CN218090524U CN202122216015.XU CN202122216015U CN218090524U CN 218090524 U CN218090524 U CN 218090524U CN 202122216015 U CN202122216015 U CN 202122216015U CN 218090524 U CN218090524 U CN 218090524U
Authority
CN
China
Prior art keywords
girder
support
truss
bridge
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122216015.XU
Other languages
Chinese (zh)
Inventor
陈涛
赵�卓
姚建峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xingtu Co ltd
Original Assignee
Xingtu Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xingtu Co ltd filed Critical Xingtu Co ltd
Priority to CN202122216015.XU priority Critical patent/CN218090524U/en
Application granted granted Critical
Publication of CN218090524U publication Critical patent/CN218090524U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

A installation device for bridge truss, include the girder, set up with pier shaft anchor and be used for supporting the support of girder, the girder is equipped with the equipment of lifting by crane that is used for lifting by crane the truss respectively, it slides along the girder to lift by crane the equipment and sets up, the girder is located the top of support, the support sets up with the girder is fixed.

Description

Installation device for bridge truss
Technical Field
The utility model relates to a bridge construction technical field especially relates to an installation device for bridge truss.
Background
In the bridge construction process, the installation of the truss is an important component, and the installation is carried out by using a crane in the prior art, so the method has the following defects that the construction cost is economically improved by using the crane for installation, the crane occupies a large space and is difficult to transport, and the operation of the crane is complex.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem that, it provides a device that is arranged in the bridge not to use the loop wheel machine to accomplish the truss installation to solve not enough that prior art exists.
The utility model discloses a technical scheme be a dismouting device that is arranged in bridge truss, be used for supporting including the girder, with pier shaft anchor setting the support of girder, the girder is equipped with the equipment of lifting by crane that is used for lifting by crane the truss respectively, it slides along the girder to lift by crane equipment and sets up, the girder is located the top of support, the support sets up with the girder is fixed.
The support includes the base, the upper and lower both ends of base have set firmly first backup pad, second backup pad respectively, the girder is located the top of first backup pad, the upper and lower both sides of girder have welded respectively and have set firmly first backing plate, second backing plate, thereby the dead lever stretches out the hole site that passes second backup pad, first backup pad, second backing plate, first backing plate from the pier shaft and links to each other girder and support are fixed continuous with the nut screw.
The girder is two I-shaped steel that arrange side by side.
The lifting equipment is an electric hoist.
The quantity of dead lever is four, the base is located the center of four dead levers.
Compared with the prior art, the beneficial effects of the utility model reside in that:
1. the utility model discloses compare in with the quick-witted installation truss of hoist, area is little, convenient operation, convenient transportation.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a partial enlarged view of the position a of the present invention.
Detailed Description
The present invention will be further described by way of examples with reference to the accompanying drawings.
As shown in fig. 1 to 2, the installation device for a bridge truss according to the present embodiment includes a main beam 1 and a support 2 anchored to a pier body 5 and used for supporting the main beam 1, wherein the main beam 1 is respectively provided with a hoisting device 4 for hoisting the truss 3, the hoisting device 4 is slidably disposed along the main beam 1, the main beam 1 is located above the support 2, and the support 2 and the main beam 1 are fixedly disposed; the main beam 1 is two I-shaped steels arranged side by side; the hoisting equipment 4 is an electric hoist. The utility model fixes the main beam 1 on the pier body 5 through the connection of the support 2, moves along the main beam 1 through the hoisting equipment 4 in the horizontal direction to drive the truss to move to a proper position, and the hoisting equipment 4 moves the truss to a proper position in the vertical direction, thereby realizing the installation of the truss 3; the embodiment replaces a crane to install the truss, and has the advantages of small floor area, convenience in operation, convenience in transportation and the like.
This embodiment support 2 includes base 21, first backup pad 22, second backup pad 23 have set firmly respectively at base 21's upper and lower both ends, girder 1 is located first backup pad 22's top, girder 1's upper and lower both sides welding respectively has set firmly first backing plate 11, second backing plate 12, thereby dead lever 6 stretches out from pier shaft 5 and passes second backup pad 23, first backup pad 22, second backing plate 12, the hole site of first backing plate 11 and nut 7 screw thread link to each other with girder 1 and support 2 are fixed continuous. The number of the fixing rods 6 is four, and the base 21 is positioned at the center of the four fixing rods 6. The main beam 1 and the support 2 are fixedly connected by the fixing rod 6 and the nut 7.

Claims (5)

1. A installation device for bridge truss, its characterized in that, include girder (1), set up with pier shaft (5) anchor and be used for supporting support (2) of girder (1), girder (1) is equipped with respectively and is used for lifting by crane equipment (4) of truss (3), it slides along girder (1) to lift by crane equipment (4) and sets up, girder (1) is located the top of support (2), support (2) and girder (1) fixed setting.
2. The mounting device for the bridge truss according to claim 1, wherein the support (2) comprises a base (21), the upper end and the lower end of the base (21) are respectively and fixedly provided with a first support plate (22) and a second support plate (23), the main beam (1) is positioned above the first support plate (22), the upper side and the lower side of the main beam (1) are respectively and fixedly provided with a first base plate (11) and a second base plate (12), and the fixing rod (6) extends out of the pier body (5) and passes through the hole positions of the second support plate (23), the first support plate (22), the second base plate (12) and the first base plate (11) and is in threaded connection with the nut (7) so as to fixedly connect the main beam (1) and the support (2).
3. A mounting arrangement for a bridge girder according to claim 1, characterized in that the girders (1) are two i-beams arranged side by side.
4. Installation for a bridge girder according to claim 1, characterized in that the hoisting device (4) is an electric hoist.
5. The installation device for a bridge truss according to claim 2, wherein the number of the fixing rods (6) is four, and the base (21) is located at the center of the four fixing rods (6).
CN202122216015.XU 2021-09-14 2021-09-14 Installation device for bridge truss Active CN218090524U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122216015.XU CN218090524U (en) 2021-09-14 2021-09-14 Installation device for bridge truss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122216015.XU CN218090524U (en) 2021-09-14 2021-09-14 Installation device for bridge truss

Publications (1)

Publication Number Publication Date
CN218090524U true CN218090524U (en) 2022-12-20

Family

ID=84442889

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122216015.XU Active CN218090524U (en) 2021-09-14 2021-09-14 Installation device for bridge truss

Country Status (1)

Country Link
CN (1) CN218090524U (en)

Similar Documents

Publication Publication Date Title
CN106948268B (en) Variable-section steel box girder pushing combined device and using method thereof
CN216474543U (en) Stay cable crane for offshore cable-stayed bridge construction
CN218090524U (en) Installation device for bridge truss
CN219617029U (en) Steel truss beam assembly welding auxiliary device
CN103375029B (en) Prestressed dome lifting cantilever crane
CN111809654A (en) Assembled tower crane foundation structure
CN107217669B (en) Pile pulling equipment and quick moving method thereof
CN213239481U (en) Precast beam static load test device
CN215925671U (en) Quick butt joint levelling device of steel case roof beam
CN101664963B (en) Multifunctional operating platform for large-volume prestressed concrete box girder tensioning
CN115341701A (en) High-altitude overhanging steel bar truss floor support plate hanging formwork construction method
CN111532999B (en) Beam erecting crane and beam erecting method
CN218090579U (en) Dismantling device for bridge truss
CN201052950Y (en) Crane
CN208502273U (en) It is a kind of for without bearing large space Steel Truss Beam hoisting frame
CN105863280A (en) Self-elevating unloading platform
CN219032970U (en) But hanging basket steel suspender continuous adjusting device
CN108343251A (en) A kind of continuance lifting method without bearing large space Steel Truss Beam
CN111362145A (en) Bridge deck crane
CN214780249U (en) Fixing device for hoisting precast beam
CN216474532U (en) Steel case roof beam installation levelling device
CN216739291U (en) Pier body adjusting device
CN217193533U (en) Steel case roof beam welding appurtenance
CN202578008U (en) Prestress dome jack-up cantilever crane
CN218508245U (en) Auxiliary device for mounting railway box girder support