CN218623668U - Assembled maintenance railing for constructional engineering - Google Patents

Assembled maintenance railing for constructional engineering Download PDF

Info

Publication number
CN218623668U
CN218623668U CN202222841338.2U CN202222841338U CN218623668U CN 218623668 U CN218623668 U CN 218623668U CN 202222841338 U CN202222841338 U CN 202222841338U CN 218623668 U CN218623668 U CN 218623668U
Authority
CN
China
Prior art keywords
rods
bracing piece
connecting rod
assembled
railing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222841338.2U
Other languages
Chinese (zh)
Inventor
宋乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Qinjun Construction Co ltd
Original Assignee
Gansu Qinjun Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Qinjun Construction Co ltd filed Critical Gansu Qinjun Construction Co ltd
Priority to CN202222841338.2U priority Critical patent/CN218623668U/en
Application granted granted Critical
Publication of CN218623668U publication Critical patent/CN218623668U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a railing technical field just discloses a railing is maintained with assembled to building engineering, bracing piece including the symmetry setting, two the connecting rod of two horizontal settings is installed to the symmetry between the bracing piece, and installs a plurality of fender rods between two connecting rods, two the inside of bracing piece is offered and is used for storing the cavity that holds of connecting rod and fender rod, and holds the cavity and seal through the apron, and this railing is maintained with assembled to building engineering, owing to set up in the inside of bracing piece and hold the cavity, consequently can directly accomodate after dismantling connecting rod and fender rod and hold in the cavity, realize tearing open the effect of adorning promptly to make things convenient for operating personnel to accomodate the arrangement to scattered spare part, it is also relatively more convenient when later stage equipment.

Description

Assembled maintenance railing for constructional engineering
Technical Field
The utility model relates to a railing technical field specifically is a railing is maintained with assembled to building engineering.
Background
The building engineering maintenance railing is made of an iron pipe and is manufactured by processing seamless iron pipes through bending, welding, polishing, high-pressure paint baking, film pasting and other layer-by-layer processes. After being assembled together to form a guardrail, the general maintenance railings are widely applied to isolation and warning of construction sites.
Need dismantle it after assembled railing uses to reduce the occupation in space, thereby convenient transportation, consequently mutual independence between a plurality of spare parts on the railing after the dismantlement, and scatter one, inconvenient user of service arranges in order and accomodates.
SUMMERY OF THE UTILITY MODEL
The utility model provides a be not enough to prior art, the utility model provides a railing is maintained with assembled to building engineering possesses and arranges in order and accomodate advantages such as the spare part after dismantling convenient operating personnel will dismantle at the back, has solved current railing and is difficult to arrange in order and accomodate the problem after dismantling.
In order to achieve the above purpose, the utility model provides a following technical scheme: the utility model provides a railing is maintained with assembled to building engineering, is including the bracing piece that the symmetry set up, two the connecting rod of two horizontal settings is installed to the symmetry between the bracing piece, and installs a plurality of guard bars between two connecting rods, two the cavity that holds that is used for saving connecting rod and guard bar is offered to the inside of bracing piece, and holds the cavity and seal through the apron.
Preferably, two fixed sleeves are symmetrically installed on one side, close to the connecting rod, of the support rods, and two ends of the connecting rod are respectively inserted into the fixed sleeves.
Preferably, a slot is formed in one side, connected with the guard bar, of each connecting rod, and two ends of each guard bar are inserted into the slots.
Preferably, the bottom of each of the two support rods is fixed with a support part, and the support parts can be any one of a balancing weight or a moving wheel.
Preferably, one side install articulated piece on the side of bracing piece, the opposite side install on the side of bracing piece with articulated piece looks adaptation articulated seat.
Preferably, the top of the two support rods is provided with a warning lamp.
To sum up, the utility model discloses a following beneficial effect:
this railing is maintained with assembled to building engineering owing to set up in the inside of bracing piece and hold the cavity, consequently can directly accomodate after dismantling connecting rod and fender rod and hold in the cavity, realizes tearing open the effect of dress promptly to make things convenient for operating personnel to accomodate the arrangement to scattered spare part, also relatively more convenient when later stage equipment.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic front sectional view of the present invention;
fig. 3 is the explosion structure diagram of the protection rod and the connecting rod of the present invention.
Wherein: 1. a support bar; 2. a connecting rod; 3. a guard bar; 4. a receiving cavity; 5. a cover plate; 6. fixing a sleeve; 7. inserting slots; 8. a support portion; 9. a hinged block; 10. a hinged seat; 11. a warning light.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts all belong to the protection scope of the present invention.
Please refer to fig. 1-3, an assembled maintenance railing for building engineering, includes two symmetrically arranged support rods 1, and two transverse connection rods 2 are symmetrically installed between two support rods 1, specifically, a fixed sleeve 6 is symmetrically installed on the opposite side of the support rods 1, the two ends of the connection rods 2 are just inserted into the fixed sleeve 6 during installation, and a plurality of protection rods 3 are installed between two transversely arranged connection rods 2, namely, a plurality of slots 7 are opened on the side of the connection rods 2 close to the protection rods 3, and each connection rod 2 is inserted into the slots 7 to install the connection rod 2.
By last knowing, bracing piece 1, connecting rod 2 and guard bar 3 constitute the main part of whole railing, can put around the construction area at the in-process of building construction, play protection and warning effect to connecting rod 2 can be dismantled with bracing piece 1, and guard bar 3 can dismantle again with between connecting rod 2, consequently can save occupation in space when dismantling.
The cavity 4 that holds that can hold connecting rod 2 and protective rod 3 is all seted up in the inside of every bracing piece 1 to will hold cavity 4 through apron 5 and seal, specifically apron 5 accessible articulated mode is installed on bracing piece 1, and fixes apron 5 through the buckle.
Consequently, can directly put into holding cavity 4 with connecting rod 2 and a plurality of fender rod 3 after will dismantling, realize tearing open promptly, need not arrange in order alone and accomodate a plurality of fender rods 3 and connecting rod 2 alone, it is more convenient to operate, occupation in the space-saving that equally can be further also promptly to take the usefulness when later stage is assembled once more.
It is further complemented that, warning light 11 is all installed at the top of every bracing piece 1, and supporting part 8 is then installed to the bottom of bracing piece 1, and supporting part 8 can be for the balancing weight with remove any one of the wheel, and warning effect can be played under the not good condition of light to warning light 11, and supporting part 8 can support and fix holistic railing when the balancing weight, then conveniently shifts holistic railing when supporting part 8 is for removing the wheel.
It needs to be supplemented that, in order to connect a plurality of railings, the side surfaces of the two support rods 1 far away from the connecting rod 2 are sequentially provided with the hinged seats 10 and the hinged blocks 9, so that when the two railings need to be connected, the hinged seats 10 and the hinged blocks 9 on the two railings can be installed, the connection of the plurality of railings is realized after the installation, any two adjacent railings can be rotated at a hinged position, the angle adjustment between the two railings is realized, and the adjustment can be carried out according to the building construction area.
When using, open connecting rod 2 and the protection rod 3 that the apron 5 on the bracing piece 1 will accomodate and take out, at first install protection rod 3 between two connecting rods 2 in proper order, secondly put into between two bracing pieces 1 with the connecting rod 2 and the protection rod 3 that assemble, and install between two bracing pieces 1, accomplish the equipment to the railing, dismantle same with it when dismantling, and directly put into and hold cavity 4 with the spare part after dismantling, and seal it through apron 5.
The standard parts used in the application document can be purchased from the market, and can be customized according to the description and the description of the attached drawings, the specific connection mode of each part adopts conventional means such as mature bolts, rivets, welding and the like in the prior art, and machines, parts and equipment adopt conventional models in the prior art.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a railing is maintained with assembled to building engineering, includes bracing piece (1) that the symmetry set up, its characterized in that: two connecting rods (2) which are transversely arranged are symmetrically arranged between the supporting rods (1), a plurality of protective rods (3) are arranged between the two connecting rods (2), a containing cavity (4) used for storing the connecting rods (2) and the protective rods (3) is arranged inside the supporting rods (1), and the containing cavity (4) is sealed through a cover plate (5).
2. The assembled maintenance rail for construction engineering according to claim 1, wherein: two fixed covers (6) are symmetrically installed on one side of the support rod (1) close to the connecting rod (2), and two ends of the connecting rod (2) are respectively inserted into the fixed covers (6).
3. The assembled maintenance rail for construction engineering according to claim 2, wherein: one side of each connecting rod (2) connected with the guard rod (3) is provided with a slot (7), and two ends of the guard rod (3) are inserted into the slots (7).
4. The assembled maintenance rail for construction engineering of claim 1, wherein: the bottom of two bracing pieces (1) all is fixed with supporting part (8), supporting part (8) can be for the balancing weight or remove any one in the wheel.
5. The assembled maintenance rail for construction engineering according to claim 1, wherein: one side install articulated piece (9) on the side of bracing piece (1), the opposite side install articulated seat (10) with articulated piece (9) looks adaptation on the side of bracing piece (1).
6. The assembled maintenance rail for construction engineering of claim 1, wherein: and warning lamps (11) are arranged at the tops of the two support rods (1).
CN202222841338.2U 2022-10-27 2022-10-27 Assembled maintenance railing for constructional engineering Active CN218623668U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222841338.2U CN218623668U (en) 2022-10-27 2022-10-27 Assembled maintenance railing for constructional engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222841338.2U CN218623668U (en) 2022-10-27 2022-10-27 Assembled maintenance railing for constructional engineering

Publications (1)

Publication Number Publication Date
CN218623668U true CN218623668U (en) 2023-03-14

Family

ID=85474722

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222841338.2U Active CN218623668U (en) 2022-10-27 2022-10-27 Assembled maintenance railing for constructional engineering

Country Status (1)

Country Link
CN (1) CN218623668U (en)

Similar Documents

Publication Publication Date Title
CN109066505B (en) Cable testing bridge convenient to installation and security performance are good
CN218623668U (en) Assembled maintenance railing for constructional engineering
CN104389454A (en) Spreading fabric tent
CN101786585B (en) Crane supporting device for field installation of boiler
CN204006760U (en) Solar water heater support folding structure and solar water heater
CN207905342U (en) A kind of scaffold for building with self-locking function
CN210092767U (en) Integrated portable installing support of network system
CN213930120U (en) But quick assembly disassembly's laser level meter
CN210195440U (en) Security protection device for construction
CN212617018U (en) Double-station anti-seismic support and hanger
CN208607874U (en) A kind of LED display fast assembling-disassembling backrest
CN211776175U (en) Combined military travel dance performance stage convenient to disassemble
CN100525679C (en) Combined picture frame
CN205354798U (en) Modularization outdoor transformer case
CN208009924U (en) A kind of construction protective device
CN214576227U (en) Rail guard convenient to dismouting for building engineering
CN211046817U (en) Solar power generation device for power grid
CN208236099U (en) A kind of wire netting of protective fence installation easy to disassemble
CN213418583U (en) Portable removal safety worker canopy
CN108978487A (en) It is a kind of easily to set up quick detachable protecting canopy frame for bridge construction
CN216380749U (en) Environment-friendly intelligent bus shelter convenient to equipment concatenation
CN211513215U (en) Fire shield for preventing falling object from high altitude
CN218633119U (en) Cable vertical stay fixing device
CN210963650U (en) Novel convenient fire station
CN215656200U (en) Lamp bracket end cover and photocuring lamp bracket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant