CN218522235U - Novel super high-rise residence floor penetrating reserved hole die - Google Patents

Novel super high-rise residence floor penetrating reserved hole die Download PDF

Info

Publication number
CN218522235U
CN218522235U CN202222518228.2U CN202222518228U CN218522235U CN 218522235 U CN218522235 U CN 218522235U CN 202222518228 U CN202222518228 U CN 202222518228U CN 218522235 U CN218522235 U CN 218522235U
Authority
CN
China
Prior art keywords
sleeve
mould
concrete
super high
dismounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202222518228.2U
Other languages
Chinese (zh)
Inventor
何再深
向银锋
赵小春
郭金龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Divion Southern Construction Co Ltd
Original Assignee
China Construction Eighth Engineering Divion Southern Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Divion Southern Construction Co Ltd filed Critical China Construction Eighth Engineering Divion Southern Construction Co Ltd
Priority to CN202222518228.2U priority Critical patent/CN218522235U/en
Application granted granted Critical
Publication of CN218522235U publication Critical patent/CN218522235U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model belongs to the technical field of buildings, and discloses a novel super high-rise dwelling floor slab reserved hole die, which comprises a die sleeve, wherein the die sleeve is of a hollow structure with two open ends; the fixing assembly is fixedly connected with the aluminum template, is positioned on the inner side of the mold sleeve and is used for fixing the mold sleeve; the mould sleeve is provided with at least one dismounting assembly, one end of each dismounting assembly is connected with the outer surface of the mould sleeve, the other end of each dismounting assembly is tightly attached to the top of the concrete, and the dismounting assemblies are used for dismounting the mould sleeve from the concrete; the isolation layer, it paints the setting at mould sleeve surface, and the isolation layer is used for preventing that the mould sleeve is by the concrete adhesion. The utility model provides a current mould at the easy slip off normal of empting the concrete in-process, and the later stage is difficult to the problem of demolising, is applicable to mould for the building.

Description

Novel super high-rise residence floor penetrating reserved hole die
Technical Field
The utility model relates to a building technical field, more specifically say that it relates to novel super high-rise house wears floor and reserves entrance to a cave mould.
Background
At present, most of floor penetrating embedded holes in construction and residential projects adopt PVC pipes as sleeve molds, the principle of the sleeve molds is that the PVC pipes are cut into short sections, the short sections are sealed by adhesive tapes at two ends and placed in the center of a point position of an aluminum template, concrete is poured after the PVC pipes are fixed by embedded steel bars, and the PVC pipes are dismantled after the concrete strength reaches 1.2 Mpa.
However, the PVC pipe is made of plastic, and is easy to damage and incapable of being reused in the dismantling process, and the traditional PVC pipe mold is bound and fixed with a horizontal steel bar on the plate surface by an iron wire, so that the sliding deviation of the sleeve is easily caused by concrete in the concrete pouring and vibrating processes, and the size deviation opening needs to be chiseled in the later period, so that the time and labor are consumed, and the forming is not attractive; and when the pouring thickness of the concrete becomes larger, the friction force between the mold and the concrete also becomes larger, so that workers are difficult to remove the mold from the concrete in the later period.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a novel super high-rise house wears floor and reserves entrance to a cave mould, has solved current mould and is empting the easy slip off normal of concrete in-process, and the later stage is difficult to the problem of demolising.
The above technical object of the present invention can be achieved by the following technical solutions: the novel super high-rise dwelling floor slab through reserved hole die comprises a die sleeve which is a hollow structure with two open ends; the fixing component is fixedly connected with the aluminum template, is positioned on the inner side of the mold sleeve and is used for fixing the mold sleeve; the mould sleeve is provided with at least one dismounting assembly, one end of each dismounting assembly is connected with the outer surface of the mould sleeve, the other end of each dismounting assembly is clung to the top of the concrete, and the dismounting assemblies are used for dismounting the mould sleeve from the concrete; the isolation layer, it paints the setting at mould sleeve surface, and the isolation layer is used for preventing that the mould sleeve is by the concrete adhesion.
The working principle of the technical scheme is as follows: firstly, pass through the bolt fastening with fixed subassembly and set up on the aluminium mould board, establish mould sleeve cover on fixed subassembly again, fixed subassembly is used for keeping the mould sleeve can not squint, then scribble in mould sleeve surface and set up the isolation layer, can begin to water cement, after the concrete strength reaches 1.2Mpa, adjust fixed subassembly earlier, remove the telescopic restriction of mould, reuse demolishs the subassembly and demolishs mould sleeve from the concrete, accomplish the entrance to a cave reservation of floor promptly at last.
To sum up, the utility model discloses following beneficial effect has:
compared with the prior art, the novel super high-rise building floor slab reserved hole die fixes the die sleeve through the fixing component, so that the die sleeve is prevented from generating sliding deviation in the process of pouring and pouring concrete and vibrating the concrete; demolish the subassembly through setting up for when the concrete thickness of pouring great, and frictional force also when the grow thereupon between mould sleeve and the concrete, workman can demolish mould sleeve from the concrete comparatively laborsavingly.
Further, the fixing assembly includes: the fixed base is matched with the inner diameter of the mold sleeve, clamped on the inner side of the mold sleeve and fixedly arranged on the aluminum template through bolts; the threaded upright rod is fixedly arranged at the top of the fixed base; and the cover plate is fixedly arranged at the top of the mold sleeve through a fastener matched with the threaded upright rod.
Furthermore, each disassembly assembly comprises a plurality of groups of first telescopic rods hinged to the outer surface of the mold sleeve, second telescopic rods hinged to the free ends of the first telescopic rods and a pry bar, wherein the length of each first telescopic rod is smaller than that of the pry bar, and the free ends of the second telescopic rods are provided with supporting blocks.
Further, the disassembling component is a sleeve handle fixedly arranged on the outer surface of the mold sleeve.
Further, the fastener is a wing nut.
Furthermore, the fixed base is of a cross structure.
Further, the isolation layer is a concrete isolation agent.
Drawings
Fig. 1 is a schematic structural diagram of one embodiment of the present invention;
FIG. 2 is a schematic structural diagram of one embodiment of the present invention;
in the figure: 1. an aluminum template; 2. concrete; 3. an isolation layer; 4. a mold sleeve; 5. a second telescopic rod; 6. a pry bar; 7. a butterfly nut; 8. a cover plate; 9. a support block; 10. a threaded upright rod; 11. a fixed base; 12. a sleeve handle; 13. a receiving groove; 14. a first telescopic rod.
Detailed Description
The present invention will be described in further detail with reference to fig. 1 to 2.
As shown in fig. 1 and fig. 2, an embodiment of the present invention provides a novel super high-rise residence floor slab-through reserved hole mold, which includes a mold sleeve 4, which is a hollow structure with two open ends; the fixing assembly is fixedly connected with the aluminum template 1, is positioned on the inner side of the mold sleeve 4 and is used for fixing the mold sleeve 4; the mould comprises two disassembling assemblies, wherein one end of each disassembling assembly is connected with the outer surface of the mould sleeve 4, the other end of each disassembling assembly is tightly attached to the top of the concrete 2, and the disassembling assemblies are used for disassembling the mould sleeve 4 from the concrete 2; isolation layer 3, it is paintd and is set up at mould sleeve 4 surface, and isolation layer 3 is used for preventing that mould sleeve 4 from being adhered by concrete 2.
The specific working process is as follows: firstly, fixing a fixing component on an aluminum template 1 through bolts, fixing a mould sleeve 4 on the outer side of the fixing component, then coating an isolating layer 3 on the outer surface of the mould sleeve 4, pouring concrete 2, adjusting the fixing component after the strength of the concrete 2 reaches 1.2Mpa, removing the limitation on the mould sleeve 4, then removing the mould sleeve 4 from the concrete 2 by using a removing component, and completing the reservation of a hole of a floor slab.
In the embodiment, the fixing component is arranged to fix the mold sleeve 4, so that the mold sleeve 4 is prevented from sliding and deviating in the processes of pouring the poured concrete 2 and vibrating the concrete 2; demolish the subassembly through setting up for 2 thickness when concreting are great, and when frictional force also grow thereupon between mould sleeve 4 and the concrete 2, workman can demolish mould sleeve 4 by in the concrete 2 comparatively laborsavingly.
In the actual use process, a concrete separant is selected as the material of the isolating layer 3.
As shown in fig. 1 and fig. 2, according to another embodiment of the present invention, the novel super high-rise dwelling house floor slab preformed hole die, wherein the fixing component comprises a fixing base 11 adapted to the inner diameter of the die sleeve 4, the fixing base 11 is clamped inside the die sleeve 4, and the fixing base 11 is fixed on the aluminum formwork 1 by bolts; the threaded upright rod 10 is fixedly arranged at the top of the fixed base 11; a cover plate 8 is fixedly arranged on top of the mould sleeve 4 by means of fasteners cooperating with threaded uprights 10.
This scheme is that fix the die sleeve 4 bottom through setting up 11 with the unable adjustment base of 4 internal diameter looks adaptations of die sleeve and spacing, fixes die sleeve 4 through setting up apron 8 and the fastener of mutually supporting with screw thread pole setting 10.
In the actual use process, the butterfly nut 7 can be used as a fastener, the butterfly nut 7 is in threaded connection with the threaded upright rod 10, and the cover plate 8 is pressed on the top of the mold sleeve 4; the fixed base 11 is in a cross shape and is made of flat steel, so that the fixed base 11 can limit the die sleeve 4 and reduce the manufacturing cost.
As shown in fig. 1, according to the utility model discloses a novel super high-rise dwelling house wears floor and reserves entrance to a cave mould, wherein each the dismantlement subassembly all includes two sets of first telescopic link 14 that articulate at the 4 surfaces of mould sleeve, articulates second telescopic link 5 and the pinch bar 6 at the 14 free ends of first telescopic link, and wherein, the length of first telescopic link 14 is less than the length of pinch bar 6, and the free end of second telescopic link 5 is provided with supporting shoe 9.
This scheme is through setting up pinch bar 6, first telescopic link 14 and second telescopic link 5, with the pin joint of second telescopic link 5 and first telescopic link 14 as the fulcrum, when concrete 2 pours deeply, even the isolation layer 3 has been set up, there is great frictional force still between concrete 2 and the outer wall of mould sleeve pipe 4, want to demolish mould sleeve pipe 4 under this condition, at first take off apron 8, and support supporting shoe 9 on concrete 2, because lever principle, workman can exert oneself downwards at the free end of pinch bar 6, the power arm is greater than the resistance arm this moment, mould sleeve pipe 4 is pried upwards, first telescopic link 14 shrink, most frictional force is overcome between mould sleeve pipe 4 and concrete 2, take out mould sleeve pipe 4 from concrete 2 completely again can.
In the actual use process, a plurality of limiting holes can be formed in the second telescopic rod 5 to adapt to different conditions (the pouring depth of the concrete 2); in order to facilitate the accommodation of the first telescopic rod 14 and the pry bar 6, an accommodation groove 13 may be fixedly provided on the mold sleeve 4.
As shown in fig. 2, according to the utility model discloses a another embodiment, novel super high-rise residence wears floor and reserves entrance to a cave mould, wherein the dismantlement subassembly is the fixed sleeve pipe handle 12 that sets up at the mould sleeve 4 surface.
This scheme makes things convenient for the workman to extract mould sleeve 4 when concrete 2 pours more shallowly through setting up sleeve pipe handle 12, when concrete 2 pours more shallowly, at first unscrew butterfly nut 7 and take off apron 8, because concrete 2 pours more shallowly this moment, frictional force is less between concrete 2 and the mould sleeve 4, the worker people can directly drag sleeve pipe handle 12 and extract mould sleeve 4 can.
The specific embodiments are only for explaining the present invention, and it is not a limitation to the present invention, and those skilled in the art can make modifications to the embodiments without inventive contribution as required after reading the present specification, but all the embodiments are protected by patent law within the scope of the claims of the present invention.

Claims (7)

1. Novel super high-rise building wears floor and reserves entrance to a cave mould, a serial communication port, include:
the mould sleeve (4) is of a hollow structure with two open ends;
the fixing assembly is fixedly connected with the aluminum template (1), is positioned on the inner side of the mold sleeve (4), and is used for fixing the mold sleeve (4);
the number of the dismounting assemblies is at least one, one end of each dismounting assembly is connected with the outer surface of the mould sleeve (4), the other end of each dismounting assembly is tightly attached to the top of the concrete (2), and the dismounting assemblies are used for dismounting the mould sleeve (4) from the concrete (2);
isolation layer (3), it paints the setting at mould sleeve (4) surface, and isolation layer (3) are used for preventing that mould sleeve (4) from being adhered by concrete (2).
2. The novel through-floor reserved hole die for the super high-rise dwelling house as claimed in claim 1, wherein the fixing component comprises:
the fixed base (11) is matched with the inner diameter of the die sleeve (4), the fixed base (11) is clamped on the inner side of the die sleeve (4), and the fixed base (11) is fixedly arranged on the aluminum template (1) through bolts;
the threaded upright rod (10) is fixedly arranged at the top of the fixed base (11);
and the cover plate (8) is fixedly arranged at the top of the mold sleeve (4) through a fastener matched with the threaded upright rod (10).
3. The novel super high-rise dwelling house floor slab reserved hole die as claimed in claim 2, wherein: each disassembling component comprises a first telescopic rod (14) hinged to the outer surface of the mold sleeve (4), a second telescopic rod (5) hinged to the free end of the first telescopic rod (14) and a pry bar (6), wherein the length of the first telescopic rod (14) is smaller than that of the pry bar (6), and a supporting block (9) is arranged at the free end of the second telescopic rod (5).
4. The novel super high-rise residence floor-penetrating reserved hole die as claimed in claim 2, wherein: the disassembly assembly may also be a sleeve handle (12) fixedly disposed on an outer surface of the mold sleeve (4).
5. A novel super high-rise residence floor penetrating reserved hole die as claimed in claim 3 or 4, wherein: the fastener is a butterfly nut (7).
6. The novel super high-rise dwelling house floor slab reserved hole die as claimed in claim 5, wherein: the fixed base (11) is of a cross structure.
7. The novel super high-rise residence floor-penetrating reserved hole die as claimed in claim 6, wherein: the isolation layer (3) is a concrete isolation agent.
CN202222518228.2U 2022-09-22 2022-09-22 Novel super high-rise residence floor penetrating reserved hole die Withdrawn - After Issue CN218522235U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222518228.2U CN218522235U (en) 2022-09-22 2022-09-22 Novel super high-rise residence floor penetrating reserved hole die

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222518228.2U CN218522235U (en) 2022-09-22 2022-09-22 Novel super high-rise residence floor penetrating reserved hole die

Publications (1)

Publication Number Publication Date
CN218522235U true CN218522235U (en) 2023-02-24

Family

ID=85246970

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222518228.2U Withdrawn - After Issue CN218522235U (en) 2022-09-22 2022-09-22 Novel super high-rise residence floor penetrating reserved hole die

Country Status (1)

Country Link
CN (1) CN218522235U (en)

Similar Documents

Publication Publication Date Title
CN211007659U (en) Device for controlling forming of embedded steel plate in concrete column on column surface
CN112497439A (en) Die and method for manufacturing bridge deck auxiliary member
CN210396134U (en) Reinforcing tool for controlling horizontal joint quality of shear wall
CN109252656B (en) High-rise building climbing template and assembling, pouring and lifting method
CN114164977A (en) Method for combining construction of aluminum template and laminated slab
CN218522235U (en) Novel super high-rise residence floor penetrating reserved hole die
CN217079684U (en) Split type form removal-free concrete hollow structure
CN112901021B (en) Prefabricated bay window processing technology
CN114837337A (en) Prestress laminated bottom plate with turnover ribs and production and construction process
CN208502251U (en) A kind of assembly type step type pump line mouth can formwork
CN203603461U (en) Floor aluminum shuttering splicing formwork structure system
CN217400011U (en) Anchor decoration pendant is exempted from to tear open template wallboard structure earlier
CN112627504A (en) Method for manufacturing wall with heat insulation board
CN219118762U (en) Device is reserved to aluminum alloy template entrance to a cave
CN112609982A (en) Method for manufacturing wall with heat-insulation plate by adopting energy-saving bolt
CN112554391B (en) Formwork-removal-free heat-insulation concrete wall structure and construction method
CN212613756U (en) Pre-buried mould of pipeline entrance to a cave
CN214402701U (en) Can have enough to meet need protective sheath of shaped steel fixing bolt that encorbelments of use
CN219343994U (en) Shaping outer windowsill coping slope finding die
CN215631590U (en) Shear wall tie rod device and connecting structure at connecting part of cast-in-place concrete floor slab
CN216516343U (en) Structure integration exempts from to tear open prefabricated hollow wall of mould
CN110965778A (en) Cast-in-place board stagnant water type reserves telescopic design mould in hole
CN217631252U (en) Concrete turn-ups one shot forming die set
CN217708656U (en) Exempt from to cut tower crane and attach wall connecting piece
CN218205698U (en) A formwork structure for high-rise building constructional column

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20230224

Effective date of abandoning: 20230816

AV01 Patent right actively abandoned

Granted publication date: 20230224

Effective date of abandoning: 20230816