CN218148971U - Waterproof construction of bamboo weaving mud wall - Google Patents

Waterproof construction of bamboo weaving mud wall Download PDF

Info

Publication number
CN218148971U
CN218148971U CN202222520318.5U CN202222520318U CN218148971U CN 218148971 U CN218148971 U CN 218148971U CN 202222520318 U CN202222520318 U CN 202222520318U CN 218148971 U CN218148971 U CN 218148971U
Authority
CN
China
Prior art keywords
bamboo
woven
compiled
mud wall
waterproof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222520318.5U
Other languages
Chinese (zh)
Inventor
罗超
蔡俊辉
孙健
罗俊鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHEC Dong Meng Engineering Co Ltd
Original Assignee
CCCC SHEC Dong Meng Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Dong Meng Engineering Co Ltd filed Critical CCCC SHEC Dong Meng Engineering Co Ltd
Priority to CN202222520318.5U priority Critical patent/CN218148971U/en
Application granted granted Critical
Publication of CN218148971U publication Critical patent/CN218148971U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The utility model relates to a waterproof construction of mud wall is compiled to bamboo, including the base frame, fixed mounting has old wooden side column on the base frame, the quantity of old wooden side column is two, two be provided with the mud wall is compiled to bamboo between the old wooden side column, the mud wall is compiled bamboo by fixed mounting bamboo between two old wooden side columns and the bamboo is compiled the strip and is compiled fossil fragments and constitute, the fossil fragments are compiled to bamboo and is arranged in the inboard that the bamboo was compiled the strip. This waterproof construction of mud wall is compiled to bamboo, carry out the separation through setting up by the waterproof board and the concrete isolation layer under the sill, make the whole basement of mud wall is compiled to bamboo stable, and certain water-proof effects has, the overall stability of mud wall is compiled to bamboo has been reinforceed simultaneously, fill in the seam between the waterproof board through setting up the piece of filling up, make the waterproof board gap be difficult for the infiltration, through setting up the old wood side post, prefabricated plate and bamboo are compiled fossil fragments and run through each other, can improve the overall stability of mud wall is compiled to bamboo, thereby it makes level the condition that the back blocks water and receive the destruction to have reduced the lime of firewood, the overall waterproof nature of mud wall is compiled to bamboo has been improved.

Description

Waterproof construction of mud wall is compiled to bamboo
Technical Field
The application relates to the technical field of bamboo woven clay walls, in particular to a waterproof structure of a bamboo woven clay wall.
Background
The bamboo-woven mud wall is also called a woven wall, is mostly seen in southern bamboo-producing areas, appears in the Han dynasty at the latest, is a wall building method, is different from the traditional house wall in that rammed earth and bricks are used, is made of bamboo woven, is coated with a layer of grass rib mud and shell or lime-ground ash, and is finally coated with a layer of plant ash slurry and is leveled.
The bamboo woven mud wall made through the traditional mode does not have waterproofness, however, receives waterproof follow-up construction, causes the vibrations of bamboo woven keel easily for the mud wall structure is compiled to the bamboo easily not hard up, leads to screed-coat mortar to take place to destroy easily, thereby reduces waterproof performance, proposes a waterproof construction of bamboo woven mud wall to this, solves the above-mentioned problem of proposing.
SUMMERY OF THE UTILITY MODEL
To prior art's not enough, this application provides a waterproof construction of mud wall is compiled to bamboo, possesses advantages such as waterproof nature, stability are better.
In order to achieve the above purpose, the present application provides the following technical solutions: a waterproof structure of a bamboo-woven mud wall comprises a base platform, wherein two old wood side columns are fixedly mounted on the base platform, and the bamboo-woven mud wall is arranged between the two old wood side columns;
the bamboo-woven mud wall is composed of bamboo-woven strips and bamboo-woven keels, wherein the bamboo-woven strips and the bamboo-woven keels are fixedly installed between two old wood side columns, the bamboo-woven keels are arranged on the inner sides of the bamboo-woven strips, prefabricated plates are fixedly installed between the top ends of the two old wood side columns, and the prefabricated plates are penetrated through by the bamboo-woven keels.
Further, the base platform is in an I-shaped arrangement, and the two old wood side columns are fixedly installed at the tops of the two ends of the base platform respectively.
Furthermore, a waterproof belt is fixedly installed at the top of the base platform.
Furthermore, a positioning piece is fixedly installed at one end of the prefabricated plate, which penetrates through and extends to the bamboo-woven keel, and the cross section of the positioning piece is in an inverted C shape.
Further, the bottom of the base platform is continuously and fixedly provided with a concrete isolation layer and waterproof boards, the number of the waterproof boards is a plurality of waterproof boards, and a gap filling piece is fixedly arranged between the waterproof boards.
Furthermore, two ends of the joint filling piece extend towards the outer side to form an acute angle and are attached to the waterproof board.
Compared with the prior art, the technical scheme of the application has the following beneficial effects:
this waterproof construction of mud wall is compiled to bamboo, carry out the separation through setting up by the waterproof board and the concrete isolation layer under the sill, make the whole basement of mud wall is compiled to bamboo stable, and certain water-proof effects has, the overall stability of mud wall is compiled to bamboo has been reinforceed simultaneously, fill in the seam between the waterproof board through setting up the piece of filling up, make the waterproof board gap be difficult for the infiltration, through setting up the old wood side post, prefabricated plate and bamboo are compiled fossil fragments and run through each other, can improve the overall stability of mud wall is compiled to bamboo, thereby it makes level the condition that the back blocks water and receive the destruction to have reduced the lime of firewood, the overall waterproof nature of mud wall is compiled to bamboo has been improved.
Drawings
FIG. 1 is a front view of the present application;
FIG. 2 is a top view of the present application;
fig. 3 is an enlarged view of fig. 1 a.
In the figure: 1. a base table; 2. old wooden side columns; 3. a waterproof tape; 4. weaving bamboo keel; 5. prefabricating a slab; 6. a positioning member; 7. bamboo strips; 8. a concrete insulating layer; 9. a waterproof sheet; 10. and (4) filling the gap.
Detailed Description
The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only a part of the embodiments of the present application, and not all of the embodiments. All other embodiments obtained by a person of ordinary skill in the art based on the embodiments in the present application without making any creative effort belong to the protection scope of the present application.
Referring to fig. 1-3, the waterproof structure of bamboo-woven mud wall in the embodiment includes a base 1, two old wood side columns 2 are fixedly mounted on the base 1, and a bamboo-woven mud wall is disposed between the two old wood side columns 2.
The sill wall is additionally arranged outside the base, and the periphery of the bamboo woven mud wall and the joint of the old wood side column 2 are fixedly provided with the pillar protecting frames, so that the sill wall can be effectively connected with the bamboo woven mud wall.
It should be noted that the base platform 1 is in an i-shaped configuration and simultaneously adopts a 120mm grey brick sill wall, and the two old wood side columns 2 are respectively and fixedly installed at the tops of the two ends of the base platform 1, so that the bamboo-woven muddy wall bottom support can be provided through the base platform 1, and the stable installation of the bamboo-woven muddy wall is ensured.
In the embodiment, the bamboo-woven mud wall is composed of bamboo-woven strips 7 and bamboo-woven keels 4 which are fixedly installed between two old wood side columns 2, the bamboo-woven keels 4 are arranged on the inner sides of the bamboo-woven strips 7, the bamboo-woven keels 4 are 50mm × 5mm in size, the bamboo-woven strips 7 are woven in a staggered mode in a size of 30mm × 5mm, the outer portions of the bamboo-woven strips 7 are leveled by using wood cement, paper ribs are plastered, and the thickness of the bamboo-woven mud wall manufactured through the bamboo-woven keels 4 and the bamboo-woven keels 7 is 40mm.
It should be noted that, in order to improve the overall earthquake-resistant and waterproof performance of the bamboo woven clay wall, the waterproof belt 3 is fixedly installed at the top of the base platform 1, and the waterproof belt 3 is connected and sealed with the bamboo woven clay wall through the firewood clay.
In order to improve the stability of the bamboo-woven mud wall, a precast slab 5 is fixedly installed between the top ends of the two old wooden side columns 2 in the embodiment, the precast slab 5 is penetrated through by the bamboo-woven keel 4, one end of the bamboo-woven keel 4 can be supported through the precast slab 5, the installation stability of the bamboo-woven keel 4 is ensured, meanwhile, a positioning piece 6 is fixedly installed on one end, extending through the bamboo-woven keel 4 to the precast slab 5, of the precast slab 5, the cross section of the positioning piece 6 is in an inverted C shape, the movement of the bamboo-woven keel 4 can be limited through the relative penetrating connection between the positioning piece 6 and the precast slab 5, and the overall stability of the bamboo-woven mud wall is ensured.
In this embodiment, the bottom of the base platform 1 is continuously and fixedly provided with the concrete isolation layer 8 and the waterproof boards 9, the number of the waterproof boards 9 is a plurality of, the caulking pieces 10 are fixedly arranged between the waterproof boards 9, and the two ends of the caulking pieces 10 extend towards the outer side to form acute angles to be attached to the waterproof boards 9, so that the connecting seams between the waterproof boards 9 are not easy to leak water.
It should be noted that the concrete isolation layer 8 is a polyurethane waterproof coating coated on the poured concrete, and is used for completing the isolation of water, so as to improve the waterproof property of the bottom side of the bamboo-woven mud wall.
The working principle of the above embodiment is as follows:
the construction method comprises the steps of building a bottom platform 1 in advance, installing a waterproof board 9 through a seam filling piece 10, pouring a concrete isolation layer 8 between the waterproof board 9 and the bottom platform 1 to complete installation of a bottom base, enabling the base to have a certain waterproof effect, installing an old wood side column 2, fixing a prefabricated board 5, completing connection by penetrating a bamboo-woven keel 4 through the prefabricated board 5, finishing structural installation of the bamboo-woven mud wall by weaving bamboo strips 7 in staggered joints, leveling by using wood cement, finishing construction by plastering paper reinforcement, and enabling the bamboo-woven mud wall to have good stability through support of the prefabricated board 5 and the bamboo-woven keel 4, and meanwhile, the waterproof effect is good.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising a … …" does not exclude the presence of another identical element in a process, method, article, or apparatus that comprises the element.
Although embodiments of the present application have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the application, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a waterproof construction of mud wall is compiled to bamboo, includes base frame (1), its characterized in that: old wood side columns (2) are fixedly installed on the base platform (1), the number of the old wood side columns (2) is two, and a bamboo-woven mud wall is arranged between the two old wood side columns (2);
the bamboo-woven mud wall is composed of bamboo-woven strips (7) and bamboo-woven keels (4) which are fixedly installed between two old wood side columns (2), the bamboo-woven keels (4) are arranged on the inner sides of the bamboo-woven strips (7), prefabricated plates (5) are fixedly installed between the top ends of the two old wood side columns (2), and the prefabricated plates (5) are penetrated through by the bamboo-woven keels (4).
2. The waterproof structure of a bamboo-woven mud wall of claim 1, wherein: the base table (1) is in an I-shaped arrangement, and the two old wood side columns (2) are fixedly arranged at the tops of two ends of the base table (1) respectively.
3. The waterproof structure of a bamboo-woven mud wall as claimed in claim 2, wherein: the top of the bottom platform (1) is fixedly provided with a waterproof belt (3).
4. The waterproof structure of bamboo-woven mud wall as claimed in claim 3, wherein: the bamboo-woven keel (4) penetrates through and extends to one end of the prefabricated plate (5) and is fixedly provided with a positioning piece (6), and the section of the positioning piece (6) is of an inverted C shape.
5. The waterproof structure of bamboo-woven mud wall as claimed in claim 4, wherein: the bottom of base frame (1) is fixed mounting in succession has concrete isolation layer (8) and waterproof board (9), and the quantity of waterproof board (9) is a plurality of, a plurality of fixed mounting has caulking piece (10) between waterproof board (9).
6. The waterproof structure of bamboo-woven mud wall as claimed in claim 5, wherein: two ends of the joint filling piece (10) extend outwards to form an acute angle to be attached to the waterproof board (9).
CN202222520318.5U 2022-09-23 2022-09-23 Waterproof construction of bamboo weaving mud wall Active CN218148971U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222520318.5U CN218148971U (en) 2022-09-23 2022-09-23 Waterproof construction of bamboo weaving mud wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222520318.5U CN218148971U (en) 2022-09-23 2022-09-23 Waterproof construction of bamboo weaving mud wall

Publications (1)

Publication Number Publication Date
CN218148971U true CN218148971U (en) 2022-12-27

Family

ID=84563135

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222520318.5U Active CN218148971U (en) 2022-09-23 2022-09-23 Waterproof construction of bamboo weaving mud wall

Country Status (1)

Country Link
CN (1) CN218148971U (en)

Similar Documents

Publication Publication Date Title
CN101798846B (en) Modularization assembled house
CN105951998A (en) Integrated assembly type residential system and construction method thereof
CN213572429U (en) Waterproof connection structure of prefabricated outer wall
CN211286074U (en) Self-heat-insulation system for prefabricated light high-strength foam concrete filled wallboard outer wall
CN109797875A (en) A kind of low energy consumption energy saving building system
CN218148971U (en) Waterproof construction of bamboo weaving mud wall
CN211523508U (en) Be used for house heat preservation intergral template external wall insulation node
CN109339355B (en) Construction method of aluminum plate roof waterproof joint adopting ALC (autoclaved lightweight concrete) plate as structural plate
CN107035027A (en) A kind of assembled steel reinforced concrete structure light wt compound external wall panel
CN212896995U (en) Assembled faces bathroom light partition wall waterproof node
CN211080616U (en) Roofing expansion joint structure under prefabricated apron
CN209412856U (en) A kind of assembled integral basement structure meeting stability against floating requirement
CN109137972A (en) A kind of assembled integral basement structure and its safely and fast construction method
CN214005755U (en) Underground chamber window well waterproof construction
CN209854950U (en) Assembled building side fascia and ground beam gap waterproof construction
CN211421462U (en) Bathroom wall waterproof construction
CN209942072U (en) Retaining roof height movement joint waterproof construction
JPS59430A (en) Underground structure and its construction
CN207760880U (en) A kind of outer wall of basement settlement joint water-proof structure
CN111254937A (en) Installation method of fabricated building
CN209990036U (en) Equal-height deformation joint waterproof structure for water storage roof
CN209990034U (en) Light-duty equipment base node structure
CN218374060U (en) Anti node structure that floats of subway station
CN218437563U (en) Waterproof structure between assembled building outer wall body plates
CN210315683U (en) Basement bottom plate stagnant water structure

Legal Events