CN218028914U - Outer frame connection processing device for building engineering - Google Patents
Outer frame connection processing device for building engineering Download PDFInfo
- Publication number
- CN218028914U CN218028914U CN202221768224.3U CN202221768224U CN218028914U CN 218028914 U CN218028914 U CN 218028914U CN 202221768224 U CN202221768224 U CN 202221768224U CN 218028914 U CN218028914 U CN 218028914U
- Authority
- CN
- China
- Prior art keywords
- fastener
- steel pipe
- oil
- fixed mounting
- bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model belongs to the field of constructional engineering, in particular to a scaffold extension connection processing device for constructional engineering, which comprises a scaffold extension vertical rod and a connection cross rod, wherein the outer surface of the scaffold extension vertical rod is fixedly provided with the connection cross rod, one side of the scaffold extension vertical rod is provided with a cross beam, the inside of the cross beam is fixedly provided with a steel pipe, the other end of the steel pipe is exposed outside the cross beam, and the outer surface of the steel pipe is provided with an auxiliary fastener; through with main fastener and the laminating of connection horizontal pole, vice fastener and steel pipe laminating, make bolt on the main fastener and the screw hole on the vice fastener on same straight line, twist this moment and move the bolt and get into the screw hole internal fixation, and then it is fixed to connect horizontal pole and steel pipe, thereby play quick fixed effect, it plays and prevents that the bolt can lose when not using to connect the rope and drop, the steel pipe can only once utilize, the later stage will leak the part and cut off outward, thereby play and need not demolish, needn't waste a large amount of manpower and materials again, the problem of installation and later stage reworking has also been reduced.
Description
Technical Field
The utility model relates to a building engineering field specifically is an outrigger connection processing apparatus for building engineering.
Background
The building engineering is the installation engineering of various technical works and completed engineering entities such as planning, investigation, design, construction and completion, and matched lines, pipelines and equipment, which are carried out for newly building, reconstructing or expanding building structures and auxiliary structure facilities, and steel pipes are often used for building frames in the building engineering, so that the outdoor construction operation of workers is facilitated.
In the field of building engineering, particularly building construction, the traditional fixing mode of the outer frame is that a small cross rod is usually used for connecting the outer frame and then extends inwards to be embraced on a column, the mode costs more manpower and material resources and wastes construction space, and the connecting piece needs to be temporarily removed when a column template is removed at the later stage and then embraces the column again, so that rework is caused and potential safety hazards are generated; therefore, in order to solve the above problems, an external frame connection processing device for construction engineering is proposed.
SUMMERY OF THE UTILITY MODEL
In order to compensate prior art's not enough, solved in building engineering especially room building field, the fixed mode of traditional outrigger is usually with little horizontal pole link outrigger, then extend towards the inside and embrace on the post, and this kind of mode cost more manpower and materials, extravagant construction space, and need demolish this connecting piece temporarily when later stage post template is demolishd, embrace the post again, can cause and do over again, can produce the problem of potential safety hazard, the utility model provides an outrigger connection processing apparatus for building engineering.
The utility model provides a technical scheme that its technical problem adopted is: the utility model discloses an outrigger connection processing device for building engineering, including outrigger pole setting and connection horizontal pole, the outer fixed surface of outrigger pole setting installs the connection horizontal pole, one side of outrigger pole setting is equipped with the crossbeam, the inside fixed mounting of crossbeam has the steel pipe, the other end of steel pipe exposes outside the crossbeam, the surface of steel pipe is equipped with vice fastener, the surface of vice fastener is seted up threaded hole, the surface of connecting the horizontal pole is equipped with main fastener, one side threaded connection of main fastener has the bolt, the one end fixed mounting of bolt has the connecting rope, the other end and the main fastener fixed connection of connecting rope; play quick fixed effect, connect the rope and play and prevent that the bolt can lose when not using and drop, the steel pipe can only once be utilized, and the later stage will leak the part outward and cut off to play and need not demolising, needn't waste a large amount of manpower and materials again, also reduced the problem of installation and later stage rework.
Preferably, an L-shaped extrusion rod is fixedly installed at the top of the main fastener, an oil box made of rubber is fixedly installed at the top of the auxiliary fastener, the oil box and the extrusion rod are on the same straight line, and an oil outlet pipe is fixedly installed at one side of the oil box; the bolt can be lubricated and conveniently screwed, and the situation that the bolt is rusted and cannot be screwed is reduced.
Preferably, an arc-shaped oil guide pipe is fixedly installed at the bottom of the oil outlet pipe, an oil injection port is formed in the bottom of the oil guide pipe, an elastic rope is fixedly installed on the inner wall of the oil injection port, and a waterproof cloth is fixedly installed at the other end of the elastic rope; the elastic rope drives the waterproof cloth to reset, and then the oil nozzle is plugged, so that the dustproof effect is achieved while the lubricating oil is prevented from dripping.
Preferably, one end of the extrusion rod is fixedly provided with a pressing plate, one side of the pressing plate is fixedly provided with a pressing column, and one end of the pressing column is fixedly sleeved with a ferrule made of rubber; the ferrule made of rubber at one end of the compression leg plays a role in protecting the oil box, and the situation that the compression leg damages the oil box is avoided.
Preferably, a flow guide frame is fixedly installed at the bottom of the auxiliary fastener, the inside of the flow guide frame is inclined, and a storage box is clamped at the bottom of the flow guide frame; collecting and conveniently reutilizing the lubricating oil.
Preferably, a bracket made of plastic is fixedly arranged at the bottom of the flow guide frame, and two rectangular plates are fixedly arranged on the inner wall of the bracket; make things convenient for receiver and water conservancy diversion frame to carry out the joint fixed.
The utility model discloses an useful part lies in:
1. the utility model discloses an it is pre-buried in the crossbeam earlier with the steel pipe, make partly of steel pipe be in the crossbeam, play fixed effect, the other end of steel pipe is outside being in the crossbeam, pre-buried position of steel pipe and outrigger pole setting are on same straight line, pass through with main fastener and connection horizontal pole laminating this moment again, vice fastener and steel pipe laminating, make bolt on the main fastener and the screw hole on the vice fastener on same straight line, twist this moment and move the bolt and get into threaded hole internal fixation, and then it is fixed with the steel pipe to connect horizontal pole and steel pipe, thereby play quick fixed effect, it plays and prevents that the bolt can lose when not using to connect the rope and drop, the steel pipe can only once only be utilized, the later stage will leak the part and cut off outward, thereby play and need not demolish, needn't waste a large amount of manpower and materials again, the problem of installation and later stage reworking has also been reduced.
2. The utility model discloses a when main fastener is close to the installation to vice fastener direction, the last stripper bar of main fastener can extrude the oil box on the vice fastener, receives the extrusion back when the oil box of rubber material, can spout the lubricating oil in the oil box through going out oil pipe, and then on the drippage bolt to play the effect that lubricating bolt conveniently twisted, also play the circumstances that reduces the bolt rust and can't twist and move simultaneously and take place.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the description below are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without inventive labor.
FIG. 1 is a schematic structural view of an upright of an external frame according to a first embodiment;
FIG. 2 is a schematic diagram of a structure shown in FIG. 1 according to a first embodiment;
FIG. 3 is a schematic view of a partial structure of an oil pipe according to an embodiment;
FIG. 4 is a schematic view of a portion of a secondary fastener according to an embodiment;
fig. 5 is a schematic structural diagram of a fixture block in the second embodiment.
In the figure: 1. an outer frame upright stanchion; 2. connecting the cross bars; 3. a cross beam; 4. a steel pipe; 5. a main fastener; 6. a secondary fastener; 7. a bolt; 8. connecting ropes; 9. a threaded hole; 10. an extrusion stem; 11. an oil box; 12. an oil outlet pipe; 13. an oil guide pipe; 14. an oil injection port; 15. waterproof cloth; 16. an elastic cord; 17. pressing a plate; 18. pressing the column; 19. a ferrule; 20. a flow guide frame; 21. a storage box; 22. a support; 23. a rectangular plate; 24. a card slot; 25. and (7) clamping blocks.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
Example one
Referring to fig. 1-4, an outrigger connection processing device for construction engineering comprises an outrigger upright rod 1 and a connection cross rod 2, wherein the outer surface of the outrigger upright rod 1 is fixedly provided with the connection cross rod 2, one side of the outrigger upright rod 1 is provided with a cross beam 3, the inside of the cross beam 3 is fixedly provided with a steel pipe 4, the other end of the steel pipe 4 is exposed outside the cross beam 3, the outer surface of the steel pipe 4 is provided with an auxiliary fastener 6, the surface of the auxiliary fastener 6 is provided with a threaded hole 9, the surface of the connection cross rod 2 is provided with a main fastener 5, one side of the main fastener 5 is in threaded connection with a bolt 7, one end of the bolt 7 is fixedly provided with a connection rope 8, and the other end of the connection rope 8 is fixedly connected with the main fastener 5; during operation, earlier with steel pipe 4 pre-buried in crossbeam 3, make steel pipe 4 partly be in crossbeam 3, play fixed effect, steel pipe 4's the other end is outside crossbeam 3, steel pipe 4 pre-buried position and outrigger pole setting 1 are on same straight line, this moment again through laminating main fastener 5 and connection horizontal pole 2, vice fastener 6 and steel pipe 4 laminating, make bolt 7 on the main fastener 5 and screw hole 9 on the vice fastener 6 on same straight line, twist bolt 7 this moment and get into screw hole 9 internal fixation, and then will connect horizontal pole 2 and steel pipe 4 fixed, thereby play quick fixed effect, it can lose when not using to connect rope 8 to play and drop to prevent bolt 7, steel pipe 4 can only once only be utilized, the later stage will leak the part and cut off, thereby play and need not demolish, the extravagant a large amount of manpower and materials again, the problem of installation and later stage reworking has also been reduced.
The top of the main fastener 5 is fixedly provided with an L-shaped extrusion rod 10, the top of the auxiliary fastener 6 is fixedly provided with an oil box 11 made of rubber, the oil box 11 and the extrusion rod 10 are on the same straight line, and one side of the oil box 11 is fixedly provided with an oil outlet pipe 12; the during operation, when main fastener 5 is close to the installation to vice fastener 6 direction, the last extrusion stem 10 of main fastener 5 can extrude the oil box 11 on the vice fastener 6, receives the extrusion back when the oil box 11 of rubber material, can spout the lubricating oil in oil box 11 through play oil pipe 12, and then on the drippage bolt 7 to play lubricated bolt 7 and conveniently twist the effect of moving, also play simultaneously and reduce the condition emergence that bolt 7 rusted and can't twist the moving.
An arc-shaped oil guide pipe 13 is fixedly installed at the bottom of the oil outlet pipe 12, an oil injection port 14 is formed in the bottom of the oil guide pipe 13, an elastic rope 16 is fixedly installed on the inner wall of the oil injection port 14, and a waterproof cloth 15 is fixedly installed at the other end of the elastic rope 16; the during operation, when oil pipe 12 is when the oil spout, can flow in oil pipe 13, lubricating oil can promote elasticity rope 16 and tarpaulin 15 to the direction of keeping away from oil spout 14 when the oil spout 14 blowout through the honeycomb duct, and then make things convenient for the lubricating oil blowout in the oil spout 14, and when oil spout 14 did not spout lubricating oil, elasticity rope 16 area tarpaulin 15 resets, and then plugs up oil spout 14 to play dirt-proof effect when avoiding lubricating oil drippage.
A pressing plate 17 is fixedly installed at one end of the extrusion rod 10, a pressing column 18 is fixedly installed at one side of the pressing plate 17, and a ferrule 19 made of rubber is fixedly sleeved at one end of the pressing column 18; during operation, when the extrusion stem 10 is moving, the pressing plate 17 and the compression leg 18 can be driven to move together, so that the oil box 11 is pressed, the pressing area is increased, a better pressing effect is achieved, the ferrule 19 made of rubber at one end of the compression leg 18 plays a role in protecting the oil box 11, and the situation that the compression leg 18 damages the oil box 11 is avoided.
A flow guide frame 20 is fixedly installed at the bottom of the auxiliary fastener 6, the inside of the flow guide frame 20 is inclined, and a storage box 21 is clamped at the bottom of the flow guide frame 20; during operation, the lubricating oil that drips on bolt 7 can continue the landing along vice fastener 6 to drip in water conservancy diversion frame 20, because water conservancy diversion frame 20 is inside to be the slope form, so can be with the leading-in receiver 21 of the lubricating oil of collecting in, and then collect lubricating oil and make things convenient for reuse.
A support 22 made of plastic is fixedly arranged at the bottom of the flow guide frame 20, and two rectangular plates 23 are fixedly arranged on the inner wall of the support 22; during operation, the support 22 of water conservancy diversion frame 20 bottom is for providing the support for receiver 21, prevents that receiver 21 and water conservancy diversion frame 20 from being shakiness in the long-time joint, or when the lubricating oil of collecting in the receiver 21 was too much heavier, leads to the condition emergence that receiver 21 dropped, and rectangular plate 23 on the support 22 is for convenient positioning receiver 21, makes things convenient for receiver 21 and water conservancy diversion frame 20 to carry out the joint fixed.
Example two
Referring to fig. 5, in a first comparative example, as another embodiment of the present invention, a clamping block 25 is fixedly installed on one side of the main fastening member 5, and a clamping groove 24 is formed on one side of the secondary fastening member 6; during operation, when using main fastener 5 and vice fastener 6, earlier with the fixture block 25 on main fastener 5 and the draw-in groove 24 chucking on the vice fastener 6 fixed, and then make things convenient for bolt 7 to aim at screw hole 9, convenient subsequent fixed mounting.
The working principle is that the steel pipe 4 is pre-embedded in the cross beam 3, so that a part of the steel pipe 4 is positioned in the cross beam 3 to play a role of fixing, the other end of the steel pipe 4 is positioned outside the cross beam 3, the pre-embedded position of the steel pipe 4 and the outrigger upright stanchion 1 are on the same straight line, at the moment, the main fastener 5 is attached to the connecting cross rod 2, the auxiliary fastener 6 is attached to the steel pipe 4, so that the bolt 7 on the main fastener 5 and the threaded hole 9 on the auxiliary fastener 6 are on the same straight line, at the moment, the screwing bolt 7 enters the threaded hole 9 to be fixed, so that the connecting cross rod 2 and the steel pipe 4 are fixed, so as to play a role of quick fixing, the connecting rope 8 plays a role of preventing the bolt 7 from losing and dropping when the bolt is not used, the steel pipe 4 can be used once only, the outer leakage part is cut off at the later stage, so as to remove the oil box without wasting a large amount of manpower, the problem of installation and later stage reworking is also reduced, when the main fastener 5 is close to the installation towards the auxiliary fastener 6, the direction of the oil box 11, so that the lubricating oil box 11 can not push the lubricating oil spray out from the oil box 7, thereby the lubricating oil spout 14, thereby reducing the situation that the lubricating oil can not be convenient for the lubricating oil spout 14, when the lubricating oil spout 14, the lubricating oil spout 14 can be pushed, and the lubricating oil spout 14, the lubricating oil spout 14 can not be pushed, and the lubricating oil spout 14, and the lubricating oil spout can not be pushed in the oil spout when the lubricating oil spout 14, when the squeeze bar 10 is moving, can take the clamp plate 17 and the compression leg 18 to move together, make to push down and extrude oil box 11, thereby increase the extrusion area, play better extrusion effect, and the lasso 19 of the rubber material of compression leg 18 one end plays the effect of protection oil box 11, avoid compression leg 18 to damage the condition emergence of oil box 11, lubricating oil that drips onto bolt 7 can continue the landing along secondary fastener 6, thereby drip into water conservancy diversion frame 20, because water conservancy diversion frame 20 is inside to be the slope form, so can lead to in the leading-in receiver 21 of the lubricating oil who collects, and then collect and convenient reuse, support 22 of water conservancy diversion frame 20 bottom is for providing the support for receiver 21, prevent long-time joint of 21 and water conservancy diversion frame 20, or when the lubricating oil of collecting in the receiver 21 is too much heavier, lead to the condition emergence that receiver 21 dropped, and rectangular plate 23 on the support 22 is for convenient receiver 21 to fix in order to make things convenient for joint with water conservancy diversion frame 20.
In the description herein, references to the description of "one embodiment," "an example," "a specific example," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention.
Claims (6)
1. The utility model provides a handling device is connected to outrigger for building engineering which characterized in that: including outrigger pole setting (1) and connection horizontal pole (2), the outer fixed surface of outrigger pole setting (1) installs connection horizontal pole (2), one side of outrigger pole setting (1) is equipped with crossbeam (3), the inside fixed mounting of crossbeam (3) has steel pipe (4), the other end of steel pipe (4) exposes outside crossbeam (3), the surface of steel pipe (4) is equipped with vice fastener (6), threaded hole (9) have been seted up on the surface of vice fastener (6), the surface of connecting horizontal pole (2) is equipped with main fastener (5), one side threaded connection of main fastener (5) has bolt (7), the one end fixed mounting of bolt (7) has connection rope (8), the other end and main fastener (5) fixed connection of connecting rope (8).
2. The exterior frame connection processing device for construction engineering according to claim 1, wherein: the top fixed mounting of main fastener (5) has the extrusion stem (10) of "L" shape, the top fixed mounting of vice fastener (6) has oil box (11) of rubber material, oil box (11) and extrusion stem (10) are on same straight line, one side fixed mounting of oil box (11) has oil pipe (12).
3. The exterior frame connection processing device for construction engineering according to claim 2, wherein: the oil injection device is characterized in that an arc-shaped oil guide pipe (13) is fixedly mounted at the bottom of the oil outlet pipe (12), an oil injection port (14) is formed in the bottom of the oil guide pipe (13), an elastic rope (16) is fixedly mounted on the inner wall of the oil injection port (14), and waterproof cloth (15) is fixedly mounted at the other end of the elastic rope (16).
4. The exterior frame connection processing device for construction engineering according to claim 3, wherein: one end fixed mounting of extrusion pole (10) has clamp plate (17), one side fixed mounting of clamp plate (17) has compression leg (18), the fixed lasso (19) that have the rubber material of cover of one end of compression leg (18).
5. The exterior frame connection processing device for construction engineering according to claim 4, wherein: the bottom fixed mounting of vice fastener (6) has water conservancy diversion frame (20), the inside of water conservancy diversion frame (20) is the slope form, the bottom joint of water conservancy diversion frame (20) has receiver (21).
6. The exterior frame connection processing device for construction engineering according to claim 5, wherein: the bottom fixed mounting of water conservancy diversion frame (20) has support (22) of plastics material, the inner wall fixed mounting of support (22) has two rectangular plates (23).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221768224.3U CN218028914U (en) | 2022-07-08 | 2022-07-08 | Outer frame connection processing device for building engineering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221768224.3U CN218028914U (en) | 2022-07-08 | 2022-07-08 | Outer frame connection processing device for building engineering |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218028914U true CN218028914U (en) | 2022-12-13 |
Family
ID=84382967
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202221768224.3U Active CN218028914U (en) | 2022-07-08 | 2022-07-08 | Outer frame connection processing device for building engineering |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218028914U (en) |
-
2022
- 2022-07-08 CN CN202221768224.3U patent/CN218028914U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN218028914U (en) | Outer frame connection processing device for building engineering | |
CN212317658U (en) | Safety net rail mount that construction used | |
CN219386617U (en) | Novel integrated pump station barrel | |
CN219569210U (en) | Sealing structure of prefabricated cabin of water supply equipment | |
CN210230394U (en) | Rail guard paint spraying apparatus for municipal works | |
CN210067479U (en) | Building piping erection equipment | |
CN209585818U (en) | The chucking device of fast demountable fence | |
CN210530309U (en) | Connecting piece for scaffold | |
CN203769327U (en) | Tower concrete pump pipe fixing device | |
CN212427519U (en) | Stable building steel structure | |
CN211775770U (en) | Synchronous dismouting mould of reservation entrance to a cave | |
CN209874657U (en) | Keep off with keeping apart to construction | |
CN217461554U (en) | Concrete placement device for civil engineering | |
CN215891488U (en) | Steel wire pipe bimetal flange connection structure | |
CN216303112U (en) | Tower crane device with screw rod adjusting type liquid spraying head | |
CN212802011U (en) | Waterproof building net for sponge city planning and construction | |
CN217747762U (en) | Steel wire rope maintenance device for building municipal construction | |
CN221481378U (en) | Rust-resistant coupling assembling of scaffold frame | |
CN218493079U (en) | Connection structure between creeping formwork and aluminium membrane | |
CN211553423U (en) | Sampling device convenient for extracting liquid components of food for food safety detection | |
CN217924730U (en) | Assembled building construction platform with dust fall function | |
CN218919908U (en) | Assembled building pipeline gallows | |
CN221774839U (en) | Maintenance water recycling system | |
CN220395019U (en) | Roof expansion joint waterproof construction | |
CN219471615U (en) | Simple protection device for paying-off reserved hole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |