CN218018255U CN202221330239.1U CN202221330239U CN218018255U CN 218018255 U CN218018255 U CN 218018255U CN 202221330239 U CN202221330239 U CN 202221330239U CN 218018255 U CN218018255 U CN 218018255U
Authority
CN
China
Prior art keywords
connecting rod
rod
trunk line
connecting tube
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221330239.1U
Other languages
Chinese (zh)
Inventor
鱼永强
王欣
李溪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Linhai Construction Engineering Group Co ltd
Original Assignee
Tianjin Linhai Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Linhai Construction Engineering Group Co ltd filed Critical Tianjin Linhai Construction Engineering Group Co ltd
Priority to CN202221330239.1U priority Critical patent/CN218018255U/en
Application granted granted Critical
Publication of CN218018255U publication Critical patent/CN218018255U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model provides a portable building pipeline mounting tool, including trunk line and connecting tube, the cover is equipped with two annular mounts between trunk line and the connecting tube, one side of two annular mounts is encircleed respectively and is connected with a plurality of head rods and second connecting rod, the surface of head rod and second connecting rod all articulates there is fixed establishment, install adjustment mechanism between two annular mounts, fixed establishment through being equipped with, establish after the one end of trunk line and connecting tube when two annular mount covers, adjust the angle of pull rod on head rod and second connecting rod according to the diameter of pipeline, make pull rod one end articulated fixed block and trunk line and connecting tube surface contact, fix two annular mounts between trunk line and connecting tube through screwing up fixing bolt, accomplish the pipeline adjustment corresponding state between trunk line and the connecting tube this moment, the installation rate is improved.

Description

Portable building pipeline mounting tool
Technical Field
The utility model relates to a piping erection technical field specifically is a portable building pipeline mounting tool.
Background
Piping refers to a device for transporting a gas, liquid or fluid with solid particles connected by pipes, pipe couplings, valves, etc. The pipeline need use the mounting tool to install in the installation, wherein the pipeline sleeve mounting tool who applies for No. 202022859081.4, including the sleeve pipe, be provided with adjustment mechanism on the sleeve pipe, adjustment mechanism includes three piece at least regulation poles, many adjust pole circumference set up in on the sleeve pipe, the utility model discloses have the effect of the convenient degree of pipeline between two parties, elevation project regulation when improving the pipe-line casing installation, but the device still has following defect when using: the device can only guarantee the centering and the elevation of pipeline, when lieing in that the installation pipeline docks, unable synchronous and installation pipeline keep the level to correspond, need calibrate with connecting tube once more, and the installation consumes more time.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a portable building pipeline installation instrument to solve the device that above-mentioned background art provided and can only guarantee placing in the middle and the elevation of pipeline, when lieing in that the installation pipeline docks, unable synchronous and installation pipeline keeps the level to correspond, need calibrate with the connecting tube once more, the installation consumes more time's problem.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a portable building piping erection instrument, includes trunk line and connecting tube, the cover is equipped with two annular mount between trunk line and the connecting tube, two one side of annular mount is encircleed respectively and is connected with a plurality of head rods and second connecting rod, the surface of head rod and second connecting rod all articulates there is fixed establishment, two install adjustment mechanism between the annular mount.
As a preferred scheme of the utility model: the fixing mechanism comprises a pull rod which is hinged to the surfaces of the first connecting rod and the second connecting rod, one end of the pull rod is hinged to a fixing block, a threaded hole penetrates through the surface of the fixing block, and a fixing bolt is connected to the inner thread of the threaded hole in a threaded manner.
As a preferred embodiment of the present invention: the adjusting mechanism comprises sliding seats hinged to two sides of the inner wall of one of the annular fixing frames, sliding grooves are formed in the surfaces of the sliding seats, connecting pieces are fixedly connected to the bottoms of the sliding seats, fastening screw rods are connected to the surfaces of the connecting pieces in a threaded mode, racks are connected to the inside of the sliding grooves in a sliding mode, and one sides of the racks are hinged to the inner wall of the other annular fixing frame.
For being as a preferred scheme of the utility model: one of them the bottom fixedly connected with support frame of head rod, the inside of support frame is rotated and is installed the transfer line, the both ends movable sleeve of transfer line is equipped with the sleeve pipe, sheathed tube one end fixedly connected with gear, gear and rack toothing are connected, one of them one side fixed mounting of gear has the rocking wheel.
As a preferred scheme of the utility model: both ends of the rack are fixedly connected with limit stop blocks.
As a preferred embodiment of the present invention: the second connecting rod is inserted and connected inside the first connecting rod.
Compared with the prior art, the beneficial effects of the utility model are that:
(1) Through the fixing mechanism, after the two annular fixing frames are sleeved at one ends of the main pipeline and the connecting pipeline, the angles of the pull rods on the first connecting rod and the second connecting rod are adjusted according to the diameters of the pipelines, so that the fixing blocks hinged to one ends of the pull rods are in surface contact with the main pipeline and the connecting pipeline, the two annular fixing frames are fixed between the main pipeline and the connecting pipeline through tightening the fixing bolts, the corresponding state of pipeline adjustment is completed between the main pipeline and the connecting pipeline, and the installation speed is improved;
(2) Through the adjustment mechanism who is equipped with, after trunk line and connecting tube are fixed to be accomplished, rotate and wave the wheel and drive the gear and follow the rotation, the rack that the gear revolve drives the meshing and connect slides in the spout that the sliding seat surface was seted up, one side of rack articulates at another annular mount inner wall, when the gear drives the rack and removes, thereby it is close to rather than the pipeline syntropy sliding seat direction of connecting to drive one of them annular mount, the second connecting rod is driven and is accomodate to the head rod inside of interlude connection, trunk line and connecting tube are close to and final butt joint this moment, accomplish the installation of pipeline.
Drawings
Fig. 1 is a schematic view of the structure of the present invention;
fig. 2 is a schematic structural view of the fixing mechanism of the present invention;
FIG. 3 is a schematic structural view of an adjusting mechanism of the present invention;
fig. 4 is a schematic view of the structure of the transmission rod of the present invention.
In the figure: 1. a main pipeline; 2. connecting a pipeline; 3. an annular fixing frame; 31. a first connecting rod; 32. a second connecting rod; 4. a fixing mechanism; 41. a pull rod; 42. a fixed block; 43. fixing the bolt; 5. an adjustment mechanism; 51. a sliding seat; 52. connecting sheets; 53. fastening a screw rod; 54. a rack; 541. a limit stop block; 55. a support frame; 56. a transmission rod; 57. a sleeve; 58. a gear; 59. a shaking wheel.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: the utility model provides a portable building pipeline mounting tool, includes trunk line 1 and connecting tube 2, and the cover is equipped with two annular mount 3 between trunk line 1 and the connecting tube 2, and one side of two annular mount 3 is encircleed respectively and is connected with a plurality of head rod 31 and second connecting rod 32, and the surface of head rod 31 and second connecting rod 32 all articulates there is fixed establishment 4, installs adjustment mechanism 5 between two annular mount 3.
In this embodiment: the fixing mechanism 4 comprises a pull rod 41 which is hinged to the surfaces of the first connecting rod 31 and the second connecting rod 32, a fixing block 42 is hinged to one end of the pull rod 41, a threaded hole is formed in the surface of the fixing block 42 in a penetrating mode, and a fixing bolt 43 is connected to the inner portion of the threaded hole in a threaded mode.
When in specific use: after two annular mount 3 cover were established at the one end of trunk line 1 and connecting tube 2, adjust the angle of pull rod 41 on head rod 31 and second connecting rod 32 according to the diameter of pipeline for the articulated fixed block 42 of pull rod 41 one end and trunk line 1 and the surface contact of connecting tube 2 fix two annular mount 3 between trunk line 1 and connecting tube 2 through screwing up fixing bolt 43, accomplish the pipeline adjustment between trunk line 1 and the connecting tube 2 this moment and correspond the state, improve the installation rate.
In this embodiment: adjustment mechanism 5 is including articulating the sliding seat 51 in one of them annular mount 3 inner wall both sides, the spout has been seted up on the surface of sliding seat 51, the bottom fixedly connected with connection piece 52 of sliding seat 51, the surperficial threaded connection of connection piece 52 has fastening screw 53, the inside sliding connection of spout has rack 54, one side of rack 54 articulates at another annular mount 3 inner wall, the bottom fixedly connected with support frame 55 of one of them head rod 31, the inside rotation of support frame 55 installs transfer line 56, the both ends movable sleeve of transfer line 56 is equipped with sleeve pipe 57, the one end fixedly connected with gear 58 of sleeve pipe 57, gear 58 is connected with the rack 54 meshing, one side fixed mounting of one of them gear 58 has rocking wheel 59, the equal fixedly connected with limit stop 541 in both ends of rack 54, second connecting rod 32 alternates to be connected inside head rod 31.
When in specific use: after the main pipeline 1 and the connecting pipeline 2 are fixed, the rotating shaking wheel 59 drives the casing 57 on one side to rotate, the casing 57 rotates to drive the casing 57 movably sleeved at the other end to rotate inside the supporting frame 55 through the transmission rod 56, the casing 57 rotates to drive the gear 58 to rotate along with the casing, the gear 58 rotates to drive the rack 54 meshed with the rack to slide in a sliding groove formed in the surface of the sliding seat 51, the sliding seat 51 is fixed on the surface of the sleeved pipeline through the fastening screw 53 connected with the surface of the bottom connecting sheet 52 in a threaded manner, one side of the rack 54 is hinged to the inner wall of the other annular fixing frame 3, when the gear 58 drives the rack 54 to move, so as to drive one of the annular fixing frames 3 to approach to the sliding seat 51 in the same direction as the pipeline connected with the annular fixing frame, the second connecting rod 32 is driven to be accommodated inside the first connecting rod 31 connected in a penetrating manner, at the time, the main pipeline 1 and the connecting pipeline 2 approach and are finally butted, the installation of the pipeline is completed, the limit stoppers 541 fixedly connected at the two ends of the rack 54 are lifted to the limit rack 54 and meshed with the gear 58, meanwhile, the fixing blocks 42 are hinged to be suitable for a large pipe diameter adjusting device with the two ends of the fixing frame, and the adjustable device can be suitable for a large pipe.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and equivalents may be made without departing from the spirit and scope of the invention.

Claims (6)

1. The utility model provides a portable building pipeline mounting tool, includes trunk line (1) and connecting tube (2), its characterized in that: the cover is equipped with two annular mount (3), two between trunk line (1) and connecting tube (2) one side of annular mount (3) is encircleed respectively and is connected with a plurality of head rods (31) and second connecting rod (32), the surface of head rod (31) and second connecting rod (32) all articulates there is fixed establishment (4), two install adjustment mechanism (5) between annular mount (3).
2. A portable construction pipe installation tool according to claim 1, wherein: the fixing mechanism (4) comprises a pull rod (41) which is hinged to the surfaces of a first connecting rod (31) and a second connecting rod (32), a fixing block (42) is hinged to one end of the pull rod (41), a threaded hole is formed in the surface of the fixing block (42) in a penetrating mode, and a fixing bolt (43) is connected to the inner portion of the threaded hole in a threaded mode.
3. A portable construction pipe installation tool according to claim 1, wherein: adjustment mechanism (5) are including articulating sliding seat (51) in one of them annular mount (3) inner wall both sides, the spout has been seted up on the surface of sliding seat (51), the bottom fixedly connected with connection piece (52) of sliding seat (51), the surperficial threaded connection of connection piece (52) has fastening screw (53), the inside sliding connection of spout has rack (54), one side of rack (54) articulates at another annular mount (3) inner wall.
4. A portable construction pipe installation tool according to claim 1, wherein: one of them the bottom fixedly connected with support frame (55) of head rod (31), the inside rotation of support frame (55) installs transfer line (56), the both ends activity cover of transfer line (56) is equipped with sleeve pipe (57), the one end fixedly connected with gear (58) of sleeve pipe (57), gear (58) are connected with rack (54) meshing, one of them one side fixed mounting of gear (58) has rocking wheel (59).
5. A portable construction pipe installation tool according to claim 3, wherein: both ends of the rack (54) are fixedly connected with limit stoppers (541).
6. A portable construction pipe installation tool according to claim 1, wherein: the second connecting rod (32) is inserted and connected inside the first connecting rod (31).
CN202221330239.1U 2022-05-31 2022-05-31 Portable building pipeline installation tool Active CN218018255U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221330239.1U CN218018255U (en) 2022-05-31 2022-05-31 Portable building pipeline installation tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221330239.1U CN218018255U (en) 2022-05-31 2022-05-31 Portable building pipeline installation tool

Publications (1)

Publication Number Publication Date
CN218018255U true CN218018255U (en) 2022-12-13

Family

ID=84373798

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221330239.1U Active CN218018255U (en) 2022-05-31 2022-05-31 Portable building pipeline installation tool

Country Status (1)

Country Link
CN (1) CN218018255U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117961048A (en) * 2024-04-01 2024-05-03 江苏盛耐新材料有限公司 Quick replacement device of ladle mouth of a river brick

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117961048A (en) * 2024-04-01 2024-05-03 江苏盛耐新材料有限公司 Quick replacement device of ladle mouth of a river brick
CN117961048B (en) * 2024-04-01 2024-06-07 江苏盛耐新材料有限公司 Quick replacement device of ladle mouth of a river brick

Similar Documents

Publication Publication Date Title
CN218018255U (en) Portable building pipeline installation tool
CN113357421B (en) Conveying pipe connecting device with adjusting function for sewage treatment
CN213290083U (en) Positioning support for pipe joint installation
CN211550728U (en) Corrugated pipe butt joint device
CN219413755U (en) Urban heating power pipeline strutting arrangement
CN218032090U (en) Plugging device
CN218599002U (en) Support frame for pipeline installation
CN216643413U (en) Reducing pipe
CN214699518U (en) Pipeline installation adjusting device for construction
CN214618177U (en) Supporting pipe installation bracket of civil construction
CN210388993U (en) Chemical industry petroleum equipment pipe installation specialized tool
CN212069266U (en) Automatic spraying device for water conservancy pipelines
CN210816581U (en) Novel complex reducing pipeline cleaning device
CN212470566U (en) Clamping device of pipe cutting machine
CN210282197U (en) Rotating frame convenient for petroleum pipeline detection
CN211589829U (en) Auxiliary butt joint valve device
CN210978735U (en) Pipeline installation adjusting device for construction
CN110757087A (en) Pipeline welding tool in complex environment
CN111941307A (en) Butt joint fixer for gas pipeline construction
CN219159711U (en) Pipeline butt joint mechanism
CN211540095U (en) Pipeline welding tool in complex environment
CN221424169U (en) Drain pipe connecting device
CN218453202U (en) Low-temperature vacuum pipeline butt joint equipment
CN219882339U (en) Pipe body convenient to butt joint
CN219854267U (en) Magnetic butt joint device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant