CN218147838U CN202222326007.5U CN202222326007U CN218147838U CN 218147838 U CN218147838 U CN 218147838U CN 202222326007 U CN202222326007 U CN 202222326007U CN 218147838 U CN218147838 U CN 218147838U
Authority
CN
China
Prior art keywords
platform
construction
rods
frame
rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222326007.5U
Other languages
Chinese (zh)
Inventor
黎磊
赵富立
吴正华
孙宗玮
刘全峰
谢南峰
何剑鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge South China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Road and Bridge South China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, Road and Bridge South China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202222326007.5U priority Critical patent/CN218147838U/en
Application granted granted Critical
Publication of CN218147838U publication Critical patent/CN218147838U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides an integration construction platform for construction of support base rubble, its technical scheme main points are that this an integration construction platform for construction of support base rubble includes platform frame and support frame, platform frame with support frame fixed connection, platform frame position in the top of support frame, the support frame can be dismantled with the bent cap and be connected. The utility model discloses an integration construction platform for construction of support base rubble, each part all adopts fixed connection's mode to link together, the structure of an integration has been formed, need not build on the bent cap, through the flatbed with integration construction platform transport to job site, utilize the crane to install, just can carry out normal rubble construction operation after the installation is accomplished, work efficiency is high, both reduce the cost input that traditional construction platform was repeatedly ann torn open, can guarantee the security of construction again, and can also guarantee the efficiency of construction.

Description

A integration construction platform for construction of support bed stone
Technical Field
The utility model relates to a bridge beam supports rubble construction technical field especially relates to an integration construction platform for construction of support rubble.
Background
In the past construction experience, the construction of the cushion stone is completed by utilizing the bent cap construction platform while the bent cap construction is basically carried out. In the transformation construction of some cushion stones, the construction of the capping beam is not needed, so that a construction platform is lacked, and the construction safety cannot be guaranteed. The conventional method is to build a construction platform on a bent cap, but the construction mode is lack of certain safety, the building is troublesome, and the working efficiency is not high.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an integration construction platform for construction of support base stone, whole structure as an organic whole need not build on the bent cap, transports integration construction platform to job site through the flatbed, utilizes the crane to install, just can carry out normal stone setting construction operation after the installation is accomplished.
In order to achieve the above object, the present invention provides the following technical solutions:
an integrated construction platform for construction of a support base rubble comprises a platform frame and a support frame, wherein the platform frame is fixedly connected with the support frame, the platform frame is positioned above the support frame, and the support frame can be detachably connected with a cover beam; the supporting frame comprises a plurality of supporting rods and a plurality of limiting rods, all the supporting rods can be arranged on the upper surface of the cover beam, two ends of all the supporting rods can extend along the width direction of the cover beam, all the supporting rods can be arranged at intervals along the length direction of the cover beam, two ends of each supporting rod are fixedly connected with the limiting rods, the upper end of each limiting rod is fixedly connected with the supporting rods, and the lower end of each limiting rod extends downwards; the platform frame comprises a plurality of first platform rods and a plurality of second platform rods, all the first platform rods are located above the supporting rods, all the first platform rods are fixedly connected with the supporting rods, all the two ends of each first platform rod can extend along the length direction of the cover beam, all the first platform rods can be arranged at intervals along the width direction of the cover beam, and each of the two ends of each first platform rod is fixedly connected with the second platform rods and each of the second platform rods is fixedly connected with all the first platform rods.
Through the scheme, all parts of the whole construction platform are connected together in a fixed connection mode, an integrated structure is formed, building on the bent cap is not needed, the integrated construction platform is transferred to a construction site through a flat car, a crane is used for installation, normal stone-padding construction operation can be carried out after installation is completed, the working efficiency is high, the cost input of repeated mounting and dismounting of the traditional construction platform is reduced, the construction safety can be guaranteed, and the construction efficiency can be guaranteed.
Furthermore, the support frame still includes a plurality of stiffeners, all the length direction of bent cap is extended, all along the both ends homoenergetic of stiffener the stiffener all sets up, each along vertical direction interval the stiffener all with gag lever post fixed connection, overall structure is more stable.
Further, the support frame still includes the bracing piece, the bracing piece is the slope setting, the one end of bracing piece with platform frame fixed connection, the other end of bracing piece with gag lever post fixed connection, the holding power is stronger, and stability is better.
Further, still include protective frame, protective frame establishes the top of platform frame, protective frame with platform frame fixed connection, the security is better.
Further, the protective frame includes a plurality of protective horizontal poles and a plurality of protective montant, all protective montant encircles the platform frame interval sets up, each protective montant's lower extreme all with platform frame fixed connection, each protective montant's upper end all upwards extends, all protective horizontal pole along vertical direction interval set up and with all protective montant fixed connection, each protective horizontal pole is cyclic annular and encircles the platform frame sets up, can enclose into the construction area that the workman stood, and the security is better.
Furthermore, the protection transverse rod and the protection vertical rod are both steel pipes, and the structure is stable.
Furthermore, the number of the first platform rods is four, the four first platform rods can be arranged at intervals in the width direction of the cover beam, and all the first platform rods are connected through the deformed steel bars, so that the connection is firmer.
Furthermore, the first platform rod and the second platform rod are connected through the deformed steel bars, so that the connection is firmer.
Furthermore, the first platform rod and the second platform rod are both angle steel, the supporting rod and the limiting rod are both I-shaped steel, and supporting force is better.
Further, the platform frame still includes the steel sheet net, the steel sheet net is located the top of first platform pole, the steel sheet net with first platform pole fixed connection can provide a more firm region of standing.
Compared with the prior art, the utility model discloses a scheme has following advantage:
all parts of whole construction platform all adopt fixed connection's mode to link together, have formed the structure of an integration, need not build on the bent cap, transport integration construction platform to the job site through the flatbed, utilize the crane to install, just can carry out normal bed stone construction operation after the installation is accomplished, work efficiency is high, has both reduced the cost input that traditional construction platform was repeatedly installed and removed, can guarantee the security of construction again, and can also guarantee the efficiency of construction.
Additional aspects and advantages of the invention will be set forth in part in the description which follows and, in part, will be obvious from the description, or may be learned by practice of the invention.
Drawings
The above and/or additional aspects and advantages of the present invention will become apparent and readily appreciated from the following description of the embodiments, taken in conjunction with the accompanying drawings of which:
fig. 1 is a schematic structural diagram of an integrated construction platform for support base stone construction according to an embodiment of the present invention;
FIG. 2 is a front view of an integrated construction platform for support base stone construction according to an embodiment of the present invention;
fig. 3 is a top view of an integrated construction platform for support base cushion stone construction in an embodiment of the present invention.
Reference numerals are as follows: 100. a support rod; 200. a limiting rod; 300. a first platform bar; 400. a second platform bar; 500. a reinforcing rod; 600. a support bar; 700. a protective cross bar; 800. a protective vertical rod; 900. a steel plate net; 1000. a support base cushion stone; 1100. and a capping beam.
Detailed Description
Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below by referring to the drawings are exemplary only for explaining the present invention, and should not be construed as limiting the present invention.
As shown in fig. 1 to 3, the utility model provides an integration construction platform for construction of support base stone, including platform frame and support frame, platform frame and support frame fixed connection, for example the welding, platform frame is located the top of support frame, and the support frame can be dismantled with bent cap 1100 and be connected, and more specifically, the support frame can be taken on bent cap 1100.
In this embodiment, the supporting frame includes a plurality of supporting rods 100 and a plurality of limiting rods 200, all supporting rods 100 can be disposed on the upper surface of the capping beam 1100, both ends of all supporting rods 100 can extend along the width direction of the capping beam 1100, that is, both ends of all supporting rods 100 extend along the front-rear direction, all supporting rods 100 can be disposed along the length direction of the capping beam 1100 at intervals, that is, both ends of all supporting rods 100 are disposed along the left-right direction at intervals, both ends of each supporting rod 100 are fixedly connected with the limiting rods 200, the upper end of each limiting rod 200 is fixedly connected with the supporting rods 100, for example, welding, the lower end of each limiting rod 200 extends downward, that is, both ends of each supporting rod 100 are connected with the limiting rods 200, the capping beam is disposed between the limiting rod 200 on the front side and the limiting rod 200 on the rear side, the distance between the front-rear limiting rods 200 is slightly greater than the width of the capping beam 1100, so that the whole supporting frame can be disposed on the capping beam 1100 and can prevent the whole platform from shaking, thereby achieving the front-rear-side limiting effect of a construction, and safety.
In this embodiment, the platform frame includes a plurality of first platform rods 300 and a plurality of second platform rods 400, all the first platform rods 300 are located above the support rods 100, all the first platform rods 300 are fixedly connected with the support rods 100, for example, welded, both ends of all the first platform rods 300 can extend along the length direction of the cover beam 1100, all the first platform rods 300 can be arranged at intervals along the width direction of the cover beam 1100, that is, both ends of all the first platform rods 300 extend along the left-right direction, both ends of each first platform rod 300 are fixedly connected with the second platform rods 400, each second platform rod 400 is fixedly connected with all the first platform rods 300, for example, welded, that is, both left and right ends of the first platform rods 300 are fixedly connected with the second platform rods 400, both ends of the second platform rods 400 extend along the front-back direction, it can be understood that both front and back ends of the cover beam 1100 are provided with the second platform rods 400, the second platform rods 400 also play a role in preventing the left-right sway of the whole platform, and the whole construction is also in high in safety, and a limit effect.
Through the scheme, each part of the whole construction platform is fixedly connected, for example, the parts are connected together in a welded mode, an integrated structure is formed, the cover beam 1100 is not required to be built, the integrated construction platform is transferred to a construction site through a flat car and is installed by a crane, normal stone-laying construction operation can be carried out after installation is completed, the working efficiency is high, the cost input of repeated installation and disassembly of the traditional construction platform is reduced, the construction safety can be guaranteed, and the construction efficiency can be guaranteed.
In this embodiment, the supporting frame further includes a plurality of stiffeners 500, the two ends of all stiffeners 500 can extend along the length direction of the bent cap 1100, all stiffeners 500 are arranged at intervals along the vertical direction, each stiffener 500 is fixedly connected with the limiting rod 200, for example, welding is performed, and the overall structure is more stable. More specifically, two reinforcing rods 500 are provided at the front side of the capping beam 1100, the two reinforcing rods 500 at the front side of the capping beam 1100 are vertically spaced apart, the two reinforcing rods 500 are provided at the rear side of the capping beam 1100, and the two reinforcing rods 500 at the rear side of the capping beam 1100 are vertically spaced apart.
In this embodiment, the support frame still includes bracing piece 600, and bracing piece 600 is the slope setting, the one end and the platform frame fixed connection of bracing piece 600, the other end and the gag lever post 200 fixed connection of bracing piece 600, and the holding power is stronger, and stability is better. More specifically, two support rods 600 are provided at the front side of the bent cap 1100, the two support rods 600 at the front side of the bent cap 1100 are respectively provided at the left and right sides of the platform frame, the two support rods 600 are provided at the rear side of the bent cap 1100, and the two support rods 600 at the rear side of the bent cap 1100 are respectively provided at the left and right sides of the platform frame.
In this embodiment, still include protective frame, protective frame establishes in the top of platform frame, protective frame and platform frame fixed connection, and the security is better. More specifically, the protective frame is of an annular structure, and the protective frame surrounds a standing area for construction of constructors.
In this embodiment, the protection frame includes a plurality of protection horizontal poles 700 and a plurality of protection montant 800, all protection montants 800 encircle the platform frame interval and set up, each protection montant 800's lower extreme all with platform frame fixed connection, each protection montant 800's upper end all upwards extends, all protection horizontal poles 700 set up and with all protection montant 800 fixed connection along vertical direction interval, each protection horizontal pole 700 is cyclic annular and encircles the platform frame setting, can enclose into the construction area that the workman stood, the security is better.
In this embodiment, the protection cross bar 700 and the protection vertical bar 800 are both steel pipes, and have stable structure.
In this embodiment, the number of the first platform bars 300 is four, the four first platform bars 300 can be arranged at intervals along the width direction of the bent cap 1100, and all the first platform bars 300 are connected through the thread steel, so that the connection is more stable.
In this embodiment, the first platform bar 300 and the second platform bar 400 are connected by the thread steel, so that the connection is more stable.
In this embodiment, the first platform bar 300 and the second platform bar 400 are both angle steels, and the supporting bar 100 and the limiting bar 200 are both i-shaped steels, so that the supporting force is better.
In this embodiment, the platform frame further comprises a steel plate mesh 900, the steel plate mesh 900 is located above the first platform bar 300, and the steel plate mesh 900 is fixedly connected with the first platform bar 300, for example, welded, so as to provide a more stable standing area.
The foregoing is only a part of the embodiments of the present invention, and it should be noted that, for those skilled in the art, a plurality of modifications and decorations can be made without departing from the principle of the present invention, and these modifications and decorations should also be regarded as the protection scope of the present invention.

Claims (10)

1. The integrated construction platform for the construction of the bearing pad stone is characterized by comprising a platform frame and a support frame, wherein the platform frame is fixedly connected with the support frame, the platform frame is positioned above the support frame, and the support frame can be detachably connected with a cover beam;
the supporting frame comprises a plurality of supporting rods and a plurality of limiting rods, all the supporting rods can be arranged on the upper surface of the cover beam, two ends of all the supporting rods can extend along the width direction of the cover beam, all the supporting rods can be arranged at intervals along the length direction of the cover beam, two ends of each supporting rod are fixedly connected with the limiting rods, the upper end of each limiting rod is fixedly connected with the supporting rods, and the lower end of each limiting rod extends downwards;
the platform frame comprises a plurality of first platform rods and a plurality of second platform rods, all the first platform rods are located above the supporting rods, all the first platform rods are fixedly connected with the supporting rods, all the two ends of each first platform rod can extend along the length direction of the cover beam, all the first platform rods can be arranged at intervals along the width direction of the cover beam, and each of the two ends of each first platform rod is fixedly connected with the second platform rods and each of the second platform rods is fixedly connected with all the first platform rods.
2. The integrated construction platform for construction of the support base cushion stone as claimed in claim 1, wherein the support frame further comprises a plurality of reinforcing rods, both ends of all the reinforcing rods can extend along the length direction of the cover beam, all the reinforcing rods are arranged at intervals along the vertical direction, and each reinforcing rod is fixedly connected with the limiting rod.
3. The integrated construction platform for construction of the support base stepping stone as claimed in claim 2, wherein the support frame further comprises a support rod, the support rod is arranged in an inclined manner, one end of the support rod is fixedly connected with the platform frame, and the other end of the support rod is fixedly connected with the limiting rod.
4. The integrated construction platform for support base and cushion stone construction as claimed in claim 3, further comprising a protection frame, wherein the protection frame is arranged above the platform frame and is fixedly connected with the platform frame.
5. The integrated construction platform for the construction of the support base cushion stone as claimed in claim 4, wherein the protection frame comprises a plurality of protection cross bars and a plurality of protection vertical bars, all the protection vertical bars are arranged around the platform frame at intervals, the lower ends of the protection vertical bars are fixedly connected with the platform frame, the upper ends of the protection vertical bars extend upwards, all the protection cross bars are arranged at intervals along the vertical direction and are fixedly connected with all the protection vertical bars, and each protection cross bar is annular and is arranged around the platform frame.
6. The integrated construction platform for construction of support base cushion stones according to claim 5, wherein the protection cross rods and the protection vertical rods are steel pipes.
7. The integrated construction platform for construction of the support base cushion stone as claimed in claim 1, wherein the number of the first platform rods is four, the four first platform rods can be arranged at intervals along the width direction of the cover beam, and all the first platform rods are connected through screw steel.
8. The integrated construction platform for construction of support base cushion stones according to claim 1, wherein the first platform rod and the second platform rod are connected through screw steel.
9. The integrated construction platform for construction of the support base and the cushion stone as claimed in claim 1, wherein the first platform rod and the second platform rod are both angle steel, and the support rod and the limiting rod are both I-shaped steel.
10. The integrated construction platform for support base and cushion construction as claimed in claim 1, wherein the platform frame further comprises a steel plate net, the steel plate net is located above the first platform rod, and the steel plate net is fixedly connected with the first platform rod.
CN202222326007.5U 2022-08-31 2022-08-31 A integration construction platform for construction of support bed stone Active CN218147838U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222326007.5U CN218147838U (en) 2022-08-31 2022-08-31 A integration construction platform for construction of support bed stone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222326007.5U CN218147838U (en) 2022-08-31 2022-08-31 A integration construction platform for construction of support bed stone

Publications (1)

Publication Number Publication Date
CN218147838U true CN218147838U (en) 2022-12-27

Family

ID=84559103

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222326007.5U Active CN218147838U (en) 2022-08-31 2022-08-31 A integration construction platform for construction of support bed stone

Country Status (1)

Country Link
CN (1) CN218147838U (en)

Similar Documents

Publication Publication Date Title
CN106638946A (en) Connecting structure of reinforced concrete swinging column and reinforced concrete foundation
CN218147838U (en) A integration construction platform for construction of support bed stone
CN206052554U (en) A kind of Construction Supporting System for square twin columns great cantilever bent cap
CN209816665U (en) Bent cap bracket suitable for round end shape pier stud
CN212688718U (en) Bent cap reinforcement bed-jig structure
CN213836320U (en) Staple bolt jack support system construction equipment
CN212000638U (en) Overhead cover beam type steel supporting structure
CN211037933U (en) Simple escalator for foundation pit
CN111778832A (en) Steel pipe support shared by bridge deck system and arch rib of steel structure arch bridge
CN216999264U (en) Pier stud framework of steel reinforcement fixing device
CN205623537U (en) Photovoltaic big -arch shelter
CN218621849U (en) Bent cap reinforcing bar fixing device
CN216406171U (en) Shaped steel concrete beam template mounting structure
CN210561763U (en) Height-adjustable beam cover bottom mould supporting structure
CN212667224U (en) Steel reinforcement cage transport vechicle
CN210712577U (en) Temporary support for mounting of arch continuous steel box girder
CN217810529U (en) Square steel pier stud top assembled operation platform
CN216999361U (en) Single-column pier cantilever capping beam assembly type bearing support device
CN211283515U (en) Regularization platform that tower crane attaches wall
CN211713706U (en) Large cantilever prefabricated bent cap installation lattice support device
CN217500995U (en) Anti-tilting device for building side column protection platform
CN217536682U (en) Pier top operation platform that precast beam erect
CN218540414U (en) Auxiliary device for erection and positioning of prefabricated T-shaped beam
CN217053061U (en) Simple device for fixing steel truss
CN218714867U (en) Foundation-free assembly jig frame of large-span prestressed arch dry coal shed

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant