CN218149893U - Hoisting structure for prefabricated part suspender - Google Patents

Hoisting structure for prefabricated part suspender Download PDF

Info

Publication number
CN218149893U
CN218149893U CN202222139157.5U CN202222139157U CN218149893U CN 218149893 U CN218149893 U CN 218149893U CN 202222139157 U CN202222139157 U CN 202222139157U CN 218149893 U CN218149893 U CN 218149893U
Authority
CN
China
Prior art keywords
component
jib
prefabricated
preformed hole
hoisting structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222139157.5U
Other languages
Chinese (zh)
Inventor
姚尚斌
姚大伟
薛建新
王真理
汪继东
杨帆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Hailong Construction Industry Co Ltd
Original Assignee
Anhui Hailong Construction Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Hailong Construction Industry Co Ltd filed Critical Anhui Hailong Construction Industry Co Ltd
Priority to CN202222139157.5U priority Critical patent/CN218149893U/en
Application granted granted Critical
Publication of CN218149893U publication Critical patent/CN218149893U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a prefabricated component jib structure of lifting by crane, including following step: the method comprises the following steps that firstly, a preformed hole of a component is positioned according to a drawing of the component, and after the position of the preformed hole is found on a die, a bottom limiting piece of a hoisting device is arranged on a die table surface for limiting; step two, screwing the suspender onto the magnet sheet through the lower thread at the bottom; step three, the installation finishes the back, pours the mould, the utility model relates to an assembled prefabricated component production technical field. This prefabricated component jib lifts by crane structure utilizes the existing preformed hole of prefabricated component to install the jib device of a dedicated area inclination and lifts by crane, and one shot forming need not repair, has solved component outward appearance colour difference problem, need not to handle hole secondary construction, has guaranteed the component quality, has reduced the construction cost who brings because of the secondary construction.

Description

Hoisting structure for prefabricated part suspender
Technical Field
The utility model relates to an assembled prefabricated component production technical field specifically is a prefabricated component jib lifts by crane structure.
Background
In recent years, the industrialization of buildings characterized by standardized design, industrial production, assembly construction, integrated decoration, etc. has become a necessary trend in the development of the building industry in China. The problems of complex process, high labor intensity, low working efficiency, wide occupied area, high production cost, poor surface flatness of a manual surface-collecting product and the like exist in the production of prefabricated parts at the present stage.
The conventional method that prefabricated component hoists temporarily in the factory still reserves rings (reinforcing bar curved anchor) on prefabricated wallboard, or reserves built-in fitting hoisting modes such as hanging nail, promotion pipe fitting, this kind of hoisting mode shortcoming still needs to cut the face reinforcing bar that stretches out and will repair cutting part position after the hoist and mount is accomplished, product quality problems such as product outward appearance has colour difference, the numerous and diverse production efficiency of this kind of method process is low, to the waste of materials such as built-in fitting material, repair material, labour, specifically as follows:
1. the existing hoisting ring hoisting mode needs cutting and repairing and can cause the problem of appearance color difference caused by repairing, but the technology uses the holes of the prefabricated part for hoisting, does not need cutting and repairing, and does not have the problem of the appearance color difference of the part caused by repairing;
2. the existing hoisting mode of the hoisting ring needs to embed bent and disassembled steel bars in the member, and can not be recycled, the hoisting of the technology is realized by utilizing the suspender, the suspender can be recycled, and the cost problem caused by raw materials is saved;
3. the existing hoisting ring hoisting mode needs cutting and repairing in the later period, a large amount of labor cost is needed, the screw rod can be screwed up in the technology, and the production efficiency is greatly improved.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art, the utility model provides a prefabricated component jib lifts by crane structure has solved the problem that the aforesaid provided.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: a precast member jib hoisting structure: including pouring jib in the preformed hole in the component and setting up the bottom locating part of mesa on the mould, the top fixedly connected with magnet piece of bottom locating part, the bottom of jib set up the lower screw thread with the top threaded connection of bottom locating part, the screw thread has been seted up at the top of jib, and the inner chamber threaded connection of going up the screw thread has the universal rings of being connected with the chain that lifts by crane.
As a further aspect of the present invention: the surface of the suspender is provided with a conical surface with the diameter gradually increasing from top to bottom, and the bottom outer ring of the suspender is welded with a bottom welding ring.
As a further aspect of the present invention: the lifting device is provided with a plurality of lifting devices which are symmetrically distributed on the preformed hole of the component.
As a further aspect of the present invention: the surface of the hanger rod is galvanized.
The method comprises the following steps:
the method comprises the following steps that firstly, a preformed hole of a component is positioned according to a drawing of the component, and after the position of the preformed hole is found on a die, a bottom limiting piece of a hoisting device is arranged on a die table surface for limiting;
step two, screwing the suspender onto the magnet sheet through the lower thread at the bottom;
thirdly, pouring the mould after the installation is finished, screwing the universal hanging ring on an upper thread of the hanging rod after the concrete reaches the demoulding strength of the concrete, and then hanging a hanging hook through a hanging chain to hoist the component;
and step four, after the hoisting is finished, moving the component to a specified position to finish the hoisting, screwing out the bottom limiting part from the hanger rod, and then disassembling.
As a further aspect of the present invention: and in the second step, the upper thread teeth of the suspender are wrapped by kraft paper.
As a further aspect of the present invention: the disassembly in the fourth step specifically comprises the following steps: the universal hanging ring is screwed out from the upper thread, then the hanging rod is knocked out from the reserved hole in the component by knocking from top to bottom, and the hanging rod is knocked out from the lower part through the conical surface of the hanging rod, so that the disassembly is completed.
Compared with the prior art, the utility model following beneficial effect possesses:
1. the utility model discloses, utilize to install the jib device of a dedicated area inclination on the current preformed hole of prefabricated component and lift by crane, one shot forming need not repair, has solved component outward appearance colour difference problem, need not to handle hole secondary construction, has guaranteed the component quality, has reduced the construction cost who brings because of the secondary construction.
2. The utility model discloses, after the drawing of patterns such as jib was accomplished, can take out the jib, adorn again when lifting by crane next component, can reuse, to lifting by crane the saving of raw and other materials to convenient operation is dismantled in the installation.
Drawings
FIG. 1 is a schematic view of the hoisting of the present invention;
FIG. 2 is an enlarged view of a portion A of FIG. 1;
FIG. 3 is a schematic structural view of the suspension rod of the present invention;
FIG. 4 is a schematic view of the suspension point position of the present invention;
fig. 5 is a structural cross-sectional view of the bottom welding ring of the present invention.
In the figure: 1. a member; 2. reserving a hole; 3. a boom; 4. screwing the threads; 5. a universal hoisting ring; 6. lower thread teeth; 7. a magnet piece; 8. a bottom stop; 9. welding a ring at the bottom; 10. a conical surface; 11. and (5) molding.
Detailed Description
To further illustrate the technical means and effects of the present invention adopted to achieve the objects of the present invention, the following detailed description of the embodiments, structures, features and effects according to the present invention will be made with reference to the accompanying drawings and preferred embodiments.
Referring to fig. 1-5, the present invention provides a technical solution: a precast member jib hoisting structure: including pouring jib 3 in the preformed hole 2 in the component 1 and setting up the bottom locating part 8 of mesa on mould 11, the top fixedly connected with magnet piece 7 of bottom locating part 8, lower thread 6 with the top threaded connection of bottom locating part 8 is seted up to the bottom of jib 3, thread 4 has been seted up at the top of jib 3, and the inner chamber threaded connection of last thread 4 has the universal rings 5 of being connected with the chain that lifts by crane, it lifts by crane to utilize the dedicated jib 3 device of taking the inclination of installation on the preformed hole 2 that prefabricated component 1 has now to lift by crane, one shot forming, need not repair, the component outward appearance colour difference problem has been solved, need not to handle hole secondary construction, component 1 quality has been guaranteed, construction cost because of the secondary construction brings has been reduced.
The surface of the suspender 3 is provided with a conical surface 10 with the diameter gradually increasing from top to bottom, and the bottom outer ring of the suspender 3 is welded with a bottom welding ring 9.
The hoisting device is provided with a plurality of hoisting devices which are symmetrically distributed on the preformed hole 2 of the member 1.
The surface of the suspender 3 is galvanized.
A special suspender 3 with inclination is arranged on the existing preformed hole 2 of the prefabricated part 1 for hoisting, and the prefabricated part is formed at one time without repairing, so that the problem of chromatic aberration of the appearance of the prefabricated part is solved;
after the lifting rod 3 and the like are demolded, the lifting rod 3 can be taken out and then is installed when the next component 1 is lifted, so that the lifting component can be repeatedly used, and the lifting raw materials are saved;
firstly, the magnet sheets 7 and the hanger rods 3 are arranged, after the poured concrete reaches the demoulding strength of the concrete, the lifting screw is screwed up and the lifting hook is hung, so that the concrete can be lifted, the lifting process is simple, and the production efficiency is improved;
the existing preformed hole 2 on the component 1 is utilized, secondary construction treatment on the hole is not needed, the quality of the component 1 is guaranteed, and the construction cost caused by secondary construction is reduced.
The method comprises the following steps:
step one, positioning a preformed hole 2 of a member 1 according to a drawing of the member 1, and after the position of the preformed hole 2 is found on a mold 11, arranging a bottom limiting part 8 of a hoisting device on the table surface of the mold 11 for limiting;
step two, screwing the suspender 3 on the magnet sheet 7 through the lower thread 6 at the bottom;
step three, after the installation is finished, pouring the mould 11, after the concrete reaches the demoulding strength of the concrete, screwing the universal hanging ring 5 on the upper screw thread 4 of the suspender 3, and then hanging a lifting hook by a lifting chain to lift the component 1;
and step four, after the hoisting is finished, moving the component 1 to a specified position to finish the hoisting, screwing out the bottom limiting part 8 from the suspender 3, and then disassembling.
And in the second step, the upper thread teeth 4 of the hanger rod 3 are wrapped by kraft paper.
The disassembly in the fourth step specifically comprises the following steps: the universal hanging ring 5 is screwed out of the upper thread 4, then the hanging rod 3 is knocked out of the preformed hole 2 in the component 1 from top to bottom, the hanging rod 3 is knocked out from the lower part through the conical surface 10 of the hanging rod 3, and the disassembly is completed.
The above description is only a preferred embodiment of the present invention, and the present invention is not limited to the above description, and although the present invention has been disclosed by the preferred embodiment, it is not limited to the present invention, and any person skilled in the art can make modifications or changes equivalent to the equivalent embodiments by utilizing the above disclosed technical contents without departing from the technical scope of the present invention, but all the modifications, changes and changes of the technical spirit of the present invention made to the above embodiments are also within the scope of the technical solution of the present invention.

Claims (5)

1. The utility model provides a prefabricated component jib hoisting structure which characterized in that: including pouring jib (3) in preformed hole (2) in component (1) and bottom locating part (8) of setting mesa on mould (11), the top fixedly connected with magnet piece (7) of bottom locating part (8), lower screw thread (6) with the top threaded connection of bottom locating part (8) are seted up to the bottom of jib (3), last screw thread (4) have been seted up at the top of jib (3), and the inner chamber threaded connection of going up screw thread (4) has universal rings (5) of being connected with the chain that lifts by crane.
2. A prefabricated part boom hoisting structure according to claim 1, wherein: the upper thread (4) of the hanger rod (3) is wrapped by kraft paper.
3. A prefabricated boom hoisting structure according to claim 1, wherein: the surface of the suspender (3) is provided with a conical surface (10) with the diameter gradually increasing from top to bottom, and the bottom outer ring of the suspender (3) is welded with a bottom welding ring (9).
4. A prefabricated boom hoisting structure according to claim 1, wherein: the hoisting structure is provided with a plurality of hoisting structures which are symmetrically distributed on the preformed hole (2) of the member (1).
5. A prefabricated boom hoisting structure according to claim 1, wherein: the surface of the hanger rod (3) is galvanized.
CN202222139157.5U 2022-08-12 2022-08-12 Hoisting structure for prefabricated part suspender Active CN218149893U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222139157.5U CN218149893U (en) 2022-08-12 2022-08-12 Hoisting structure for prefabricated part suspender

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222139157.5U CN218149893U (en) 2022-08-12 2022-08-12 Hoisting structure for prefabricated part suspender

Publications (1)

Publication Number Publication Date
CN218149893U true CN218149893U (en) 2022-12-27

Family

ID=84551333

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222139157.5U Active CN218149893U (en) 2022-08-12 2022-08-12 Hoisting structure for prefabricated part suspender

Country Status (1)

Country Link
CN (1) CN218149893U (en)

Similar Documents

Publication Publication Date Title
CN102328881B (en) Device and method for hoisting entire oversized steel reinforcement cage in one step
CN204609154U (en) The hollow stair system of a kind of prefabricated assembling type reinforced concrete
CN109968501B (en) Prefabricated stand convenient to installation and preparation mould thereof
CN218149893U (en) Hoisting structure for prefabricated part suspender
CN102561779B (en) Barrel-shaped integral concrete water storage tower tank and preparation method thereof
CN108560842B (en) Precast concrete stair section with multipurpose holes and preparation and application thereof
CN109732773B (en) Mounting node and mounting method of support hinged concrete prefabricated part
CN108547383A (en) A kind of lifting diagonal brace integration embedded part and application method
CN210164235U (en) Simple slip form mold for small-diameter reinforced concrete cylinder structure
CN115370159A (en) Hoisting mode for prefabricated part suspender
CN111395271A (en) Suspended sliding form for second-stage concrete lining of gate slot and construction method
CN210758391U (en) Prefabricated component demoulding horizontal hoisting assembly capable of being recycled
CN106065565B (en) A kind of construction method of prefabricated architectural concrete pier column
CN213412372U (en) Mould for prefabricated staircase
CN210658449U (en) Remove aluminum alloy template structure
CN204609298U (en) Turnover plate type entirety hangs sky stair template
CN210238546U (en) Prefabricated reinforced concrete sump pit child mould structure
CN210316545U (en) Novel cast-in-place area of prefabricated wallboard of assembled is consolidated device
CN210651255U (en) Horizontal-hanging combined part for demolding prefabricated parts
CN112976256A (en) Production process of prestressed concrete laminated slab bottom plate
CN205777484U (en) Elevator Integral lifting core
CN212924077U (en) Temporary road pavement uses guidance tape
CN112643850B (en) Preparation process of concrete prefabricated part
CN209868943U (en) Split type stair forming die
CN219820124U (en) Prefabricated round pipe culvert mould

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant