CN218579441U CN202223071377.5U CN202223071377U CN218579441U CN 218579441 U CN218579441 U CN 218579441U CN 202223071377 U CN202223071377 U CN 202223071377U CN 218579441 U CN218579441 U CN 218579441U
Authority
CN
China
Prior art keywords
crossbeam
cross beam
hoist
longeron
concrete pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223071377.5U
Other languages
Chinese (zh)
Inventor
任锦威
温俊林
李�根
王枝超
许力中
陈锦威
张晟
王虎虎
司晋伟
马耀华
马安仁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Fifth Construction Group Co Ltd
Original Assignee
Shanxi Fifth Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Fifth Construction Group Co Ltd filed Critical Shanxi Fifth Construction Group Co Ltd
Priority to CN202223071377.5U priority Critical patent/CN218579441U/en
Application granted granted Critical
Publication of CN218579441U publication Critical patent/CN218579441U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model belongs to the technical field of the pipeline hoist and mount, solved traditional lifting device and can not adapt to the quick hoist and mount and the problem of quality assurance of ordinary level extension concrete pipe section. The utility model provides a concrete pipe hoist device, including U type roof beam, balancing weight and flexible crossbeam, U type roof beam includes first crossbeam, second crossbeam and longeron, is equipped with the rope structure that is used for U type roof beam to go up and down on the first crossbeam, and the one end that the longeron was kept away from to first crossbeam is provided with the balancing weight that is used for pipeline hoist and mount balance, and the one end that the longeron was kept away from to the second crossbeam is connected with flexible crossbeam in the horizontal direction, and flexible crossbeam slides and the accessible retaining member is fixed along the length direction of second crossbeam. The device effectively increases the length of the second beam by arranging the telescopic beam, and can adapt to quick hoisting and quality guarantee of a common-grade lengthened concrete pipe section; the balance of the whole device is realized through the balancing weight.

Description

Concrete pipeline hoist device
Technical Field
The utility model belongs to the technical field of the pipeline hoist and mount, concretely relates to concrete pipeline hoist device.
Background
Drainage works are important subsection works of municipal works, and concrete prefabricated pipe fittings are generally adopted as laid pipelines. Position concrete precast pipe spare length is longer for a bit, and when this type of pipe fitting was hoisted to traditional lifting device, easy the emergence was rocked, can not once install the concrete pipe hoist and mount and target in place, has the problem to the pipeline interface repeatedly, can not adapt to the quick hoist and mount and the quality assurance of ordinary level extension concrete pipe section.
Disclosure of Invention
The utility model discloses a solve traditional lifting device and can not adapt to the quick hoist and mount of ordinary level extension concrete pipe section and the problem of quality assurance, provide a concrete pipe hoist device.
The utility model discloses a following technical scheme realizes: the utility model provides a concrete pipe hoist device, includes U type roof beam, balancing weight and flexible crossbeam, U type roof beam includes first crossbeam, second crossbeam and longeron, is equipped with the rope structure that is used for U type roof beam to go up and down on the first crossbeam, and the one end that the longeron was kept away from to first crossbeam is provided with the balancing weight that is used for pipeline hoist and mount balance, and the one end that the longeron was kept away from to the second crossbeam is connected with flexible crossbeam at the horizontal direction, and flexible crossbeam slides and the accessible retaining member is fixed along the length direction of second crossbeam.
Preferably, the balancing weight is for being equipped with the notched square iron plate, balancing weight slidable connection is on the top of first crossbeam, and the one end of first crossbeam is equipped with the limiting plate that prevents the balancing weight and break away from, is provided with the bolt hole on the balancing weight, and balancing weight accessible clamp bolt fixes on first crossbeam.
Preferably, the telescopic cross beam is provided with a groove structure, a plurality of pulleys are symmetrically arranged at the upper end and the lower end of the groove structure, a sliding rail is arranged on the second cross beam, and the telescopic cross beam is connected with the sliding rail of the second cross beam in a sliding manner through the pulleys; the retaining member is connecting bolt, and equal interval is provided with the bolt hole that is used for installing the retaining member on second crossbeam and the flexible crossbeam.
Preferably, the center position of the longitudinal beam is provided with a manual adjusting centering rod.
Preferably, the outer side of the longitudinal beam is provided with a thrust plate, and the inner side of the longitudinal beam is provided with an anti-collision layer.
Compared with the prior art, the beneficial effects of the utility model are that:
the device effectively increases the length of the second beam by arranging the telescopic beam, and can adapt to quick hoisting and quality guarantee of a common-grade lengthened concrete pipe section; realize the balance of integrated device through the balancing weight, make things convenient for constructor to finely tune the position about the pipeline on telescopic crossbeam through manual regulation centering rod.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required to be used in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a perspective view of the overall structure in the present embodiment;
fig. 2 is a schematic front view of the overall structure in this embodiment.
In the figure: 1-U-shaped beam; 11-a first beam; 111-a limiting plate; 12-a second beam; 13-a stringer; 2-a balancing weight; 3, telescoping a cross beam; 4-a pulley; 5, manually adjusting the centering rod; 6-a thrust plate; 7-an anti-collision layer; 8-a rope structure; 9-a hold-down bolt; 10-locking member.
Detailed Description
The technical solutions in the embodiments of the present invention will be apparent from and fully described in conjunction with the accompanying drawings in the embodiments of the present invention, and it is apparent that the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
It should be understood that the structures, ratios, sizes, etc. shown in the drawings and attached to the description are only used for matching the disclosure and are not used for limiting the practical limitations of the present invention, so that the technical meanings of the modifications, the changes of the ratio relationships or the adjustment of the size of the structure are not essential, and the modifications, the ratio relationships or the adjustment of the size of any structure should still fall within the scope of the technical contents of the present invention without affecting the efficacy and the achievable purpose of the present invention.
The utility model provides an embodiment:
as shown in fig. 1 and 2, a concrete pipeline hoist device, including U type roof beam 1, balancing weight 2 and telescopic cross beam 3, U type roof beam 1 includes first crossbeam 11, second crossbeam 12 and longeron 13, is equipped with the rope structure 8 that is used for U type roof beam 1 to go up and down on first crossbeam 11, and the one end that longeron 13 was kept away from to first crossbeam 11 is provided with balancing weight 2 that is used for pipeline hoist and mount balance, and the one end that longeron 13 was kept away from to second crossbeam 12 is connected with telescopic cross beam 3 at the horizontal direction, and telescopic cross beam 3 slides and accessible retaining member 10 is fixed along the length direction of second crossbeam 12.
In this embodiment, U type roof beam 1 is a U type transverse arrangement's steel member, hangs the tube coupling and hoists on U type crossbeam through hanging, for being fit for ordinary type and the hoist and mount of elongated concrete tube coupling, has set up telescopic crossbeam 3 device at U type opening part, through adjusting telescopic crossbeam 3 for the flexible distance of second crossbeam 12, adapts to the hoist and mount that is fit for ordinary type and elongated concrete tube coupling. Wherein 11 long 1.8m of first crossbeam of U type roof beam, second crossbeam 12 are equipped with flexible crossbeam 3, and the overall length is 2.5m after flexible, and the length of second crossbeam 12 is 1.5m, can freely assemble flexible section length 1.5m, and flexible crossbeam 3 and the overlap joint of second crossbeam 12 are 50cm, and the flexible section length of bottom telescoping device overlap joint part uses the pulley to adjust.
The counterweight block 2 is a square iron block provided with a groove, the counterweight block 2 can be connected to the top end of the first cross beam 11 in a sliding manner, one end of the first cross beam 11 is provided with a limiting plate 111 for preventing the counterweight block 2 from being separated, the counterweight block 2 is provided with a bolt hole, and the counterweight block 2 can be fixed on the first cross beam 11 through a compression bolt 9; in order to ensure balanced hoisting and even stress, the counterweight block 2 is arranged above the first cross beam 11, the counterweight can be adjusted according to the actual construction situation on site, the balance of the concrete pipe fitting is controlled or one end of the concrete pipe fitting is inclined, so that the alignment and installation of the pipeline are facilitated, and particularly the installation of the lengthened concrete pipe joint is realized.
The telescopic cross beam 3 is provided with a groove structure, the upper end and the lower end of the groove structure are symmetrically provided with a plurality of pulleys 4, the second cross beam 12 is provided with a slide rail, and the telescopic cross beam 3 is connected with the slide rail of the second cross beam 12 in a sliding manner through the pulleys 4; retaining member 10 is connecting bolt, and second crossbeam 12 and telescopic crossbeam 3 are all provided with the bolt hole that is used for installing retaining member 10 at the interval. One end of the second beam 12 is provided with a limiting structure to prevent the telescopic beam 3 from separating from the second beam 12.
And a manual adjusting centering rod 5 is arranged at the central position of the longitudinal beam 13, the rod length of the manual adjusting centering rod 5 is 80cm, each side of the manual adjusting centering rod exceeds 25cm of the U-shaped beam, and the manual adjusting centering rod is welded by a phi 32 steel bar. The centering device is used for centering the concrete pipeline, so that the center line position of the concrete pipeline is effectively guaranteed, and the accuracy of the forming position of the concrete pipeline is effectively guaranteed.
A thrust plate 6 is arranged on the outer side of the longitudinal beam 13, and an anti-collision layer 7 is arranged on the inner side of the longitudinal beam 13; anticollision layer 7 adopts flexible material, prevents that concrete pipeline's pipeline section from rather than the collision, causes the damage to the device, and then reduces life, but the outside of longeron 13 sets up thrust plate 6 that can collide, and thrust plate 6 adopts 1cm back steel sheet, and steel sheet width 40cm for the installation is impeld to machinery, guarantees to connect closely between the pipe fitting.
The utility model discloses a theory of operation is: according to waiting to hoist concrete pipe's size adjustment telescopic beam's flexible length, mediate the counter weight according to the actual construction condition in scene again, promote the distance plate and make U type roof beam remove, the balanced or one end slope of the telescopic beam of 5 control of rethread manual regulation centering rod inserts concrete pipe spare, contacts with anticollision layer 7 when concrete pipe spare's one end, accomplishes concrete pipe's hoist and mount through the hoist and mount rope. When the pipelines are in butt joint, the concrete pipeline is moved to a preset position only through the hoisting rope, and the position of the concrete pipeline opening is adjusted through manually adjusting the centering rod.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any changes or substitutions that can be easily conceived by those skilled in the art within the technical scope of the present invention should be covered by the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (5)

1. The utility model provides a concrete pipe hoist device, its characterized in that, including U type roof beam (1), balancing weight (2) and telescopic cross beam (3), U type roof beam (1) is equipped with rope structure (8) that are used for U type roof beam (1) to go up and down including first crossbeam (11), second crossbeam (12) and longeron (13) on first crossbeam (11), and the one end of longeron (13) is kept away from in first crossbeam (11) is provided with balancing weight (2) that are used for pipeline hoist and mount balance, and the one end that longeron (13) were kept away from in second crossbeam (12) is connected with telescopic cross beam (3) in the horizontal direction, and telescopic cross beam (3) slide and accessible retaining member (10) are fixed along the length direction of second crossbeam (12).
2. The concrete pipeline hoisting device according to claim 1, wherein the counterweight (2) is a square iron block provided with a groove, the counterweight (2) is slidably connected to the top end of the first beam (11), one end of the first beam (11) is provided with a limiting plate (111) for preventing the counterweight (2) from being separated, the counterweight (2) is provided with a bolt hole, and the counterweight (2) can be fixed on the first beam (11) through a pressing bolt (9).
3. The concrete pipeline hoisting device according to claim 1, wherein the telescopic cross beam (3) is provided with a groove structure, a plurality of pulleys (4) are symmetrically arranged at the upper end and the lower end of the groove structure, slide rails are arranged at the upper end and the lower end of the second cross beam (12), and the telescopic cross beam (3) is slidably connected with the slide rails of the second cross beam (12) through the pulleys (4); retaining member (10) are connecting bolt, and equal interval is provided with the bolt hole that is used for installing retaining member (10) on second crossbeam (12) and telescopic cross beam (3).
4. A concrete pipe hoist according to claim 1, characterized in that the longitudinal beam (13) is provided with a manually adjustable centering rod (5) in its central position.
5. The concrete pipe hoisting device according to claim 4, wherein the outer side of the longitudinal beam (13) is provided with a thrust plate (6), and the inner side of the longitudinal beam (13) is provided with an anti-collision layer (7).
CN202223071377.5U 2022-11-20 2022-11-20 Concrete pipeline hoist device Active CN218579441U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223071377.5U CN218579441U (en) 2022-11-20 2022-11-20 Concrete pipeline hoist device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223071377.5U CN218579441U (en) 2022-11-20 2022-11-20 Concrete pipeline hoist device

Publications (1)

Publication Number Publication Date
CN218579441U true CN218579441U (en) 2023-03-07

Family

ID=85378981

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223071377.5U Active CN218579441U (en) 2022-11-20 2022-11-20 Concrete pipeline hoist device

Country Status (1)

Country Link
CN (1) CN218579441U (en)

Similar Documents

Publication Publication Date Title
US8317244B1 (en) Apparatus and method for positioning an object in a building
CN108147273A (en) A kind of adjustable large-scale steel pipe suspender
CN218579441U (en) Concrete pipeline hoist device
CN207109546U (en) A kind of interim hinge device of arch rib
CN210976552U (en) Foldable operation platform device in elevator shaft
CN209568372U (en) A kind of interim articulated structure of suspension bridge stiffened steel girder
CN111379227A (en) Variable-width platform device for hydraulic creeping formwork for quickly constructing double-limb cable tower and construction method
CN212358012U (en) Widening platform device of hydraulic creeping formwork for quickly constructing double-limb cable tower
CN110409684A (en) A kind of civilian villa liftable roof truss
CN208814490U (en) A kind of novel drainage ditch cover plate hanging apparatus
CN210342669U (en) Anti-bank activity reinforcing apparatus of cast in situ concrete
CN205838299U (en) A kind of simple and easy hoisting device
CN217947344U (en) Prefabricated component lifting device
CN215828159U (en) Lifting appliance for reinforced concrete pipe
CN220747725U (en) Superimposed sheet hoist and mount positioner
CN220080849U (en) Ancient building roofing hanging wire device
CN220745086U (en) Lifting appliance for prefabricated wallboard
CN220412691U (en) Tower crane attachment fixing device
CN209308383U (en) It is a kind of for prevent damage exterior finish split blade type hydraulic lifting climbing frame
CN218841482U (en) Pipeline lifting device for construction
CN213202175U (en) Connecting suspension arm for tower crane
CN220868890U (en) Precast shear wall hoist and mount positioner
CN217676331U (en) QT integrated board hoist and mount protection device
CN209651720U (en) Architectural Equipment Multifunctional hoisting device
CN218988579U (en) Hydropower pipeline installation overhead hoist

Legal Events