CN218175612U - Movable guardrail formwork mounting operation platform - Google Patents
Movable guardrail formwork mounting operation platform Download PDFInfo
- Publication number
- CN218175612U CN218175612U CN202222443395.5U CN202222443395U CN218175612U CN 218175612 U CN218175612 U CN 218175612U CN 202222443395 U CN202222443395 U CN 202222443395U CN 218175612 U CN218175612 U CN 218175612U
- Authority
- CN
- China
- Prior art keywords
- platform
- construction
- counter weight
- link
- operation platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model provides a portable guardrail formwork erection operation platform, including the tie-beam, tie-beam one end has set firmly the counter weight platform, and the other end has set firmly construction platform, is equipped with pedestrian's passageway between counter weight platform, tie-beam and the construction platform, and counter weight platform top both sides have set firmly the second link, and construction platform top both sides have set firmly first link, and bolt and second link and first link fixed connection are passed through at counter weight platform both ends. The operation platform is welded by profile steel and is provided with the counterweight platform, so that the safety performance of the bridge guardrail in the installation process of the template outside the bridge guardrail is improved; the operation platform can be used in a turnover mode, so that the construction cost of a vertical ladder stand, a lifting vehicle and the like is saved; the operation platform can freely move along the direction of the guardrail, so that the installation time of the construction operation platform is saved, and the construction is more efficient; operation platform equipment convenient and fast, the integral connection is more firm, and pedestrian's passageway sets up the personnel of being convenient for business turn over construction platform.
Description
Technical Field
The utility model relates to a civil engineering's field, concretely relates to portable guardrail formwork installation operation platform.
Background
The construction of bridge anticollision barrier generally carries out the form setting after the guardrail reinforcing bar construction finishes. Templates on two sides of the guardrail can be directly installed on the guardrail in the bridge; when the external guardrail of a bridge or the internal guardrail of a split bridge is constructed, the external guardrail is limited by the operation space, the external guardrail template usually adopts a vertical ladder, a lift truck and the like as the operation platform for installing the template, but the vertical ladder, the lift truck and the like have lower efficacy, so the operation platform needs to be improved.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a main aim at provides a portable guardrail formwork mounting operation platform solves the problem in the above-mentioned background art.
In order to solve the technical problem, the utility model discloses the technical scheme who adopts is: including the tie-beam, tie-beam one end has set firmly the counter weight platform, and the other end has set firmly construction platform, is equipped with pedestrian's passageway between counter weight platform, tie-beam and the construction platform, and counter weight platform top both sides have set firmly the second link, and construction platform top both sides have set firmly first link, and bolt and second link and first link fixed connection are passed through at counter weight platform both ends.
In the preferred scheme, the two sides of the connecting beam main body are single-slope beam bodies formed by I-shaped steel, and the bottoms of the two beam bodies are connected through a plurality of cross beams.
In a preferred scheme, a second steel plate is fixedly arranged at the bottom of the connecting beam, guard railings are fixedly arranged on the periphery of the connecting beam, an inlet is formed in one end of each guard railing, a hole is formed in the other end of each guard railing, and the hole is formed in the second steel plate.
In the preferred scheme, the counterweight platform is a framework formed by square steel, a second crawling ladder is fixedly arranged on the outer side of the counterweight platform, an inclined strut is fixedly arranged at the top of the inner side of the counterweight platform, the inclined strut abuts against the bottom of the connecting beam, and the second crawling ladder is arranged below the inlet.
In the preferred scheme, the counterweight block is fixedly arranged in the counterweight platform, and rollers are arranged at four corners of the bottom of the counterweight platform.
In the preferred scheme, the construction platform is a framework formed by square steel, a first crawling ladder is fixedly arranged on one side inside the construction platform, a first steel plate is fixedly arranged at the bottom of the construction platform, and the first crawling ladder is arranged below the hole.
The utility model provides a portable guardrail formwork erection operation platform, beneficial effect:
1. the operation platform is welded by profile steel and is provided with the balance weight platform, so that the safety performance of the bridge guardrail outer side template in the installation process is improved;
2. the operation platform can be used in a turnover mode, so that the construction cost of a vertical ladder stand, a lifting vehicle and the like is saved;
3. the operation platform can freely move along the direction of the guardrail, so that the installation time of the construction operation platform is saved, and the construction is more efficient;
4. operation platform equipment convenient and fast, the monolithic union is more firm, and the pedestrian passageway sets up the personnel of being convenient for business turn over construction platform.
Drawings
The invention will be further explained with reference to the following figures and examples:
FIG. 1 is a side view of the overall structure of the present invention;
FIG. 2 is an exploded view of the overall structure of the present invention;
FIG. 3 is a front view of the overall structure of the present invention;
FIG. 4 is a top view of the overall structure of the present invention;
in the figure: a construction platform 1; a first link frame 101; a first ladder stand 102; a first steel plate 103; a connecting beam 2; a guard rail 201; a second steel plate 202; a hole 203; an inlet 204; a counterweight platform 3; a second link frame 301; a second ladder 302; a diagonal brace 303.
Detailed Description
Example 1
As shown in fig. 1 to 4, a movable guardrail formwork installation operation platform comprises a connecting beam 2, a counterweight platform 3 is fixedly arranged at one end of the connecting beam 2, a construction platform 1 is fixedly arranged at the other end of the connecting beam, pedestrian passages are arranged between the counterweight platform 3, the connecting beam 2 and the construction platform 1, second connecting frames 301 are fixedly arranged on two sides of the top of the counterweight platform 3, first connecting frames 101 are fixedly arranged on two sides of the top of the construction platform 1, and two ends of the counterweight platform 3 are fixedly connected with the second connecting frames 301 and the first connecting frames 101 through bolts. From this structure, counter weight platform 3 hangs construction platform 1 in the bridge outside through tie-beam 2, and counter weight platform 3 and construction platform 1 are connected convenient and fast with tie-beam 2, connect more firmly firm. The pedestrian passageway is arranged so that workers can conveniently enter and exit the construction platform 1.
In the preferred scheme, the two sides of the main body of the connecting beam 2 are single-slope beam bodies formed by I-shaped steel, and the bottoms of the two beam bodies are connected through a plurality of cross beams. With this structure, the connection beam 2 can have a sufficient bending resistance, and the stability of the suspended construction platform 1 can be ensured.
In a preferred scheme, a second steel plate 202 is fixedly arranged at the bottom of the connecting beam 2, a protective guard 201 is fixedly arranged on the peripheral side of the connecting beam 2, one end of the protective guard 201 is provided with an inlet 204, the other end of the protective guard is provided with a hole 203, and the hole 203 is formed in the second steel plate 202. With the structure, workers can enter the second steel plate 202 from the inlet 204 and then enter the construction platform 1 from the hole 203, and the guard rail 201 can ensure the safety of the workers in walking. The second steel plate 202 may be a scaffold or a skid-proof mat.
In the preferred scheme, the counterweight platform 3 is a framework made of square steel, the second ladder 302 is fixedly arranged on the outer side of the counterweight platform 3, the inclined bracket 303 is fixedly arranged on the top of the inner side of the counterweight platform 3, the inclined bracket 303 abuts against the bottom of the connecting beam 2, and the second ladder 302 is arranged below the inlet 204. From this structure, on the staff can get into tie-beam 2 from second cat ladder 302, then in getting into construction platform 1 from tie-beam 2, the bracing frame 303 can guarantee to the support of tie-beam 2 connect. Ensure the integral structure to be more stable and firm.
In the preferred scheme, counter weight platform 3 internal stability has the balancing weight, and 3 bottom four corners of counter weight platform are equipped with the gyro wheel. From this structure, the stability that hangs can be guaranteed to the balancing weight. The roller may make the whole movable.
In the preferred scheme, the construction platform 1 is a framework formed by square steel, a first ladder stand 102 is fixedly arranged on one side inside the construction platform 1, a first steel plate 103 is fixedly arranged at the bottom of the construction platform 1, and the first ladder stand 102 is arranged below the hole 203. With this configuration, the first steel plate 103 is a scaffold or a patterned mat, and a worker can enter the first steel plate 103 through the first ladder 102 from the hole 203.
The above-mentioned embodiments are merely preferred embodiments of the present invention, and should not be considered as limitations of the present invention, and the protection scope of the present invention should be defined by the technical solutions described in the claims, and includes equivalent alternatives of technical features in the technical solutions described in the claims. Namely, equivalent alterations and modifications within the scope of the invention are also within the scope of the invention.
Claims (6)
1. The utility model provides a portable guardrail formwork erection operation platform, characterized by: including tie-beam (2), tie-beam (2) one end has set firmly counter weight platform (3), the other end has set firmly construction platform (1), counter weight platform (3), be equipped with pedestrian's passageway between tie-beam (2) and construction platform (1), counter weight platform (3) top both sides have set firmly second link (301), construction platform (1) top both sides have set firmly first link (101), bolt and second link (301) and first link (101) fixed connection are passed through at counter weight platform (3) both ends.
2. The mobile guardrail formwork installation and operation platform of claim 1, wherein: the two sides of the main body of the connecting beam (2) are single-slope beam bodies formed by I-shaped steel, and the bottoms of the two beam bodies are connected through a plurality of cross beams.
3. The movable guardrail formwork mounting and operating platform as claimed in claim 2, wherein: the bottom of the connecting beam (2) is fixedly provided with a second steel plate (202), the periphery of the connecting beam (2) is fixedly provided with a protective guard (201), one end of the protective guard (201) is provided with an inlet (204), the other end of the protective guard is provided with a hole (203), and the hole (203) is formed in the second steel plate (202).
4. The movable guardrail formwork mounting and operating platform as claimed in claim 1, wherein: the counterweight platform (3) is a framework formed by square steel, the second ladder stand (302) is fixedly arranged on the outer side of the counterweight platform (3), the inclined bracket (303) is fixedly arranged on the top of the inner side of the counterweight platform (3), the inclined bracket (303) abuts against the bottom of the connecting beam (2), and the second ladder stand (302) is arranged below the inlet (204).
5. The mobile guardrail formwork installation and operation platform of claim 4, wherein: the counterweight block is fixedly arranged in the counterweight platform (3), and rollers are arranged at four corners of the bottom of the counterweight platform (3).
6. The mobile guardrail formwork installation and operation platform of claim 1, wherein: the construction platform (1) is a framework formed by square steel, a first ladder stand (102) is fixedly arranged on one side inside the construction platform (1), a first steel plate (103) is fixedly arranged at the bottom of the construction platform (1), and the first ladder stand (102) is arranged below the hole (203).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222443395.5U CN218175612U (en) | 2022-09-15 | 2022-09-15 | Movable guardrail formwork mounting operation platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222443395.5U CN218175612U (en) | 2022-09-15 | 2022-09-15 | Movable guardrail formwork mounting operation platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218175612U true CN218175612U (en) | 2022-12-30 |
Family
ID=84623254
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222443395.5U Active CN218175612U (en) | 2022-09-15 | 2022-09-15 | Movable guardrail formwork mounting operation platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218175612U (en) |
-
2022
- 2022-09-15 CN CN202222443395.5U patent/CN218175612U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN115788012A (en) | Hydraulic climbing formwork integral climbing and sliding device and method suitable for inclined wall construction | |
CN218175612U (en) | Movable guardrail formwork mounting operation platform | |
CN216109994U (en) | Communication tower with lifting system | |
CN212478487U (en) | Construction platform for building construction | |
CN211946009U (en) | Tower crane pedestrian passageway device | |
CN212129859U (en) | Detachable steel structure aerial work operating platform | |
CN209891694U (en) | Building faces limit structure post construction protection frame | |
JP3049300B2 (en) | Construction method of beam truss in building with overhead traveling crane | |
CN218147841U (en) | Template construction platform integrated device | |
CN216840813U (en) | Vertical passage structure for building shaping of assembly type house construction project | |
CN117513711A (en) | Mobile operation platform for side bottom construction of suspended vestibule of atrium | |
CN216840490U (en) | Multi-functional platform of assembly type structure stairwell | |
CN218623258U (en) | Climbing structure of attached scaffold | |
CN211899832U (en) | Building construction site stair | |
CN213679551U (en) | Tower crane pedestrian passageway | |
CN217840796U (en) | Portable anti-overturning mobile operation platform | |
CN217326382U (en) | Lifting elevator derrick suitable for elevator shaft with side wall | |
CN212154077U (en) | Safety protection scaffold for building engineering construction | |
CN218346833U (en) | Independent beam formwork support bearing bracket | |
CN212612022U (en) | High mound reinforcement integral type shaped steel scaffold frame | |
CN114380179B (en) | Safety construction method of hoistway elevator | |
CN214034693U (en) | Modular assembly step ladder | |
CN207177260U (en) | A kind of multifunctional mobile safety climbing ladder | |
CN219158370U (en) | Attached lifting operation safety protection platform with openable protective net | |
CN214117614U (en) | Creeping formwork top part breaking type stair gap bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |