CN218560816U CN202223133627.3U CN202223133627U CN218560816U CN 218560816 U CN218560816 U CN 218560816U CN 202223133627 U CN202223133627 U CN 202223133627U CN 218560816 U CN218560816 U CN 218560816U
Authority
CN
China
Prior art keywords
welded
cylinder
frame
lifting
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202223133627.3U
Other languages
Chinese (zh)
Inventor
王恒
张传儒
宋潇
宋杰
李锋
李胜国
孙伟亮
周鲁
何海玉
尚伟军
任冰心
梁龙
曲超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Engineering Co Ltd of China Railway 14th Bureau Co Ltd
Original Assignee
Fourth Engineering Co Ltd of China Railway 14th Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd of China Railway 14th Bureau Co Ltd filed Critical Fourth Engineering Co Ltd of China Railway 14th Bureau Co Ltd
Priority to CN202223133627.3U priority Critical patent/CN218560816U/en
Application granted granted Critical
Publication of CN218560816U publication Critical patent/CN218560816U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a net rack lifting support on a hoop steel frame column, which comprises a connecting frame, wherein the connecting frame is symmetrically welded at the tops of two sides of a concrete frame, a vertical beam is welded on the connecting frame, and a limiting component is arranged on the vertical beam at one side; the transverse beam is welded at the tops of the vertical beams at two sides, the top of the transverse beam is welded with a lifting platform beam, a lifting machine is installed on one side, far away from the vertical beams, of the top of the lifting platform beam, and the limiting assembly comprises an installation component, a fixing cylinder and an adjusting mechanism; the mounting member includes a first stiffener plate and a second stiffener plate. The utility model discloses a spacing lifting rope of gyro wheel makes the lifting rope steadily promote, through adjusting the distance between structure regulation grip block and the lifting rope, through the fixed lifting rope of grip block centre gripping, can play the stabilizing action to lifting rope after lifting by crane, dismantles and installs the solid fixed cylinder through the mounting member convenience, and the stiffening plate increases the bearing capacity of solid fixed cylinder, increases the security.

Description

一种抱箍钢框柱上的网架提升支架A network frame lifting bracket on a hoop steel frame column

技术领域technical field

本实用新型涉及网架提升相关技术领域,具体为一种抱箍钢框柱上的网架提升支架。The utility model relates to the technical field related to grid lifting, in particular to a grid lifting bracket on a hooped steel frame column.

背景技术Background technique

网架是由多根杆件按照一定的网格形式通过节点连结而成的空间结构,构成网架的基本单元有三角锥、三棱体、正方体和截头四角锥等,这些基本单元可组合成平面形状的三边形、四边形、六边形和圆形或其他任何形体,具有空间受力、重量轻、刚度大、抗震性能好等优点,可用作体育馆、影剧院、展览厅、候车厅、体育场看台雨篷、飞机库、双向大柱网架结构距车间等建筑的屋盖。The grid is a spatial structure formed by connecting multiple rods through nodes according to a certain grid form. The basic units that constitute the grid include triangular pyramids, triangular bodies, cubes, and truncated quadrangular pyramids. These basic units can be combined Trigons, quadrangles, hexagons and circles or any other shapes in a plane shape have the advantages of space force, light weight, high rigidity, and good seismic performance. They can be used as gymnasiums, theaters, exhibition halls, and waiting halls. , stadium stand canopy, hangar, two-way large column grid structure and the roof of the workshop and other buildings.

网架工程建设需要进行高空作业,现有的网架提升主要采用提升机,提升机需要搭设提升支架,现有的提升支架结构单一,未设置限位组件,提升稳定性不足,安全系数较低。The construction of the network frame project requires high-altitude operations. The existing network frame is mainly lifted by a hoist, and the hoist needs to be erected with a lifting bracket. The existing lifting bracket has a single structure and no limit components are set. The lifting stability is insufficient and the safety factor is low. .

实用新型内容Utility model content

本实用新型的目的在于提供一种抱箍钢框柱上的网架提升支架,以解决上述背景技术中提出的问题。The purpose of this utility model is to provide a network frame lifting bracket on a hooped steel frame column to solve the problems raised in the above-mentioned background technology.

为实现上述目的,本实用新型提供如下技术方案:一种抱箍钢框柱上的网架提升支架,装载在混凝土框架顶部,包括:In order to achieve the above purpose, the utility model provides the following technical solutions: a grid lifting bracket on the hoop steel frame column, which is loaded on the top of the concrete frame, including:

连接框架,所述连接框架对称焊接于混凝土框架两侧顶部,连接框架上焊接有竖梁,一侧竖梁上设置有限位组件;A connection frame, the connection frame is symmetrically welded to the tops of both sides of the concrete frame, a vertical beam is welded on the connection frame, and a limiting component is arranged on one side of the vertical beam;

横梁,横梁焊接于两侧竖梁顶部,横梁顶部焊接有提升平台梁,提升平台梁顶部远离竖梁的一侧安装有提升机。The crossbeam is welded to the top of the vertical beams on both sides, the top of the crossbeam is welded with a lifting platform beam, and the side of the lifting platform beam top away from the vertical beam is equipped with a hoist.

作为本技术方案的进一步优选的,所述限位组件包括安装构件、固定筒和调节机构,安装构件包括第一加劲板和第二加劲板,第一加劲板焊接于固定筒一侧上端,第二加劲板焊接于固定筒一侧下端。As a further preference of this technical solution, the limit assembly includes a mounting member, a fixing cylinder and an adjustment mechanism, the mounting member includes a first stiffening plate and a second stiffening plate, the first stiffening plate is welded to the upper end of one side of the fixing cylinder, the second The two stiffeners are welded to the lower end of one side of the fixed cylinder.

作为本技术方案的进一步优选的,所述第一加劲板和第二加劲板远离固定筒的一端均焊接有连接支架,连接支架的两端焊接有安装板,安装板通过螺栓安装于一侧竖梁相互靠近的一端。As a further preference of this technical solution, the ends of the first stiffening plate and the second stiffening plate far away from the fixing cylinder are welded with connecting brackets, and the two ends of the connecting bracket are welded with mounting plates, and the mounting plates are installed on one side of the vertical wall through bolts. The ends of the beams that are close to each other.

作为本技术方案的进一步优选的,所述调节机构包括电机盒和转筒,电机盒内部安装有电机,电机输出端固定套设有直齿轮,转筒设置于固定筒内腔。As a further preferred aspect of the technical solution, the adjustment mechanism includes a motor box and a rotating cylinder, a motor is installed inside the motor box, a spur gear is fixedly sleeved at the output end of the motor, and the rotating cylinder is arranged in the inner cavity of the fixing cylinder.

作为本技术方案的进一步优选的,所述固定筒顶部和底部均安装有轴承垫圈,轴承垫圈通过轴承与转筒顶部和底部转动连接,转筒内部螺纹套设有导向筒,导向筒内部对称设置有夹持板。As a further preference of this technical solution, bearing washers are installed on the top and bottom of the fixed cylinder, and the bearing washers are rotatably connected with the top and bottom of the rotating cylinder through bearings, and the internal thread of the rotating cylinder is provided with a guide cylinder, which is arranged symmetrically With clamping plate.

作为本技术方案的进一步优选的,所述夹持板外侧固定有连接板,连接板通过传动杆与导向筒内壁铰接,夹持板底部安装有滑板,滑板与底部轴承垫圈滑动连接。As a further preferred solution of this technical solution, a connecting plate is fixed on the outside of the clamping plate, the connecting plate is hinged to the inner wall of the guide cylinder through a transmission rod, a slide plate is installed at the bottom of the clamping plate, and the slide plate is slidably connected to the bottom bearing washer.

作为本技术方案的进一步优选的,所述电机盒安装于第一加劲板顶部,且与固定筒的一侧固定连接,电机盒和固定筒相贴合的一侧开设有通孔,转筒的外侧与固定筒内壁不接触,转筒外侧开设有齿槽,直齿轮部位位于通孔内部,且与齿槽啮合。As a further preference of this technical solution, the motor box is installed on the top of the first stiffening plate, and is fixedly connected to one side of the fixed cylinder, and a through hole is opened on the side of the motor box and the fixed cylinder, and the rotating cylinder The outer side is not in contact with the inner wall of the fixed cylinder, and the outer side of the rotating cylinder is provided with tooth grooves, and the spur gear is located inside the through hole and meshes with the tooth grooves.

作为本技术方案的进一步优选的,所述夹持板内侧开设有凹槽,凹槽内滑动安装有安装框,安装框和凹槽间固定有弹簧,安装框内侧配合有滚轮。As a further preferred embodiment of the technical solution, a groove is provided on the inner side of the clamping plate, a mounting frame is slidably installed in the groove, a spring is fixed between the mounting frame and the groove, and rollers are fitted on the inside of the mounting frame.

本实用新型提供了一种抱箍钢框柱上的网架提升支架,具备以下有益效果:The utility model provides a grid lifting bracket on a hoop steel frame column, which has the following beneficial effects:

1本实用新型通过滚轮限位起吊绳,使起吊绳平稳提升,通过调节结构调节夹持板与起吊绳之间的距离,通过夹持板夹持固定起吊绳,能够在起吊后对起吊绳起到稳定作用,通过安装构件方便对固定筒进行拆卸和安装,加劲板增加固定筒的承载能力,增加安全性。1 The utility model limits the hoisting rope through the rollers, so that the hoisting rope can be lifted smoothly, adjusts the distance between the clamping plate and the hoisting rope by adjusting the structure, clamps and fixes the hoisting rope through the clamping plate, and can lift the hoisting rope after hoisting To achieve a stable effect, it is convenient to disassemble and install the fixed cylinder through the installation components, and the stiffening plate increases the bearing capacity of the fixed cylinder and increases safety.

附图说明Description of drawings

图1为本实用新型的整体结构示意图;Fig. 1 is the overall structural representation of the utility model;

图2为本实用新型的安装构件在固定筒上分布示意图;Fig. 2 is a schematic diagram of the distribution of the installation components of the present invention on the fixed cylinder;

图3为本实用新型的调节结构在固定筒上分布示意图;Fig. 3 is a schematic diagram of the distribution of the adjustment structure of the utility model on the fixed cylinder;

图4为本实用新型的直齿轮与转筒连接结构俯视图;Fig. 4 is a top view of the connection structure between the spur gear and the drum of the present invention;

图5为本实用新型的固定筒内部结构剖面图;Fig. 5 is a sectional view of the internal structure of the fixed cylinder of the present invention;

图6为本实用新型的图5中A处结构放大图;Figure 6 is an enlarged view of the structure at A in Figure 5 of the present utility model;

图7为转筒内部结构俯视图。Figure 7 is a top view of the internal structure of the drum.

图中:1、混凝土框架;2、连接框架;3、竖梁;4、横梁;5、提升平台梁;6、提升机;7、固定筒;8、第一加劲板;9、第二加劲板;10、连接支架;11、安装板;12、电机盒;13、轴承垫圈;14、电机;15、直齿轮;16、转筒;17、导向筒;18、夹持板;19、连接板;20、传动杆;21、安装框;22、滚轮;23、弹簧;24、滑板。In the figure: 1. Concrete frame; 2. Connecting frame; 3. Vertical beam; 4. Beam; 5. Lifting platform beam; 6. Hoist; 7. Fixed cylinder; 8. First stiffening plate; Plate; 10, connecting bracket; 11, mounting plate; 12, motor box; 13, bearing washer; 14, motor; 15, spur gear; 16, rotating cylinder; 17, guide cylinder; 18, clamping plate; Plate; 20, transmission rod; 21, installation frame; 22, roller; 23, spring; 24, slide plate.

具体实施方式Detailed ways

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

下面结合附图描述本实用新型的具体实施例Describe the specific embodiment of the utility model below in conjunction with accompanying drawing

如图1所示,一种抱箍钢框柱上的网架提升支架,装载在混凝土框架1顶部,包括:As shown in Figure 1, a network frame lifting bracket on a hooped steel frame column is loaded on the top of a concrete frame 1, including:

连接框架2,连接框架2对称焊接于混凝土框架1两侧顶部,连接框架2共有四组,四组连接框架2与混凝土框架1顶部平行,部分连接框架2浇筑在混凝土框架1内部,连接框架2上焊接有竖梁3,竖梁3与连接框架2垂直,一侧竖梁3上设置有限位组件,限位组件靠近提升机6,起到限位提升机6上起吊绳的作用。Connection frame 2, connection frame 2 is symmetrically welded to the top of both sides of concrete frame 1, there are four groups of connection frame 2, four groups of connection frame 2 are parallel to the top of concrete frame 1, part of connection frame 2 is poured inside concrete frame 1, connection frame 2 Vertical beam 3 is welded on the top, and vertical beam 3 is perpendicular to connecting frame 2, and limit assembly is arranged on one side vertical beam 3, and limit assembly is close to hoist 6, plays the effect of lifting rope on the limit hoist 6.

如图2所示,限位组件包括安装构件、固定筒7和调节机构,安装构件包括第一加劲板8和第二加劲板9,第一加劲板8焊接于固定筒7一侧上端,第二加劲板9焊接于固定筒7一侧下端,第一加劲板8和第二加劲板9起到支撑固定筒7的作用。As shown in Figure 2, the limit assembly includes a mounting member, a fixing cylinder 7 and an adjustment mechanism, the mounting member includes a first stiffening plate 8 and a second stiffening plate 9, the first stiffening plate 8 is welded to the upper end of one side of the fixing cylinder 7, the second Two stiffening plates 9 are welded to the lower end of one side of the fixing cylinder 7 , and the first stiffening plate 8 and the second stiffening plate 9 play a role in supporting the fixing cylinder 7 .

如图3所示,调节机构包括电机盒12和转筒16,电机盒12内部安装有电机14,电机14输出端固定套设有直齿轮15,转筒16设置于固定筒7内腔,电机盒12起到保护电机14的作用,电机14与外部电源开关电性连接,直齿轮15与电机14不接触。As shown in Figure 3, the adjustment mechanism includes a motor box 12 and a rotating cylinder 16, a motor 14 is installed inside the motor box 12, a spur gear 15 is fixedly sleeved at the output end of the motor 14, the rotating cylinder 16 is arranged in the inner cavity of the fixed cylinder 7, and the motor The box 12 plays the role of protecting the motor 14, the motor 14 is electrically connected with the external power switch, and the spur gear 15 is not in contact with the motor 14.

如图1、图2、图3和图7所示,电机盒12安装于第一加劲板8顶部,且与固定筒7的一侧固定连接,电机盒12和固定筒7相贴合的一侧开设有通孔,转筒16的外侧与固定筒7内壁不接触,避免转筒16转动受到固定筒7阻挡,转筒16外侧开设有齿槽,直齿轮15部位位于通孔内部,且与齿槽啮合,通孔与直齿轮15间具有活动间隙,直齿轮15在通孔内能够转动,通过齿槽带动转筒16转动。As shown in Figure 1, Figure 2, Figure 3 and Figure 7, the motor box 12 is installed on the top of the first stiffening plate 8, and is fixedly connected with one side of the fixed cylinder 7, and the motor box 12 and the fixed cylinder 7 are fitted together. A through hole is opened on the side, and the outer side of the drum 16 is not in contact with the inner wall of the fixed drum 7, so as to prevent the rotation of the drum 16 from being blocked by the fixed drum 7. The outer side of the drum 16 is provided with tooth grooves, and the spur gear 15 is located inside the through hole, and is connected with the The tooth grooves are meshed, and there is a movable gap between the through hole and the spur gear 15. The spur gear 15 can rotate in the through hole, and the rotating cylinder 16 is driven to rotate through the tooth grooves.

如图1所示,横梁4,横梁4焊接于两侧竖梁3顶部,横梁4顶部焊接有提升平台梁5,提升平台梁5顶部远离竖梁3的一侧安装有提升机6,提升平台梁5起到安装和固定提升机6的作用。As shown in Figure 1, crossbeam 4, crossbeam 4 are welded on both sides vertical beam 3 tops, and crossbeam 4 tops are welded with lifting platform beam 5, and the side of lifting platform beam 5 top away from vertical beam 3 is equipped with hoist 6, and lifting platform The beam 5 plays the role of installing and fixing the hoist 6.

如图3和图4所示,固定筒7顶部和底部均安装有轴承垫圈13,轴承垫圈13通过轴承与转筒16顶部和底部转动连接,固定筒7、转筒16、导向筒17顶部和底部均开设有开口,轴承垫圈13呈圆环形,通过轴承限位转筒16,转筒16内部螺纹套设有导向筒17,导向筒17比转筒16高度短,导向筒17在转筒16内部具有螺纹升降空间,转筒16和固定筒7高度相同,导向筒17内部对称设置有夹持板18,夹持板18顶部截面为圆弧形,夹持板18内侧呈弧形凹陷,增加与起吊绳表面的接触面积,夹持板18为耐磨材质,增加与起吊绳之间的阻力,增加稳定性。As shown in Fig. 3 and Fig. 4, bearing washer 13 is installed on the top and bottom of fixed cylinder 7, bearing washer 13 is connected with rotating cylinder 16 top and bottom by bearing, fixed cylinder 7, rotating cylinder 16, guide cylinder 17 tops and There are openings at the bottom, the bearing washer 13 is circular, and the rotating drum 16 is limited by the bearing. The inner thread of the rotating drum 16 is provided with a guide cylinder 17, which is shorter than the height of the rotating drum 16. 16 has a threaded lifting space inside, the rotating cylinder 16 and the fixed cylinder 7 have the same height, and the inside of the guide cylinder 17 is symmetrically provided with a clamping plate 18, the top section of the clamping plate 18 is arc-shaped, and the inner side of the clamping plate 18 is curved and concave Increase the contact area with the surface of the lifting rope, and the clamping plate 18 is made of wear-resistant material, which increases the resistance between the lifting rope and the stability.

如图5和图6所示,夹持板18内侧开设有凹槽,凹槽内滑动安装有安装框21,通过凹槽限位安装框21,安装框21和凹槽间固定有弹簧23,安装框21内侧配合有滚轮22,弹簧23呈压缩状态时,滚轮22完全进入凹槽内部,弹簧23未受到压力时,滚轮22部位位于凹槽外侧。As shown in Figures 5 and 6, a groove is provided on the inner side of the clamping plate 18, and a mounting frame 21 is slidably installed in the groove, and the mounting frame 21 is limited by the groove, and a spring 23 is fixed between the mounting frame 21 and the groove. The inner side of the installation frame 21 is equipped with a roller 22. When the spring 23 is compressed, the roller 22 enters the groove completely. When the spring 23 is not under pressure, the roller 22 is located outside the groove.

如图1和图2所示,本实施例中,具体的:第一加劲板8和第二加劲板9远离固定筒7的一端均焊接有连接支架10,连接支架10的两端焊接有安装板11,安装板11通过螺栓安装于一侧竖梁3相互靠近的一端,通过安装板11和螺栓实现对限位组件的安装和固定。As shown in Figures 1 and 2, in this embodiment, specifically: the ends of the first stiffening plate 8 and the second stiffening plate 9 away from the fixed cylinder 7 are welded with connecting brackets 10, and the two ends of the connecting bracket 10 are welded with mounting brackets. The plate 11 and the mounting plate 11 are installed on one end of the side vertical beam 3 close to each other through bolts, and the installation and fixing of the position-limiting components are realized through the mounting plate 11 and the bolts.

如图5所示,本实施例中,具体的:夹持板18外侧固定有连接板19,连接板19通过传动杆20与导向筒17内壁铰接,传动杆20共有两组,两组传动杆20呈向下倾斜设置,夹持板18底部安装有滑板24,滑板24与底部轴承垫圈13滑动连接,滑板24起到限位夹持板18的作用,直线夹持板18的直线滑动。As shown in Figure 5, in this embodiment, specifically: the connecting plate 19 is fixed on the outside of the clamping plate 18, and the connecting plate 19 is hinged to the inner wall of the guide cylinder 17 through the transmission rod 20. The transmission rod 20 has two groups, and the two groups of transmission rods 20 is inclined downwards and is provided with a slide plate 24 at the bottom of the clamping plate 18. The slide plate 24 is slidably connected with the bottom bearing washer 13. The slide plate 24 plays the role of limiting the clamping plate 18, and the straight line sliding of the clamping plate 18.

工作原理,在使用时,通过螺栓将安装板11安装固定,将起吊绳端部穿过固定筒7,且位于两个夹持板18间,启动电机14,电机14带动直齿轮15转动,直齿轮15带动转筒16转动,转筒16带动导向筒17螺纹转动,导向筒17带动两个夹持板18相互靠近,使滚轮22与导向绳贴合,提升机6驱动起吊绳对网架提升时,滚轮22在安装框21内部滚动,起到限位起吊绳的作用,使起吊绳稳定滑动,需要固定起吊绳时,启动电机14带动两个夹持板18相互靠近,此时滚轮22受到挤压,带动安装框21在凹槽内部滑动,滑动过程中挤压弹簧23,滚轮22进入凹槽内部,两个夹持板18固定夹持住起吊绳并固定。The working principle is that when in use, the mounting plate 11 is installed and fixed by bolts, the end of the lifting rope is passed through the fixing cylinder 7, and is located between the two clamping plates 18, the motor 14 is started, and the motor 14 drives the spur gear 15 to rotate. The gear 15 drives the rotary drum 16 to rotate, and the rotary drum 16 drives the guide cylinder 17 to rotate threadedly. The guide cylinder 17 drives the two clamping plates 18 to approach each other, so that the roller 22 fits the guide rope, and the hoist 6 drives the lifting rope to lift the grid frame , the roller 22 rolls inside the installation frame 21, and plays the role of limiting the lifting rope, so that the lifting rope slides stably. When the lifting rope needs to be fixed, the starting motor 14 drives the two clamping plates 18 to approach each other. Squeeze to drive the installation frame 21 to slide inside the groove, squeeze the spring 23 during the sliding process, the roller 22 enters the inside of the groove, and the two clamping plates 18 fixedly clamp and fix the lifting rope.

尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, those skilled in the art can understand that various changes and modifications can be made to these embodiments without departing from the principle and spirit of the present invention , replacements and modifications, the scope of the present utility model is defined by the appended claims and their equivalents.

Claims (8)

1.一种抱箍钢框柱上的网架提升支架,装载在混凝土框架(1)顶部,其特征在于,包括:1. A network frame lifting bracket on a hoop steel frame column, loaded on the top of a concrete frame (1), is characterized in that, comprising: 连接框架(2),所述连接框架(2)对称焊接于混凝土框架(1)两侧顶部,连接框架(2)上焊接有竖梁(3),一侧竖梁(3)上设置有限位组件;The connection frame (2), the connection frame (2) is symmetrically welded to the top of both sides of the concrete frame (1), the vertical beam (3) is welded on the connection frame (2), and the vertical beam (3) on one side is provided with a limit components; 横梁(4),横梁(4)焊接于两侧竖梁(3)顶部,横梁(4)顶部焊接有提升平台梁(5),提升平台梁(5)顶部远离竖梁(3)的一侧安装有提升机(6)。The beam (4), the beam (4) is welded to the top of the vertical beams (3) on both sides, the top of the beam (4) is welded with the lifting platform beam (5), and the top of the lifting platform beam (5) is away from the side of the vertical beam (3) A hoist (6) is installed. 2.根据权利要求1所述的一种抱箍钢框柱上的网架提升支架,其特征在于:所述限位组件包括安装构件、固定筒(7)和调节机构,安装构件包括第一加劲板(8)和第二加劲板(9),第一加劲板(8)焊接于固定筒(7)一侧上端,第二加劲板(9)焊接于固定筒(7)一侧下端。2. A network frame lifting bracket on a hoop steel frame column according to claim 1, characterized in that: said limit assembly includes a mounting member, a fixing cylinder (7) and an adjustment mechanism, and the mounting member includes a first Stiffener (8) and the second stiffener (9), the first stiffener (8) is welded on the upper end of one side of the fixed cylinder (7), and the second stiffener (9) is welded on the lower end of one side of the fixed cylinder (7). 3.根据权利要求2所述的一种抱箍钢框柱上的网架提升支架,其特征在于:所述第一加劲板(8)和第二加劲板(9)远离固定筒(7)的一端均焊接有连接支架(10),连接支架(10)的两端焊接有安装板(11),安装板(11)通过螺栓安装于一侧竖梁(3)相互靠近的一端。3. The grid lifting bracket on the hooped steel frame column according to claim 2, characterized in that: the first stiffening plate (8) and the second stiffening plate (9) are far away from the fixing cylinder (7) One end of each is welded with connecting bracket (10), and the two ends of connecting bracket (10) are welded with mounting plate (11), and mounting plate (11) is installed in an end that side vertical beam (3) is close to each other by bolt. 4.根据权利要求2所述的一种抱箍钢框柱上的网架提升支架,其特征在于:所述调节机构包括电机盒(12)和转筒(16),电机盒(12)内部安装有电机(14),电机(14)输出端固定套设有直齿轮(15),转筒(16)设置于固定筒(7)内腔。4. The grid lifting bracket on the hoop steel frame column according to claim 2, characterized in that: the adjustment mechanism includes a motor box (12) and a rotating drum (16), and the inside of the motor box (12) A motor (14) is installed, and the output end of the motor (14) is fixedly sleeved with a spur gear (15), and the rotating cylinder (16) is arranged in the inner cavity of the fixed cylinder (7). 5.根据权利要求2所述的一种抱箍钢框柱上的网架提升支架,其特征在于:所述固定筒(7)顶部和底部均安装有轴承垫圈(13),轴承垫圈(13)通过轴承与转筒(16)顶部和底部转动连接,转筒(16)内部螺纹套设有导向筒(17),导向筒(17)内部对称设置有夹持板(18)。5. The network frame lifting bracket on a hoop steel frame column according to claim 2, characterized in that: bearing washers (13) are installed on the top and bottom of the fixed cylinder (7), and the bearing washers (13) ) is rotationally connected with the top and bottom of the rotating cylinder (16) through bearings, the internal thread of the rotating cylinder (16) is provided with a guide cylinder (17), and the inside of the guide cylinder (17) is symmetrically provided with a clamping plate (18). 6.根据权利要求5所述的一种抱箍钢框柱上的网架提升支架,其特征在于:所述夹持板(18)外侧固定有连接板(19),连接板(19)通过传动杆(20)与导向筒(17)内壁铰接,夹持板(18)底部安装有滑板(24),滑板(24)与底部轴承垫圈(13)滑动连接。6. The network frame lifting bracket on a hoop steel frame column according to claim 5, characterized in that: a connecting plate (19) is fixed on the outside of the clamping plate (18), and the connecting plate (19) passes through The transmission rod (20) is hinged with the inner wall of the guide cylinder (17), and a slide plate (24) is installed at the bottom of the clamping plate (18), and the slide plate (24) is slidably connected with the bottom bearing washer (13). 7.根据权利要求4所述的一种抱箍钢框柱上的网架提升支架,其特征在于:所述电机盒(12)安装于第一加劲板(8)顶部,且与固定筒(7)的一侧固定连接,电机盒(12)和固定筒(7)相贴合的一侧开设有通孔,转筒(16)的外侧与固定筒(7)内壁不接触,转筒(16)外侧开设有齿槽,直齿轮(15)部位位于通孔内部,且与齿槽啮合。7. The network frame lifting bracket on the hoop steel frame column according to claim 4, characterized in that: the motor box (12) is installed on the top of the first stiffening plate (8), and is connected with the fixed cylinder ( One side of 7) is fixedly connected, and the side where the motor box (12) and the fixed cylinder (7) fit together is provided with a through hole, the outer side of the rotating cylinder (16) does not contact the inner wall of the fixed cylinder (7), and the rotating cylinder ( 16) The outer side is provided with tooth grooves, and the spur gear (15) is located inside the through hole and meshes with the tooth grooves. 8.根据权利要求5所述的一种抱箍钢框柱上的网架提升支架,其特征在于:所述夹持板(18)内侧开设有凹槽,凹槽内滑动安装有安装框(21),安装框(21)和凹槽间固定有弹簧(23),安装框(21)内侧配合有滚轮(22)。8. The network frame lifting bracket on a hoop steel frame column according to claim 5, characterized in that: the inner side of the clamping plate (18) is provided with a groove, and a mounting frame ( 21), a spring (23) is fixed between the mounting frame (21) and the groove, and a roller (22) is matched with the mounting frame (21) inboard.
CN202223133627.3U 2022-11-25 2022-11-25 Net rack lifting support on hoop steel frame column Expired - Fee Related CN218560816U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223133627.3U CN218560816U (en) 2022-11-25 2022-11-25 Net rack lifting support on hoop steel frame column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223133627.3U CN218560816U (en) 2022-11-25 2022-11-25 Net rack lifting support on hoop steel frame column

Publications (1)

Publication Number Publication Date
CN218560816U true CN218560816U (en) 2023-03-03

Family

ID=85305590

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223133627.3U Expired - Fee Related CN218560816U (en) 2022-11-25 2022-11-25 Net rack lifting support on hoop steel frame column

Country Status (1)

Country Link
CN (1) CN218560816U (en)

Similar Documents

Publication Publication Date Title
CN206278848U (en) A kind of dynamic Ding many loop wheel machine pedestal operation platforms of Sheng rotation types of overall Zi
CN116573530A (en) A kind of hoisting device and installation method for installing bridge body of road and bridge construction
CN117303197A (en) Movable hanging bracket
CN112661030A (en) Hoisting, supporting and placing device applied to steel structure and using method thereof
CN218560816U (en) Net rack lifting support on hoop steel frame column
CN218201925U (en) Overhead hoist is built in room
CN118289626A (en) A rigid-flexible combined posture-adjustable hanger
CN203531497U (en) Multifunctional rotary holding pole
CN209259612U (en) A kind of feeding device for construction
CN223133973U (en) Steel material lifting equipment capable of storing materials
CN220705095U (en) A construction suspension
CN222989725U (en) An attached electric lifting platform narrow platform
CN221796716U (en) Hoisting equipment for large-span automatic warehouse steel structure
CN222253256U (en) A device for installing inclined columns of steel structure buildings
CN222743946U (en) A construction material lifting equipment
CN114412154B (en) Operating system for dismantling vertical mast
CN221682431U (en) Used for construction devices on both sides of beams
CN222204592U (en) A segmented boom device with a load structure
CN221607649U (en) A steel structure lifting device
CN221840466U (en) Climbing frame safety detection device
CN117868446A (en) Construction platform convenient to outdoor building and interior decoration
CN222225800U (en) A crane with a balance adjustment structure
CN118164401B (en) Auxiliary lifting device for building steel structure installation
CN217999069U (en) Pre-arranged beam supporting assembly for building engineering
CN214734062U (en) Steel bar truss handling device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20230303

CF01 Termination of patent right due to non-payment of annual fee