CN108661301A - Derrick stand modularization assembling platform and application method - Google Patents
Derrick stand modularization assembling platform and application method Download PDFInfo
- Publication number
- CN108661301A CN108661301A CN201810651472.1A CN201810651472A CN108661301A CN 108661301 A CN108661301 A CN 108661301A CN 201810651472 A CN201810651472 A CN 201810651472A CN 108661301 A CN108661301 A CN 108661301A
- Authority
- CN
- China
- Prior art keywords
- stand
- derrick
- platform
- basis
- modularization assembling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 11
- 238000010276 construction Methods 0.000 claims abstract description 11
- 229910000831 Steel Inorganic materials 0.000 claims description 20
- 239000010959 steel Substances 0.000 claims description 20
- 238000009434 installation Methods 0.000 claims description 10
- 241000269793 Cryothenia peninsulae Species 0.000 claims description 3
- 238000005266 casting Methods 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 3
- 239000000203 mixture Substances 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims description 2
- 239000002689 soil Substances 0.000 claims description 2
- 210000003205 muscle Anatomy 0.000 claims 1
- 238000003466 welding Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000036244 malformation Effects 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/17—Comprising essentially pre-assembled three-dimensional elements, e.g. cubic elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Jib Cranes (AREA)
Abstract
Derrick stand modularization assembling platform and application method, including basis, the basis are made of concrete connection built-in fitting, and the basis is connected with platform by built-in fitting, and the platform includes Vierendeel girder, supporting beam and fixed beam.The present invention derrick stand modularization assembling platform and application method can be rapidly and efficiently progress derrick stand modularization assembling centering, accelerate the speed of derrick stand assembling centering, improve the quality and working efficiency of derrick stand assembling centering, the labor intensity of construction personnel is reduced, construction cost is saved.
Description
Technical field
The present invention relates to a kind of operation platform of derrick of copper-mine stand modularization assembling, specifically a kind of derrick stand moulds
Block assembly platform and application method.
Technical background
Traditional derrick stand construction laterally assembling, hangs into vertical and then is attached with crane.I.e. first by two root posts
It is laterally placed, connects horizontal gird and support and centering between column, then right angle setting column top tie-beam and support, most
It is transversely mounted crossbeam and support between two root posts and column again afterwards, forms it into frame structure, crane lifting is used after adjusting centering
To installation site.The drawbacks of this installation is:1, it needs repeatedly to measure adjustment, size Control difficulty is big, while in frame
More tubing is needed to be supported before centering fastening.2, after the completion of overall package centering, lifting stand is laterally turned into vertically
When easily there is malformation.
Invention content
Technical problem to be solved by the present invention lies in the deficiency for overcoming the above-mentioned prior art, provide it is a kind of it is simple in structure,
The derrick stand modularization assembling platform and application method to work well.
The present invention is realized with following technical solution:A kind of derrick stand modularization assembling platform, including basis, it is described
Basis is made of concrete connection built-in fitting, and the basis is connected with platform by built-in fitting, and the platform includes Vierendeel girder, branch
Support beam and fixed beam.
It is further:The concrete on the basis is embedded in underground and the 100mm that bassets, the concrete on the basis
Size is 3066mm × 3066mm × 600mm.
The basis uses C25 concrete.
The built-in fitting is made of steel plate and several spirals, the vertical welding of the spiral on the steel plate, phase
The adjacent spiral interval is identical.
The size of the steel plate is 2066mm × 2066mm × 20mm, and the length and diameter of the spiral is respectively
360mm and 25mm is divided into 415mm between the spiral.
The platform surrounds frame by several Vierendeel girders, and supporting beam is connected between the Vierendeel girder, the Vierendeel girder
Junction is equipped with fixed beam, and the fixed beam lower part welds together with built-in fitting, and the fixed beam top is equipped with and stand connects
The bolt hole that fishplate bar is used cooperatively.
The material model of the Vierendeel girder, supporting beam and fixed beam is HW309 × 306 × 10 × 14.
The fixed beam includes outer grid beam and inner beam, and the outer grid beam surrounds rectangular, and the inner beam connects opposite outline border
Beam.
A kind of application method of derrick stand modularization assembling platform as described in claim 1,
Include the following steps:
A, it before derrick stand modularization assembling platform makes, is made in platform according to stand installation site and crane radius of turn
The heart carries out the datum line construction of derrick stand modularization assembling platform using theodolite according to the appearance and size of stand.
B, 4 bases of construction determine that the location and shape on basis, casting concrete are put down on the basis of making according to drawing size
Face levelness and absolute altitude meet assembly platform arrangement and require, and built-in fitting are placed in above the concrete after pouring, spiral is inserted
Enter in concrete.
Four Vierendeel girders, two supporting beams and four fixed beams are formed the general frame of platform, and made by c, assembly platform
With high-strength bolt connect fasten, on the basis of carry out Leveling and centering after with basic embedded board weld.
Derrick second layer column lower end is attached tightly by d, assembling stand using mounting hole on bolt and fixed beam position
Whether measuring center line and Diagonal Dimension meet the requirements after Gu, then install connecting cross beam, direct centering the upper end of the column ruler
Very little and verticality of stand column after the completion of centering, carries out whole fastening, and be fixed using steel pipe, shaped steel.
E, on the stand column crane lifting to derrick installation position of derrick bottommost, bottom stage crossbeam is installed after centering
And bearing diagonal.
F, directly the second layer stand of derrick is lifted to pithead position and bottom abutting joint, then in group using crane
It closes and continues assembling stand third layer and above section on platform, one section of often assembling stand is just lifted into well head and derrick installation centering
Good hypomere is attached centering.
The present invention has the following advantages:The derrick stand modularization assembling platform and application method of the present invention can be rapidly and efficiently
Progress derrick stand modularization assembling centering, accelerate derrick stand assembling centering speed, improve derrick stand assembling looks for
Positive quality and working efficiency reduces the labor intensity of construction personnel, saves construction cost.
Description of the drawings
Fig. 1 is the overall structure diagram of the present invention;
Fig. 2 is the front view of assembly platform of the present invention;
Fig. 3 is the upward view of assembly platform of the present invention;
Fig. 4 is the front view of built-in fitting of the present invention;
Fig. 5 is the left view of built-in fitting of the present invention;
Fig. 6 is construction location schematic diagram of the present invention;
In figure:1, platform, 2, basis, 3, built-in fitting, 4, crane, 5, pit shaft, 6, stand, 7, derrick, 11, Vierendeel girder, 12, support
Beam, 13, fixed beam, 14, outer grid beam, 15, inner beam, 31, steel plate, 32, spiral.
Specific implementation mode
A kind of derrick stand modularization assembling platform as shown in Figures 1 to 6, including basis 2, described basic 2 is by coagulation
Soil connection built-in fitting 3 forms, and described basic 2 are connected with platform 1 by built-in fitting 3, and the platform 1 includes Vierendeel girder 11, support
Beam 12 and fixed beam 13.The platform 1 surrounds frame by several Vierendeel girders 11, and supporting beam is connected between the Vierendeel girder 11
12, the junction of the Vierendeel girder 11 is equipped with fixed beam 13, and 13 lower part of the fixed beam welds together with built-in fitting 3, described
The bolt hole that 13 top of fixed beam is equipped with and stand connecting plate is used cooperatively.The assembly platform of the present invention consists of two parts, and one
Be it is buried under basis, second is that with basis connect the platform being placed on ground, basic body is concrete, is fixedly arranged above pre-buried
Part, by built-in fitting, basis and platform weld together, and basic quantity is not unique, simultaneously because the setting on basis is in underground,
Therefore the stability and intensity for strengthening platform, conducive to the accuracy of the stand size and structure that process is improved;Platform master
It to be made of Vierendeel girder, supporting beam and fixed beam, Vierendeel girder forms the integral outer frame structure of platform, and inside passes through supporting beam
Connection adds the stiff stability of general frame, while adjacent Vierendeel girder junction is equipped with fixed beam, and Vierendeel girder and supporting beam are steady
Gu the position of fixed beam play the role of it is vital, the downward both ends of fixed beam be connected separately with basis and stand, lower end pass through
Welding is connect with built-in fitting, and upper end is connect by bolt hole with stand connecting plate, for realizing the connection of platform and stand, is realized
The function of console module assembling stand.
A kind of derrick stand modularization assembling platform as shown in Figures 1 to 6, basic 2 concrete are embedded in underground
And the 100mm that bassets, the size of basic 2 concrete is 3066mm × 3066mm × 600mm.Described basic 2 use
C25 concrete.The basic body of the present invention is formed by concreting, and meets plane levelness and absolute altitude symbol on platform base
It is combined assembling platform arrangement to require, while basis is basseted 100mm, and pours be fixed with built-in fitting above, pass through built-in fitting
With the welding of fixed beam, greatly improve the stability of platform, specifically set there are four basis, and with four angle phases of the stand of derrick
It is corresponding, play the role of reinforcing stability when forming stand.
A kind of derrick stand modularization assembling platform as shown in Figures 1 to 6, the built-in fitting 3 is by steel plate 31 and several
Spiral 32 forms, and the spiral 32 is vertical to be welded on steel plate 31, and the adjacent spiral 32 is spaced phase
Together.The size of the steel plate 31 is 2066mm × 2066mm × 20mm, and the length and diameter of the spiral 32 is respectively
360mm and 25mm is divided into 415mm between the spiral 32.The built-in fitting of the present invention is by steel plate and welds on the steel plate
Spiral forms, and spiral is uniformly welded on the same side of steel plate, and spiral is towards concreting when use
Entire built-in fitting is firmly fixed together with concreting part by square part.
A kind of derrick stand modularization assembling platform as shown in Figures 1 to 6, the Vierendeel girder 11, supporting beam 12 and solid
The material model for determining beam 13 is HW309 × 306 × 10 × 14.The fixed beam 13 includes outer grid beam 14 and inner beam 15, described outer
Grid beam 14 surrounds rectangular, and the inner beam 15 connects opposite outer grid beam 14.The fixed beam of the present invention plays connection basis and stand
Effect, therefore the stability of fixed beam is most important, and the structure of fixed beam is made of four outer grid beams for forming lateral frame,
Outer grid beam composition is rectangular, intermediate to connect opposite outer grid beam by inner beam and reinforce stability, and the lower part of fixed beam is and built-in fitting
Weld together, the bolt hole that top is arranged on inner beam and stand connecting plate is used cooperatively, the stand for being assembled with needs
Connection, is bolted convenient for stand installation and removal when assembled, while can guarantee strength and stability when assembled.
A kind of application method of derrick stand modularization assembling platform as described in claim 1,
Include the following steps:
A, before derrick stand modularization assembling platform makes, platform 1 is made according to 6 installation site of stand and 4 radius of turn of crane
Center carry out the datum line construction of derrick stand modularization assembling platform using theodolite according to the appearance and size of stand 6.
B, 4 bases 2 of construction determine that the location and shape on basis 2, casting concrete make on basis 2 according to drawing size
Plane levelness and absolute altitude meet assembly platform arrangement and require, and built-in fitting are placed in above the concrete after pouring, spiral
It is inserted into concrete.
Four Vierendeel girders, 11, two supporting beams 12 and four fixed beams 13 are formed the entirety of platform 1 by assembly platform 1 c,
Frame, and using high-strength bolt connection fastening, welded with basic embedded board after Leveling and centering is carried out on basis 2.
D, assembling stand 6 connects 7 second layer column lower end of derrick using bolt and mounting hole on 13 position of fixed beam
Whether measuring center line and Diagonal Dimension meet the requirements after connecing fastening, then install connecting cross beam, on direct centering column
It holds size and verticality of stand column, after the completion of centering, carries out whole fastening, and be fixed using steel pipe, shaped steel.
Bottom stage is installed horizontal e, on the stand column crane lifting to derrick installation position of 7 bottommost of derrick, after centering
Beam and bearing diagonal.
F, directly the second layer stand 6 of derrick 7 is lifted to pithead position and bottom abutting joint using crane, is then existed
Continue assembling stand third layer and above section on combined platform, one section of often assembling stand is just lifted into well head and is installed with derrick 7
The good hypomere of centering is attached centering.
Claims (9)
1. a kind of derrick stand modularization assembling platform, it is characterised in that:Including basis(2), the basis(2)Connected by concrete
Connect built-in fitting(3)Composition, the basis(2)Pass through built-in fitting(3)It is connected with platform(1), the platform(1)Including Vierendeel girder
(11), supporting beam(12)And fixed beam(13).
2. a kind of derrick stand modularization assembling platform as described in claim 1, it is characterised in that:The basis(2)It is mixed
Solidifying soil is embedded in underground and the 100mm that bassets, the basis(2)Concrete size be 3066mm × 3066mm × 600mm.
3. a kind of derrick stand modularization assembling platform as claimed in claim 2, it is characterised in that:The basis(2)Using
C25 concrete.
4. a kind of derrick stand modularization assembling platform as described in claim 1, it is characterised in that:The built-in fitting(3)By
Steel plate(31)With several spirals(32)Composition, the spiral(32)Vertical is welded on steel plate(31)On, it is adjacent
The spiral(32)It is spaced identical.
5. a kind of derrick stand modularization assembling platform as claimed in claim 4, it is characterised in that:The steel plate(31)Ruler
Very little is 2066mm × 2066mm × 20mm, the spiral(32)Length and diameter be respectively 360mm and 25mm, the spiral shell
Line reinforcing bar(32)Between be divided into 415mm.
6. a kind of derrick stand modularization assembling platform as described in claim 1, it is characterised in that:The platform(1)If by
Dry Vierendeel girder(11)Surround frame, the Vierendeel girder(11)Between be connected with supporting beam(12), the Vierendeel girder(11)Connection
Place is equipped with fixed beam(13), the fixed beam(13)Lower part and built-in fitting(3)Weld together, the fixed beam(13)Top is set
There is the bolt hole being used cooperatively with stand connecting plate.
7. a kind of derrick stand modularization assembling platform as described in claim 1, it is characterised in that:The Vierendeel girder(11)、
Supporting beam(12)And fixed beam(13)Material model be HW309 × 306 × 10 × 14.
8. a kind of derrick stand modularization assembling platform as described in claim 1, it is characterised in that:The fixed beam(13)Packet
Include outer grid beam(14)And inner beam(15), the outer grid beam(14)Surround rectangular, the inner beam(15)Connect opposite outer grid beam
(14).
9. a kind of application method of derrick stand modularization assembling platform as described in claim 1, it is characterised in that:
Include the following steps:
A, before derrick stand modularization assembling platform makes, according to stand(6)Installation site and crane(4)Radius of turn is made flat
Platform(1)Center, using theodolite according to stand(6)Appearance and size, carry out derrick stand modularization assembling platform benchmark
Line is constructed;
B, 4 bases of construction(2), basis is determined according to drawing size(2)Location and shape, casting concrete makes basis(2)
Upper plane levelness and absolute altitude meet assembly platform arrangement and require, and built-in fitting are placed in above the concrete after pouring, screw-thread steel
Muscle is inserted into concrete;
C, assembly platform(1), by four Vierendeel girders(11), two pieces supporting beams(12)With four fixed beams(13)Form platform(1)
General frame, and using high-strength bolt connection fastening, on basis(2)It is welded with basic embedded board after upper carry out Leveling and centering;
D, assembling stand(6), by derrick(7)Second layer column lower end uses bolt and fixed beam(13)Mounting hole carries out on position
Whether measuring center line and Diagonal Dimension meet the requirements after connection fastening, then install connecting cross beam, direct centering column
Upper end size and verticality of stand column after the completion of centering, carry out whole fastening, and be fixed using steel pipe, shaped steel;
E, derrick(7)On the stand column crane lifting to derrick installation position of bottommost, bottom stage crossbeam is installed after centering
And bearing diagonal;
F, using crane directly by derrick(7)Second layer stand(6)Then lifting exists to pithead position and bottom abutting joint
Continue assembling stand third layer and above section on combined platform, one section of often assembling stand is just lifted into well head and derrick(7)Peace
The good hypomere of dress centering is attached centering.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810651472.1A CN108661301B (en) | 2018-06-22 | 2018-06-22 | Modular assembly platform for vertical frames of well frames and use method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810651472.1A CN108661301B (en) | 2018-06-22 | 2018-06-22 | Modular assembly platform for vertical frames of well frames and use method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108661301A true CN108661301A (en) | 2018-10-16 |
CN108661301B CN108661301B (en) | 2024-06-07 |
Family
ID=63772916
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810651472.1A Active CN108661301B (en) | 2018-06-22 | 2018-06-22 | Modular assembly platform for vertical frames of well frames and use method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108661301B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109594753A (en) * | 2018-12-05 | 2019-04-09 | 江苏春都钢结构工程有限公司 | A kind of new steel structure engineering rack |
CN114961291A (en) * | 2022-05-23 | 2022-08-30 | 中国十七冶集团有限公司 | Modularized installation method for dust removal ventilation shaft in steelmaking environment |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203296361U (en) * | 2013-06-14 | 2013-11-20 | 江西建工第一建筑有限责任公司 | Long-span steel structure cross assembling hoisting platform |
KR101363795B1 (en) * | 2012-12-10 | 2014-02-20 | 한국건설기술연구원 | Joint construction of modular unit structure and foundation concrete |
CN205444851U (en) * | 2015-12-28 | 2016-08-10 | 美联钢结构建筑系统(上海)股份有限公司 | Construction platform device |
CN107419802A (en) * | 2017-08-10 | 2017-12-01 | 中冶天工集团天津有限公司 | A prefabricated concrete frame structure and its construction method |
CN208618771U (en) * | 2018-06-22 | 2019-03-19 | 中煤第五建设有限公司 | A kind of derrick stand modularization assembling platform |
-
2018
- 2018-06-22 CN CN201810651472.1A patent/CN108661301B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101363795B1 (en) * | 2012-12-10 | 2014-02-20 | 한국건설기술연구원 | Joint construction of modular unit structure and foundation concrete |
CN203296361U (en) * | 2013-06-14 | 2013-11-20 | 江西建工第一建筑有限责任公司 | Long-span steel structure cross assembling hoisting platform |
CN205444851U (en) * | 2015-12-28 | 2016-08-10 | 美联钢结构建筑系统(上海)股份有限公司 | Construction platform device |
CN107419802A (en) * | 2017-08-10 | 2017-12-01 | 中冶天工集团天津有限公司 | A prefabricated concrete frame structure and its construction method |
CN208618771U (en) * | 2018-06-22 | 2019-03-19 | 中煤第五建设有限公司 | A kind of derrick stand modularization assembling platform |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109594753A (en) * | 2018-12-05 | 2019-04-09 | 江苏春都钢结构工程有限公司 | A kind of new steel structure engineering rack |
CN114961291A (en) * | 2022-05-23 | 2022-08-30 | 中国十七冶集团有限公司 | Modularized installation method for dust removal ventilation shaft in steelmaking environment |
Also Published As
Publication number | Publication date |
---|---|
CN108661301B (en) | 2024-06-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102561712B (en) | Accurate positioning frame for large steel column and equipment foundation fixing bolt and construction method thereof | |
CN104674945A (en) | Tree-shaped steel pipe column structure and construction method thereof | |
CN106346596A (en) | Precast stair template matching system | |
CN108411790A (en) | A kind of adjustable installing bracket of prefabricated assembled segmentation bent cap | |
CN109235280A (en) | The operation platform and construction method of bridge coping | |
CN109853365A (en) | A kind of high pier construction of modularization prefabrication and assembly construction based on high-strength bolt connection and production method | |
CN104500106B (en) | A kind of tunnel inverted arch construction mould bases and tunnel inverted arch construction technology | |
CN108661301A (en) | Derrick stand modularization assembling platform and application method | |
CN109267493A (en) | Construction method for installing steel cover beam across river course | |
CN109469094A (en) | Super High bottom plate interpolation fashioned iron column construction method and fixed structure | |
CN209194354U (en) | High-altitude long-span binder base-supporting shellfish thunder support construction | |
CN209114333U (en) | A kind of combined steel structural unit block | |
CN110670734A (en) | Fixing device for pre-buried steel plate under shock insulation support and construction method thereof | |
CN208618771U (en) | A kind of derrick stand modularization assembling platform | |
CN206189607U (en) | Rag bolt location structure | |
CN214498388U (en) | Assembled overhanging formwork support bent | |
CN110258294A (en) | Steel truss arch bridge installs system and its construction method | |
CN105821770B (en) | Connecting and locating method for multiple tower roots and large-size concrete bearing platform foundation of steel structure main tower | |
CN220035215U (en) | A hang mould support that is used for bridge main tower mound top to pour | |
CN107938854A (en) | A kind of steel girder erection method using built-in fitting | |
CN219604164U (en) | Variable cross-section special-shaped steel tower crown mounting device | |
CN111648611A (en) | Embedded part support device and embedded part installation method using the embedded part support device | |
CN208379444U (en) | A kind of adjustable installing bracket of prefabricated assembled segmentation bent cap | |
CN100362195C (en) | A method of processing and installing pre-embedded anchor bolts at the foot of a leaning tower | |
CN106930406B (en) | A kind of preparation method of Anchor Bolts in Steel Column Bases positioning structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant |