CN218147846U - Movable operation platform for removing internal template of hollow pier - Google Patents

Movable operation platform for removing internal template of hollow pier Download PDF

Info

Publication number
CN218147846U
CN218147846U CN202222480056.4U CN202222480056U CN218147846U CN 218147846 U CN218147846 U CN 218147846U CN 202222480056 U CN202222480056 U CN 202222480056U CN 218147846 U CN218147846 U CN 218147846U
Authority
CN
China
Prior art keywords
sling
platform
demolishing
mobile work
hollow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222480056.4U
Other languages
Chinese (zh)
Inventor
丁建声
王瑞
阮梦飞
张迎春
迟文科
李文涛
余鸿耀
黄炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
2nd Engineering Co Ltd of MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
2nd Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC, 2nd Engineering Co Ltd of MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN202222480056.4U priority Critical patent/CN218147846U/en
Application granted granted Critical
Publication of CN218147846U publication Critical patent/CN218147846U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The application relates to a movable operation platform for removing a template in a hollow pier, which comprises a bearing platform and a sling, wherein one end of the sling is connected to a connecting part, the other end of the sling is detachably connected to the template, and a plurality of connecting parts are respectively arranged at two ends of the bearing platform; the sling is also provided with an adjusting mechanism for adjusting the distance between the two ends of the sling. The application provides safe and reliable operation space for constructors, reduces construction risks and has great popularization value. When the movable operation platform is used, the movable operation platform is not in contact with poured concrete and has no damage to a pier body. The movable operation platform is suitable for construction of various hollow piers and has wide application range.

Description

Movable operation platform for removing internal template of hollow pier
Technical Field
The application relates to the technical field of bridge construction, in particular to a movable operation platform for removing an internal template of a hollow pier.
Background
With the gradual maturity of the bridge construction process and the gradual increase of the scale of the bridge, the high and large hollow piers are used more and more, and the rollover method is widely used for the construction of the high and large hollow piers as a mature construction process. When the pier body formwork construction is carried out by adopting a formwork overturning method, the outer formwork has large space and can be provided with an operation platform integrated with the formwork, the inner formwork is limited by the space, the operation platform is difficult to install, no operation platform is provided when the formwork is dismantled, and the construction is difficult. The general method is that an operator fastens a safety belt and climbs on an adjacent template for dismantling, and the method has high safety risk, difficult operation and low construction efficiency.
Disclosure of Invention
The embodiment of the application provides a movable operation platform for demolising hollow pier internal formwork to solve among the correlation technique operation workman and tie the safety belt climbing and demolish on adjacent template, there is the safety risk height, the problem of operational difficulties.
The embodiment of the application provides a movable operation platform for demolising hollow mound internal template, and it includes:
the bearing platform is provided with a plurality of connecting parts at two ends respectively;
and one end of the sling is connected to the connecting part, the other end of the sling is detachably connected to the template, and the sling is further provided with an adjusting mechanism for adjusting the distance between the two ends of the sling.
In some embodiments, the adjustment mechanism is a chain block;
the sling includes two cable sections, chain block is located two between the cable section, and two the one end of cable section is connected respectively connecting portion and template, two the other end of cable section is connected respectively on two couples of chain block.
In some embodiments, two slings are attached to the connecting portion.
In some embodiments, the connecting portion is a lifting lug, or a through hole is separately formed on an edge portion of the bearing platform, so that the edge portion forms the connecting portion.
In some embodiments, two connecting portions are respectively disposed at two ends of the bearing platform.
In some embodiments, the sling is connected to a seam between two adjacent formworks.
In some embodiments, skirting boards are arranged around the bearing platform.
In some embodiments, the skirting board has a height of 20cm to 50cm.
In some embodiments, the bearing platform comprises a transverse section steel, a longitudinal section steel and a backing plate, the transverse section steel and the longitudinal section steel are welded to form a frame body, and the backing plate is laid on the frame body.
In some embodiments, the backing plate is made of wood or steel wire.
The technical scheme who provides this application brings beneficial effect includes:
the application provides safe and reliable operation space for constructors, reduces construction risks and has great popularization value.
When the movable operation platform is used, the movable operation platform is not in contact with poured concrete and has no damage to a pier body.
The movable operation platform is suitable for construction of various hollow piers and has wide application range.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings needed to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present application, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without creative efforts.
Fig. 1 is a plan view of a movable work platform in a pier body according to an embodiment of the present invention;
fig. 2 is a schematic working diagram of the movable working platform in the pier body according to the embodiment of the present application.
In the figure: 1. a load-bearing platform; 10. a connecting portion; 11. transverse section steel; 12. longitudinal section steel; 13. a backing plate; 2. a template; 3. a sling; 30. a cable segment; 4. an adjustment mechanism; 5. skirting boards; 6. a pier body.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are some embodiments of the present application, but not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
Referring to fig. 1 and fig. 2, the embodiment of the present application provides a movable work platform for removing a formwork inside a hollow pier, the movable work platform includes a bearing platform 1, a sling 3 and an adjusting mechanism 4, the bearing platform 1 slightly smaller than the inside size of the pier body 6 is made of a shaped steel material according to the inside size of the pier body 6, and two ends of the bearing platform 1 are respectively provided with a plurality of connecting portions 10; one end of the sling 3 is connected to the connecting part 10, the other end of the sling is detachably connected to the formwork 2, and the sling 3 is further provided with an adjusting mechanism 4 for adjusting the distance between the two ends of the sling 3.
This application is connected the both ends of hoist cable 3 respectively on connecting portion 10 and pier shaft 6 in the template 2 of the superiors, through adjustment mechanism 4, adjust the interval between the both ends point of hoist cable 3, so that load-bearing platform 1 is located the below of the template 2 of lower floor, collide with load-bearing platform 1 when avoiding hanging out template 2, constructor stands on load-bearing platform 1, demolish and hang away the template 2 of lower floor, reuse adjustment mechanism 4 and promote load-bearing platform 1, reach upper template 2 departments, continue tearing open, therefore, can accomplish the interior template 2 of pier shaft 6 and demolish work.
Therefore, the method and the device provide safe and reliable operation space for constructors, reduce construction risks and have high popularization value.
When the movable operation platform is used, the movable operation platform is not in contact with poured concrete and has no damage to a pier body.
The movable operation platform is suitable for construction of various hollow piers and has wide application range.
In order to achieve adjustment of the distance between the two ends of the sling 3, in some preferred embodiments, detailed means are provided, see fig. 2, wherein the adjusting mechanism 4 is a chain block; the sling 3 comprises two cable sections 30, the chain block is positioned between the two cable sections 30, one end of each cable section 30 is connected with the connecting part 10 and the template 2, and the other end of each cable section 30 is connected with two hooks of the chain block. The operating personnel can realize the promotion and the transfer of load-bearing platform 1 through chain block, and after load-bearing platform 1 reachd preset position, chain block can also lock temporarily to guarantee that load-bearing platform 1 can not reciprocate.
Because the pouring of the hollow pier is usually one-section-by-one-section pouring, that is, after the pouring of the next section is completed, the formwork is removed, and then the pouring of the previous section is performed, when only one sling 3 is connected to the connecting part 10, after the formwork is removed from the lower section of the poured pier body 6 (the uppermost formwork 2 is not removed), when the upper section of the pier body 6 is poured and needs to be removed, the slings 3 need to be removed one by one from the uppermost formwork 2 of the lower section of the pier body 6, and then the upper section of the pier body is connected to the uppermost formwork 2 of the upper section of the pier body 6, so that the method is not very dangerous.
Therefore, in order to improve the safety factor and the stripping efficiency, the connecting part 10 is connected with two slings 3.
When the next pier body 6 is demolished, one of the two slings 3 is connected to the uppermost formwork 2 in the next pier body 6, after other formworks 2 except the uppermost formwork 2 are demolished, the inner formwork demolishing work of the pier body 6 is completed, the construction of the pier body 6 is performed, after the construction is completed, the other sling 3 is connected to the uppermost formwork 2 of the pier body 6, the original connection between the sling 3 and the uppermost formwork 2 of the next pier body 6 is released, the formwork is continuously demolished, and the pier body 6 is demolished piece by piece and layer by layer.
For the connection of the suspension cable 3, the connecting portion 10 may have various forms, such as, for example, a lifting lug, and as another example, a through hole may be formed in the edge portion of the carrying platform 1, so that the edge portion forms the connecting portion 10, and the suspension cable 3 may pass through the through hole and be tied to the carrying platform 1.
Referring to fig. 1, in order to make the load-bearing platform 1 more stable, two connecting portions 10 are respectively disposed at two ends of the load-bearing platform 1, and preferably, four connecting portions 10 are respectively located at four corners of the platform 1.
In order to facilitate the lifting out of the formworks from the slings after the formworks are removed, the slings 3 are connected to the abutted seams between the two adjacent formworks 2.
In order to prevent the tool from sliding off, referring to fig. 2, skirting boards 5 are arranged around the carrying platform 1. The height of the skirting board 5 is determined according to actual needs, and can be selected to be 20 cm-50 cm, for example.
Referring to fig. 1, the bearing platform 1 includes a transverse section steel 11, a longitudinal section steel 12, and a backing plate 13, the transverse section steel 11 and the longitudinal section steel 12 are welded to form a frame body, the backing plate 13 is laid on the frame body, and the backing plate 13 is made of a wood board or a steel wire mesh. Bearing platform 1 is formed by shaped steel welding, and simple structure can repeatedly be used, practices thrift the cost.
In the description of the present application, it should be noted that the terms "upper", "lower", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, which are only for convenience in describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and operate, and thus, should not be construed as limiting the present application. Unless expressly stated or limited otherwise, the terms "mounted," "connected," and "connected" are intended to be inclusive and mean, for example, that they may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present application can be understood by those of ordinary skill in the art as the case may be.
It is noted that, in this application, relational terms such as "first" and "second," and the like, are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising a … …" does not exclude the presence of another identical element in a process, method, article, or apparatus that comprises the element.
The above description is merely exemplary of the present application and is presented to enable those skilled in the art to understand and practice the present application. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the application. Thus, the present application is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (10)

1. The utility model provides a movable operation platform for demolising hollow pier inside template which characterized in that, it includes:
the bearing platform (1), wherein two ends of the bearing platform (1) are respectively provided with a plurality of connecting parts (10);
and one end of the sling is connected to the connecting part (10), the other end of the sling is detachably connected to the sling (3) on the template (2), and the sling (3) is further provided with an adjusting mechanism (4) for adjusting the distance between the two ends of the sling (3).
2. A mobile work platform for demolishing internal formwork of hollow piers as claimed in claim 1, wherein:
the adjusting mechanism (4) adopts a chain block;
hoist cable (3) are including two cable segments (30), chain block is located two between cable segment (30), and two the one end of cable segment (30) is connected respectively connecting portion (10) and template (2), two the other end of cable segment (30) is connected respectively on two couples of chain block.
3. A mobile work platform for demolishing internal formwork of hollow piers as claimed in claim 1, wherein: the connecting part (10) is connected with two slings (3).
4. A mobile work platform for demolishing internal formwork of hollow piers as claimed in claim 1, wherein: the connecting part (10) adopts a lifting lug, or the edge part of the bearing platform (1) is separately provided with a through hole, so that the edge part forms the connecting part (10).
5. A mobile work platform for demolishing internal formwork of hollow piers as claimed in claim 1, wherein: two ends of the bearing platform (1) are respectively provided with two connecting parts (10).
6. A mobile work platform for demolishing internal formwork of hollow piers as claimed in claim 1, wherein: the sling (3) is connected to the abutted seam between the two adjacent formworks (2).
7. A mobile work platform for demolishing internal formwork of hollow piers as claimed in claim 1, wherein: skirting boards (5) are arranged around the bearing platform (1).
8. A mobile work platform for demolishing internal formwork of hollow piers as claimed in claim 7, wherein: the height of the skirting board (5) is 20-50 cm.
9. A mobile work platform for demolishing internal formwork of hollow piers as claimed in claim 1, wherein: bearing platform (1) is including horizontal shaped steel (11), vertical shaped steel (12) to and backing plate (13), horizontal shaped steel (11) and vertical shaped steel (12) weld into the support body, just backing plate (13) are laid on the support body.
10. A mobile work platform for demolishing internal formwork of hollow piers as claimed in claim 9, wherein: the backing plate (13) is made of a wood plate or a steel wire mesh.
CN202222480056.4U 2022-09-19 2022-09-19 Movable operation platform for removing internal template of hollow pier Active CN218147846U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222480056.4U CN218147846U (en) 2022-09-19 2022-09-19 Movable operation platform for removing internal template of hollow pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222480056.4U CN218147846U (en) 2022-09-19 2022-09-19 Movable operation platform for removing internal template of hollow pier

Publications (1)

Publication Number Publication Date
CN218147846U true CN218147846U (en) 2022-12-27

Family

ID=84563010

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222480056.4U Active CN218147846U (en) 2022-09-19 2022-09-19 Movable operation platform for removing internal template of hollow pier

Country Status (1)

Country Link
CN (1) CN218147846U (en)

Similar Documents

Publication Publication Date Title
CN101435276B (en) Hydraulic lifting and positioning device for steel beam at top of silo structure and construction method thereof
CN101824910B (en) Quick template supporting construction method of elevator shaft
CN114575589A (en) Construction method for lifting template of electric hoist of steel reinforced concrete structural column
CN113927729A (en) Automatic production system of prefabricated hollow pier
CN218147846U (en) Movable operation platform for removing internal template of hollow pier
JP3074765U (en) Pillar building construction system equipment
CN111809528A (en) Pier column vertical back cage platform channel construction method and back cage platform channel device
CN209193460U (en) A kind of movable lifting Large-size rebar cage weld job operating platform
CN204983692U (en) Concrete panel's hoist device
CN216516954U (en) Self-climbing concrete distributing device in super high-rise well way
CN206722431U (en) Discharging platform for high-rise building construction
CN204492133U (en) A kind of easy insulated column construction tool frame
CN209797236U (en) Box girder external mold hoisting device
CN112360136A (en) Formwork support frame body of concrete pouring wall body of elevator shaft and erection method thereof
JP3811846B2 (en) Steel tower dismantling method and apparatus
CN208857711U (en) A kind of high-altitude integral hoisting formula operating platform
CN209227391U (en) Self-propelled bridge-collision-avoidance wall form trolley
CN219059723U (en) Wet joint connection module
CN210744587U (en) Extra-high voltage converter transformer lifting seat maintenance platform
CN218090542U (en) Bridge breast board construction equipment
CN214423942U (en) Formwork support frame body of concrete pouring wall body of elevator shaft
CN216689038U (en) Wet seam construction auxiliary device
CN212404855U (en) A mounting structure that is used for construction platform that steel-pipe pile support set up
CN221116795U (en) Retaining wall steel form hoisting assembly
CN211548755U (en) Hydraulic climbing formwork for building construction