CN218881689U - Building infrastructure crack repairing device - Google Patents

Building infrastructure crack repairing device Download PDF

Info

Publication number
CN218881689U
CN218881689U CN202222073376.8U CN202222073376U CN218881689U CN 218881689 U CN218881689 U CN 218881689U CN 202222073376 U CN202222073376 U CN 202222073376U CN 218881689 U CN218881689 U CN 218881689U
Authority
CN
China
Prior art keywords
storehouse
board
repairing
repair
storehouse body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222073376.8U
Other languages
Chinese (zh)
Inventor
邱永平
陈骋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Xinhezhou Investment Development Co ltd
Original Assignee
Anhui Xinhezhou Investment Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Xinhezhou Investment Development Co ltd filed Critical Anhui Xinhezhou Investment Development Co ltd
Priority to CN202222073376.8U priority Critical patent/CN218881689U/en
Application granted granted Critical
Publication of CN218881689U publication Critical patent/CN218881689U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a building infrastructure crack repair ware, including repairing the storehouse body, repairing the storehouse body top setting store the storehouse and store the pump body of storehouse inner wall fixed connection, repair the storehouse body with store and be fixed with the grab handle board between the storehouse, and grab handle board and repair the storehouse body and be vertical distribution, and the lateral wall fixed connection of snap ring board have a cross brace board, the bottom of cross brace board is provided with repairs check fender mechanism, repair the bottom of the storehouse body and set up the annular of having a bottom, the bottom threaded connection of annular of the bottom has a bottom spray tube. The utility model discloses can insert the repair storehouse body of tubular structure to the gap in to can connect the laminating with the snap ring board at the outer wall of repairing the storehouse body, realize horizontal extension board and the combination of repairing the storehouse body, the in-process of pouring into the concrete in the gap, the elasticity that utilizes the spring is used for the end pressure plate and provides decurrent elasticity, makes the laminating of baffle body on the gap surface, thereby can shelter from the concrete that is about to spill over in the gap, and then reduces the construction and the clean degree of difficulty in later stage.

Description

Building infrastructure crack repairing device
Technical Field
The utility model relates to a construction technical field especially relates to a building infrastructure crack repairing device.
Background
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, and also can be a process of changing various lines on a design drawing into a real object at a specified place.
At present, a common crack repairing mode is to pour a proper amount of concrete into a crack, the crack can be filled after the concrete is solidified, and the concrete is easy to overflow in the process of pouring into the crack, so that the construction difficulty is increased.
SUMMERY OF THE UTILITY MODEL
In order to overcome the not enough of prior art, the utility model provides a building infrastructure crack repair ware can solve common crack repair mode and pour into appropriate amount concrete in to the gap, treat that the concrete can realize filling the fissured after solidifying, and pour the in-process in gap into at the concrete, spill over easily, increased the construction degree of difficulty.
In order to solve the technical problem, the utility model provides a following technical scheme: the utility model provides a building infrastructure crack repair ware, including the repair storehouse body, repair the storehouse of storehouse body top setting and store the pump body of storehouse inner wall fixed connection, repair the storehouse body with store and be fixed with the grab handle board between the storehouse, and grab handle board and repair the storehouse body and be the vertical distribution, the lower terminal surface of grab handle board just is located the LED lamp storehouse of a side-mounting of the repair storehouse body, the surface of the repair storehouse body encircles the laminating and has the snap ring board, and the lateral wall fixed connection of snap ring board has the cross brace board, the bottom of cross brace board is provided with repairs check mechanism, repair the bottom of the storehouse body and set up end annular, the bottom threaded connection of end annular has end spray tube.
As a preferred technical scheme of the utility model, it includes spring, end clamp plate, the slider body and the baffle body to repair check fender mechanism, the spring is fixed laminate in the bottom of horizontal extension board, the end clamp plate is fixed laminate in the one end of horizontal extension board is kept away from to the spring, the spout is seted up to the bottom of end clamp plate, slider body sliding connection is inboard in the spout, the baffle body is fixed in one side of spout is kept away from to the slider body.
As a preferred technical scheme of the utility model, the snap ring board is kept away from the one end of horizontal extension board and is seted up threaded hole, the end board adopts square platelike structure.
As a preferred technical scheme of the utility model, the repair storehouse body adopts tubular structure, and the output of the pump body passes through the hose connection with the kneck of the repair storehouse body.
As a preferred technical scheme of the utility model, the inside of storing the storehouse and the one side that is located the pump body are provided with rabbling mechanism, and store the top in storehouse and seted up the pan feeding mouth.
As a preferred technical scheme of the utility model, the surface of storing the storehouse is provided with rabbling mechanism, the rabbling mechanism includes the pivot body, even branch, stirring roller and rocker, the pivot body is fixed in store the lateral wall in storehouse, the rocker rotate connect in the internal inboard of pivot, even the branch is fixed in the front end of rocker, the stirring roller is fixed in even branch keeps away from the one end of rocker.
Compared with the prior art, the utility model discloses the beneficial effect that can reach is:
the utility model discloses can insert the repair storehouse body of tubular structure to the gap in to can connect the laminating with the snap ring board at the outer wall of the repair storehouse body, realize the combination of horizontal extension board and the repair storehouse body, the in-process of pouring into the concrete in the gap, utilize the elastic action of spring to provide decurrent elasticity for the end pressure plate, make the laminating of baffle body on the gap surface, thereby can shelter from the concrete that is about to overflow in the gap, and then reduce the construction and the clean degree of difficulty in later stage.
Drawings
FIG. 1 is an external view of the present invention;
fig. 2 is a bottom view of the present invention;
FIG. 3 is a side view of the rotating shaft of the present invention;
FIG. 4 is a side view of the bottom plate of the present invention;
FIG. 5 is an internal view of the storage compartment of the present invention;
wherein: 1. repairing the bin body; 2. a bottom ring groove; 3. a bottom nozzle; 4. a snap ring plate; 5. a transverse support plate; 6. a spring; 7. a bottom platen; 8. a slider body; 9. a partition plate body; 10. a rotating shaft body; 11. a feeding port; 12. connecting a supporting rod; 13. a stirring roller; 14. a pump body; 15. an LED lamp bin; 16. a grip plate; 17. a rocker; 18. and (7) storing the bin.
Detailed Description
In order to make the technical means, the creation features, the achievement purposes and the functions of the invention easy to understand, the invention is further explained below with reference to the specific embodiments, but the following embodiments are only the preferred embodiments of the invention, not all. Based on the embodiments in the implementation, other embodiments obtained by those skilled in the art without any creative work belong to the protection scope of the present invention. The experimental methods in the following examples are conventional methods unless otherwise specified, and materials, reagents and the like used in the following examples are commercially available unless otherwise specified.
Examples
Referring to fig. 1-5, the utility model provides a crack repairing device for building infrastructure, which comprises a repairing cabin body 1, a storage cabin 18 arranged on the top of the repairing cabin body 1 and a pump body 14 fixedly connected with the inner wall of the storage cabin 18, wherein the repairing cabin body 1 adopts a tubular structure, the output end of the pump body 14 is connected with the interface of the repairing cabin body 1 through a hose, so that the storage cabin 18, the pump body 14 and the repairing cabin body 1 are communicated, the concrete stored on the inner wall of the storage cabin 18 can be discharged into the repairing cabin body 1 through the driving of the pump body 14, and is discharged downwards from the bottom of the repairing cabin body 1 to realize the gap repairing, a handle plate 16 is fixed between the repairing cabin body 1 and the storage cabin 18, the handle plate 16 is vertically distributed with the repairing cabin body 1, through the designed handle plate 16, the whole device can be held by constructors for operation, the LED lamp bin 15 is arranged on the lower end face of the handle plate 16 and located on one side of the repairing bin body 1, and in the process of injecting concrete into a gap, the LED lamp bin 15 after being lightened is utilized to irradiate the gap, so that a constructor can conveniently observe the injection degree of the concrete in the gap and the depth of the gap, and can conveniently carry out gap repairing work, the surface of the repairing bin body 1 is provided with the clamp ring plate 4 in a surrounding manner, one end of the clamp ring plate 4, far away from the transverse support plate 5, is provided with a threaded hole, the side wall of the clamp ring plate 4 is fixedly connected with the transverse support plate 5, when the transverse support plate 5 and the repairing bin body 1 are installed, two groups of transverse support plates 5 at one end of the transverse support plate 5 are attached to the outer wall of the repairing bin body 1, bolts are installed in the threaded holes of the clamp ring plate 4, the two groups of clamp ring plates 4 are fastened, so that the transverse support plate 5 is fixed on one side of the repairing bin body 1, the bottom of repairing the storehouse body 1 is seted up end annular 2, and the bottom threaded connection of end annular 2 has end spray tube 3, and spray tube 3 installs under repairing storehouse body 1 through the threaded connection with top end annular 2 under at the end, can be according to the shape difference in gap moreover, install the end spray tube 3 of different export sizes and pattern can, improve the adaptability.
The bottom of horizontal support board 5 is provided with repairs check fender mechanism, repair check fender mechanism includes spring 6, end clamp plate 7, slider body 8 and baffle body 9, spring 6 is fixed to be laminated in the bottom of horizontal support board 5, end clamp plate 7 is fixed to be laminated in the one end that horizontal support board 5 was kept away from to spring 6, the spout is seted up to the bottom of end clamp plate 7, slider body 8 sliding connection is inboard in the spout, baffle body 9 is fixed in slider body 8 and is kept away from the one side of spout, end clamp plate 7 adopts square plate structure, after the below injection concrete of end spray tube 3, the muddy earth fills in the gap, along with the gap is filled up, unnecessary concrete can outwards spill over along the gap, in order to avoid too much concrete to spill over and cause extravagant and the increase of the work degree of difficulty, utilize the elastic force effect of spring 6 to provide decurrent pressure for end clamp plate 7, make baffle body 9 with the closely laminating in end clamp plate 7 bottom have decurrent pressure of exerting pressure, like this, after concrete is filled up in the gap, make the concrete be difficult for overflowing from the baffle from the gap through the body 9 of exerting pressure.
In order to improve the solidification speed of concrete, water glass generally needs to be mixed in the concrete to reduce the solidification time of the concrete, an agitating mechanism is arranged inside the storage bin 18 and on one side of the pump body 14, a feeding port 11 is formed in the top of the storage bin 18, the feeding port 11 is used for injecting the concrete and part of the water glass, an agitating mechanism is arranged on the surface of the storage bin 18 and comprises a rotating shaft body 10, a connecting rod 12, an agitating roller 13 and a rocker 17, the rotating shaft body 10 is fixed on the side wall of the storage bin 18, the rocker 17 is rotatably connected to the inner side of the rotating shaft body 10, the connecting rod 12 is fixed at the front end of the rocker 17, the agitating roller 13 is fixed at one end, far away from the rocker 17, of the connecting rod 12, after the concrete and the water glass are injected into the storage bin 18, the rocker 17 is held and is rotated, a plurality of groups of connecting rod 12 and agitating roller 13 fixedly connected with the front end of the rocker 17 rotate inside the storage bin 18, the concrete and the water glass can be agitated through the rotation of the agitating roller 13 and the connecting rod 12, so that the water glass can be more uniformly combined with the concrete, and gaps in the concrete can be more uniformly solidified.
In the present disclosure, unless expressly stated or limited otherwise, the first feature "on" or "under" the second feature may comprise direct contact between the first and second features, or may comprise contact between the first and second features not directly. Also, the first feature being "on," "above" and "over" the second feature includes the first feature being directly on and obliquely above the second feature, or merely indicating that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature includes the first feature being directly under and obliquely below the second feature, or simply meaning that the first feature is at a lesser elevation than the second feature.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It should be understood by those skilled in the art that the present invention is not limited by the above embodiments, and the description in the above embodiments and the description is only preferred examples of the present invention, and is not intended to limit the present invention, and that the present invention can have various changes and modifications without departing from the spirit and scope of the present invention, and these changes and modifications all fall into the scope of the claimed invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides a building infrastructure crack repairing device, includes the pump body (14) of repairing storehouse body (1), the storehouse (18) of storing that the storehouse body (1) top of repairing set up and storing storehouse (18) inner wall fixed connection, its characterized in that: repair the storehouse body (1) with store and be fixed with handle board (16) between storehouse (18), and handle board (16) and repair the storehouse body (1) and be vertical distribution, the lower terminal surface of handle board (16) just is located LED lamp storehouse (15) of repairing one side installation of the storehouse body (1), the surface of repairing the storehouse body (1) is encircleed the laminating and is had snap ring board (4), and the lateral wall fixed connection of snap ring board (4) has horizontal support board (5), the bottom of horizontal support board (5) is provided with repairs check and keeps off the mechanism, repair the bottom of the storehouse body (1) and set up end annular (2), the bottom threaded connection end spray tube (3) of end annular (2).
2. The crack repairing device for building infrastructure as claimed in claim 1, wherein: repair check and keep off mechanism and include spring (6), end clamp plate (7), the slider body (8) and baffle body (9), spring (6) fixed laminating in the bottom of cross-brace board (5), end clamp plate (7) fixed laminating in the one end of cross-brace board (5) is kept away from in spring (6), the spout is seted up to the bottom of end clamp plate (7), slider body (8) sliding connection is inboard in the spout, baffle body (9) are fixed in one side that the spout was kept away from in slider body (8).
3. The crack repairing device for building infrastructure as claimed in claim 2, wherein: one end of the snap ring plate (4) far away from the transverse support plate (5) is provided with a threaded hole, and the bottom pressing plate (7) is of a square plate-shaped structure.
4. The crack repairing device for building infrastructure as claimed in claim 1, wherein: the repairing bin body (1) is of a cylindrical structure, and the output end of the pump body (14) is connected with the interface of the repairing bin body (1) through a hose.
5. The crack repairing device for building infrastructure as claimed in claim 1, wherein: one side of the inside of the storage bin (18) and the pump body (14) is provided with a stirring mechanism, and the top of the storage bin (18) is provided with a feeding port (11).
6. The crack repairing device for building infrastructure as claimed in claim 1, wherein: the surface of storing storehouse (18) is provided with rabbling mechanism, rabbling mechanism includes the pivot body (10), links a pole (12), stirring roller (13) and rocker (17), the pivot body (10) are fixed in store the lateral wall in storehouse (18), rocker (17) rotate connect in the inboard of the pivot body (10), even branch (12) are fixed in the front end of rocker (17), stirring roller (13) are fixed in link branch (12) keep away from the one end of rocker (17).
CN202222073376.8U 2022-08-08 2022-08-08 Building infrastructure crack repairing device Active CN218881689U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222073376.8U CN218881689U (en) 2022-08-08 2022-08-08 Building infrastructure crack repairing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222073376.8U CN218881689U (en) 2022-08-08 2022-08-08 Building infrastructure crack repairing device

Publications (1)

Publication Number Publication Date
CN218881689U true CN218881689U (en) 2023-04-18

Family

ID=85947980

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222073376.8U Active CN218881689U (en) 2022-08-08 2022-08-08 Building infrastructure crack repairing device

Country Status (1)

Country Link
CN (1) CN218881689U (en)

Similar Documents

Publication Publication Date Title
CN206317241U (en) A kind of cement mortar agitation mixer of construction
CN218881689U (en) Building infrastructure crack repairing device
CN211689813U (en) Avoid extravagant embedment device for highway construction of pitch
CN203818308U (en) Die opening distributing device of prestressed centrifugal pile
CN201386244Y (en) Asphalt cement mortar grouting device
CN211333908U (en) Anti-blocking overflow water recovery device for stirrer
CN210916939U (en) Road cementation of fissures device for municipal works
CN210553126U (en) Turnover tilting type quartz stone water tank casting machine
CN208732668U (en) A kind of flotation tank
CN203752329U (en) Small-sized stirring cart for construction sites
CN220363847U (en) Watering device suitable for water and electricity engineering job site
CN214026300U (en) Layering continuous grouting forming equipment
CN207915715U (en) A kind of caisson template stops sizing device
CN217781687U (en) Municipal works road is with irritating sealing device
CN218322273U (en) Road cementation of fissures device is used in town road construction
CN219855260U (en) A bare concrete production facility for industrial factory building
CN214194548U (en) Concrete placement equipment for hydraulic engineering construction
CN210302756U (en) Energy saving and emission reduction is with construction sewage sedimentation tank
CN219050955U (en) Special agitator tank of high-efficient polycarboxylate water reducing agent production
CN203891171U (en) Automatic plugging device of draining port
CN212976209U (en) Clout clearance mechanism after concrete mixing for city building
CN209163475U (en) A kind of masonry mortar automatic pouring device
CN211821263U (en) Filling vertical pipe buffer device
CN217173269U (en) Detergent filling equipment
CN220428767U (en) Pouring anti-overflow device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant