CN218523129U - Pipe laying construction device of pipe rammer - Google Patents

Pipe laying construction device of pipe rammer Download PDF

Info

Publication number
CN218523129U
CN218523129U CN202222301586.8U CN202222301586U CN218523129U CN 218523129 U CN218523129 U CN 218523129U CN 202222301586 U CN202222301586 U CN 202222301586U CN 218523129 U CN218523129 U CN 218523129U
Authority
CN
China
Prior art keywords
guide rail
pipe
rammer
slider
guide rails
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222301586.8U
Other languages
Chinese (zh)
Inventor
张跃
初存吉
孙伟
赵坤
王栋
许文鹏
马德一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 10 Engineering Group Co Ltd
Original Assignee
China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 10 Engineering Group Co Ltd filed Critical China Railway No 10 Engineering Group Co Ltd
Priority to CN202222301586.8U priority Critical patent/CN218523129U/en
Application granted granted Critical
Publication of CN218523129U publication Critical patent/CN218523129U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a rammer pipe hammer pipe laying construction equipment belongs to non-excavation pipeline laying technical field. It includes rammer pipe hammer bracket, guider, rammer pipe hammer bracket includes two parallel arrangement's first guide rail, a plurality of first slider, many sleepers, guider includes two parallel arrangement's second guide rail, a plurality of second slider, many sleepers, first guide rail and second guide rail are H shaped steel, be provided with a plurality of first sliders on two first guide rails respectively, it is provided with a plurality of second sliders to slide respectively on two second guide rails, guide rail length direction interval arrangement many sleepers are all followed to first guide rail lower part and second guide rail lower part, first guide rail and second guide rail all pass through bolt and sleeper fixed connection, the lower part of sleeper all buries in basic pit bottom plate concrete, all there are a plurality of transverse connection component of spaced connection between two first guide rails and between two second guide rails. The utility model discloses the installation accuracy is high, and the guide rail basis is stable, can guarantee to ram tub construction precision and quality.

Description

Pipe laying construction device of pipe rammer
Technical Field
The utility model relates to a rammer pipe hammer pipe laying construction equipment, mainly used adopt the construction of rammer pipe hammer pipe laying, belong to non-excavation pipeline laying technical field.
Background
The pipe laying of the pipe rammer belongs to non-directional pipe laying, the pipe laying construction of the pipe rammer usually adopts a pipe rammer bracket and a guide rail, the pipe rammer is fixed on the pipe rammer bracket, and a steel sleeve to be laid is arranged on the guide rail. Traditional rammer pipe hammer bracket and guide rail are because installation deviation, and the guide rail materials match improperly, bear the weight of the unstable all aspects reasons such as that cause the direction deviation of basis of guide rail easily, influence rammer pipe construction precision and quality, and the outside anticorrosive coating of pipe laying in-process pipeline is destroyed easily.
Disclosure of Invention
To the above-mentioned defect that exists among the prior art, the utility model provides a rammer pipe hammer layingconstruction device that installation accuracy is high, guide rail basis is stable, can guarantee rammer pipe construction precision and quality.
The utility model discloses a realize through following technical scheme: the utility model provides a pipe laying construction device of pipe rammer, characterized by: including rammer pipe hammer bracket, guider, rammer pipe hammer bracket includes two parallel arrangement's first guide rail, a plurality of first slider, many sleepers, guider includes two parallel arrangement's second guide rail, a plurality of second slider, many sleepers, first guide rail with the second guide rail is H shaped steel, is provided with a plurality of first sliders on two first guide rails respectively, and it is provided with a plurality of second sliders to slide respectively on two second guide rails, and guide rail length direction interval arrangement many sleepers are all followed to first guide rail lower part and second guide rail lower part, and first guide rail and second guide rail all pass through bolt rather than sleeper fixed connection of lower part, and the lower part of sleeper all buries in base pit floor slab concrete, all has a plurality of transverse connection members of spaced connection between two first guide rails and between two second guide rails.
The utility model discloses in, the pipe rammer hammer bracket is used for installing the pipe rammer hammer, and the pipe rammer hammer is installed on first slider upper portion during the installation, can adjust the position of pipe rammer hammer through first slider, and pipe rammer hammer position adjustment can be in the same place first slider and first guide rail welded fastening after finishing. The guiding device is used for supporting and guiding the steel sleeve to be paved, the steel sleeve is arranged on the second sliding block, and when the steel sleeve is hammered by the pipe rammer, the second sliding block and the steel sleeve move together along the second guide rail. The utility model discloses rational in infrastructure, the guide rail basis is stable, can guarantee in the construction that the rammer pipe hammer axis is unanimous with being rammed steel casing pipe axis, has guaranteed the construction precision, and the setting of second slider can effectively prevent to be destroyed by the outside anticorrosive coating of rammer steel casing pipe simultaneously.
Furthermore, in order to ensure the stability and the moving reliability of the steel sleeve in the construction process, one second sliding block is arranged on each second guide rail at intervals of 2-3 m.
Furthermore, in order to ensure the stability of the guide rail foundation, the height of the part of the sleeper exposed out of the base plate of the foundation pit is 2-3mm.
Furthermore, in order to ensure the structural strength and stability of the guide rail, the arrangement interval of the transverse connecting components is 0.5m.
Further, in order to guarantee the stability of the foundation, a plurality of stiffening ribs are arranged on two sides of the H-shaped steel along the length direction of the H-shaped steel at intervals.
Furthermore, the surface of the second sliding block, which is in contact with the steel sleeve to be rammed, is provided with a rubber sheet. The rubber is arranged on the second sliding block, so that an anticorrosive coating outside the steel sleeve can be effectively protected from being damaged in the construction process.
The utility model has the advantages that: the utility model has the advantages of reasonable design, the construction is simple and convenient, and the guide rail basis is stable, and rammer pipe hammer bracket and guider installation accuracy is high, is difficult for appearing the directional deviation by rammer steel casing pipe, and the construction precision is high, and through set up the second slider on second guide rail upper portion, can prevent effectively that the steel casing pipe anticorrosive coating from destroying, has guaranteed rammer pipe construction precision and quality.
Drawings
Fig. 1 is a schematic structural diagram of the present invention;
fig. 2 is a schematic structural view of the guiding device of the present invention;
FIG. 3 is a schematic top view of FIG. 2;
FIG. 4 is a schematic view of the pipe rammer bracket of the present invention;
FIG. 5 is a schematic top view of FIG. 4;
in the figure, the steel casing 1, the steel casing 2, the second sliding block 3, the second guide rail 4, the bolt 5, the sleeper 6, the transverse connecting member 7, the rubber sheet 8, the stiffening rib 9, the foundation pit bottom plate concrete 10, the first sliding block 11, the first guide rail 12 and the pipe rammer hammer.
Detailed Description
The invention will now be further described by way of non-limiting examples with reference to the accompanying drawings:
as shown in the attached drawings, the pipe ramming hammer pipe laying construction device comprises a pipe ramming hammer bracket and a guide device, wherein the pipe ramming hammer bracket comprises two first guide rails 11 arranged in parallel, a plurality of first sliding blocks 10 and a plurality of sleepers 5, the first guide rails 11 are made of H-shaped steel, the two first guide rails 11 are respectively provided with a plurality of first sliding blocks 10, the first sliding blocks 10 are slidably arranged at the tops of the first guide rails 11, and the lower parts of the first sliding blocks 10 are provided with sliding grooves matched with upper flange plates of the first guide rails 11. A plurality of sleepers 5 are arranged at intervals at the lower part of the first guide rail 11 along the length direction of the guide rail, the distance between the sleepers is about 0.5m, and the first guide rail 11 is fixedly connected with the sleepers 5 at the lower part of the first guide rail through bolts 4. The lower part of the sleeper 5 is embedded in the foundation pit bottom plate concrete 9, and preferably, the height of the part of the sleeper 5 exposed out of the foundation pit bottom plate is 2-3mm. A plurality of stiffening ribs 8 are arranged on two sides of the H-shaped steel at intervals along the length direction of the H-shaped steel, and the stiffening ribs 8 are connected with the H-shaped steel in a welding mode. A plurality of transverse connecting components 6 are connected between the two first guide rails 11 at intervals, and two ends of each transverse connecting component 6 are respectively connected with the two first guide rails 11 in a welding manner. Preferably, the transverse connecting members 6 are disposed at a pitch of 0.5m. The pipe rammer support is used for installing the pipe rammer, and the pipe rammer is installed on the upper portion of the first slider 10 during installation, and the position of the pipe rammer can be adjusted by moving the first slider 10, and the first slider 10 and the first guide rail 11 can be welded and fixed together after the pipe rammer is adjusted in position.
The guide device comprises two second guide rails 3 arranged in parallel, a plurality of second sliding blocks 2 and a plurality of sleepers 5, the second guide rails 3 are made of H-shaped steel, the two second guide rails 3 are respectively provided with the second sliding blocks 2 in a sliding mode, the second sliding blocks 2 are arranged at the tops of the second guide rails 3 in a sliding mode, and sliding grooves are formed in the lower portions of the second sliding blocks 2 and matched with upper flange plates of the second guide rails 3. Preferably, one second sliding block 2 is arranged on each second guide rail 3 at intervals of 2-3m, and the second sliding blocks 2 on the two guide rails can be correspondingly arranged. And a plurality of sleepers 5 are arranged at the lower part of the second guide rail 3 at intervals along the length direction of the guide rail, the distance between the sleepers is about 0.5m, and the second guide rail 3 is fixedly connected with the sleepers 5 at the lower part of the second guide rail through bolts 4. The lower part of the sleeper 5 is embedded in the foundation pit floor concrete 9. In order to ensure the stability of the guide rail foundation, the height of the part of the sleeper 5 exposed out of the bottom plate of the foundation pit is preferably 2-3mm. A plurality of stiffening ribs 8 are arranged on two sides of the H-shaped steel of the second guide rail 3 at intervals along the length direction of the guide rail and used for improving the structural strength of the guide rail, and the stiffening ribs 8 are welded with the H-shaped steel. A plurality of transverse connecting components 6 are connected between the two second guide rails 3 at intervals, and two ends of each transverse connecting component 6 are respectively connected with the two second guide rails 3 in a welding manner. Preferably, the transverse connecting members 6 are disposed at a pitch of 0.5m. In order to protect the anticorrosive coating of the steel casing to be rammed, a rubber sheet 7 is preferably arranged on the surface of the second sliding block 2, which is in contact with the steel casing to be rammed, so that the anticorrosive coating outside the steel casing can be prevented from being damaged during ramming.
Utilize the utility model discloses during the construction, accessible adjustment sleeper exposes the height or the H shaped steel specification of foundation ditch bottom plate, makes rammer pipe hammer axis unanimous with the steel casing pipe axis of being rammed, ensures the construction precision.
The utility model discloses the construction is simple, and is rational in infrastructure, and rammer pipe hammer bracket and guider installation accuracy are high, and the guide rail basis is stable, can effectively guarantee rammer pipe construction precision and quality.
Other parts in this embodiment are all the prior art, and are not described herein again.

Claims (6)

1. The utility model provides a pipe laying construction equipment of rammer pipe hammer, characterized by: including pipe rammer bracket, guider, pipe rammer bracket includes two parallel arrangement's first guide rail (11), a plurality of first slider (10), many sleepers, guider includes two parallel arrangement's second guide rail (3), a plurality of second slider (2), many sleepers, first guide rail (11) with second guide rail (3) are H shaped steel, are provided with a plurality of first slider (10) on two first guide rails (11) respectively, and it is provided with a plurality of second slider (2) to slide respectively on two second guide rails (3), and first guide rail (11) lower part and second guide rail (3) lower part all follow guide rail length direction interval arrangement many sleepers, and first guide rail (11) and second guide rail (3) all are through bolt and sleeper fixed connection rather than the lower part, and the lower part of sleeper all buries in basic pit bottom plate concrete, all have a plurality of transverse connection component (6) of interval between two first guide rails (11) and between two second guide rails (3).
2. The rammed pipe hammer pipelaying construction device of claim 1, wherein: one second sliding block (2) is arranged on each second guide rail (3) at intervals of 2-3 m.
3. The rammer pipe-laying construction device according to claim 1, wherein: the height of the part of the sleeper exposed out of the bottom plate of the foundation pit is 2-3mm.
4. The rammer pipe-laying construction device according to claim 1, wherein: the transverse connecting members (6) are arranged at a pitch of 0.5m.
5. The rammed pipe hammer pipelaying construction device of claim 1, wherein: a plurality of stiffening ribs are arranged on two sides of the H-shaped steel at intervals along the length direction of the H-shaped steel.
6. The rammer pipe laying construction apparatus of claim 1, 2, 3, 4 or 5, wherein: and a rubber sheet is arranged on the surface of the second sliding block (2) contacted with the steel sleeve to be tamped.
CN202222301586.8U 2022-08-31 2022-08-31 Pipe laying construction device of pipe rammer Active CN218523129U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222301586.8U CN218523129U (en) 2022-08-31 2022-08-31 Pipe laying construction device of pipe rammer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222301586.8U CN218523129U (en) 2022-08-31 2022-08-31 Pipe laying construction device of pipe rammer

Publications (1)

Publication Number Publication Date
CN218523129U true CN218523129U (en) 2023-02-24

Family

ID=85244002

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222301586.8U Active CN218523129U (en) 2022-08-31 2022-08-31 Pipe laying construction device of pipe rammer

Country Status (1)

Country Link
CN (1) CN218523129U (en)

Similar Documents

Publication Publication Date Title
CN106641440A (en) Underground pipeline jacking construction method capable of transversely passing through railway line
CN102518300B (en) Embedded conical bearing joint type steel structural support and construction method thereof
CN113622316A (en) Steel truss girder multipoint traction type pushing construction system and construction method thereof
CN218523129U (en) Pipe laying construction device of pipe rammer
JP4559370B2 (en) Girder erection method by erection gutter from the side of bridge
CN102733406B (en) Railway construction method of solid concrete roadbed in large-size industrial plant
CN113832947A (en) Device and method for reinforcing multiple-track railway with small space passing under shield tunnel
CN110509424B (en) Construction method for transversely moving beams by double-track trolley
CN109944165A (en) A kind of temporary support method of the modularization regulating posture for the installation of prefabricated bent cap
CN212560935U (en) Ballastless track roadbed transition section filler replacement structure
CN115075146B (en) Method for connecting prefabricated bent cap through prestressed tendons and steel bars
CN110439004A (en) A kind of the packaged type inner supporting device and its application method of pattern foundation pit supporting structure
CN209177871U (en) Platform structure for memorial archway continuously hoisting
CN108867683A (en) A kind of removable basic and its construction method of rail mounted
CN108506032B (en) Construction method of large-volume top longitudinal beam in pilot tunnel
CN111549582A (en) Construction method of steel spring floating slab track bed
CN218438128U (en) Spliced type supporting guide rail system
CN114717883B (en) Rapid installation method of prefabricated foundation structure for railway detection equipment
CN213951813U (en) Permanent-temporary combined channel protection system for metallurgical equipment
CN218711819U (en) Open type ballast bed plate and ballast bed
CN114439489B (en) Subway tunnel shield machine receiving device suitable for limited space and construction method thereof
CN212480337U (en) Adjustable guide rail system for pipe jacking
CN215108948U (en) Reinforcing back pressure device for resisting subway tunnel floating
CN217419727U (en) Prefabricated foundation structure for railway detection equipment
CN204455878U (en) Urban interchange maintenance is used can length travel temporary support system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant