CN218373992U - A auxiliary device for installation is pour to illumination foundation frame - Google Patents

A auxiliary device for installation is pour to illumination foundation frame Download PDF

Info

Publication number
CN218373992U
CN218373992U CN202221990812.1U CN202221990812U CN218373992U CN 218373992 U CN218373992 U CN 218373992U CN 202221990812 U CN202221990812 U CN 202221990812U CN 218373992 U CN218373992 U CN 218373992U
Authority
CN
China
Prior art keywords
beams
foundation frame
illumination
positioning
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221990812.1U
Other languages
Chinese (zh)
Inventor
姜同贵
黄子兴
田源
王先平
杨杰
武锋
吴健
王祖林
张远彬
麻帅康
谢瑾佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 7 Co Ltd
Original Assignee
Sinohydro Bureau 7 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 7 Co Ltd filed Critical Sinohydro Bureau 7 Co Ltd
Priority to CN202221990812.1U priority Critical patent/CN218373992U/en
Application granted granted Critical
Publication of CN218373992U publication Critical patent/CN218373992U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses an auxiliary device for installation is pour to illumination foundation frame. The combined steel frame is composed of a supporting beam, a fixed beam, a connecting beam and a positioning beam; two supporting beams are arranged in parallel, the two supporting beams are connected and fixed through two parallel fixing beams, four connecting beams which are arranged vertically and have the same length are welded to four inner angles formed by intersection of the fixing beams and the supporting beams respectively, positioning beams of the parallel supporting beams are transversely arranged at the tail ends of the four connecting beams in a welding and fixing mode, through holes are formed in the middle of each positioning beam, and hole sites formed by the through holes of the four positioning beams and four suspension screws of the lighting foundation frame are used for being fixed in a suspension mode respectively in a corresponding mode. The utility model provides the high stability of illumination foundation frame in concreting and concrete hardening process effectively avoids illumination foundation frame to take place to remove or slope and hardening in-process concrete inflation leads to it to take place to squint to illumination foundation frame location in the installation, the foundation frame of placing that can be accurate is favorable to quality control.

Description

A auxiliary device for installation is pour to illumination foundation frame
Technical Field
The utility model belongs to the technical field of illumination construction machinery design, a illumination construction auxiliary device design is related to, specifically is an auxiliary device for installation is pour to illumination foundation frame.
Background
The traditional municipal lighting foundation frame installation process usually adopts a mode of using a steel bar welding support between the lighting foundation frame and a foundation pit retaining wall to fix the lighting foundation frame, and then concrete is poured. Practice shows that the method for fixing by using the steel bar welding support is not firm, the problems of deviation, inclination and the like of the illumination foundation frame can easily occur when concrete is poured, and great influence is generated on the subsequent installation work and the illumination engineering quality; on the other hand, traditional illumination foundation frame installation construction can pour the concrete cushion earlier and then carry out the installation of illumination foundation frame for realizing the bottom concrete protective layer, can show slightly complicacy on the process, also can produce certain influence to the construction progress. For the rapidly developing municipal engineering infrastructure construction, the traditional illumination foundation frame installation and construction method needs to be improved urgently.
Disclosure of Invention
The utility model discloses an auxiliary device for installation is pour to illumination foundation frame. The to-be-solved problem of the utility model is exactly to above not enough and provide a simple structure, easy and simple to handle's municipal administration illumination foundation frame and pour installation auxiliary device.
The technical scheme is as follows:
the utility model provides an auxiliary device for installation is pour to illumination foundation frame which characterized in that: the auxiliary device is a combined steel frame which is used for detachably suspending and fixing the lighting foundation frame; the combined steel frame consists of a supporting beam, a fixed beam, a connecting beam and a positioning beam; two supporting beams are arranged in parallel, the two supporting beams are connected and fixed through two parallel fixing beams, four connecting beams which are arranged vertically and are equal in length are welded at four inner angles formed by the intersection of the fixing beams and the supporting beams respectively, positioning beams of the parallel supporting beams are transversely arranged at the tail ends of the four connecting beams in a welding and fixing mode, through holes are formed in the middle of each positioning beam, and hole sites formed by the through holes of the four positioning beams and four suspension screws of the lighting foundation frame are correspondingly used for suspension and fixation respectively.
And further, through holes are formed in two ends of each supporting beam and are used for being fixed on the lighting foundation frame pouring foundation through expansion bolts or ground nails.
The utility model discloses a supporting beam, fixed beam, tie-beam and the fixed welding of locating beam that combination steel frame can be cut into by the angle steel constitute.
When the supporting beam is fixed on the lighting foundation frame pouring foundation, the positioning beam fixed at the tail end of each connecting beam is positioned above the surface of the lighting foundation frame pouring concrete.
Compared with the prior art, the utility model discloses the beneficial effect who has is:
the utility model provides the high stability of illumination foundation frame in concreting and concrete hardening process effectively avoids at blowing in-process hard aggregate and reinforcing bar collision and leads to illumination foundation frame to take place to remove or incline and hardening in-process concrete inflation leads to it to take place to squint to there is the positioning action illumination foundation frame in the installation, can be more accurate place illumination foundation frame, be favorable to project quality control.
The utility model has the advantages of being simple in structure and simple in operation, illumination foundation frame concrete protective layer can once only pour the completion, does not need earlier to pour the concrete cushion and treats that it hardens the installation of illumination foundation frame again, compares with traditional mounting process, has reduced the work progress, the effectual required engineering time of construction that shortens the illumination engineering, is favorable to project progress control.
The utility model discloses the device can used repeatedly, compares traditional mounting process and pours the reinforcing bar together and can reduce the material and use, is favorable to project cost control.
Drawings
FIG. 1 is a schematic plan view of the auxiliary device of the present invention;
FIG. 2 is a partial schematic view of the auxiliary device of the present invention;
FIG. 3 is a front view of the auxiliary device of the present invention;
fig. 4 is a left side view of the auxiliary device of the present invention;
fig. 5 is a top view of the auxiliary device of the present invention.
In the figure, 1-supporting beam, 2-fixed beam, 3-connecting beam, 4-positioning beam, 5-lighting foundation frame, 6-expansion screw, 7-nut and 8-concrete.
Detailed Description
The following description is provided for further illustration of the present invention with reference to specific embodiments, which are intended to be further illustrations of the principles of the present invention, without any limitation to the present invention, and the present invention is not limited to the same or similar techniques.
As shown in the figure, the utility model is used for the auxiliary device for installing the illumination foundation frame, and comprises a supporting beam 1, a fixed beam 2, a connecting beam 3 and a positioning beam 4; the supporting beam 1 is arranged on a foundation pit of the illumination foundation, the fixed beam 2 is used for being fixed with the supporting beam 1 arranged on the foundation pit, the connecting beam 3 is used for connecting the supporting beam 1 and the positioning beam 4, and the positioning beam 4 is used for combining the auxiliary device with the illumination foundation frame.
The supporting beam 1 is provided with a round hole and is fixed with the foundation ground by an expansion screw 6 penetrating through the round hole; the positioning beam 4 is provided with a positioning adjusting hole for fixing with the lighting base frame through a nut 7.
The parallel supporting beam 1 and the parallel fixing beam 2 are vertically fixed on a horizontal plane, the connecting beam 3 is vertically fixed with the supporting beam 1 on a vertical plane, and the positioning beam 4 is arranged parallel to the supporting beam 1 on the vertical plane.
As shown in the figure, the device can be formed by welding and fixing galvanized angle steel.
In this embodiment, the supporting beam 1 is formed by arranging two 2.2m galvanized angle steels in parallel, and a round hole is formed at a position 500mm away from the edge of each end, and is connected with the foundation ground through an expansion screw 6. The fixed beam 2 is welded with the supporting beam 1 in a quadrilateral way by two parallelly placed 450mm galvanized angle steels; two positioning beams 4 are arranged below each supporting beam 1, a positioning adjusting hole is formed in the center of each positioning beam 4, the positioning adjusting holes of the four positioning beams 4 form a 400mm-400mm square which corresponds to the screws of the illumination basic frame one by one, and the illumination basic frame is connected with the installation auxiliary device through the illumination basic matching nut 7; the connecting beam 3 is formed by vertically placing four galvanized steel angles with the thickness of 200mm on a vertical plane and welding an upper structure formed by the supporting beam 1 and the fixed beam 2 and the positioning beam 4 into a whole.
During construction, firstly, four positioning adjusting holes of the positioning beam 4 of the installation auxiliary device correspondingly penetrate through four screw rods of the illumination foundation frame 5 on the ground and are connected through the matched nuts 7 of the illumination foundation frame, and then the well-connected installation auxiliary device and the illumination foundation frame 5 are movably placed in a foundation pit; adjusting the position of the supporting beam 1 at the foundation pit opening to adjust the illumination basic frame 5 to the center of the foundation pit, determining the position of the illumination basic frame 5, and then fixing the illumination basic frame with the ground by penetrating an expansion screw 6 through a round hole formed in the supporting beam 1; and the lighting foundation frame 5 is adjusted to a proper height and leveled by adjusting the nut 7, and the nut 7 is protected by a protective film before pouring to prevent the concrete from polluting the concrete and influencing subsequent disassembly.

Claims (4)

1. The utility model provides an auxiliary device for installation is pour to illumination foundation frame which characterized in that: the auxiliary device is a combined steel frame which is used for detachably suspending and fixing the lighting foundation frame; the combined steel frame consists of a support beam, a fixed beam, a connecting beam and a positioning beam; the two supporting beams are arranged in parallel, the two supporting beams are fixedly connected through the two parallel fixing beams, four inner angles formed by the intersection of the fixing beams and the supporting beams are respectively welded with four connecting beams which are vertically arranged and have the same length, the tail ends of the four connecting beams are fixedly welded with positioning beams transversely arranged on the parallel supporting beams, through holes are formed in the middle of each positioning beam, and hole sites formed by the through holes of the four positioning beams and four suspension screws of the lighting foundation frame are respectively and correspondingly used for suspension and fixation.
2. An auxiliary device for pouring installation of a lighting foundation frame according to claim 1, wherein: through holes are formed in two ends of each supporting beam and are used for being fixed on the lighting foundation frame pouring foundation through expansion bolts or ground nails.
3. An auxiliary device for pouring installation of a lighting foundation frame according to claim 2, wherein: the combined steel frame is formed by welding and fixing a support beam, a fixed beam, a connecting beam and a positioning beam which are cut by angle steel.
4. An auxiliary device for pouring and installing a lighting foundation frame as claimed in claim 2, wherein: when the supporting beam is fixed on the lighting foundation frame pouring foundation, the positioning beam fixed at the tail end of each connecting beam is positioned above the surface of the lighting foundation frame pouring concrete.
CN202221990812.1U 2022-07-30 2022-07-30 A auxiliary device for installation is pour to illumination foundation frame Active CN218373992U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221990812.1U CN218373992U (en) 2022-07-30 2022-07-30 A auxiliary device for installation is pour to illumination foundation frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221990812.1U CN218373992U (en) 2022-07-30 2022-07-30 A auxiliary device for installation is pour to illumination foundation frame

Publications (1)

Publication Number Publication Date
CN218373992U true CN218373992U (en) 2023-01-24

Family

ID=84962757

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221990812.1U Active CN218373992U (en) 2022-07-30 2022-07-30 A auxiliary device for installation is pour to illumination foundation frame

Country Status (1)

Country Link
CN (1) CN218373992U (en)

Similar Documents

Publication Publication Date Title
CN102561712B (en) Precise positioning frame for large steel columns and equipment foundation fixing bolts and construction method of precise positioning frame
CN112127641A (en) Accurate fixing method for anchor plate foundation bolt
CN106702907B (en) A kind of Bridge guardrail base adjustable flange disk construction method
CN112127637A (en) Construction method for pre-buried vertical component steel bars of foundation layer of fabricated building
CN110670734A (en) Fixing device for pre-buried steel plate under shock insulation support and construction method thereof
CN218373992U (en) A auxiliary device for installation is pour to illumination foundation frame
CN116516982A (en) Construction method for adjusting concrete support of station enclosure structure to steel support
CN214245823U (en) Advance through structure of new and old structure girder on two sides of mid-partition wall
CN112096096B (en) Positioning device for embedded steel plate and construction method thereof
CN108661301A (en) Derrick stand modularization assembling platform and application method
CN208618771U (en) A kind of derrick stand modularization assembling platform
CN208586529U (en) A kind of gradient precast beam support leveling device
JPH10317391A (en) Foundation structure for steel tower and method for constructing the same
CN105298140A (en) Reinforcing steel bar positioning frame and positioning method for constructing external shear walls
CN108824203A (en) A kind of gradient precast beam support leveling device
CN215801767U (en) Overweight equipment foundation bolt high accuracy embedded structure
CN218324002U (en) Installation fine-tuning device for large foundation bolt of equipment foundation
CN215366862U (en) Fetal membrane device of prefabricated T roof beam end
CN218205785U (en) Concrete pouring flatness control device
CN219509179U (en) Beam bottom surface formwork appurtenance
CN213114328U (en) Square column and tie beam one shot forming construction equipment
CN117266226A (en) Large-scale equipment foundation bolt installation device and method
CN110984208A (en) Construction method for steel column embedded bolt base
JP2021105272A (en) Precast floor slab construction method
JPH0666025A (en) Floor forming method using floor supporting beam and floor supporting beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant