CN217925988U - Positioning device for installing underground water pipe - Google Patents

Positioning device for installing underground water pipe Download PDF

Info

Publication number
CN217925988U
CN217925988U CN202221286258.9U CN202221286258U CN217925988U CN 217925988 U CN217925988 U CN 217925988U CN 202221286258 U CN202221286258 U CN 202221286258U CN 217925988 U CN217925988 U CN 217925988U
Authority
CN
China
Prior art keywords
base
water pipe
underground water
rubber
supporting seat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221286258.9U
Other languages
Chinese (zh)
Inventor
计平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHAANXI HUABIN COAL INDUSTRY CO LTD
Original Assignee
SHAANXI HUABIN COAL INDUSTRY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHAANXI HUABIN COAL INDUSTRY CO LTD filed Critical SHAANXI HUABIN COAL INDUSTRY CO LTD
Priority to CN202221286258.9U priority Critical patent/CN217925988U/en
Application granted granted Critical
Publication of CN217925988U publication Critical patent/CN217925988U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a positioner is used in underground water pipe installation belongs to underground water pipe installation technical field, a positioner is used in underground water pipe installation, the on-line screen storage device comprises a base, the shrinkage pool has been seted up to base one end symmetry, the projection is installed to base other end symmetry, the rubber support is installed to the base top, rubber support top fixedly connected with backup pad, the supporting seat is installed to backup pad top symmetry, the arc wall has been seted up at the supporting seat top, just the arc wall inboard bonds and has the rubber slab, supporting seat bottom symmetry fixedly connected with stand, it can realize, avoids the device to damage because of the pipeline falls the too big impact force of in-process under to through the projection that utilizes base one end installation, peg graft to the inboard of the shrinkage pool that the base other end was seted up, make things convenient for quick butt joint between the device, can be a sharp setting between the messenger's device, thereby can guarantee to lay according to the straight line between the pipeline.

Description

Positioning device for installing underground water pipe
Technical Field
The utility model relates to a downhole pipe installs technical field, and more specifically says, relates to a positioner is used in downhole pipe installation.
Background
The length of single propulsion of the underground water pipes during construction is only about 5 meters, and the central deep-buried water ditch and the operation area of the inspection well are influenced by clearance and limitation of the tunnel after excavation, so that the underground water pipes are difficult to pass by machinery and vehicles, have great influence on tunnel excavation and excavation, have long operation period and restrict timely follow-up of an inverted arch and a secondary lining. If can pinpoint during the installation construction deeply bury the vertical slope of drain pipe, can not only guarantee construction quality, can also accelerate the activity duration, a single line tunnel center deeply bury drain pipe installation positioner in current patent, the technique disclosed in patent application number CN201922383558.3 can solve above-mentioned problem.
However, the existing positioning devices cannot be connected, so that the pipeline cannot be laid linearly when the pipeline is laid, and the pipeline can generate large vibration when being hoisted to the device, so that the device is easily damaged.
SUMMERY OF THE UTILITY MODEL
1. Technical problem to be solved
To the problem that exists among the prior art, the utility model aims to provide a positioner is used in underground pipe installation, it can realize avoiding the device to damage because of the pipeline falls the too big in-process impact force down to through the projection that utilizes base one end installation, peg graft to the inboard of the shrinkage pool that the base other end was seted up, make things convenient for the quick butt joint between the device, make and be a sharp setting between the device, thereby can guarantee to lay according to the straight line between the pipeline.
2. Technical scheme
In order to solve the above problems, the utility model adopts the following technical proposal.
The utility model provides a positioner is used in underground pipe installation, includes the base, the shrinkage pool has been seted up to base one end symmetry, the projection is installed to base other end symmetry, the rubber support is installed to the base top, rubber support top fixedly connected with backup pad, the supporting seat is installed to backup pad top symmetry, the arc wall has been seted up at the supporting seat top, just the arc wall inboard bonds there is the rubber slab, supporting seat bottom symmetry fixedly connected with stand.
Furthermore, one end of the convex column is fixedly connected with a connecting seat, and the connecting seat is connected with the side wall of the base through an expansion bolt.
Furthermore, the concave hole corresponds to the convex column, the inner diameter of the concave hole is matched with the outer diameter of the convex column, and the convex column and the concave hole form an embedded structure.
Further, the rubber support is provided with a plurality of, and is a plurality of base upper surface edge is installed to two bisymmetry of rubber support, the equal fixedly connected with mounting panel in rubber support top and bottom, and the mounting panel is connected with the base through expansion bolts and backup pad respectively.
Furthermore, the upper surface of the rubber plate is provided with anti-skid grains.
Furthermore, the bottom end of the upright post is integrally formed with a mounting seat, the mounting seat is abutted against the upper surface of the support plate, and the mounting seat is connected with the support plate through an expansion bolt.
3. Advantageous effects
Compared with the prior art, the utility model has the advantages of:
(1) This scheme, vibration and earthquake load when can effectually bear the pipeline whereabouts through rubber support and rubber slab, thereby play fine buffering and absorbing effect, avoid the device to damage because of the pipeline falls the in-process impact force under too big, and through the projection that utilizes base one end installation, peg graft to the inboard of the shrinkage pool that the base other end was seted up, thereby link up between two devices mutually, moreover, the steam generator is simple in structure, make things convenient for the quick butt joint between the device, make and to be a sharp setting between the device, thereby can guarantee to lay according to the straight line between the pipeline.
(2) This scheme, through set up anti-skidding line at rubber slab upper surface, when the pipeline contacted with the rubber slab, frictional force between effectual increase pipeline and the rubber slab to pipeline activity when the butt joint between can effectually be avoided to the pipeline.
Drawings
Fig. 1 is a schematic perspective view of the present invention;
fig. 2 is a schematic structural view at another viewing angle of the present invention;
fig. 3 is a schematic view of the supporting seat structure of the present invention.
The numbering in the figures illustrates:
1. a base; 101. concave holes;
2. a convex column; 201. a connecting seat;
3. a rubber support; 301. mounting a plate;
4. a support plate;
5. a supporting seat; 501. a rubber plate; 502. a column; 503. and (7) mounting a seat.
Detailed Description
The technical solution in the embodiment of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiment of the present invention; obviously, the described embodiments are only a part of the embodiments of the present invention, and not all embodiments, and all other embodiments obtained by those skilled in the art without any inventive work are within the scope of the present invention based on the embodiments of the present invention.
Example (b):
referring to fig. 1-3, a positioning device for installing a down-hole pipe comprises a base 1, wherein one end of the base 1 is symmetrically provided with concave holes 101, the other end of the base 1 is symmetrically provided with convex columns 2, a rubber support 3 is arranged above the base 1, a support plate 4 is fixedly connected above the rubber support 3, a support seat 5 is symmetrically arranged above the support plate 4, the top of the support seat 5 is provided with an arc-shaped groove, a rubber plate 501 is bonded on the inner side of the arc-shaped groove, and the bottom of the support seat 5 is symmetrically and fixedly connected with upright columns 502;
after installing the position of pipe laying through with the device, then hoist first section pipeline to the top of device, and the arc wall that supporting seat 5 top set up and the radian looks adaptation of pipeline outer wall, thereby support the pipeline through supporting seat 5, and the arc wall inboard at supporting seat 5 top bonds and has rubber slab 501, consequently when the pipeline is contacting with supporting seat 5, the effectual isolation vibration of usable rubber slab 501 and absorption impact force, and install rubber support 3 through between base 1 and the backup pad 4, vibration and seismic load when consequently can effectually bearing the pipeline whereabouts, thereby play fine buffering and absorbing effect, avoid the device to damage because of the pipeline falls the too big in-process impact force down, after first section pipeline installation is fixed, through the projection 2 of utilizing base 1 one end installation, peg graft to the inboard of shrinkage pool 101 that the base 1 other end was seted up, thereby link up two devices mutually, moreover, the steam generator is simple in structure, make things convenient for the quick butt joint between the device, can be a straight line setting between the messenger's device.
Referring to fig. 1, 2 one end fixedly connected with connecting seats 201 of projection, connecting seat 201 are connected with 1 lateral wall of base through expansion bolts, have opened in advance through 1 lateral wall of base and connecting seat 201 butt department and are equipped with the screw hole, and the via hole that sets up on through base 1 is corresponding with the screw hole that 1 lateral wall of base was seted up to the convenience is installed projection 2.
Referring to fig. 1 and 2, the concave hole 101 corresponds to the convex pillar 2, the inner diameter of the concave hole 101 is matched with the outer diameter of the convex pillar 2, and the convex pillar 2 and the concave hole 101 form an embedded structure, and the convex pillar 2 is inserted into the inner side of the concave hole 101, so that the two devices can be conveniently and rapidly connected together, and the structure is simple and the operation is convenient.
Referring to fig. 1 and 2, the rubber supports 3 are provided with a plurality of rubber supports, the edges of the upper surface of the base 1 are symmetrically arranged on the plurality of rubber supports 3, the top ends and the bottom ends of the rubber supports 3 are fixedly connected with the mounting plate 301, the mounting plate 301 is connected with the base 1 through the support plate 4 and the expansion bolts, and the rubber supports 3 are conveniently and quickly mounted and fixed.
Referring to fig. 1, the upper surface of the rubber plate 501 is provided with anti-slip lines, and the anti-slip lines are arranged on the upper surface of the rubber plate 501, so that when a pipeline is in contact with the rubber plate 501, the friction force between the pipeline and the rubber plate 501 can be effectively increased, and the pipeline can be effectively prevented from moving when being butted.
Referring to fig. 1 and 3, the bottom end of the upright 502 is integrally formed with a mounting seat 503, the mounting seat 503 abuts against the upper surface of the supporting plate 4, and the mounting seat 503 is connected to the supporting plate 4 through an expansion bolt, so that the supporting seat 5 can be conveniently and rapidly mounted and fixed on the supporting plate 4.
When in use: after installing the position of pipe laying through with the device, then hoist first section pipeline to the top of device, and the arc wall that supporting seat 5 top set up and the radian looks adaptation of pipeline outer wall, thereby support the pipeline through supporting seat 5, and the arc wall inboard at supporting seat 5 top bonds there is rubber slab 501, consequently when the pipeline is contacting with supporting seat 5, the effectual isolation vibration of usable rubber slab 501 and absorption impact force, and install rubber support 3 between base 1 and backup pad 4, vibration and seismic load when consequently can effectually bearing the pipeline whereabouts, thereby play fine buffering and absorbing effect, avoid the device to damage because of the pipeline falls the too big impact force of in-process down, after first section pipeline installation is fixed, through the projection 2 of utilizing base 1 one end installation, peg graft to the inboard of shrinkage pool 101 that the base 1 other end was seted up, thereby with linking mutually between two devices, moreover, the steam generator is simple in structure, make things convenient for the quick butt joint between the device, make and can be a sharp setting between the device, thereby can guarantee to carry out according to the straight line between the pipeline.
The above description is only the preferred embodiment of the present invention; the scope of the present invention is not limited thereto. Any person skilled in the art should also be able to cover the technical scope of the present invention by replacing or changing the technical solution and the improvement concept of the present invention with equivalents and modifications within the technical scope of the present invention.

Claims (6)

1. The utility model provides a positioner is used in underground pipe installation which characterized in that: including base (1), shrinkage pool (101) have been seted up to base (1) one end symmetry, projection (2) are installed to base (1) other end symmetry, rubber support (3) are installed to base (1) top, rubber support (3) top fixedly connected with backup pad (4), supporting seat (5) are installed to backup pad (4) top symmetry, the arc wall has been seted up at supporting seat (5) top, just rubber slab (501) have been bonded to the arc wall inboard, supporting seat (5) bottom symmetry fixedly connected with stand (502).
2. The positioning device for installing the underground water pipe according to claim 1, wherein: one end of the convex column (2) is fixedly connected with a connecting seat (201), and the connecting seat (201) is connected with the side wall of the base (1) through an expansion bolt.
3. The positioning device for installing the underground water pipe according to claim 1, wherein: the concave hole (101) corresponds to the convex column (2), the inner diameter of the concave hole (101) is matched with the outer diameter of the convex column (2), and the convex column (2) and the concave hole (101) form an embedded structure.
4. The positioning device for installing the underground water pipe according to claim 1, wherein: rubber support (3) are provided with a plurality ofly, and are a plurality of base (1) upper surface edge is installed to two bisymmetry in rubber support (3), rubber support (3) top and the equal fixedly connected with mounting panel (301) in bottom, and mounting panel (301) are connected with base (1) through expansion bolts and backup pad (4) respectively.
5. The positioning device for installing the underground water pipe according to claim 1, wherein: the upper surface of the rubber plate (501) is provided with anti-skid grains.
6. The positioning device for installing the underground water pipe according to claim 1, wherein: the mounting base (503) is integrally formed at the bottom end of the upright column (502), the mounting base (503) is abutted to the upper surface of the support plate (4), and the mounting base (503) is connected with the support plate (4) through an expansion bolt.
CN202221286258.9U 2022-05-26 2022-05-26 Positioning device for installing underground water pipe Expired - Fee Related CN217925988U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221286258.9U CN217925988U (en) 2022-05-26 2022-05-26 Positioning device for installing underground water pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221286258.9U CN217925988U (en) 2022-05-26 2022-05-26 Positioning device for installing underground water pipe

Publications (1)

Publication Number Publication Date
CN217925988U true CN217925988U (en) 2022-11-29

Family

ID=84178449

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221286258.9U Expired - Fee Related CN217925988U (en) 2022-05-26 2022-05-26 Positioning device for installing underground water pipe

Country Status (1)

Country Link
CN (1) CN217925988U (en)

Similar Documents

Publication Publication Date Title
CN105465481A (en) Construction method for jacking structure of pipe jacking work well
CN205479706U (en) Push pipe work jing ding advances structure
CN217925988U (en) Positioning device for installing underground water pipe
CN202927262U (en) Pipeline installation pillar in oil/gas pipeline tunnel
CN106968164B (en) Cable way bridge abutment
CN218348052U (en) Anti device that floats of mucky soil layer underground piping
JP3557861B2 (en) Basic seismic isolation method for existing structures
JP2006524784A (en) Tube fixing system
CN212405217U (en) Pile foundation underpins structure
CN113338277A (en) Building structure pile foundation reinforcing apparatus
CN113090816A (en) Self-anchored internally-penetrated nodular cast iron pipe installation method
CN211649268U (en) Novel pipe jacking back pipe laying device
CN210531783U (en) Pipe jacking for municipal works
CN217030423U (en) Pre-buried fixed support device of drainage pipe
JP3731975B2 (en) Method and apparatus for positioning a steel pipe column when installing a plug-in type steel pipe column
CN210369987U (en) Anti-falling safety rope device for construction of foundation pit steel enclosing purlin
CN213951813U (en) Permanent-temporary combined channel protection system for metallurgical equipment
CN220849675U (en) Auxiliary guiding device for pipe jacking construction
CN213448065U (en) Bridge beam supports installation leveling shockproof equipment
CN218818610U (en) A conduit fixing support for municipal administration utility tunnel
CN215925613U (en) Bridge settlement support
CN207316232U (en) A kind of line holder structure
CN217054359U (en) Template clamping device for building reinforcement
CN218845305U (en) Protection structure for existing underground pipeline in foundation pit
CN216077144U (en) Concrete filled steel tube support and anchor rod supporting device in coordination

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20221129