleeve and hoisting screw, the top of swing joint is connected with connecting screw, and installs the adapter sleeve in the outside top of connecting screw, the top middle part of adapter sleeve is provided with hoisting screw.
Further, the connecting screw rod and the lifting screw rod are in threaded connection with the connecting sleeve, and the connecting screw rod is in rotary connection with the mounting sleeve through the movable joint.
Further, the assembly mechanism comprises a first assembly groove and a first keel, and the first keel is arranged below the inner part of the first assembly groove.
Further, the assembly mechanism further comprises a first fixing seat, the first fixing seat is arranged on two sides above the first keel, and the first fixing seat is fixedly connected with the main framework.
Further, the assembly mechanism further comprises a second keel, the second keel is arranged below the first keel, and a second assembly groove is formed in the surface of the first keel.
Further, the assembly mechanism further comprises a second fixing seat, the second fixing seat is arranged on two sides above the second keel, and the second fixing seat is fixedly connected with the first keel.
Compared with the prior art, the utility model provides the light steel assembled keel frame which has the following beneficial effects: this light steel assembled dragon skeleton can take place the slope after integral hoisting to and independent adjustment is carried out when the interval of unilateral needs to be adjusted, has saved the time of work, can carry out the assembly installation of regulation formula simultaneously, and more level and smooth after the installation.
1. According to the utility model, the mounting sleeve and the main framework can be mounted together through the fixing bolts, the adjusting holes and the mounting holes, so that the integral keel frame is hoisted under the cooperation of the hoisting mechanism, the integral keel frame can be screwed and stretched with the connecting screw rod and the hoisting screw rod through the connecting sleeve, the integral hoisting can be inclined through the running fit of the movable joints at the end parts of the connecting screw rod and the hoisting screw rod, and independent screwing adjustment can be performed when the spacing of a single side is required to be adjusted, thereby being more convenient and quicker in operation and saving the working time;
2. according to the utility model, the first keel, the second keel and the main framework can be assembled through the first fixing seat and the second fixing seat, the mounting positions and the number of the first keel and the second keel can be adjusted according to the working requirement through the first assembling groove and the second assembling groove, and meanwhile, the bottoms of the first keel and the second keel after sliding assembly can be flush through the first assembling groove and the second assembling groove, so that the integral keel frame is smoother, and the use effect is better and more attractive.
Drawings
FIG. 1 is a schematic view of the overall elevation of a light steel fabricated keel frame according to the utility model;
FIG. 2 is a schematic view of a first keel portion of a light steel fabricated pallet according to the utility model in a right-side view;
fig. 3 is a schematic perspective view of a light steel assembled keel frame mounting sleeve according to the utility model.
In the figure: 1. a main skeleton; 2. a mounting mechanism; 201. a mounting sleeve; 202. a fixing bolt; 203. an adjustment aperture; 3. a lifting mechanism; 301. a movable joint; 302. a connecting screw; 303. connecting sleeves; 304. a lifting screw; 4. an assembly mechanism; 401. a first fitting groove; 402. a first keel; 403. a first fixing seat; 404. a second keel; 405. the second fixing seat; 5. a second fitting groove; 6. and (5) mounting holes.
Detailed Description
Embodiments of the present utility model are described in further detail below with reference to the accompanying drawings and examples. The following examples are illustrative of the utility model but are not intended to limit the scope of the utility model.
As shown in fig. 1 and 3, a light steel assembled keel frame comprises a main framework 1 and a lifting mechanism 3, wherein a mounting mechanism 2 for mounting and fixing is arranged in the middle of two sides of the main framework 1, the lifting mechanism 3 for inclination adjustment is arranged in the middle of the upper part of the mounting mechanism 2, the mounting mechanism 2 comprises a mounting sleeve 201, a fixing bolt 202 and an adjusting hole 203, the middle of the surface of the mounting sleeve 201 is provided with a mounting hole 6, the middle of the mounting hole 6 is provided with the fixing bolt 202, the surface of the main framework 1 is provided with the adjusting hole 203, the lifting mechanism 3 comprises a movable joint 301, a connecting screw 302, a connecting sleeve 303 and a lifting screw 304, the connecting screw 302 is connected above the movable joint 301, the connecting sleeve 303 is arranged above the outer part of the connecting screw 302, the lifting screw 304 is arranged in the middle of the upper part of the connecting sleeve 303, the connecting screw 302 and the lifting screw 304 are in threaded connection with the connecting sleeve 303, the connecting screw 302 is in rotary connection with the mounting sleeve 201 through the movable joint 301, the mounting sleeve 201 and the main framework 1 can be mounted together through the fixing bolt 202, the adjusting hole 203 and the mounting hole 6, so that the integral keel frame is hoisted under the cooperation of the lifting mechanism 3, the connecting screw 302 and the lifting screw 304 can be screwed and telescopic through the connecting sleeve 303, the connecting screw 302 and the movable joint 301 at the end part of the lifting screw 304 are in rotary fit, the whole hoisting can be inclined, and independent screwing adjustment is performed when the spacing of one side needs to be adjusted, so that the operation is more convenient and quick, and the working time is saved;
as shown in fig. 1 and 2, the mounting mechanism 4 for mounting is installed to the lower mid-mounting of the main frame 1, the mounting mechanism 4 includes first mounting groove 401 and first fossil fragments 402, and the inside below of first mounting groove 401 is provided with first fossil fragments 402, the mounting mechanism 4 still includes first fixing base 403, and first fixing base 403 installs the top both sides at first fossil fragments 402, and first fixing base 403 and main frame 1 fixed connection, the mounting mechanism 4 still includes second fossil fragments 404, and second fossil fragments 404 set up the inside below at first fossil fragments 402, and second mounting groove 5 has been seted up on the surface of first fossil fragments 402, mounting mechanism 4 still includes second fixing base 405, and second fixing base 405 installs the top both sides at second fossil fragments 404, and second fixing base 405 and first fossil fragments 402 fixed connection, through first fixing base 403 and second fixing base 405, can carry out the assembly between first fossil fragments 402, second fossil fragments 404 and main frame 1, through first mounting groove 401 and second mounting groove 5, can be according to the needs of work adjust first fossil fragments and second fossil fragments 404 and make the whole mount the position and make first fossil fragments 404 and second fossil fragments 404 more flush with each other simultaneously, thereby the bottom mounting groove 404 is more smooth, and more flush effect is realized.
Working principle: as shown in fig. 1 to 3, in the use of the light steel fabricated keel frame, the mounting sleeve 201 and the main framework 1 can be firstly mounted together through the fixing bolt 202, the adjusting hole 203 and the mounting hole 6, so that the whole keel frame is hoisted under the cooperation of the hoisting mechanism 3, then the whole keel frame can be screwed and telescopic with the connecting screw 302 and the hoisting screw 304 through the connecting sleeve 303, then the whole keel frame can be inclined after being integrally hoisted under the running fit of the movable joint 301 at the end part of the connecting screw 302 and the hoisting screw 304, and independent screwing adjustment can be carried out when the spacing of one side needs to be adjusted, at the moment, the first keel 402, the second keel 404 and the main framework 1 can be assembled through the first fixing seat 403 and the second fixing seat 405, then the mounting position and the number of the first keel 402 and the second keel 404 can be adjusted according to working requirements through the first assembling groove 401 and the second assembling groove 5, and finally the first assembling groove 401 and the second assembling groove 5 can enable the whole keel frame 404 to be leveled after the first keel 402 and the second keel frame are assembled in a sliding mode.
The embodiments of the utility model have been presented for purposes of illustration and description, and are not intended to be exhaustive or limited to the utility model in the form disclosed. Many modifications and variations will be apparent to those of ordinary skill in the art. The embodiments were chosen and described in order to best explain the principles of the utility model and the practical application, and to enable others of ordinary skill in the art to understand the utility model for various embodiments with various modifications as are suited to the particular use contemplated.

Claims (6)

1. The utility model provides a light steel assembled keel frame, includes main skeleton (1) and hoisting mechanism (3), its characterized in that, the both sides mid-mounting of main skeleton (1) has installation mechanism (2) that are used for installing fixedly for inclination adjustment hoisting mechanism (3) set up in the top middle part of installation mechanism (2), the below mid-mounting of main skeleton (1) has assembly mechanism (4) that are used for the assembly installation, installation mechanism (2) are including installation cover (201), fixing bolt (202) and regulation hole (203), and the surface mid-portion of installation cover (201) has seted up mounting hole (6) to mid-mounting of mounting hole (6) has fixing bolt (202), regulation hole (203) have been seted up on the surface of main skeleton (1), hoisting mechanism (3) are including swing joint (301), connecting screw (302), adapter sleeve (303) and hoisting screw (304), the top of swing joint (301) is connected with connecting screw (302), and connecting screw (303) are installed to the outside top of connecting screw (302), and the top of adapter sleeve (304) is provided with hoisting screw (303).
2. A light steel fabricated keel frame according to claim 1, wherein the connecting screw (302) and the lifting screw (304) are in threaded connection with the connecting sleeve (303), and the connecting screw (302) is in rotational connection with the mounting sleeve (201) through the movable joint (301).
3. A light steel fabricated keel frame according to claim 1, wherein the assembly means (4) comprises a first assembly groove (401) and a first keel (402), and wherein the first keel (402) is arranged inside the first assembly groove (401) below.
4. A light steel fabricated keel frame according to claim 3, wherein the assembly mechanism (4) further comprises a first fixing base (403), the first fixing base (403) is mounted on two sides above the first keel (402), and the first fixing base (403) is fixedly connected with the main keel frame (1).
5. A light steel fabricated keel frame according to claim 3, wherein the assembly means (4) further comprises a second keel (404), and the second keel (404) is arranged under the inside of the first keel (402), and the surface of the first keel (402) is provided with a second assembly groove (5).
6. The light steel assembled keel frame according to claim 5, wherein the assembly mechanism (4) further comprises a second fixing seat (405), the second fixing seat (405) is installed on two sides above the second keel (404), and the second fixing seat (405) is fixedly connected with the first keel (402).
CN202223429214.XU 2022-12-21 2022-12-21 Light steel assembled keel frame Active CN219033752U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223429214.XU CN219033752U (en) 2022-12-21 2022-12-21 Light steel assembled keel frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223429214.XU CN219033752U (en) 2022-12-21 2022-12-21 Light steel assembled keel frame

Publications (1)

Publication Number Publication Date
CN219033752U true CN219033752U (en) 2023-05-16

Family

ID=86274856

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223429214.XU Active CN219033752U (en) 2022-12-21 2022-12-21 Light steel assembled keel frame

Country Status (1)

Country Link
CN (1) CN219033752U (en)

Similar Documents

Publication Publication Date Title
CN208430687U (en) Self-anchored type suspended-cable structure support construction and system
CN210177780U (en) High light gauge steel of security
CN219033752U (en) Light steel assembled keel frame
CN219636715U (en) Assembled building wallboard overhead hoist
CN215112320U (en) Adjustable lifting type ceiling lamp
CN204781500U (en) Stone material curtain pendant bolt regulation mechanism
CN210430814U (en) Bracket arm for cable bridge
CN208329169U (en) A kind of skeleton symbol quick-mounting type suspension type is built in the air
CN209567734U (en) A kind of simple Special-purpose lifting device
CN213710062U (en) Furred ceiling telescopic machanism and furred ceiling
CN220848661U (en) Fixed support of attached lifting scaffold
CN220705123U (en) Scaffold adjustable screw rod component
CN221027065U (en) Integral type roof beam and have its traction type well construction elevator
CN110273465A (en) A kind of Intelligent balcony based on photovoltaic power generation
CN205822548U (en) A kind of furred ceiling mounting structure of built-in clothes airing machine
CN117868367B (en) Be used for building curtain installation mosaic structure
CN220058509U (en) GRG assembled furred ceiling light gauge steel structure
CN218149192U (en) Connection structure of light gauge steel and wall body
CN220704878U (en) Rotary mounting system for hidden frame curtain wall
CN217998995U (en) Novel prefabricated mixed connecting piece
CN214785213U (en) Assembly type building structure
CN216766461U (en) Suspended ceiling structure convenient to installation
CN220203143U (en) Decorative structural member for green building roof
CN217998590U (en) Ceiling connecting piece
CN215406923U (en) Assembled steel construction building dysmorphism post