CN218024832U - Steel construction elevator well top hook structure - Google Patents

Steel construction elevator well top hook structure Download PDF

Info

Publication number
CN218024832U
CN218024832U CN202221991432.XU CN202221991432U CN218024832U CN 218024832 U CN218024832 U CN 218024832U CN 202221991432 U CN202221991432 U CN 202221991432U CN 218024832 U CN218024832 U CN 218024832U
Authority
CN
China
Prior art keywords
steel
lifting hook
plate
hook
steel beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221991432.XU
Other languages
Chinese (zh)
Inventor
陈辉
孟灿
周志锦
王颖
谭雪松
夏生生
陈威
邓玮玲
张纯
胡晓阳
张艳锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiangtan Architectural Design Institute Group Co ltd
Original Assignee
Xiangtan Architectural Design Institute Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiangtan Architectural Design Institute Group Co ltd filed Critical Xiangtan Architectural Design Institute Group Co ltd
Priority to CN202221991432.XU priority Critical patent/CN218024832U/en
Application granted granted Critical
Publication of CN218024832U publication Critical patent/CN218024832U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

A steel structure elevator hoistway top hook structure, comprising: the steel beam comprises a lifting hook plate, a stiffening plate and a steel beam, wherein the lifting hook plate is arranged on the lower flange of the steel beam, and the stiffening plate is respectively connected with the side surface of the lifting hook plate and the lower flange of the steel beam. The application provides a pair of steel construction elevator well top lifting hook structure simple manufacture, simple to operate, lifting hook board, stiffening plate and girder steel can be directly at the welding preparation of mill and accomplish the back on-the-spot installation, through adopting lifting hook board and stiffening plate and girder steel integral welding to transmit the lifting hook load, compares traditional elevator lifting hook structure, can reduce the local stress concentration on girder steel bottom flange, makes the stress distribution more tend to evenly.

Description

Steel construction elevator well top hook structure
Technical Field
The utility model belongs to the technical field of building structure component, concretely relates to steel construction elevator well top lifting hook structure.
Background
At present, civil engineering, namely old community transformation projects, which is the key development of the country, is actively promoted all over the country, and the addition of elevators in old multi-storey residential buildings is a key content of the old community transformation projects. To this kind of add after, its well generally adopts steel frame construction more, to steel construction elevator well top lifting hook, the tradition is done the law and is adopted round steel bending to take shape back and well top girder steel bottom flange welded mode more, can produce great concentrated stress to girder steel bottom flange like this, has reduced the safe deposit of component.
SUMMERY OF THE UTILITY MODEL
The application provides a steel construction elevator well top hook structure, include: the steel beam comprises a lifting hook plate, a stiffening plate and a steel beam, wherein the lifting hook plate is arranged on the lower flange of the steel beam, and the stiffening plate is respectively connected with the side surface of the lifting hook plate and the lower flange of the steel beam.
Preferably, a hook hole is reserved in the middle of the hook plate.
Preferably, the stiffener plate is arranged perpendicular to the hanger plate.
Preferably, two stiffening plates are arranged on each side of the hook plate.
Preferably, the steel beam is rectangular in cross section.
The application provides a pair of steel construction elevator well top lifting hook structure simple manufacture, simple to operate, lifting hook board, stiffening plate and girder steel can be directly at the welding preparation of mill and accomplish the back on-the-spot installation, through adopting lifting hook board and stiffening plate and girder steel integral welding to transmit the lifting hook load, compares traditional elevator lifting hook structure, can reduce the local stress concentration on girder steel bottom flange, makes the stress distribution more tend to evenly.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural view of a hook structure at the top of a steel structure elevator shaft provided by the present invention;
fig. 2 is the utility model provides a pair of steel construction elevator well top hook structure's side schematic diagram.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in detail with reference to the accompanying drawings. It should be understood that the description is intended for purposes of illustration only and is not intended to limit the scope of the present disclosure. Moreover, in the following description, descriptions of well-known structures and techniques are omitted so as to not unnecessarily obscure the concepts of the present invention.
In an embodiment of the present application, as shown in fig. 1-2, the present application provides a steel structure elevator hoistway top hook structure, including: the steel beam comprises a hook plate 1, a stiffening plate 3 and a steel beam 4, wherein the hook plate 1 is arranged on the lower flange of the steel beam 4, and the stiffening plate 3 is respectively connected with the side surface of the hook plate 1 and the lower flange of the steel beam 4.
In the present embodiment, the stiffener 3 serves to ensure lateral stability and rigidity of the hook plate 1 while dispersing the stress transmitted from the hook plate 1 to the lower flange of the steel beam 4.
In the embodiment of the present application, a hook hole 2 is left in the middle of the hook plate 1.
In the present embodiment, the hook hole 2 is used for passing a cable therethrough and hanging an object such as a motor or the like.
In the embodiment of the present application, the stiffener 3 is arranged perpendicular to the hanger plate 1.
In the embodiment of the present application, two stiffening plates 3 are disposed on each side of the hook plate 1.
In the embodiment of the present application, the material of the hook plate 1 is Q235B grade steel.
In the embodiment of the present application, the width of the hook plate 1 is the same as that of the steel beam 4, and the lower part is semicircular.
In the embodiment of the present application, the thickness of the hanger plate 1 is not less than 16mm.
In the embodiment of the present application, the diameter of the hook hole 2 is not less than 50mm.
In the embodiment of the present application, the stiffening plate 3 is made of Q235B grade steel.
In the embodiment of the present application, the thickness of the stiffener plate 3 is not less than 6mm.
In the embodiment of the present application, the section of the steel beam 4 is rectangular.
The application provides a pair of steel construction elevator well top lifting hook structure simple manufacture, simple to operate, lifting hook plate, stiffening plate and girder steel can be directly at the welding of mill and accomplish the back on-the-spot installation, through adopting lifting hook plate and stiffening plate and girder steel whole welding to transmit the lifting hook load, compares traditional elevator lifting hook structure, can reduce the local stress concentration on girder steel bottom flange, makes the stress distribution more tend to evenly.
It is to be understood that the above-described embodiments of the present invention are merely illustrative of or explaining the principles of the invention and are not to be construed as limiting the invention. Therefore, any modification, equivalent replacement, improvement and the like made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. Further, it is intended that the appended claims cover all such variations and modifications as fall within the scope and boundaries of the appended claims or the equivalents of such scope and boundaries.

Claims (5)

1. A steel construction elevator well top lifting hook structure which characterized in that includes: the steel beam comprises a lifting hook plate, a stiffening plate and a steel beam, wherein the lifting hook plate is arranged on the lower flange of the steel beam, and the stiffening plate is respectively connected with the side surface of the lifting hook plate and the lower flange of the steel beam.
2. The steel structure elevator hoistway top hook structure of claim 1, wherein a hook hole is left at a middle position of the hook plate.
3. The steel structure elevator hoistway top hook structure of claim 1, wherein the stiffener plates are arranged perpendicular to the hook plates.
4. The steel structure elevator hoistway top hook structure of claim 1, wherein two stiffening plates are provided on each side of the hook plate.
5. The steel structure elevator hoistway top hook structure of claim 1, wherein the steel beam is rectangular in cross-section.
CN202221991432.XU 2022-07-31 2022-07-31 Steel construction elevator well top hook structure Active CN218024832U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221991432.XU CN218024832U (en) 2022-07-31 2022-07-31 Steel construction elevator well top hook structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221991432.XU CN218024832U (en) 2022-07-31 2022-07-31 Steel construction elevator well top hook structure

Publications (1)

Publication Number Publication Date
CN218024832U true CN218024832U (en) 2022-12-13

Family

ID=84342137

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221991432.XU Active CN218024832U (en) 2022-07-31 2022-07-31 Steel construction elevator well top hook structure

Country Status (1)

Country Link
CN (1) CN218024832U (en)

Similar Documents

Publication Publication Date Title
CN211846850U (en) Hoist device is used in assembly type building installation
CN218024832U (en) Steel construction elevator well top hook structure
CN213682849U (en) Shear connector, prefabricated steel beam and steel-concrete combined beam
CN214783820U (en) Lifting point reinforced overweight underground continuous wall reinforcement cage
CN214399503U (en) Multi-steel-beam component hoisting rigging for high-rise steel structure construction
CN205527272U (en) Modulization hanging beam
CN208294101U (en) A kind of large-span steel girder mounting slip and promote coupling apparatus
CN207046633U (en) It is a kind of can fast positioning installation steel structure type elevator hoistways
CN207553615U (en) A kind of elevator shaft climbing form frame windrow platform
CN207293918U (en) A kind of truss hoisting
CN211257444U (en) Assembled wall frame unit with reinforced structure
CN213011524U (en) Steel construction lifting hoisting point device
CN219261853U (en) Cantilever type floor carrier plate supporting structure
CN205709390U (en) A kind of traction machine arrangement of machine-roomless lift
CN212769452U (en) Large-span single-beam crane
CN205653974U (en) Folded plate truss concrete slab formula component
CN205555835U (en) High altitude (HA) escalator truss
CN220080635U (en) Flue bearing structure and flue system using same
CN213868429U (en) Lightweight steel structure shear wall
CN210001410U (en) Lifting lug and lifting appliance
CN220201125U (en) Beam lifting device
CN214993028U (en) Steel box girder support baffle
CN217998360U (en) High-rise building high-altitude large-span connected structure with post-cast strip
CN217399379U (en) Hang basket type of falling T both shoulders cross arm steel suspender
CN213296934U (en) Light-duty mixed structure prefabricated staircase

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant