Prior art keywords
template
screw
water stop
punching
stop screw
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222326346.3U
Other languages
Chinese (zh)
Inventor
孙福堂
魏开泰
孙富平
裴晶
王艳飞
王钊
陈大凌
李强
李博良
聂福刚
王增
韩银虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningxia First Construction Co ltd
Original Assignee
Ningxia First Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningxia First Construction Co ltd filed Critical Ningxia First Construction Co ltd
Priority to CN202222326346.3U priority Critical patent/CN218541543U/en
Application granted granted Critical
Publication of CN218541543U publication Critical patent/CN218541543U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

A concrete wall pouring template fixed water stop screw structure comprises a water stop screw, a limiting sleeve, a template screw perforating base plate, a fastening screw thread and a template; the water stop screw is provided with a water stop sheet, and the front end rod head and the rear end rod head are respectively of a threaded rod structure; the two ends of the front end rod head and the rear end rod head of the water stop screw rod are respectively and sequentially provided with a limiting sleeve, a template screw rod perforation base plate, a template and a fastening screw thread; the template screw perforation backing plate is arranged on the template screw perforation from the outer side of the template. The template screw punching backing plate structure has the advantages that through the matched use of the template screw punching backing plate structure, the stress area of the template screw hole is increased, the pressure conduction is dispersed, the deformation resistance of a template and the flatness of a joint are improved, the construction quality is improved, the template punching clamp edge can effectively protect the template screw punching, and the damage of a water stop screw to the template screw punching is reduced; the template screw perforating base plate and the fastening screw thread can be repeatedly used, so that the construction cost is reduced.

Description

Concrete wall pouring template fixing water-stop screw structure
Technical Field
The utility model belongs to the technical field of the concrete construction, concretely relates to a fixed stagnant water screw rod structure of template for concrete wall pours use.
Background
The fixed stagnant water screw rod structure of template is the formwork structure that concrete wall pours in the work progress commonly used, the defect that current construction technology exists lies in, the template outside adopts fastener fastening nut cooperation to install and fixes the template at stagnant water screw rod both ends, because at the concrete placement in-process, the outside pressure that both sides template bore is higher, so fastening bolt perforation position atress on the template is higher, cause the template after repetitious usage, produce the deformation after dismouting beat many times, very big influence the life of template. Common injuries include: the stress of the using tip part of the mountain walking clamping piece is too large, so that the template deforms; the deformation of the template screw hole caused by the extrusion of the template screw hole due to the overlarge stress of the screw. The deformation of screw rod hole position on the template very easily causes the aversion of concrete pouring in-process template, can lead to the wall body to pour construction problems such as production protruding swell, especially two templates happen to need when the concatenation position is fixed, lead to adjacent template to produce the dislocation after the deformation, form obvious construction defect.
Disclosure of Invention
The utility model aims at solving the fixed stagnant water screw rod structure template screw rod hole of current concrete wall form and easily damaging to and the easy scheduling problem that warp of mountain line fastener, provide one kind and can protect and improve the concrete wall who installs the atress intensity and pour fixed stagnant water screw rod structure of template to template screw rod hole.
In order to realize the purpose, the technical scheme adopted by the concrete wall pouring template fixing water stop screw structure comprises a water stop screw, a limiting sleeve, a template screw perforating base plate, a fastening screw thread and a template; the water stop screw is provided with a water stop sheet, and the front end rod head and the rear end rod head are respectively of a threaded rod structure; the two ends of the front end rod head and the rear end rod head of the water stop screw are respectively and sequentially provided with a limiting sleeve, a template screw punching base plate, a template and a fastening screw thread; the limiting sleeve is fixedly arranged on the water stop screw according to the thickness of the wall; the upper part of the template is provided with a template screw through hole, and the template is arranged on the water stop screw through the template screw through hole and is fixedly arranged on the outer side of the limiting sleeve; the template screw perforation base plate is arranged on the template screw perforation from the outer side of the template; the fastening screw thread is adjusted and installed on the water stop screw rod through a thread structure, and is pushed inwards from the outer side of the template to be pressed on the template screw rod perforation base plate, so that the template is transversely fixed on the water stop screw rod.
The water stop screw comprises a threaded rod piece with a single group of water stop sheets and multiple groups of water stop sheets.
The limiting sleeve is adjusted and installed and fixed on the water stop screw rod by adopting a threaded sleeve structure, or is fixedly welded on the water stop screw rod as an interval according to the thickness of the wall body.
The template screw perforating base plate is of a cone frustum structure with a large upper part and a small lower part, a base plate screw perforating hole is formed along the axis, and a template perforating clamping edge is arranged along the edge opening of the base plate screw perforating hole on one side of the large circular end face; the template screw punching backing plate is installed in a matched mode with a template screw punching hole of the template through a template punching clamping edge, the large circular end face is pressed on the template, and the small circular end face is fixedly arranged in a pressing mode through the fastening screw thread end face.
The size of the small round end face of the template screw punching base plate is larger than or equal to the size of the end face of the fastening screw thread.
The beneficial effects of the utility model reside in that: by using the template screw perforation backing plate structure in a matched manner, the stress area of the template screw hole is increased, the pressure conduction is dispersed, the deformation resistance of the template is improved, the template perforation clamp edge can effectively protect the template screw perforation, and the damage of the water stop screw to the template screw perforation is reduced; the large end face structure of the cone frustum of the template screw perforation base plate is used at the joint of adjacent templates, so that the flatness of the joint can be improved, and the construction quality is improved; the template screw rod punching base plate and the fastening screw thread are not easy to damage and can be repeatedly used, and the construction cost is reduced.
Drawings
FIG. 1 is a schematic view of the overall installation structure of the present invention;
FIG. 2 is a schematic sectional structure of the present invention;
FIG. 3 is a schematic view of the installation structure of the screw rod on the end face of the template of the present invention;
FIG. 4 is a schematic view of the screw mounting structure at the joint of the end faces of the formwork;
FIG. 5 is an end view of the template screw through hole shim plate of the present invention;
FIG. 6 is a side view of the template screw through-hole shim plate of the present invention;
FIG. 7 is a side sectional view of the template screw perforated base plate of the present invention;
in the drawings: the water-stopping device comprises a water-stopping screw 1, a water-stopping sheet 11, a front end rod head 12, a rear end rod head 13, a limiting sleeve 2, a template screw perforating base plate 3, a base plate screw perforating hole 31, a template perforating clamping edge 32, a fastening screw thread 4, a template 5, a first template 51, a second template 52, a template screw perforating hole 53 and concrete 6.
Detailed Description
To make the objects, technical solutions and advantages of the present invention clearer, the technical solutions of the present invention will be described in detail with reference to the embodiments.
Example 1
The concrete wall pouring template fixing water stop screw structure shown in the attached figures 1-7 comprises a water stop screw 1, a limiting sleeve 2, a template screw perforating base plate 3, a fastening screw thread 4 and a template 5; three water stop sheets 11 are arranged on the water stop screw rod 1, and a front end rod head 12 and a rear end rod head 13 are respectively of a threaded rod structure; the two ends of the front end rod head 12 and the rear end rod head 13 of the water stop screw 1 are respectively and sequentially provided with a limiting sleeve 2, a template screw punching base plate 3, a template 5 and a fastening screw thread 4; the limiting sleeve 2 is fixedly arranged on the water stopping screw rod 1 according to the thickness of the wall body, and the limiting sleeve 2 is adjusted, arranged and fixed on the water stopping screw rod 1 by adopting a threaded sleeve structure or is fixedly welded on the water stopping screw rod 1 as an interval according to the thickness of the wall body; the upper part of the template 5 is provided with a template screw through hole 53, and the template 5 is arranged on the water stop screw 1 through the template screw through hole 53 and is fixedly arranged on the outer side of the limiting sleeve 2; the template screw punching base plate 3 is arranged on a template screw punching hole 53 from the outer side of the template 5, the template screw punching base plate 3 is of a truncated cone structure with a large upper part and a small lower part, a base plate screw punching hole 31 is formed along the axis, a template punching clamping edge 32 is arranged along the edge opening of the base plate screw punching hole 31 on one side of the large circular end face, the template screw punching base plate 3 is matched with the template screw punching hole 53 of the template 5 through the template punching clamping edge 32, the large circular end face is pressed on the template 5, the small circular end face is pressed and fixed through the end face of a fastening screw thread 4, and the size of the small circular end face of the template screw punching base plate 3 is larger than or equal to the size of the end face of the fastening screw thread 4; the fastening screw thread 4 is adjusted and installed on the water stop screw rod 1 through a thread structure, is pushed inwards from the outer side of the template 5 to be pressed on the template screw rod perforated base plate 3, and fixes the template 5 on the water stop screw rod 1 along the transverse direction.
Example 2
With the attached drawings 1-4, the utility model discloses concrete wall pouring template fixed water stop screw structure work progress and principle.
1) The limiting sleeves 2 fixedly arranged on the water stopping screw rods 1 are adjusted according to the design thickness of the concrete wall, the limiting sleeves 2 are symmetrically arranged towards two sides at the center parts of the water stopping screw rods 1, and the distance between the outer sides of the limiting sleeves 2 at two sides of the front end rod head 12 and the rear end rod head 13 is ensured to be the design thickness size of the concrete wall.
2) Laying a wall steel reinforcement framework according to the design position of a concrete wall on a construction site, fixedly erecting pouring templates 5 on two sides of the framework respectively, fixing the two templates 5 by laying and installing water stop screws 1, arranging the templates 5 on two sides of the wall in a contraposition mode, penetrating the front end rod head 12 and the rear end rod head 13 of each water stop screw 1 from the template screw through holes 53 on the templates 5 on two sides respectively, and jacking the templates 5 on two sides to the outer side position of the limiting sleeve 2.
3) From the outer sides of the two side templates 5, a template screw perforation backing plate 3 and a fastening screw thread 4 are respectively arranged on the front end rod head 12 and the rear end rod head 13 which penetrate out from the template screw perforation 53 in sequence, one side of the big circular end surface of the template screw perforation backing plate 3 with the template screw perforation clamp edge 32 is matched with the template screw perforation 53, the template screw perforation clamp edge 32 is arranged in the template screw perforation 53, the fastening screw thread 4 is adjusted to inwards press the template screw perforation backing plate 3, so that one side of the big circular end surface of the template screw perforation backing plate 3 is completely pressed on the template 5 at the position of the template screw perforation 53, and the template 5 does not transversely shake along the water stop screw 1 any more.
4) And (3) after the templates 5 are installed and fixed in the steps 1-3 at the root part, pouring concrete 6 between the templates 5 and vibrating and tamping the concrete to complete the concrete wall pouring operation.
5) After the concrete is completely solidified and solid, the fastening screw threads 4 are sequentially detached from the front end rod head 12 and the rear end rod head 13 of the water stop screw 1, then the template 5 is taken out from the front end rod head 12 and the rear end rod head 13 through the traditional modes of knocking, pulling and the like, and the template screw perforating base plate 3 is taken down from the water stop screw 1 together along with the removal process of the template 5 and then taken down from the template 5.
6) And (4) recovering and storing the detached template 5, the template screw punching base plate 3 and the fastening screw threads 4.
7) And (3) treating the concrete wall surface, cutting off and grinding the front-end rod head 12 and the rear-end rod head 13 of the water stop screw rod 1 extending out of the wall surface along the wall surface, and finishing the construction of the reinforced concrete wall body.
In the step 3) of the process, the large round end surface of the template screw perforation base plate 3 can increase the stress area of the template 5 at the template screw perforation 53, and the cone frustum structure can disperse the pressure conduction, thereby reducing the deformation of the template; the template punching clamping edge 32 of the template screw punching base plate 3 prevents the template screw punching 53 from directly contacting the water stop screw 1, and reduces the damage to the template screw punching 53 when the water stop screw 1 is pressed too much; as shown in fig. 4, the position of the water stop screw 1 is just located at the joint of the first formwork 51 and the second formwork 52 on the same side, and the large circular end face of the formwork screw perforation backing plate 3 fixes the first formwork 51 and the second formwork 52 on two sides through the surface, so that the joint of two adjacent formworks 5 can be better fixed, and the joint of the first formwork 51 and the joint of the second formwork 52 are kept flush. The template 5, the template screw perforating base plate 3 and the fastening screw thread 4 are effectively recycled for multiple times through the construction process step 6), only the water stop screw 1 is consumed in each construction, and the construction cost can be effectively reduced.

Claims (5)

1. The utility model provides a concrete wall pours template fixed water stop screw rod structure which characterized in that: comprises a water stop screw rod (1), a limiting sleeve (2), a template screw rod perforation backing plate (3), a fastening screw thread (4) and a template (5); a water stop sheet (11) is arranged on the water stop screw rod (1), and the front end rod head (12) and the rear end rod head (13) are respectively of a threaded rod structure; the two ends of the front end rod head (12) and the rear end rod head (13) of the water stop screw (1) are respectively and sequentially provided with a limiting sleeve (2), a template screw perforating base plate (3), a template (5) and a fastening screw thread (4); the limiting sleeve (2) is fixedly arranged on the water stop screw rod (1) according to the thickness of the wall body; the upper part of the template (5) is provided with a template screw through hole (53), and the template (5) is arranged on the water stop screw (1) through the template screw through hole (53) and fixedly arranged on the outer side of the limiting sleeve (2); the template screw perforation backing plate (3) is arranged on the template screw perforation (53) from the outer side of the template (5); the fastening screw threads (4) are adjusted and installed on the water stop screw rod (1) through a thread structure, are inwards pushed and pressed on the template screw rod perforation base plate (3) from the outer side of the template (5), and are used for fixing the template (5) on the water stop screw rod (1) along the transverse direction.
2. The concrete wall pouring template fixing water stop screw structure of claim 1, wherein: the water stop screw (1) comprises a threaded rod piece with a single group of water stop sheets and multiple groups of water stop sheets.
3. The concrete wall pouring template fixing water stop screw structure according to claim 1, characterized in that: the limiting sleeve (2) is adjusted and installed and fixed on the water stop screw rod (1) by adopting a threaded sleeve structure, or is fixedly welded on the water stop screw rod (1) as an interval according to the thickness of a wall body.
4. The concrete wall pouring template fixing water stop screw structure of claim 1, wherein: the template screw punching base plate (3) is of a cone frustum structure with a large upper part and a small lower part, a base plate screw punching hole (31) is formed along the axis, and a template punching clamping edge (32) is arranged along the edge opening of the base plate screw punching hole (31) on one side of the large circular end surface; the template screw punching backing plate (3) is matched and installed with a template screw punching hole (53) of the template (5) through a template punching clamping edge (32), the large circular end face is pressed on the template (5), and the small circular end face is fixedly pressed through the end face of the fastening screw thread (4).
5. The concrete wall pouring template fixing water stop screw structure of claim 4, wherein: the size of the small circular end face of the template screw punching base plate (3) is larger than or equal to the size of the end face of the fastening screw thread (4).
CN202222326346.3U 2022-09-02 2022-09-02 Concrete wall pouring template fixing water-stop screw structure Active CN218541543U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222326346.3U CN218541543U (en) 2022-09-02 2022-09-02 Concrete wall pouring template fixing water-stop screw structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222326346.3U CN218541543U (en) 2022-09-02 2022-09-02 Concrete wall pouring template fixing water-stop screw structure

Publications (1)

Publication Number Publication Date
CN218541543U true CN218541543U (en) 2023-02-28

Family

ID=85270539

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222326346.3U Active CN218541543U (en) 2022-09-02 2022-09-02 Concrete wall pouring template fixing water-stop screw structure

Country Status (1)

Country Link
CN (1) CN218541543U (en)

Similar Documents

Publication Publication Date Title
CN204081445U (en) To encorbelment i iron anchor device
CN218541543U (en) Concrete wall pouring template fixing water-stop screw structure
CN205000643U (en) Wall stagnant water bolt is worn to waterproof concrete shear force wall
CN210032625U (en) Accurate stop device of template
CN210013473U (en) Inverted L-shaped side form reinforcing structure
CN213626680U (en) Water stop pull rod structure for subway construction
CN210508401U (en) Pull rod assembly for building shuttering
CN210164246U (en) Reinforcing apparatus for construction
CN212866822U (en) Tool type wall connecting piece
CN212224611U (en) Shear force wall pouring template reinforcing apparatus
CN210031534U (en) Pump line fixing device and bridge pier body suitable for bridge pier body
CN210598152U (en) Split bolt assembly
CN217680526U (en) Template clamp
CN220301341U (en) Concrete dam upset template anchor
CN201401009Y (en) Hook bolt split flat steel reinforcing component
CN217711658U (en) Positioning connection assembly for scaffold
CN211622638U (en) Concrete wall beam template is to drawing structure
CN217518167U (en) Self-adaptation concrete beam template reinforcing apparatus
CN218406520U (en) Shear force wall supporting tool
CN215760444U (en) Reinforcing tool for anti-ridge template
CN215630700U (en) Fixer for embedded steel part on side wall of concrete cast-in-place structure
CN217840898U (en) Fixing tool for plate belt or waist beam template
CN202299432U (en) Waterproof concrete shear wall tool type water-stopping split bolt
CN220621135U (en) Accurate positioner of wearing roof beam sleeve and mounting structure thereof
CN210598136U (en) Screw rod reinforcing piece with fixing piece for side mold of building outer side beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant