CN218522294U - Device for installing and positioning embedded bolts of mooring post in port engineering - Google Patents

Device for installing and positioning embedded bolts of mooring post in port engineering Download PDF

Info

Publication number
CN218522294U
CN218522294U CN202222005777.XU CN202222005777U CN218522294U CN 218522294 U CN218522294 U CN 218522294U CN 202222005777 U CN202222005777 U CN 202222005777U CN 218522294 U CN218522294 U CN 218522294U
Authority
CN
China
Prior art keywords
crossbeam
gag lever
plate body
lever post
clamp plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222005777.XU
Other languages
Chinese (zh)
Inventor
刘有良
苏长合
刘宗广
林文彬
李斌
王博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Ocean Construction Development Co ltd
Original Assignee
Cccc Ocean Construction Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc Ocean Construction Development Co ltd filed Critical Cccc Ocean Construction Development Co ltd
Priority to CN202222005777.XU priority Critical patent/CN218522294U/en
Application granted granted Critical
Publication of CN218522294U publication Critical patent/CN218522294U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Landscapes

  • Clamps And Clips (AREA)

Abstract

The utility model relates to a harbour engineering equipment field discloses a harbour engineering is pre-buried bolt installation location's of post device, including crossbeam, clamp plate body and preceding gag lever post, the equal fixedly connected with pole setting in both ends about the crossbeam, and the lower extreme fixedly connected with landing leg of pole setting, preceding gag lever post fixed connection is on the right side wall of the landing leg on right side, and the left side wall of left landing leg on the gag lever post after the fixedly connected with gag lever post to the lower extreme fixedly connected with fixing bolt of back gag lever post, clamp plate body erection joint is at the up end of crossbeam, and the junction of clamp plate body and crossbeam has seted up the bolt hole, constitute welding integrated structure between crossbeam, pole setting and the landing leg, and left pole setting is the slope setting at the lower extreme of crossbeam. The utility model discloses, the breast wall template is fixed basis, and is more firm, adjusts the plane position of bollard location steel sheet to arbitrary direction through the clamp plate, more is favorable to control location accuracy and efficiency of construction.

Description

Device for installing and positioning embedded bolts of mooring post in port engineering
Technical Field
The utility model relates to a port engineering equipment field specifically is a device of harbour engineering bollard embedded bolt installation location.
Background
In the port engineering construction, pier bollard usually adopts buried bolt to fix in advance, before the pouring of bollard foundation concrete, buried bolt need install and fix in advance to satisfy the concrete pouring in-process mounted position and do not change, the fixed mode of buried bolt is mostly connected bolt and foundation reinforcement at present and fixes, and concrete pouring in-process reinforcing bar can take place to remove, leads to the bollard buried bolt position to take place the deviation, influences construction quality.
The prior Chinese patent discloses a novel assembled type mooring and berthing device, the publication number is CN209795746U, the publication date is 2019.12.17, and the technology is suitable for long-time manual overwater operation and can quickly and conveniently complete the installation of mooring and berthing facilities in projects without large-volume concrete pouring conditions.
But still have some problems in this patent technique, mainly for the installation of ship tying post with embedded bolt fix on ship tying post basis steel reinforcement cage, in the concrete placement process, the steel reinforcement cage can take place displacement and subside under the lateral pressure that the concrete produced and the vertical load that the construction load produced on the steel reinforcement cage, seriously influences the construction quality of embedded bolt installation, need survey crew to check and adjust repeatedly in the installation simultaneously, influences the efficiency of construction. In view of the above situation, those skilled in the art provide a device for installing and positioning embedded bolts of mooring columns in port engineering.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a device of harbour engineering bollard embedded bolt installation location, to solve the bollard installation mode of putting forward in the above-mentioned background and fix embedded bolt on bollard basis steel reinforcement cage, the concrete placement in-process, the steel reinforcement cage can take place the displacement and subside under the lateral pressure that the concrete produced and the vertical load that the construction load produced on the steel reinforcement cage, seriously influence the construction quality of embedded bolt installation, need measuring personnel to check and adjust repeatedly in the installation simultaneously, influence the problem of efficiency of construction.
In order to achieve the above purpose, the utility model provides a following technical scheme:
the utility model provides a device of harbour engineering system post buried bolt installation location in advance, includes crossbeam, clamp plate body and preceding gag lever post, the equal fixedly connected with pole setting in both ends about the crossbeam, and the lower extreme fixedly connected with landing leg of pole setting, preceding gag lever post fixed connection is on the right side wall of the landing leg on right side, and the gag lever post behind the fixedly connected with on the left side wall of left landing leg to the lower extreme fixedly connected with fixing bolt of back gag lever post, clamp plate body erection joint is at the up end of crossbeam, and the bolt hole has been seted up to the junction of clamp plate body and crossbeam.
As a further aspect of the present invention: constitute the welding integrated structure between crossbeam, pole setting and the landing leg, and the left pole setting is the slope setting at the lower extreme of crossbeam to be perpendicular setting between pole setting and the crossbeam on right side, the crossbeam is the main loading end of fixed bollard location steel sheet, and pole setting and landing leg are used for propping up on the breast wall template, conveniently support and handle.
As the utility model discloses further scheme again: the up end of back gag lever post and preceding gag lever post is on the coplanar, and back gag lever post and preceding gag lever post welded connection on the lateral wall of the landing leg of the left and right sides respectively to back gag lever post is "L" font structure, fixes whole locating rack on the breast wall template through fixing bolt, and is easy to assemble fixed.
As a further aspect of the present invention: the clamp plate body is bilateral symmetry setting about the axis of crossbeam, and the clamp plate body passes through clamp plate bolt erection joint at the up end of crossbeam, is convenient for firmly install the bollard on the crossbeam, avoids sliding the skew.
As the utility model discloses further scheme again: the clamp plate body is of a Z-shaped structure, the lower end face of the clamp plate body is tightly attached to the cross beam, the upper end of the clamp plate body is arranged in a hollow mode with the cross beam, and the mooring post embedded steel plate is conveniently fixed on the cross beam.
As a further aspect of the present invention: the cross beam, the vertical rod and the supporting legs are all angle steel so as to improve the overall strength.
The utility model has the advantages that:
1. the positioning frame can take a breast wall template as a fixed foundation and is firmer, the positioning frame consists of a cross beam and a pressing plate body, the positioning frame is used for fixing a positioning steel plate of a pre-embedded bolt of a mooring bollard, and the pre-embedded bolt is fixed on the positioning steel plate through a screw;
2. this locating rack accessible clamp plate body is to the plane position of arbitrary direction adjustment mooring post location steel sheet, more is favorable to controlling location accuracy and efficiency of construction, and the clamp plate body is installed fixed mooring post through the clamp plate bolt, and the firm installation of being convenient for avoids the skew to rock.
Drawings
The present invention will be further described with reference to the accompanying drawings.
FIG. 1 is a schematic front view of a device for installing and positioning embedded bolts of mooring bollards in port engineering;
FIG. 2 is a schematic side view of FIG. 1;
FIG. 3 is a schematic top view of FIG. 1;
fig. 4 is a schematic view of the installation structure of the bollard positioning plate in this embodiment.
In the figure: 1. a cross beam; 2. erecting a rod; 3. a support leg; 4. a pressing plate body; 5. a platen bolt; 6. bolt holes; 7. a rear stopper rod; 8. a front limit lever; 9. fixing the bolt; 10. mooring bollard positioning steel plates; 11. and (5) tying a ship column and embedding bolts.
Detailed Description
The technical solution in the embodiment of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiment of the present invention, please refer to fig. 1 to 3, and the embodiment of the present invention is as follows:
a device for installing and positioning embedded bolts of mooring bollards in port engineering is shown in figure 1: including crossbeam 1, clamp plate body 4 and preceding gag lever post 8, crossbeam 1 controls the equal fixedly connected with pole setting 2 in both ends, and the lower extreme fixedly connected with landing leg 3 of pole setting 2, preceding gag lever post 8 fixed connection is on the right side wall of landing leg 3 on right side, and gag lever post 7 behind the fixedly connected with on the left side wall of left landing leg 3, and the lower extreme fixedly connected with fixing bolt 9 of back gag lever post 7, clamp plate body 4 erection joint is at crossbeam 1's up end, and clamp plate body 4 has seted up bolt hole 6 with crossbeam 1's junction (this bolt hole is waist type hole, realize clamp plate body 4 adjustable in position promptly).
In fig. 1, 2 and 3: crossbeam 1, constitute welding integral structure between pole setting 2 and the landing leg 3, and left pole setting 2 is the slope setting at crossbeam 1's lower extreme, and be perpendicular setting between pole setting 2 on right side and the crossbeam 1, the up end of back gag lever post 7 and preceding gag lever post 8 is on the coplanar, and welded connection on the lateral wall of landing leg 3 of the left and right sides respectively is distinguished with preceding gag lever post 7, and back gag lever post 7 is "L" font structure, crossbeam 1 is the main loading end of fixed bollard location steel sheet, pole setting 2 and landing leg 3 are used for setting up on the breast wall template, convenient support processing.
In fig. 1, 2 and 3: the clamp plate body 4 is bilateral symmetry setting about the axis of crossbeam 1, and clamp plate body 4 passes through clamp plate bolt 5 erection joint at the up end of crossbeam 1, and clamp plate body 4 is "Z" font structure, and is closely laminating setting under the clamp plate body 4 between terminal surface and the crossbeam 1 to be cavity setting between clamp plate body 4's the upper end and the crossbeam 1, be convenient for firmly install on crossbeam 1 with the bollard of mooring, avoid sliding the skew.
The utility model discloses a theory of operation is: with reference to fig. 1-4, after binding of a breast wall of a port engineering and a foundation steel bar of a mooring post is completed, a breast wall formwork is installed, a positioning frame is placed at the position of the foundation of the mooring post, supporting legs 3 of the positioning frame are supported on top surfaces of side forms on the front side and the rear side of the breast wall, fixing bolts 9 are screwed down to fix the positioning frame on the breast wall formwork, a mooring post positioning steel plate 10 is placed on the top surface of a cross beam 1, mooring post embedded bolts 11 are installed on the positioning steel plate, a measurer checks the plane position of the mooring post embedded bolts 11, a pressure plate bolt 5 is screwed down after the plane position is correct, the mooring post positioning steel plate 10 is fixed, the measurer checks the horizontal elevation of the embedded bolts, and the elevation is adjusted by nuts on the mooring post embedded bolts 11 to meet design requirements.
Above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the design of the present invention, equivalent replacement or change should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a device of harbour engineering system post embedded bolt installation location, includes crossbeam (1), clamp plate body (4) and preceding gag lever post (8), its characterized in that, the equal fixedly connected with pole setting (2) in both ends about crossbeam (1), and lower extreme fixedly connected with landing leg (3) of pole setting (2), preceding gag lever post (8) fixed connection is on the right side wall of landing leg (3) on right side, and behind the fixedly connected with gag lever post (7) on the left side wall of left landing leg (3) to the lower extreme fixedly connected with fixing bolt (9) of back gag lever post (7), clamp plate body (4) erection joint is at the up end of crossbeam (1), and bolt hole (6) have been seted up in the junction of clamp plate body (4) and crossbeam (1).
2. The device for installing and positioning the embedded bolts of the mooring bollards in the port engineering according to claim 1 is characterized in that the cross beam (1), the vertical rods (2) and the support legs (3) form a welding integrated structure, the vertical rod (2) on the left side is obliquely arranged at the lower end of the cross beam (1), and the vertical rod (2) on the right side is vertically arranged with the cross beam (1).
3. The device for mounting and positioning the embedded bolts of the mooring bollards in the port engineering according to claim 1, wherein the upper end surfaces of the rear limiting rod (7) and the front limiting rod (8) are on the same plane, the rear limiting rod (7) and the front limiting rod (8) are respectively welded on the side walls of the left and right supporting legs (3), and the rear limiting rod (7) is in an L-shaped structure.
4. The device for mounting and positioning the embedded bolts of the mooring bollard in the port engineering according to claim 1, wherein the pressing plate bodies (4) are arranged in a bilateral symmetry manner about the central axis of the cross beam (1), and the pressing plate bodies (4) are mounted and connected to the upper end face of the cross beam (1) through pressing plate bolts (5).
5. The device for installing and positioning the embedded bolts of the mooring post in the port engineering according to claim 4, wherein the pressure plate body (4) is in a Z-shaped structure, the lower end face of the pressure plate body (4) is tightly attached to the cross beam (1), and the upper end of the pressure plate body (4) is arranged in a hollow manner with the cross beam (1).
6. The device for installing and positioning the embedded bolts of the mooring posts in the port engineering according to any one of claims 1-5, wherein the cross beam (1), the vertical rod (2) and the supporting legs (3) are all angle steel.
CN202222005777.XU 2022-08-01 2022-08-01 Device for installing and positioning embedded bolts of mooring post in port engineering Active CN218522294U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222005777.XU CN218522294U (en) 2022-08-01 2022-08-01 Device for installing and positioning embedded bolts of mooring post in port engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222005777.XU CN218522294U (en) 2022-08-01 2022-08-01 Device for installing and positioning embedded bolts of mooring post in port engineering

Publications (1)

Publication Number Publication Date
CN218522294U true CN218522294U (en) 2023-02-24

Family

ID=85242190

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222005777.XU Active CN218522294U (en) 2022-08-01 2022-08-01 Device for installing and positioning embedded bolts of mooring post in port engineering

Country Status (1)

Country Link
CN (1) CN218522294U (en)

Similar Documents

Publication Publication Date Title
CN202031179U (en) Centre line aligning and elevation adjusting device of basic embedded bolts
CN111851565B (en) Steel structure stand column alignment structure with cup-mouth type foundation and construction method thereof
CN201071510Y (en) Lattice column locating and verticality adjusting guide frame device
CN203270600U (en) Fixed support for installing embedded bolts of high-precision equipment
CN206986719U (en) A kind of bridge floor anti-collision wall reinforcing bar positioning installation apparatus
CN112127641A (en) Accurate fixing method for anchor plate foundation bolt
CN110670734A (en) Fixing device for pre-buried steel plate under shock insulation support and construction method thereof
CN208310244U (en) A kind of device for control panel surface evenness
CN218522294U (en) Device for installing and positioning embedded bolts of mooring post in port engineering
CN213867975U (en) Frame column jacking structure in deviation rectifying and reinforcing engineering
CN202430737U (en) Overall positioning and reinforcing device for equipment foundation row and group embedded bolt
CN211499816U (en) Device for pouring construction of cantilever support of steel-concrete composite beam
CN212477455U (en) Pre-buried positioner of bridge suspension cable anchor cylinder
CN102518145A (en) Device for wholly positioning and strengthening groups of embedded bolts in ranks on device foundations
CN203429556U (en) System for quickly installing and positioning cable saddle
CN112095485A (en) Bridge stay cable anchor cylinder pre-embedded positioning device and using method thereof
CN212742614U (en) Foundation inner stand column positioning and mounting structure
CN212477442U (en) Steel box girder mounting bracket
CN210529741U (en) Independent foundation embedded bolt mounting structure
CN210976594U (en) Auxiliary mounting device for laminated plate
CN205224073U (en) Mould is fixed to contact net
CN210887284U (en) Fixed stay stirrup of pre-buried festival of tower crane foundation
CN208361753U (en) A kind of tower crane supporting leg anchoring pre-buried structure and tower crane
CN210029721U (en) Prefabricated bridge deck hoisting frame
CN215801767U (en) Overweight equipment foundation bolt high accuracy embedded structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant