CN218479567U CN202222490894.XU CN202222490894U CN218479567U CN 218479567 U CN218479567 U CN 218479567U CN 202222490894 U CN202222490894 U CN 202222490894U CN 218479567 U CN218479567 U CN 218479567U
Authority
CN
China
Prior art keywords
super high
installation device
operating
support frame
rise building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222490894.XU
Other languages
Chinese (zh)
Inventor
吴海波
苗夏
苏国庆
熊国磊
葛千军
汤昆
李�浩
殷亚涛
宋磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
CCCC Ruitong Construction Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
CCCC Ruitong Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, CCCC Ruitong Construction Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202222490894.XU priority Critical patent/CN218479567U/en
Application granted granted Critical
Publication of CN218479567U publication Critical patent/CN218479567U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a super high-rise building partition plate installation device, which comprises a winch, two operating platforms, two supporting frames and a bottom support, wherein the two operating platforms are arranged side by side, one side of each operating platform is provided with a crawling ladder, the other side of each operating platform is connected with the supporting frame, and the supporting frame is connected between the other sides of the two operating platforms; the winch is arranged on one of the operating platforms, the pulley is arranged at the top of the supporting frame, the winch is connected with the pull rope, the pull rope winds around the pulley from the top and then extends downwards to be connected with the bottom support, and the universal wheels are arranged at the bottom of the operating platform. The utility model discloses the installation of lifting by crane of partition plate is carried out at the indoor of superelevation layer height to the in-process manpower cooperation hoist engine of lifting by crane, and semi-automatization operation, installation effectiveness is high, and labour saving and time saving has protected operating personnel's safety. Adopt two operation platform can carry out effectual support to the support frame, but also make things convenient for the staff to use operation platform to carry out other interior decoration operations.

Description

Super high-rise building partition plate installation device
Technical Field
The utility model relates to a building board erection equipment field, concretely relates to super high-rise building partition plate installation device especially relates to a super high-rise building double-deck light hollow partition plate's installation device.
Background
The light hollow partition wall board is a new type of energy-saving wall material and is made up of porcelain granules, cement, sand, steel wire net sheet and glass fibre net. The light hollow partition board has the advantages of light weight, high strength, multiple environmental protection, heat preservation and insulation, sound insulation, breathing moisture, fire prevention, rapid construction, reduction of the cost of the wall body and the like, and the light hollow partition board can improve the assembly rate and meet the requirement of the assembly rate of the building when being adopted by the building.
At present, a lot of light hollow partition boards are adopted for building construction to be used as indoor partition walls, the application range of the light hollow partition board products is wide, and the light hollow partition boards are suitable for non-bearing inner partition walls and building outer walls of civil and industrial buildings and agricultural buildings such as residential districts, hotels and office buildings.
The light hollow partition board has the conventional weight of about 230kg, so the working surface in the building is limited, and the installation is difficult. The traditional installation process needs 3-4 persons for cooperation operation, the wall body is firstly hoisted to a corresponding floor, then the wall body is moved to an installation position by cooperation of the persons, then the wall plate is lifted to be erected, and finally the wall plate is installed and fixed. For manual operation, the weight of the light hollow partition wall board is still very large, the existing installation tool still has the problem of consuming physical force, and especially for some super high-rise buildings (the height of the building indoor floor is more than 5 m), the installation efficiency of the double-layer hollow partition wall board is very low, and the double-layer hollow partition wall board is difficult to assemble in place at one time.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a solve one kind or several kinds that prior art has technical problem, provide a super high-rise building partition plate installation device.
The utility model provides an above-mentioned technical problem's technical scheme as follows: the installation device for the partition board of the super high-rise building comprises a winch, two operating platforms, two supporting frames and a bottom support, wherein the two operating platforms are arranged side by side; the multifunctional lifting device is characterized in that a winch is arranged on one of the operating platforms, a pulley is arranged at the top of the supporting frame, the winch is connected with a pull rope, the pull rope winds around the pulley from top to bottom and extends downwards to be connected with a bottom support, and universal wheels are arranged at the bottom of the operating platform.
The utility model has the advantages that: the utility model discloses a superelevation layer height building partition plate installation device lifts by crane the indoor installation that lifts by crane of carrying out partition plate of in-process manpower cooperation hoist engine at superelevation layer height, and whole installation only needs 2 people's cooperations alright to accomplish, convenient operation, semi-automatization operation, and the installation effectiveness is high, and labour saving and time saving has protected operating personnel's safety. The bottom of the operating platform is guided by the universal wheels, and 360-degree rotation operation can be realized. The position of the ladder stand is fixed by the operating platform, so that the stability of the ladder stand is improved, and the ladder stand is safer and more reliable to use. Adopt two operation platform can carry out effectual support to the support frame, but also make things convenient for the staff to use operation platform to carry out other interior decoration operations.
On the basis of the technical scheme, the utility model discloses can also do following improvement.
Further, the bottom support comprises a connecting rod and a connecting plate, the connecting rod is vertically fixed in the middle of one side edge of the connecting plate, and the lower end of the pull rope is connected with the connecting rod.
The beneficial effect of adopting the further scheme is that: through setting up connecting rod and connecting plate, conveniently be connected fixedly with the stay cord, also conveniently place partition plate on the connecting plate, support the promotion to the partition plate of suitable counter weight.
Furthermore, the upper end of the connecting rod is connected with a supporting rod which is horizontally arranged, and two ends of the supporting rod are respectively connected with the side edge of the connecting plate through supporting ropes.
The beneficial effect of adopting the further scheme is that: through setting up branch and a rope, make the structure of collet more firm, make partition plate's promotion more stable.
Further, the supporting frame is of an inverted U-shaped structure, and the top of the supporting frame is higher than that of the operating platform; the pulley is arranged obliquely relative to the plane of the support frame.
The beneficial effect of adopting the further scheme is that: the support frame of the inverted U-shaped structure is adopted, so that the pulley is convenient to mount. The pulley that the slope was arranged is favorable to the stay cord on one side hoist engine more adaptation pulley structure, avoids the increase or the stress of frictional force too big.
Further, the top of operation platform is equipped with the scaffold board, the both sides of scaffold board are equipped with the protection railing.
The beneficial effect of adopting the further scheme is that: through setting up the scaffold board, make things convenient for operating personnel to step on operation platform and operate, the setting of preventing guardrail bar also plays the effect that safety is strengthened to operating personnel.
Further, the guard rail on the top of each operating platform extends along the direction from the ladder stand to the supporting frame.
The beneficial effect of adopting the further scheme is that: the operation channel is conveniently enclosed by the protective barrier on each operation platform.
Furthermore, a protective rope is connected to the pull rope in a sliding mode and sleeved on the pull rope in an annular mode.
The beneficial effect of adopting the further scheme is that: can play further enhancement location effect to the partition plate on the connecting plate, prevent that the partition plate from inclining, can make the more steady quilt of partition plate hoist.
Furthermore, the width of each step of the ladder stand is 180-220 mm, and the height of each step is 230-300 mm.
Furthermore, brake pads are arranged on the universal wheels, the pull ropes are steel wire ropes, and the supporting frame is a square steel tube.
The beneficial effect of adopting the further scheme is that: the setting of brake block prevents that partition plate installation process operation platform from taking place the displacement. The pull rope is a steel wire rope, and is durable and high in tensile strength.
Furthermore, an X-shaped support frame is arranged on the inner side of the operating platform.
Drawings
Fig. 1 is a schematic perspective view of the installation device of the super high-rise building partition board of the utility model;
fig. 2 is a schematic view of the structure of the installation device of the partition board of the super high-rise building of the utility model;
fig. 3 is a structural schematic view of the installation device of the partition board of the super high-rise building of the utility model matched with the building;
fig. 4 is a schematic structural diagram of another embodiment of the shoe of the present invention.
In the drawings, the components represented by the respective reference numerals are listed below:
1. an operating platform; 2. climbing a ladder; 3. a universal wheel; 4. a scaffold board; 5. a guard rail; 6. a winch; 7. a support bar; 8. a pulley; 9. pulling a rope; 10. a connecting rod; 11. a connecting rod; 12. a protective rope; 13. a brake pad; 14. an X-shaped support frame; 15. building; 16. a connecting plate; 17. a partition plate; 18. a strut; 19. and (7) rope supporting.
Detailed Description
The principles and features of the present invention are described below in conjunction with the following drawings, the examples given are only intended to illustrate the present invention and are not intended to limit the scope of the present invention.
As shown in fig. 1 to 3, the partition board installation apparatus for a super high-rise building of the present embodiment includes a winch 6, two operation platforms 1, a support frame and a bottom support, wherein the operation platforms 1 are arranged side by side, one side of each operation platform 1 is provided with a ladder 2, the other side of each operation platform 1 is connected with the support frame, and the support frame is connected between the other sides of the two operation platforms 1; one of the operation platform 1 is provided with a winch 6, the top of the support frame is provided with a pulley 8, the winch 6 is connected with a pull rope 9, the pull rope 9 bypasses the pulley 8 from the top and then extends downwards and is connected with a bottom support, and the bottom of the operation platform 1 is provided with a universal wheel 3. This superelevation layer high building partition plate installation device equipment is convenient, and economical and practical accomodates the space that the back occupy and is little, makes things convenient for depositing and transporting of device, and the operation platform of this device also can regard as superelevation layer high building to build by laying bricks or stones engineering construction and decorate finishing work construction work platform.
Specifically, the hoist 6 is an electric hoist.
In a preferred embodiment of the shoe, as shown in fig. 1, the shoe comprises a connecting rod 11 and a connecting plate 16, the connecting rod 11 is vertically fixed at the middle position of one side edge of the connecting plate 16, and the lower end of the pull rope 9 is connected with the connecting rod 11. The connecting rod can be made of round steel, and the connecting plate can be made of a steel plate. Through setting up connecting rod and connecting plate, conveniently be connected fixedly with the stay cord, also conveniently place partition plate 17 on connecting plate 16, support the promotion to partition plate 17 of suitable counter weight.
In a further embodiment of the bottom bracket, as shown in fig. 4, the upper end of the connecting rod 11 is connected to a horizontally arranged strut 18, and two ends of the strut 18 are connected to the side edges of the connecting plate 16 through a supporting rope 19. Through setting up branch and a rope, make the structure of collet more firm, make partition plate's promotion more stable.
As shown in fig. 1 to 3, the supporting frame of the present embodiment is an inverted U-shaped structure, and the top of the supporting frame is higher than the top of the operating platform 1; the support frame of the inverted U-shaped structure is adopted, and the pulley is convenient to install. The pulley 8 is obliquely arranged relative to the surface of the support frame. The pulley that the slope was arranged is favorable to the stay cord on one side hoist engine more adaptation pulley structure, avoids the increase or the stress of frictional force too big.
As shown in fig. 1 to 3, a scaffold board 4 is disposed on the top of the operating platform 1, and guard rails 5 are disposed on two sides of the scaffold board 4. Through setting up the scaffold board, make things convenient for operating personnel to step on operation platform and operate, the setting of preventing guardrail bar also plays the effect that safety is strengthened to operating personnel.
As shown in fig. 1 to 3, the guard rail 5 on the top of each operating platform 1 of the present embodiment extends in the direction from the ladder 2 to the supporting frame. The guard rail 5 may be 1200mm in height. The operation channel is conveniently enclosed by the protective barrier on each operation platform.
As shown in fig. 1 to 3, a protective rope 12 is slidably connected to the pulling rope 9 in the present embodiment, and the protective rope 12 is annularly sleeved on the pulling rope 9. Can play further enhancement location effect to the partition plate on the connecting plate, prevent that the partition plate from inclining, can make the more steady quilt of partition plate hoist.
One specific scheme of the embodiment is that the step width of the ladder stand 2 is 180-220 mm, and the height of each step is 230-300 mm. Specifically, the step width of the ladder stand 2 is 180mm, 190mm, 200mm, 210mm and 220mm, and the height of each step is 230mm, 240mm, 250mm, 260mm, 270mm, 280mm, 290mm and 300mm.
As shown in fig. 1, the universal wheel 3 of the present embodiment is provided with a brake pad 13; the pull rope 9 is a steel wire rope, and the support frame is a square steel pipe. The setting of brake block prevents that partition plate installation process operation platform from taking place the displacement. The pull rope is a steel wire rope, so that the device is durable and high in tensile strength.
As shown in fig. 1, an X-shaped support frame 14 is disposed inside the operation platform 1 of the present embodiment.
The support frame of this embodiment is square steel pipe. The support frame includes bracing piece 7 and connecting rod 10, bracing piece 7 and connecting rod 10 all adopt square steel pipe. The operation platform 1 can also be made of steel pipes to form a frame body, and the frame body is paved with transverse steel pipes and longitudinal steel pipes to form a scaffold. The two support rods 7 are vertically fixed on the operating platform 1 respectively, and two ends of the connecting rod 10 are connected with the top ends of the two support rods 7 respectively. The pulley 8 is installed at a middle position of the connecting rod 10.
The super high-rise building partition board installation device of this embodiment is at the during operation, and on moving the collet with the hollow partition board of light, sheathe the protective rope 12 in the middle of the hollow partition board of light, because the collet links to each other with the stay cord 9 of hoist engine, the collet is connected after the stay cord 9 of hoist engine 6 passes pulley 8, and the people climbs to scaffold board 4 through cat ladder 2 on, lifts by crane installation at in-process manpower cooperation hoist engine 6, lifts by crane the hollow partition board of light. Whole installation need 2 people cooperation alright accomplish, labour saving and time saving, convenient operation, semi-automatization operation, the installation effectiveness is high, operation labour saving and time saving. The adoption hoist engine 6 of this embodiment pulls up the hollow partition wall board of light, and operation platform and pulley combination can realize 360 rotation operations, realize the location through the fixed universal wheel 3 of brake block 13, and this device can regard as 15 masonry engineering construction of super high-rise building and decoration and fitment engineering construction operation platform simultaneously, convenient operation, semi-automatization operation, and the installation effectiveness is high, operation labour saving and time saving.
The super high-rise building partition board installation device of this embodiment lifts by crane the installation of lifting by crane that in-process manpower cooperation hoist engine carries out partition board in super high-rise indoor, and whole installation only needs 2 people's cooperations alright to accomplish, convenient operation, and semi-automatization operation, the installation effectiveness is high, and labour saving and time saving has protected operating personnel's safety. The bottom of the operating platform is guided by the universal wheels, and 360-degree rotation operation can be realized. The position of the ladder stand is fixed by the operating platform, so that the stability of the ladder stand is improved, and the ladder stand is safer and more reliable to use. Adopt two operation platform can carry out effectual support to the support frame, but also make things convenient for the staff to use operation platform to carry out other interior decoration operations.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential", and the like, indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include at least one such feature. In the description of the present invention, "a plurality" means at least two, e.g., two, three, etc., unless specifically limited otherwise.
In the present invention, unless otherwise expressly stated or limited, the terms "mounted," "connected," and "fixed" are to be construed broadly and may, for example, be fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; they may be directly connected or indirectly connected through intervening media, or they may be connected internally or in any other suitable relationship, unless expressly stated otherwise. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
In the present application, unless expressly stated or limited otherwise, the first feature may be directly on or directly under the second feature or indirectly via intermediate members. Also, a first feature "on," "above," and "over" a second feature may be directly on or obliquely above the second feature, or simply mean that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature may be directly under or obliquely under the first feature, or may simply mean that the first feature is at a lesser elevation than the second feature.
In the description herein, references to the description of the term "one embodiment," "some embodiments," "an example," "a specific example," or "some examples," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above are not necessarily intended to refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples. Furthermore, various embodiments or examples and features of different embodiments or examples described in this specification can be combined and combined by one skilled in the art without contradiction.
While embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting the present invention, and that variations, modifications, substitutions and alterations of the above embodiments may be made by those of ordinary skill in the art without departing from the scope of the present invention.

Claims (10)

1. The installation device for the partition board of the super high-rise building is characterized by comprising two windlasses, two operating platforms, two support frames and a bottom support, wherein the two operating platforms are arranged side by side; the multifunctional lifting device is characterized in that a winch is arranged on one of the operating platforms, a pulley is arranged at the top of the supporting frame, the winch is connected with a pull rope, the pull rope winds around the pulley from top to bottom and extends downwards to be connected with a bottom support, and universal wheels are arranged at the bottom of the operating platform.
2. The apparatus as claimed in claim 1, wherein the bottom bracket comprises a connecting rod and a connecting plate, the connecting rod is vertically fixed at a middle position of one side of the connecting plate, and the lower end of the pull rope is connected with the connecting rod.
3. The installation device of partition boards for super high-rise buildings according to claim 2, wherein the upper ends of the connecting rods are connected with horizontally arranged supporting rods, and the two ends of the supporting rods are respectively connected with the side edges of the connecting plates through supporting ropes.
4. The installation device of partition boards for super high-rise buildings according to claim 1, wherein the support frame is of an inverted U-shaped structure, and the top of the support frame is higher than the top of the operating platform; the pulley is obliquely arranged relative to the plane of the support frame.
5. The installation device of partition boards for super high-rise buildings according to claim 1, wherein a scaffold board is arranged on the top of the operation platform, and protective railings are arranged on two sides of the scaffold board.
6. The installation apparatus for partition boards in super high-rise buildings according to claim 5, wherein the guard rail at the top of each of the operation platforms is arranged to extend in a direction from the ladder to the support frame.
7. The installation device of a partition board for a super high-rise building according to claim 1, wherein a protection rope is slidably connected to the pulling rope, and the protection rope is annularly sleeved on the pulling rope.
8. The installation device of the partition board of the super high-rise building as claimed in claim 1, wherein the ladder stand has a step width of 180 to 220mm and a height of 230 to 300mm per step.
9. The installation device of the partition board for the super high-rise building according to claim 1, wherein the universal wheels are provided with brake pads, the pull rope is a steel wire rope, and the support frame is a square steel pipe.
10. The installation device of partition board for super high-rise building according to claim 1, wherein an X-shaped support frame is provided inside the operation platform.
CN202222490894.XU 2022-09-20 2022-09-20 Super high-rise building partition plate installation device Active CN218479567U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222490894.XU CN218479567U (en) 2022-09-20 2022-09-20 Super high-rise building partition plate installation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222490894.XU CN218479567U (en) 2022-09-20 2022-09-20 Super high-rise building partition plate installation device

Publications (1)

Publication Number Publication Date
CN218479567U true CN218479567U (en) 2023-02-14

Family

ID=85167258

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222490894.XU Active CN218479567U (en) 2022-09-20 2022-09-20 Super high-rise building partition plate installation device

Country Status (1)

Country Link
CN (1) CN218479567U (en)

Similar Documents

Publication Publication Date Title
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN201826516U (en) Novel attached lifting scaffold
CA2665985A1 (en) Scaffold elevator
CN111255217A (en) Elevator shaft shaping operation platform and operation method thereof
CN111395730A (en) Curtain wall construction system and method suitable for high-rise building with special-shaped giant columns
CN218479567U (en) Super high-rise building partition plate installation device
CN209568688U (en) A kind of elevating construction platform
CN209011528U (en) A kind of all steel attachment type raise scaffold
CN113107180B (en) All-steel structure climbing frame
CN212581394U (en) Portable small-size material transport device
CN216108092U (en) Construction system for installing steel bar formwork of building pier column
CN211974269U (en) From climbing formula elevartor shaft steel platform
CN112942886B (en) Construction method for additionally building corridor in old building
JP3950800B2 (en) Suspension scaffold
CN212334397U (en) Auxiliary tool for hoisting and moving pipeline
KR101668177B1 (en) Electric Powered Multistage Work Platform
CN211923466U (en) Elevator shaft regularization operation platform
CN211366866U (en) Safe and environment-friendly automatic lifting device for scaffold steel pipe
CN210655915U (en) Connecting device for climbing frame and tower crane
CN210561720U (en) Pier stud maintenance repair operation platform
CN209924409U (en) Wall-attached self-climbing electric lifting platform
CN114436134A (en) Glass vertical hoisting in-place tool capable of being flexibly adjusted and displaced in multiple directions and use method
CN112761345A (en) Construction method and operation platform for shaped elevator shaft
WO1995006177A1 (en) Liftable scaffold
CN219931561U (en) Integral lifting type elevator shaft operation platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant