CN218617125U - Suspension type scaffold is used in boats and ships segmentation planking construction - Google Patents

Suspension type scaffold is used in boats and ships segmentation planking construction Download PDF

Info

Publication number
CN218617125U
CN218617125U CN202223205891.3U CN202223205891U CN218617125U CN 218617125 U CN218617125 U CN 218617125U CN 202223205891 U CN202223205891 U CN 202223205891U CN 218617125 U CN218617125 U CN 218617125U
Authority
CN
China
Prior art keywords
steel mesh
base frame
steel
railing
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223205891.3U
Other languages
Chinese (zh)
Inventor
周文娟
黄鹏
练博强
徐波
胡海萍
余富斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Huangchuan Marine Engineering Co ltd
Original Assignee
Guangzhou Huangchuan Marine Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Huangchuan Marine Engineering Co ltd filed Critical Guangzhou Huangchuan Marine Engineering Co ltd
Priority to CN202223205891.3U priority Critical patent/CN218617125U/en
Application granted granted Critical
Publication of CN218617125U publication Critical patent/CN218617125U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a suspension type scaffold for ship subsection shell plate construction, which comprises a base frame, a steel mesh plate, a steel mesh cover, a suspension chain, a railing post and a railing seat; the base frame comprises channel steel and angle steel; the side surface of the base frame is also provided with lug plates at equal intervals, and the suspension chain is used for hoisting the base frame through the lug plates; the steel mesh covers are arranged on the base frame at intervals, one ends of the steel mesh covers are hinged with the angle steels, and the steel mesh plates are fixedly arranged among the steel mesh covers; an upper channel and a lower channel are formed between the steel mesh cover and the angle steel and the base frame after the steel mesh cover is turned over; a straight ladder is fixedly arranged in the upper channel and the lower channel; through the suspension chain passes through otic placode hoist and mount bed frame, recycles steel mesh board, steel mesh cover and lays on the bed frame, forms the work area of the staff work of standing of being convenient for, and the steel mesh cover of deuterogamying is articulated with the bed frame to the staff of being convenient for removes between upper and lower adjacent both sides bed frame, and whole concatenation forms, and the installation is simple, and the installation effectiveness is high, need not the welding, also is convenient for shorten the period of setting up.

Description

Suspension type scaffold is used in boats and ships segmentation planking construction
Technical Field
The utility model relates to a ship segmentation field of building, concretely relates to suspension type scaffold is used in construction of ship segmentation planking.
Background
In the process of building a ship, a large number of scaffolds need to be erected, and the erection of the conventional scaffold needs a large amount of manpower and material resources, the erection process is complex, the erection time is long, the control of the ship building period is not facilitated, and meanwhile, the conventional scaffold is repeatedly dismantled and erected, so that the manpower and working hour waste is often serious; in addition, other workloads such as welding temporary horse boards and the like are also accompanied, the workload of on-site welding and dismantling polishing is also increased, and further the building efficiency is not high and the building time is long.
SUMMERY OF THE UTILITY MODEL
In view of the above, the present invention provides a suspended scaffold for the construction of ship sectional planking, which is used to solve the above-mentioned problems.
In order to solve the technical problem, the technical scheme of the utility model is that: a suspended scaffold for ship sectional planking construction comprises a base frame, a steel mesh plate, a steel mesh cover, a suspended chain, a railing post and a railing seat;
the base frame comprises parallel channel steel and angle steel fixed on the channel steel by bolts at equal intervals; the side surface of the base frame is also provided with lug plates at equal intervals, and the suspension chain is used for hoisting the base frame through the lug plates; the steel mesh covers are arranged on the base frame at intervals, one ends of the steel mesh covers are hinged with the angle steels, the steel mesh plates are fixedly arranged among the steel mesh covers, and a working area is formed among the base frame, the steel mesh plates and the steel mesh covers; an upper channel and a lower channel are formed between the steel mesh cover and the angle steel and the base frame after the steel mesh cover is turned over; a straight ladder is fixedly arranged in the upper channel and the lower channel;
the railing seats are fixedly arranged on two sides of the base frame, and the railing posts are fixedly arranged on the railing seats; the railing is fixedly installed on the side face of the railing post and the side face of the suspension chain.
Preferably, the railing seat is provided with a mounting hole, and one section of the railing post is inserted and fixed in the mounting hole.
Preferably, the number of the railings is three at equal intervals.
Preferably, the ear plate is provided with two through holes, and shackles are hinged in the through holes.
Preferably, a railing hanging ring is arranged on the inner side of the suspension chain, and the railing is fixed with the suspension chain through the railing hanging ring.
Preferably, a suspension clamp is arranged at the top of the suspension chain.
Preferably, chain hooks are arranged at two ends of the handrail.
The utility model discloses technical effect mainly embodies: through the suspension chain passes through otic placode hoist and mount bed frame, recycles steel mesh board, steel mesh lid and lays on the bed frame, forms the work area of the staff of being convenient for work of standing, and the steel mesh lid of deuterogamying is articulated with the bed frame to be convenient for the staff removes between upper and lower adjacent both sides bed frame, whole concatenation forms, not only the installation is simple, the installation effectiveness is high, need not the welding, also is convenient for shorten the period of setting up.
Drawings
FIG. 1 is a diagram A illustrating the effect of the present invention;
fig. 2 is a side view of the present invention;
fig. 3 is a front view of the present invention;
FIG. 4 is a top view of the base frame;
fig. 5 is a usage effect diagram B of the present invention.
The reference signs are: 1-base frame, 11-channel steel, 12-angle steel, 13-ear plate, 14-shackle, 2-steel mesh plate, 3-steel mesh cover, 4-suspension chain, 41-railing suspension ring, 42-suspension clamp, 5-railing, 51-chain hook, 6-railing post, 7-railing seat and 8-vertical ladder.
Detailed Description
The following detailed description of the embodiments of the present invention is made with reference to the accompanying drawings, so as to make the technical solutions of the present invention easier to understand and grasp.
In the present embodiment, it should be understood that the terms "middle", "upper", "lower", "top", "right", "left", "above", "back", "middle", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of describing the present invention, and do not indicate or imply that the referred devices or elements must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
In the present embodiment, if the connection or fixing manner between the components is not specifically described, the connection or fixing manner may be a bolt fixing manner, a pin connecting manner, or the like, which is commonly used in the prior art, and therefore, details thereof are not described in the present embodiment.
A suspended scaffold for ship sectional outer plate construction is shown in figures 1-5 and comprises a base frame 1, a steel mesh plate 2, a steel mesh cover 3, a suspension chain 4, a railing 5, a railing post 6 and a railing seat 7;
the base frame 1 comprises parallel channel steel 11 and angle steel 12 fixed on the channel steel 11 through bolts at equal intervals; the side surface of the base frame 1 is also provided with lug plates 13 at equal intervals, and the suspension chain 4 is used for hoisting the base frame 1 through the lug plates; the steel mesh covers 3 are arranged on the base frame 1 at intervals, one ends of the steel mesh covers are hinged to the angle steels 12, the steel mesh plates 2 are fixedly arranged among the steel mesh covers 3, and a working area is formed among the base frame 1, the steel mesh plates and the steel mesh covers 3, so that workers can stand in the working area to weld and spray paint on outer plates and wall plates of ship sections; the space of a working area can be increased when the steel mesh cover 3 is not turned over, and an up-and-down channel is formed between the steel mesh cover 3 and the angle steel 12 and the base frame 1 after the steel mesh cover 3 is turned over, so that workers can conveniently move up and down to the base frames 1 with different heights; a straight ladder 8 is fixedly arranged in the upper and lower channels, so that the workers can move up and down conveniently;
the railing seats 7 are fixedly arranged on two sides of the base frame 1, and the railing columns 6 are fixedly arranged on the railing seats 7; the railing 5 is fixedly arranged on the side surfaces of the railing post 6 and the suspension chain 4; the railing 5 and the railing post 6 are bound and fixed through iron wires.
The guardrail rod seat 7 is provided with a mounting hole, and one end of the guardrail rod column 6 is inserted and fixed in the mounting hole.
In this embodiment, three balustrades 5 are provided at equal intervals.
The ear plate 13 is provided with two through holes, the through holes are internally hinged with shackles 14, and the suspension chains 4 are prolonged through the shackles and the ear plate, so that the corresponding base frame 1 is arranged according to the working requirement.
The inboard of suspension chain 4 is provided with railing link 41, railing 5 through railing link 41 with suspension chain 4 is fixed.
The top of the suspension chain 4 is provided with a suspension clamp 42 for clamping the top of the outer plate of the valley bottom ship.
The both ends of railing 5 are provided with chain couple 51 for two adjacent railings 5 articulate the chain through chain couple 51, thereby improve the stationarity of scaffold frame, reduce and rock.
In the embodiment, the scaffold is not welded and fixed, so that the construction period is conveniently shortened, and the mounting efficiency of the scaffold is improved; and can extend along direction of height and length direction according to the work demand to because spare part is few and the chain is convenient for roll up and accomodate, the space of stacking is convenient for reduce after the scaffold is demolishd, when solving conventional scaffold and idle, occupation space is big problem.
The utility model discloses technical effect mainly embodies: through the suspension chain passes through otic placode hoist and mount bed frame, recycles steel mesh board, steel mesh cover and lays on the bed frame, forms the work area of the staff work of standing of being convenient for, and the steel mesh cover of deuterogamying is articulated with the bed frame to the staff of being convenient for removes between upper and lower adjacent both sides bed frame, and whole concatenation forms, and not only the installation is simple, the installation effectiveness is high, need not the welding, also is convenient for shorten the period of setting up.
Of course, the above is only a typical example of the present invention, and besides, the present invention can also have other various specific embodiments, and all technical solutions adopting equivalent replacement or equivalent transformation are all within the scope of the present invention as claimed.

Claims (7)

1. A suspended scaffold for ship sectional planking construction is characterized by comprising a base frame, a steel mesh plate, a steel mesh cover, a suspended chain, a railing post and a railing seat;
the pedestal comprises parallel channel steel and angle steel fixed on the channel steel by bolts at equal intervals; the side surface of the base frame is also provided with lug plates at equal intervals, and the suspension chain is used for hoisting the base frame through the lug plates; the steel mesh covers are arranged on the base frame at intervals, one ends of the steel mesh covers are hinged with the angle steels, the steel mesh plates are fixedly arranged among the steel mesh covers, and a working area is formed among the base frame, the steel mesh plates and the steel mesh covers; an upper channel and a lower channel are formed between the steel mesh cover and the angle steel and the base frame after the steel mesh cover is turned over; a straight ladder is fixedly arranged in the upper channel and the lower channel;
the railing seats are fixedly arranged on two sides of the base frame, and the railing columns are fixedly arranged on the railing seats; the railing is fixedly installed on the side surfaces of the railing post and the suspension chain.
2. The suspended scaffold for the segmental planking construction of ships according to claim 1, wherein said rail seat is provided with a mounting hole, and a section of said rail post is inserted and fixed in said mounting hole.
3. The suspended scaffold for ship sectional outer plate construction as claimed in claim 2, wherein three railings are provided at equal intervals.
4. The suspended scaffold for the construction of the outer plate of the ship section as claimed in claim 3, wherein the ear plate is provided with two through holes, and the through holes are internally hinged with shackles.
5. The suspended scaffold for ship sectional planking construction as claimed in claim 4, wherein a rail hanging ring is provided at an inner side of the suspension chain, and the rail is fixed to the suspension chain by the rail hanging ring.
6. The suspended scaffold for the segmental planking construction of ships according to claim 5, wherein a suspension clamp is provided on the top of the suspension chain.
7. The suspended scaffold for ship sectional planking construction as claimed in claim 3, wherein chain hooks are provided at both ends of the balustrade.
CN202223205891.3U 2022-11-30 2022-11-30 Suspension type scaffold is used in boats and ships segmentation planking construction Active CN218617125U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223205891.3U CN218617125U (en) 2022-11-30 2022-11-30 Suspension type scaffold is used in boats and ships segmentation planking construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223205891.3U CN218617125U (en) 2022-11-30 2022-11-30 Suspension type scaffold is used in boats and ships segmentation planking construction

Publications (1)

Publication Number Publication Date
CN218617125U true CN218617125U (en) 2023-03-14

Family

ID=85452550

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223205891.3U Active CN218617125U (en) 2022-11-30 2022-11-30 Suspension type scaffold is used in boats and ships segmentation planking construction

Country Status (1)

Country Link
CN (1) CN218617125U (en)

Similar Documents

Publication Publication Date Title
CN214831957U (en) Assembled multi-high-rise steel column butt joint operation platform
CN214740171U (en) Ancient building wall body hoist and mount migration device
CN218617125U (en) Suspension type scaffold is used in boats and ships segmentation planking construction
CN211470603U (en) Telescopic tower crane passageway
CN204703076U (en) Truss mould plate
CN209780193U (en) Suspension type scaffold
CN110552495A (en) assembled building combined tool type outer protective frame system and construction method thereof
CN104878700A (en) Truss and formwork
JPH09195228A (en) Build-up trestle for bridge pier reinforcing work and its using method
CN111945561B (en) Special-shaped cable tower decorative plate installation device and construction method
CN209924407U (en) Combined working platform for steel structure high-altitude installation
CN112627045A (en) Hang basket template scissors cat ladder
CN113202281A (en) Building templates operation platform
CN114108499A (en) Suspended casting beam reference section hinged type triangular bracket combined hanging basket integrated device and construction method thereof
CN220014399U (en) Hanging basket fixing structure
CN2656540Y (en) Telescopic elevator shaft formwork
CN217517805U (en) Cantilever hidden beam structure convenient to install
CN2238872Y (en) Extension electrical lift well die carrier
CN218667143U (en) Bridge pier column reinforcing bar installation auxiliary stand
CN218779913U (en) Operating platform for pouring operators
CN206477253U (en) Bridge maintenance platform support boom device
CN216999353U (en) Assembled pier stud protection platform
CN219342890U (en) Bridge high pier column prestress tensioning construction platform
CN217627276U (en) Attached hoisting device
CN218581144U (en) Large steel pipe support parallel-connection movable construction platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant