CN218149647U - Harmless anchor tool formula scaffold frame of encorbelmenting draws anchor firmware - Google Patents

Harmless anchor tool formula scaffold frame of encorbelmenting draws anchor firmware Download PDF

Info

Publication number
CN218149647U
CN218149647U CN202220574691.6U CN202220574691U CN218149647U CN 218149647 U CN218149647 U CN 218149647U CN 202220574691 U CN202220574691 U CN 202220574691U CN 218149647 U CN218149647 U CN 218149647U
Authority
CN
China
Prior art keywords
steel
anchor
pull rod
wall
rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220574691.6U
Other languages
Chinese (zh)
Inventor
孙永刚
曹震毅
滕仰波
盛健
徐咏春
屈杰
黄华
徐国华
朱锋
陈皓
吴霄雷
马丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shipbuilding NDRI Engineering Co Ltd
Original Assignee
China Shipbuilding NDRI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shipbuilding NDRI Engineering Co Ltd filed Critical China Shipbuilding NDRI Engineering Co Ltd
Priority to CN202220574691.6U priority Critical patent/CN218149647U/en
Application granted granted Critical
Publication of CN218149647U publication Critical patent/CN218149647U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

本实用新型属于建筑领域,具体公开了一种无损拉锚工具式悬挑脚手架拉锚固件,包括预埋在墙或梁上部和下部的预埋套管,预埋套管内通过穿墙或梁的高强螺杆安装有与墙或梁贴合的钢压板,且钢压板通过高强螺帽固定在高强螺杆上;上部的钢压板底部焊接固定有上拉杆,下部的钢压板上安装有与墙或梁垂直的工字钢悬挑梁,工字钢悬挑梁末端焊接有耳板,耳板上通过螺栓安装有倾斜设置的下拉杆,且上拉杆和下拉杆端部通过花篮式拉杆连接;所述工字钢悬挑梁上放置有工字钢滑套,工字钢滑套上插入脚手架立杆,脚手架立杆之间连接有脚手架横杆。本实用新型施工方便、施工成本较低,稳定性好,且能够减少外墙渗水,装置整体拆装方便,可循环周转使用。

Figure 202220574691

The utility model belongs to the field of construction, and specifically discloses a non-destructive anchor pulling tool-type cantilevered scaffold pulling anchor, which includes pre-embedded sleeves embedded in the upper and lower parts of walls or beams, and the embedded sleeves pass through walls or beams. The high-strength screw rod is equipped with a steel pressure plate that is attached to the wall or beam, and the steel pressure plate is fixed on the high-strength screw rod through a high-strength nut; the bottom of the upper steel pressure plate is welded and fixed with a pull-up rod, and the lower steel pressure plate is installed. The I-shaped steel cantilever beam, the end of the I-shaped steel cantilever beam is welded with an ear plate, the ear plate is installed with an obliquely arranged lower rod through a bolt, and the ends of the upper rod and the lower rod are connected by a flower basket type rod; I-shaped steel sliding sleeves are placed on the beams of the steel cantilever, scaffolding poles are inserted into the I-steel sliding sleeves, and scaffolding cross bars are connected between the scaffolding poles. The utility model has the advantages of convenient construction, low construction cost, good stability, and can reduce water seepage of the outer wall.

Figure 202220574691

Description

一种无损拉锚工具式悬挑脚手架拉锚固件A non-destructive pulling anchor tool-type cantilevered scaffold pulling anchor

技术领域technical field

本实用新型涉及建筑领域,具体为一种无损拉锚工具式悬挑脚手架拉锚固件。The utility model relates to the construction field, in particular to a non-destructive anchor pulling tool type cantilever scaffold pulling anchor.

背景技术Background technique

目前,随着高层与超高层建筑的发展,悬挑脚手架的应用越来越普及。传统建筑施工过程中所使用的型钢悬挑脚手架拉锚固件,基本上都是通过穿越楼板及墙体中进行的预埋,这种简易的预埋方法,其缺点是周转材料投入量大,浪费大量材料,不能周转使用,施工成本高,穿墙后形成的孔洞不易封堵密实,有渗水的隐患;且安装固定、预埋精度控制难度大,占用室内空间,阻挡通行,存在安全隐患;拆除困难,必要时还需进行切割,影响后续工序的施工。At present, with the development of high-rise and super high-rise buildings, the application of cantilevered scaffolding is becoming more and more popular. The steel cantilevered scaffold anchors used in the traditional building construction process are basically pre-embedded through the floor and wall. This simple pre-embedded method has the disadvantage of a large amount of turnover materials and waste A large amount of materials cannot be recycled, and the construction cost is high. The holes formed after passing through the wall are not easy to be sealed and dense, and there is a hidden danger of water seepage; and it is difficult to control the accuracy of the installation and pre-embedding, occupying indoor space, blocking traffic, and posing safety hazards; demolition Difficult, if necessary, it needs to be cut, which will affect the construction of the subsequent process.

实用新型内容Utility model content

本实用新型的目的在于提供一种无损拉锚工具式悬挑脚手架拉锚固件,以解决上述背景技术中提出的问题。The purpose of the utility model is to provide a non-destructive pulling anchor tool-type cantilevered scaffold pulling anchor to solve the problems raised in the above-mentioned background technology.

为实现上述目的,本实用新型提供如下技术方案:一种无损拉锚工具式悬挑脚手架拉锚固件,包括预埋在墙或梁上部和下部的预埋套管,预埋套管内通过穿墙或梁的高强螺杆安装有与墙或梁贴合的钢压板,且钢压板通过高强螺帽固定在高强螺杆上;上部的钢压板底部焊接固定有倾斜设置的上拉杆,下部的钢压板上安装有与墙或梁垂直的工字钢悬挑梁,工字钢悬挑梁末端焊接有耳板,耳板上通过螺栓安装有倾斜设置的下拉杆,且上拉杆和下拉杆端部通过花篮式拉杆连接;所述工字钢悬挑梁上放置有工字钢滑套,工字钢滑套上插入脚手架立杆,脚手架立杆之间连接有脚手架横杆。In order to achieve the above purpose, the utility model provides the following technical solutions: a non-destructive anchor pulling tool type cantilevered scaffold pull anchor, including the embedded sleeves embedded in the upper and lower parts of the wall or beam, and the embedded sleeves pass through the wall Or the high-strength screw of the beam is installed with a steel pressure plate that fits the wall or beam, and the steel pressure plate is fixed on the high-strength screw through a high-strength nut; the bottom of the upper steel pressure plate is welded and fixed with an inclined upper pull rod, and the lower steel pressure plate is installed There is an I-steel cantilever beam perpendicular to the wall or beam, the end of the I-steel cantilever beam is welded with an ear plate, the ear plate is installed with an obliquely set lower rod through a bolt, and the ends of the upper rod and the lower rod are passed through a flower basket Tie rod connection: I-steel sliding sleeves are placed on the I-steel cantilever beams, scaffolding poles are inserted into the I-steel sliding sleeves, and scaffolding cross bars are connected between the scaffolding poles.

优选的,在墙或梁下部预埋有双排预埋套管,共四个,所述工字钢悬挑梁靠近墙或梁的一端设置有四孔锚固钢板,四孔锚固钢板套设在四个预埋套管的高强螺杆上并通过高强螺帽与下部的钢压板贴合固定。Preferably, there are four rows of pre-embedded casings pre-embedded in the lower part of the wall or beam, and the end of the I-shaped steel cantilever beam near the wall or beam is provided with four-hole anchoring steel plates, and the four-hole anchoring steel plates are sleeved on the The high-strength screws of the four pre-embedded casings are attached and fixed to the lower steel pressure plate through the high-strength nuts.

优选的,所述工字钢悬挑梁为带有三角支托的18#工字钢。Preferably, the I-beam cantilever beam is 18# I-beam with triangular supports.

优选的,所述上拉杆和下拉杆相对端分别设置有与花篮式拉杆螺纹连接的螺纹段,且上拉杆和下拉杆的螺纹段的螺旋方向相反。Preferably, the opposite ends of the upper pull rod and the lower rod are respectively provided with threaded sections threadedly connected with the turnbuckle rod, and the helical directions of the threaded sections of the upper pull rod and the lower rod are opposite.

与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the utility model are:

本实用新型提供的一种无损拉锚工具式悬挑脚手架拉锚固件及其施工工艺,施工方便、施工成本较低,稳定性好,且能够减少外墙渗水,装置整体拆装方便,可循环周转使用。The utility model provides a non-destructive anchor pulling tool-type cantilevered scaffold pulling anchor and its construction technology, which is convenient in construction, low in construction cost, good in stability, and can reduce water seepage of the outer wall. The overall device is easy to disassemble and can be recycled. Turnaround use.

附图说明Description of drawings

图1为本实用新型的整体结构示意图。Figure 1 is a schematic diagram of the overall structure of the utility model.

图中:1、高强螺杆;2、预埋套管;3、钢压板;4、高强螺帽;5、上拉杆;6、花篮式拉杆;7、下拉杆;8、耳板;9、工字钢滑套;10、工字钢悬挑梁;11、四孔锚固钢板;12、脚手架横杆;13、脚手架立杆。In the figure: 1. High-strength screw; 2. Embedded casing; 3. Steel plate; 4. High-strength nut; 10. I-steel cantilever beam; 11. Four-hole anchor steel plate; 12. Scaffold cross bar; 13. Scaffold pole.

具体实施方式detailed description

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

在本实用新型的描述中,需要说明的是,术语“竖直”、“上”、“下”、“水平”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本实用新型和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。In the description of the present utility model, it should be noted that the orientation or positional relationship indicated by the terms "vertical", "upper", "lower" and "horizontal" are based on the orientation or positional relationship shown in the accompanying drawings, only It is for the convenience of describing the utility model and simplifying the description, but does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the utility model.

在本实用新型的描述中,还需要说明的是,除非另有明确的规定和限定,术语“设置”、“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本实用新型中的具体含义。In the description of the present utility model, it should also be noted that, unless otherwise specified and limited, the terms "setting", "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection , can also be detachably connected, or integrally connected; can be mechanically connected, can also be electrically connected; can be directly connected, can also be indirectly connected through an intermediary, and can be internal communication between two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present utility model according to specific situations.

请参阅图1,本实用新型提供一种技术方案:一种无损拉锚工具式悬挑脚手架拉锚固件,包括预埋在墙或梁上部和下部的预埋套管2,预埋套管2内通过穿墙或梁的高强螺杆1安装有与墙或梁贴合的钢压板3,且钢压板3通过高强螺帽4固定在高强螺杆1上;上部的钢压板3底部焊接固定有倾斜设置的上拉杆5,下部的钢压板3上安装有与墙或梁垂直的工字钢悬挑梁10,工字钢悬挑梁10末端焊接有耳板8,耳板8上通过螺栓安装有倾斜设置的下拉杆7,且上拉杆5和下拉杆7端部通过花篮式拉杆6连接;所述工字钢悬挑梁10上放置有工字钢滑套9,工字钢滑套9上插入脚手架立杆13,脚手架立杆13之间连接有脚手架横杆12。Please refer to Figure 1, the utility model provides a technical solution: a non-destructive anchor pulling tool type cantilevered scaffold pulling anchor, including the embedded casing 2 embedded in the upper and lower parts of the wall or beam, the embedded casing 2 The high-strength screw 1 passing through the wall or beam is installed with a steel pressure plate 3 that fits the wall or beam, and the steel pressure plate 3 is fixed on the high-strength screw 1 through a high-strength nut 4; the upper steel pressure plate 3 is welded and fixed at the bottom. The upper pull rod 5, the steel pressure plate 3 at the lower part is equipped with an I-steel cantilever beam 10 perpendicular to the wall or beam, the end of the I-steel cantilever beam 10 is welded with an ear plate 8, and the ear plate 8 is installed with a tilting beam through bolts. The lower rod 7 is provided, and the ends of the upper rod 5 and the lower rod 7 are connected by a flower basket type rod 6; the I-beam sliding sleeve 9 is placed on the I-beam cantilever beam 10, and the I-beam sliding sleeve 9 is inserted into the Scaffolding uprights 13, scaffolding crossbars 12 are connected between the scaffolding uprights 13.

进一步的,在墙或梁下部预埋有双排预埋套管2,共四个,所述工字钢悬挑梁10靠近墙或梁的一端设置有四孔锚固钢板11,四孔锚固钢板11套设在四个预埋套管2的高强螺杆1上并通过高强螺帽4与下部的钢压板3贴合固定。Further, there are four rows of pre-embedded casings 2 pre-embedded in the lower part of the wall or beam. The end of the I-shaped steel cantilever beam 10 near the wall or beam is provided with a four-hole anchoring steel plate 11, and the four-hole anchoring steel plate 11 is sleeved on the high-strength screw rods 1 of the four pre-embedded casings 2 and fixed by the high-strength nut 4 and the lower steel pressure plate 3.

进一步的,所述工字钢悬挑梁10为带有三角支托的18#工字钢。Further, the I-steel cantilever beam 10 is 18# I-steel with triangular supports.

进一步的,所述上拉杆5和下拉杆7相对端分别设置有与花篮式拉杆6螺纹连接的螺纹段,且上拉杆5和下拉杆7的螺纹段的螺旋方向相反。Further, the opposite ends of the upper tie rod 5 and the lower rod 7 are respectively provided with threaded sections threaded with the turnbuckle tie rod 6 , and the helical directions of the threaded sections of the upper tie rod 5 and the lower rod 7 are opposite.

所述无损拉锚工具式悬挑脚手架拉锚固件的施工工艺,包括如下具体步骤:The construction process of the non-destructive anchor pulling tool type cantilevered scaffold pulling anchors includes the following specific steps:

S1、根据确定的施工方案,首先在梁或墙的上部预埋单个预埋套管2,在其下部预埋双排预埋套管2,钢筋模板验收合格,混凝土浇筑完成且待混凝土达到施工要求强度后(一般可取75%的强度),拆除模板;S1. According to the determined construction plan, first pre-embed a single pre-embedded casing 2 on the upper part of the beam or wall, and pre-embed double rows of pre-embedded casings 2 on the lower part. The steel formwork is accepted, and the concrete pouring is completed and the concrete is ready for construction. After the strength is required (generally 75% strength is desirable), the formwork is removed;

S2、拆除模板后,将四孔锚固钢板11与工字钢悬挑梁10焊接组成结合体,并装配在双排预埋套管2上,根据施工方案在工字钢悬挑梁10上放置工字钢滑套9,将脚手架立杆13插在工字钢滑套9上,并在脚手架立杆13之间安设脚手架横杆12;S2. After removing the formwork, weld the four-hole anchor steel plate 11 and the I-steel cantilever beam 10 to form a combination, and assemble it on the double-row embedded casing 2, and place it on the I-steel cantilever beam 10 according to the construction plan I-shaped steel sliding sleeve 9, scaffold pole 13 is inserted on the I-shaped steel sliding sleeve 9, and scaffold cross bar 12 is installed between scaffold vertical pole 13;

S3、在梁或墙的上部,高强螺杆1通过单个预埋套管2穿墙或梁,钢压板3通过高强螺母4固定在高强螺杆1上,将上拉杆5焊接固定在钢压板3上;S3. On the upper part of the beam or wall, the high-strength screw rod 1 passes through the wall or beam through a single embedded casing 2, the steel pressure plate 3 is fixed on the high-strength screw rod 1 through the high-strength nut 4, and the upper pull rod 5 is welded and fixed on the steel pressure plate 3;

S4、在工字钢悬挑梁10末端焊接耳板8,并通过螺栓在耳板8上安装下拉杆7,利用花篮式拉杆6连接上拉杆5和下拉杆7的螺纹段,实现稳固的体系。S4. Weld the ear plate 8 at the end of the I-steel cantilever beam 10, and install the lower rod 7 on the ear plate 8 through bolts, and use the flower basket type rod 6 to connect the threaded sections of the upper rod 5 and the lower rod 7 to realize a stable system .

具体的:specific:

预埋双排预埋套管2在梁中,四孔锚固钢板11与工字钢悬挑梁10焊接在一起,通过高强螺栓4与钢压板3固定在墙或梁上;上层墙或梁与下层墙或梁相同位置预埋单个预埋套管2,上拉杆5和下拉杆7通过花篮式拉杆6连接,上拉杆5焊接固定在上部钢压板3上,并通过高强螺栓4固定在上部预埋套管2的高强螺杆1上,下拉杆7与工字钢悬挑梁10上的耳板8连接,完成稳固的结构体系。The pre-embedded double-row pre-embedded casing 2 is in the beam, the four-hole anchor steel plate 11 is welded with the I-steel cantilever beam 10, and is fixed on the wall or beam by high-strength bolts 4 and steel pressure plate 3; the upper wall or beam and A single pre-embedded casing 2 is pre-embedded in the same position of the lower wall or beam, the upper tie rod 5 and the lower rod 7 are connected by a basket-type tie rod 6, the upper tie rod 5 is welded and fixed on the upper steel pressure plate 3, and is fixed on the upper pre-built by high-strength bolts 4. The high-strength screw rod 1 embedded in the casing pipe 2 is connected with the lug plate 8 on the I-steel cantilever beam 10 to complete a stable structural system.

建筑底部低层采用普通的脚手架进行搭设,完成低层的结构主体的施工,一般为2-5层;低层2-5层混凝土浇筑前,根据确定的施工方案,确定工字钢悬挑梁10的位置,正确预埋双排预埋套管2在梁或墙上,待混凝土达到施工要求强度后,将工字钢悬挑梁10放置在预埋套管2内的高强螺杆1位置,用高强螺栓4将工字钢悬挑梁10固定,上层墙或梁的上拉杆5固定,下方采取下拉杆7与工字钢悬挑梁10上的耳板8螺栓连接,中间采用花篮式拉杆6连接,组成稳固的三角结构,采用工字钢滑套9固定在工字钢悬挑梁10上,钢管脚手架固定在工字钢滑套9上;拆除时,只需将各个位置的高强螺栓4以及下拉杆7与耳板8连接处的螺栓拧下即可,可循环周转使用。The lower floors at the bottom of the building are erected with ordinary scaffolding to complete the construction of the main structure of the lower floors, generally 2-5 floors; before the concrete pouring of the 2-5 floors of the lower floors, determine the position of the I-beam cantilever beam 10 according to the determined construction plan , correctly pre-embed the double-row pre-embedded casing 2 on the beam or wall. After the concrete reaches the required construction strength, place the I-steel cantilever beam 10 on the position of the high-strength screw 1 in the pre-embedded casing 2, and use the high-strength bolt 4 Fix the I-steel cantilever beam 10, fix the upper pull rod 5 of the upper wall or beam, connect the lower rod 7 with the bolts on the lug plate 8 on the I-steel cantilever beam 10, and use the flower basket type tie rod 6 in the middle to connect, A stable triangular structure is formed, and the I-steel sliding sleeve 9 is used to fix the I-steel cantilever beam 10, and the steel pipe scaffolding is fixed on the I-steel sliding sleeve 9; The bolt at the joint between the pull rod 7 and the ear plate 8 can be unscrewed and can be used in a cycle.

尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, those skilled in the art can understand that various changes and modifications can be made to these embodiments without departing from the principle and spirit of the present invention , replacements and modifications, the scope of the present utility model is defined by the appended claims and their equivalents.

Claims (4)

1. A lossless anchor pulling tool type overhanging scaffold pulling anchor part is characterized by comprising pre-buried sleeves (2) pre-buried at the upper part and the lower part of a wall or a beam, a steel pressing plate (3) attached to the wall or the beam is installed in the pre-buried sleeves (2) through high-strength screw rods (1) penetrating through the wall or the beam, and the steel pressing plate (3) is fixed on the high-strength screw rods (1) through high-strength screw caps (4); an upper pull rod (5) which is obliquely arranged is welded and fixed at the bottom of the upper steel pressing plate (3), an I-shaped steel cantilever beam (10) which is perpendicular to a wall or a beam is installed on the lower steel pressing plate (3), an ear plate (8) is welded at the tail end of the I-shaped steel cantilever beam (10), a lower pull rod (7) which is obliquely arranged is installed on the ear plate (8) through a bolt, and the end parts of the upper pull rod (5) and the lower pull rod (7) are connected through a basket-type pull rod (6); i-steel sliding sleeves (9) are placed on the I-steel cantilever beams (10), scaffold upright rods (13) are inserted into the I-steel sliding sleeves (9), and scaffold cross rods (12) are connected between the scaffold upright rods (13).
2. The non-destructive anchor pulling tool type overhanging scaffold pull anchor of claim 1, wherein: the wall or beam lower part is pre-embedded with two rows of pre-embedded sleeves (2), the total number of the four pre-embedded sleeves is four, one end of the I-shaped steel cantilever beam (10) close to the wall or beam is provided with a four-hole anchoring steel plate (11), and the four-hole anchoring steel plate (11) is sleeved on the high-strength screws (1) of the four pre-embedded sleeves (2) and is fixedly attached to the steel pressing plate (3) at the lower part through high-strength nuts (4).
3. The non-destructive anchor pulling tool type overhanging scaffold pull anchor of claim 1, wherein: the I-steel cantilever beam (10) is 18# I-steel with a triangular bracket.
4. The non-destructive anchor pulling tool type overhanging scaffold pull anchor of claim 1, wherein: opposite ends of the upper pull rod (5) and the lower pull rod (7) are respectively provided with a threaded section in threaded connection with the flower basket type pull rod (6), and the thread direction of the threaded sections of the upper pull rod (5) and the lower pull rod (7) is opposite.
CN202220574691.6U 2022-03-16 2022-03-16 Harmless anchor tool formula scaffold frame of encorbelmenting draws anchor firmware Active CN218149647U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220574691.6U CN218149647U (en) 2022-03-16 2022-03-16 Harmless anchor tool formula scaffold frame of encorbelmenting draws anchor firmware

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220574691.6U CN218149647U (en) 2022-03-16 2022-03-16 Harmless anchor tool formula scaffold frame of encorbelmenting draws anchor firmware

Publications (1)

Publication Number Publication Date
CN218149647U true CN218149647U (en) 2022-12-27

Family

ID=84548844

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220574691.6U Active CN218149647U (en) 2022-03-16 2022-03-16 Harmless anchor tool formula scaffold frame of encorbelmenting draws anchor firmware

Country Status (1)

Country Link
CN (1) CN218149647U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN120350803A (en) * 2025-06-13 2025-07-22 中国二十二冶集团有限公司 Anchoring type overhanging scaffold

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN120350803A (en) * 2025-06-13 2025-07-22 中国二十二冶集团有限公司 Anchoring type overhanging scaffold

Similar Documents

Publication Publication Date Title
CN110878522B (en) Construction system and construction method of beam under main tower
CN216239741U (en) Formwork system of high-rise cantilevered concrete structures
CN108999394B (en) Construction process of floor type scaffold rotary cantilever type scaffold
CN115680116A (en) Assembled frame beam column connecting node and construction method thereof
CN114182883A (en) Large-section square tube concrete column and construction method
CN113756554A (en) Construction platform and construction method for cast-in-place reinforced concrete support cantilever scaffold
CN217782879U (en) Adjustable clip supports formula beam type template strutting arrangement
CN114704063A (en) Anchoring-free anchoring-tool type overhanging scaffold anchoring part and construction process thereof
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN216109030U (en) Precast concrete ground beam-shear force wall connected node
CN207700746U (en) The upper buttress of existing building base isolation reinforcement constructs
CN203640257U (en) Support of overhanging type scaffold
CN211572514U (en) Scalable regulation outer wall scaffold frame
CN202544138U (en) Opening connecting node of concrete-filled steel tubular frame column and reinforced concrete frame beam
CN213806581U (en) Super high-rise high-altitude large-span cantilever concrete structure formwork support system
CN111764424B (en) Anti-corrosion industrial factory building concrete cup mouth type prefabricated bearing platform
CN221481494U (en) A suspended exterior wall formwork system
CN219909312U (en) Assembled RC prefabricated column-RC roof beam connected node
CN110952767A (en) Assembled bolt connection scaffold wall connecting piece and mounting method
CN213391138U (en) Assembled beam side scaffold construction device that encorbelments
CN110805256A (en) Construction process of flower basket pull rod tool type overhanging scaffold
CN113638506A (en) Precast concrete ground beam-frame column connecting joint and construction method thereof
CN219622238U (en) Anti-interference structure of steel pull rod of flower basket frame
CN223922599U (en) An unconventional cantilever scaffold
CN224078701U (en) Reinforcing system of adjustable single-side formwork

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant