CN217870462U - Anchor rope shutoff pier nose connection structure - Google Patents

Anchor rope shutoff pier nose connection structure Download PDF

Info

Publication number
CN217870462U
CN217870462U CN202222241433.9U CN202222241433U CN217870462U CN 217870462 U CN217870462 U CN 217870462U CN 202222241433 U CN202222241433 U CN 202222241433U CN 217870462 U CN217870462 U CN 217870462U
Authority
CN
China
Prior art keywords
anchor
shutoff
connection structure
muscle portion
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222241433.9U
Other languages
Chinese (zh)
Inventor
王良木
张方晗
刘恒新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Survey Design And Research Institute Co ltd
Original Assignee
Hangzhou Survey Design And Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Survey Design And Research Institute Co ltd filed Critical Hangzhou Survey Design And Research Institute Co ltd
Priority to CN202222241433.9U priority Critical patent/CN217870462U/en
Application granted granted Critical
Publication of CN217870462U publication Critical patent/CN217870462U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model belongs to the technical field of the technique of engineering construction and specifically relates to a anchor rope shutoff pier nose connection structure is related to, it includes anchor slab, ground tackle and anchor pier, anchor slab one end butt is on the face of accepting of mounted position, the one end of accepting the face is kept away from at the anchor slab to the ground tackle setting, the anchor pier includes body and a plurality of anchor hook bar, the body is formed by concrete placement, the body bottom covers in the anchor slab, the area on body top is less than the area of body bottom, the anchor hook bar is located this internally, the anchor hook bar tip fixed connection is on the anchor slab. This application has the effect that the condition that reduces the anchor pier and appear becoming flexible or drop appears.

Description

Anchor rope shutoff pier nose connection structure
Technical Field
The application relates to the technical field of engineering construction, in particular to an anchor cable plugging pier head connecting structure.
Background
In the supporting engineering in construction, the prestressed anchor pier is widely used, and the prestressed anchor pier mainly has the function of reinforcing an underground cavern, a side slope, a foundation pit and the like by suspending and prepressing surrounding rocks so as to ensure that the engineering is self-stable.
Traditional prestressed anchorage pier is in the use, because of there is not effective connected node between the ground tackle of anchor rope and the anchor pier for the anchor pier can appear becoming flexible or the condition that drops when the anchor pier stress appears changing in the construction or after the construction is accomplished in the anchor pier, and the anchor pier drops under this condition can receive great influence to the anticorrosive effect of steel strand wires.
SUMMERY OF THE UTILITY MODEL
In order to reduce the anchor pier and appear not hard up or the condition that drops, this application provides an anchor rope shutoff pier nose connection structure.
The application provides a pair of anchor rope shutoff pier nose connection structure adopts following technical scheme:
the utility model provides an anchor rope shutoff pier nose connection structure, includes the anchor rope, the anchor rope includes anchor slab, ground tackle and steel strand wires, anchor slab one end butt is on the face of accepting of mounted position, the ground tackle sets up the one end of accepting the face of keeping away from at the anchor slab, steel strand wires pass respectively ground tackle with the anchor slab still includes the anchor pier, the anchor pier includes that body and a plurality of anchor are bent to collude the muscle, the body is formed by concrete placement, the body cover in the anchor slab with the ground tackle, steel strand wires tip salient in ground tackle just is located this internal, the anchor is bent to collude the muscle and is located this internal and clearance fit, the anchor is bent to collude muscle tip fixed connection in on the anchor slab.
By adopting the technical scheme, after the steel strand is installed on the anchor plate and the anchorage device, the anchoring hook rib is welded on the anchor plate, and concrete is used for grouting to form the corresponding anchor pier. Like this when the anchor block carries out the shutoff to ground tackle, anchor slab and the steel strand wires of naked hourglass outside the ground tackle fixed, the anchor curved hook muscle sets up at this internally for the body has the drawknot point, has strengthened the body in the anchor block and ground tackle, anchor slab and the naked steel strand wires of leaking outside the ground tackle be connected, makes the anchor block of concrete can not drop or become flexible.
Preferably, the curved muscle of colluding of anchor divide into first muscle portion, second muscle portion and third muscle portion, first muscle portion fixed connection in the anchor slab, second muscle portion with be the angle setting between the first muscle portion, second muscle portion with the side of body is parallel, third muscle portion with second muscle portion is angle setting and inwards contracts.
Through adopting above-mentioned technical scheme, set up the shape of the curved muscle of colluding of inside buckled anchor in order to laminate the body, effectively support the body.
Preferably, an angle between the first rib and the second rib is an acute angle, and an angle between the second rib and the second rib is a right angle.
By adopting the technical scheme, after the angle is set, the anchoring bent hook rib has a better supporting effect.
Preferably, the anchoring bent hook ribs are four in number and are wound in the body at the same interval angle.
Through adopting above-mentioned technical scheme, four anchor are bent to collude the muscle and improve the support effect.
Preferably, the anchor plate is square, and the four anchoring bent hook ribs are respectively and fixedly connected to four corners of the anchor plate.
By adopting the technical scheme, the anchoring bent hook ribs are arranged at the four corners of the anchor plate, and the stress is uniform.
Preferably, the anchorage device is provided with a plurality of first mounting holes for penetrating steel strands, the anchor plate is provided with a plurality of second mounting holes for penetrating steel strands, the first mounting holes and the second mounting holes are correspondingly arranged, and the first mounting holes and the second mounting holes are uniformly wound around the center line of the anchorage device.
Preferably, the anchorage device is provided with a clamping piece mounting piece for fixing the steel strand, the thickness of one end, far away from the anchor plate, of the clamping piece mounting piece is larger than that of one end, close to the anchor plate, of the clamping piece mounting piece, and the clamping piece mounting piece is in clearance interference fit with the first mounting hole and the steel strand.
Preferably, the anchoring hook rib is made of steel.
Preferably, the anchor plate is provided with an asphalt coating.
By adopting the technical scheme, the asphalt coating is used for corrosion prevention.
In summary, the present application includes at least one of the following beneficial technical effects:
1. after the steel strand wires are installed on the anchor plate and the anchorage device, the anchoring hook ribs are welded on the anchor plate, and concrete is used for grouting to form the corresponding anchor pier. Therefore, when the anchor pier blocks and fixes the anchorage device, the anchor plate and the steel strand which is exposed outside the anchorage device, the anchoring bent hook rib is arranged in the body, so that the body has a pulling node, the connection between the body in the anchor pier and the anchorage device, between the body in the anchor pier and the steel strand which is exposed outside the anchorage device and between the body in the anchor pier and the steel strand is enhanced, and the concrete anchor pier cannot fall off or become loose;
2. the anchoring hook rib bent inwards is arranged to fit the shape of the body, so that the body is effectively supported;
3. the anchoring bent hook ribs are arranged at the four corners of the anchor plate, so that the stress is uniform.
Drawings
FIG. 1 is a schematic view of the overall structure of the embodiment of the present application without including a body;
FIG. 2 is a schematic diagram of the overall structure of the embodiment of the present application when including a body;
FIG. 3 is a top view of an embodiment of the present application including a body;
FIG. 4 isbase:Sub>A schematic cross-sectional view taken along line A-A of FIG. 3;
fig. 5 is a partially enlarged schematic view of a portion a in fig. 4.
Description of reference numerals: 1. an anchor plate; 2. an anchorage device; 3. anchoring piers; 31. a body; 32. anchoring the bent hook rib; 321. a first rib portion; 322. a second rib portion; 323. a third rib portion; 4. a clip mounting member; 5. and (4) steel strands.
Detailed Description
The present application is described in further detail below with reference to figures 1-5.
The embodiment of the application discloses anchor rope shutoff pier nose connection structure.
As shown in fig. 1 and 2, an anchor cable plugging pier head connecting structure comprises an anchor cable and an anchor pier 3, wherein the anchor cable comprises an anchor plate 1, an anchor device 2 and steel strands 5.
The anchor plate 1 is a square, in this case a 300mm 20mm steel plate. One end of the steel plate is connected to a slope with a corresponding anchor hole in construction in an abutting mode, and an asphalt coating used for corrosion prevention is arranged on the anchor plate 1.
The anchor 2 is cylindrical, and the anchor 2 is arranged at the center of one end of the anchor plate 1, which is far away from the slope bearing surface.
The anchor plate 1 is used for being mutually abutted with the bearing surface to bear the prestress of the steel strand 5, and the anchorage device 2 is used for fixedly mounting the steel strand 5.
As shown in fig. 3 and 4, the anchorage device 2 is provided with a plurality of first mounting holes for the steel strands 5 to penetrate through, the anchor plate 1 is provided with a plurality of second mounting holes for the steel strands 5 to penetrate through, and the first mounting holes and the second mounting holes are arranged correspondingly. The number of the first mounting holes is 9, one of the first mounting holes is located at the center of the anchor 2, the other 8 first mounting holes are uniformly arranged around the periphery along the center line of the anchor 2, and the distance and the angle between every two adjacent first mounting holes are the same. Therefore, after the steel strand 5 is installed, the stress is uniform, and the steel strand 5 installed at a hole site is prevented from being broken due to more stress caused by the deviation of the hole site at a certain position. The opening position of the second mounting hole corresponds to the opening position of the first mounting hole.
As shown in fig. 1 and 2, the anchor block 3 includes a body 31 and a plurality of anchoring hooks 32, the body 31 is formed by pouring concrete and has a trapezoidal shape, the top end and the bottom end of the body 31 are both in the positive direction, and the area of the top end is smaller than that of the bottom end. The bottom end of the body 31 covers the entire anchor plate 1 and has an area larger than that of the anchor plate 1. The anchoring hook rib 32 is located in the body 31 and used for supporting the body 31, and the end part of the anchoring hook rib 32 is fixedly connected to the anchor plate 1.
The anchoring bent rib 32 is a round bar of 6 or 8 in this application.
The body 31 uses fine stone concrete with grade not lower than C30.
By the method, after the steel strand 5 is installed on the anchor plate 1 and the anchorage device 2, the anchoring bent hook rib 32 is welded on the anchor plate 1, and concrete is used for grouting to form the corresponding anchor pier 3. Make anchor pier 3 can be to ground tackle 2, anchor slab 1 and naked hourglass carry out the shutoff with steel strand wires 5 outside the ground tackle fixedly, at ground tackle 2, anchor slab 1 has on the face of accepting through anchor pier 3 and slope the junction forms a whole, simultaneously because in the construction, need be at ground tackle 2, anchor slab 1 and naked hourglass scribble anticorrosive material such as pitch and butter on the steel strand wires 5 outside the ground tackle, anchor pier 3 and anchor slab 1 like this, there is the interlayer between ground tackle 2, lead to anchor pier 3 to drop very easily, the event collude muscle 32 through buckling the anchor and sets up at this internally, make the body have the drawknot point, body 31 and ground tackle 2 in the anchor pier 3 have been strengthened, anchor slab 1 and the connection of the steel strand wires 5 of naked hourglass outside the ground tackle, make the anchor pier 3 of concrete can not drop or become flexible.
As shown in fig. 1 and 4, the anchoring curved-hooking rib 32 includes a first rib portion 321, a second rib portion 322 and a third rib portion 323, the first rib portion 321 is fixed on the anchor plate 1, and the first rib portion 321 and the anchor plate 1 are parallel to each other. Second muscle 322 and first muscle 321 are the acute angle setting between, and second muscle 322 is parallel with the adjacent side of body 31, and third muscle 323 and second muscle 322 are the right angle setting between. Through the setting of the inner inclination angle, the rudiment framework of the trapezoid body is formed when the body 31 is poured, and the best supporting effect of the anchor pier 3 with the shape can be obtained after the analysis of the supporting stress.
The specific angle and length can be changed according to the specification of the anchor pier and the design size requirement of plugging.
As shown in fig. 1 and 2, in one embodiment, four anchoring hooks 32 are provided, and four anchoring hooks 32 are wound around the body 31 at equal intervals. Furthermore, because the anchor plate 1 is square, the four anchoring bent-hooking ribs 32 are respectively arranged at the four corners of the anchor plate 1, so that the strength distribution is more uniform.
As shown in fig. 4 and 5, when the steel strand 5 is installed, in order to ensure the stability of the steel strand 5, a clip installation part 4 is further arranged on the anchorage device 2, the thickness of one end, away from the anchor plate 1, of the clip installation part 4 is greater than the thickness of one end, close to the anchor plate 1, of the clip installation part 4, the clip installation part 4 is in interference fit with the first installation hole, after the steel strand 5 passes through the first installation hole and the second installation hole respectively, the end, with smaller thickness, of the clip installation part 4 is inserted into a gap between the first installation hole and the steel strand 5, the thickness of the other end is larger, when the steel strand 5 needs to move inwards due to stress, due to the interference fit between the clip installation part 4 and the first installation hole as well as the steel strand 5, the tension is tighter, a certain creep occurs under the action of prestress, the anticorrosion effect is ensured, and a certain protective layer space is reserved.
Further, in order to avoid the rib falling condition after concrete pouring, at least 25mm of gap is left between the body 31 and the anchoring hook rib 32 to be used as a protective layer.
The implementation principle is as follows:
after the steel strand 5 is installed on the anchor plate 1 and the anchorage device 2, the anchoring bent hook rib 32 is welded on the anchor plate 1, and concrete is used for grouting to form the corresponding anchor pier 3. Make anchor pier 3 can be to ground tackle 2, anchor slab 1 and the steel strand wires 5 of naked hourglass outside ground tackle block up fixedly, at ground tackle 2, anchor slab 1 has had the junction to form a whole on the face of accepting through anchor pier 3 and slope, simultaneously because in the construction, need be at ground tackle 2, anchor slab 1 and naked hourglass scribble anticorrosive material such as pitch and butter on the steel strand wires 5 outside ground tackle, anchor pier 3 and anchor slab 1 like this, there is the interlayer between ground tackle 2, lead to anchor pier 3 to drop very easily, the event colludes muscle 32 through with the anchor bend and sets up originally internally, make the body have the bonding point, body 31 and ground tackle 2 in the anchor pier 3 have been strengthened, anchor slab 1 and the naked connection of leaking the steel strand wires 5 outside ground tackle, make the anchor pier 3 of concrete can not drop or become flexible.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: equivalent changes in structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (9)

1. The utility model provides an anchor rope shutoff pier nose connection structure, includes the anchor rope, the anchor rope includes anchor slab (1), ground tackle (2) and steel strand wires (5), anchor slab (1) one end butt is on the face of accepting of mounted position, ground tackle (2) set up the one end of accepting the face keeping away from in anchor slab (1), steel strand wires (5) pass respectively ground tackle (2) with anchor slab (1), its characterized in that: still include anchor block (3), anchor block (3) include body (31) and a plurality of anchor curved bar (32) of colluding, body (31) are formed by concrete placement, body (31) cover in anchor slab (1) with ground tackle (2), steel strand wires (5) tip salient in ground tackle (2) just are located in body (31), the anchor curved bar (32) of colluding is located body (31) interior and clearance fit, the anchor curved bar (32) end fixed connection of colluding in on anchor slab (1).
2. The anchor rope shutoff pier nose connection structure of claim 1, wherein: the curved muscle (32) of colluding of anchor divide into first muscle portion (321), second muscle portion (322) and third muscle portion (323), first muscle portion (321) fixed connection in anchor slab (1), second muscle portion (322) with be the angle setting between first muscle portion (321), second muscle portion (322) with the side of body (31) is parallel, third muscle portion (323) with second muscle portion (322) are the angle setting and inwards shrink.
3. The anchor rope shutoff pier nose connection structure of claim 2, wherein: the angle between first muscle portion (321) and second muscle portion (322) is the acute angle, the angle between second muscle portion (322) and second muscle portion (322) is the right angle.
4. The anchor rope shutoff pier nose connection structure of claim 3, wherein: the four anchoring bent hook ribs (32) are arranged in the body (31) in a winding mode, and the four anchoring bent hook ribs (32) are wound at the same interval and at the same angle.
5. The anchor rope shutoff pier nose connection structure of claim 4, wherein: the anchor plate (1) is square, and the four anchoring bent hook ribs (32) are fixedly connected to four corners of the anchor plate (1) respectively.
6. The anchor rope shutoff pier nose connection structure of claim 1, wherein: a plurality of first mounting holes used for penetrating the steel strands (5) are formed in the anchor (2), a plurality of second mounting holes used for penetrating the steel strands (5) are formed in the anchor plate (1), the first mounting holes and the second mounting holes are correspondingly arranged, and the first mounting holes and the second mounting holes are uniformly arranged around the center line of the anchor (2).
7. The anchor rope shutoff pier nose connection structure of claim 6, wherein: be provided with clamping piece installed part (4) that are used for fixed steel strand wires (5) on ground tackle (2), clamping piece installed part (4) are kept away from the one end thickness of anchor slab (1) is greater than and is close to the thickness of the one end of anchor slab (1), and with the clearance interference fit between first mounting hole and steel strand wires (5).
8. The anchor rope shutoff pier nose connection structure of claim 5, wherein: the anchoring bent hook rib (32) is made of steel.
9. The anchor rope shutoff pier nose connection structure of claim 1, wherein: and the anchor plate (1) is provided with an asphalt coating.
CN202222241433.9U 2022-08-24 2022-08-24 Anchor rope shutoff pier nose connection structure Active CN217870462U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222241433.9U CN217870462U (en) 2022-08-24 2022-08-24 Anchor rope shutoff pier nose connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222241433.9U CN217870462U (en) 2022-08-24 2022-08-24 Anchor rope shutoff pier nose connection structure

Publications (1)

Publication Number Publication Date
CN217870462U true CN217870462U (en) 2022-11-22

Family

ID=84078736

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222241433.9U Active CN217870462U (en) 2022-08-24 2022-08-24 Anchor rope shutoff pier nose connection structure

Country Status (1)

Country Link
CN (1) CN217870462U (en)

Similar Documents

Publication Publication Date Title
CN106869012B (en) Using the prefabricated thin-wall bent cap of prestressing with bond system
US7523924B2 (en) Devices, systems, and methods for reinforcing concrete and/or asphalt cement
JP2007277891A (en) Shaft skeleton, shaft, segment and construction method of shaft
CN111254955A (en) Prestressed anchor cable frame beam device suitable for stability of strongly weathered rock slope
CN110055979A (en) For the precast prestressed concrete anchor pier of slope reinforcement and production and construction method
KR100817901B1 (en) Reinforced Earth Retaining Wall Structure of Perforated Slope
CN217870462U (en) Anchor rope shutoff pier nose connection structure
WO2011161493A1 (en) Reinforced soil structure
JP4630851B2 (en) Anchor for slope
CN208486272U (en) A kind of constructing structure of two-tube diagonal brace deep basal pit
CN108018877B (en) Prefabricated assembly type pipe gallery assembling device and assembling method
CN218346208U (en) Permanent side slope supporting structure based on reinforced concrete pile
CN216239882U (en) Connecting node structure is implanted to roof beam slab transformation anchor bar
CN110067251A (en) For the prefabricated reinforced concrete anchor pier of slope reinforcement and production and construction method
CN212316985U (en) Retaining wall foundation structure
CN212026273U (en) Slope prestress anchoring device of non-steel waist beam
JP2571751B2 (en) Pier
CN213653481U (en) Prestressed anchor cable frame beam device suitable for stability of strongly weathered rock slope
CN111809521A (en) Tunnel type anchorage structure for cable crane and construction method thereof
CN210066763U (en) Foundation pit side wall structure reinforcing and supporting device
CN206723592U (en) For protecting the structural member of submerged pipeline
CN218757624U (en) Zipper type prefabricated underground continuous wall joint
JPS6092518A (en) Connection of pile heads under water
CN218540431U (en) Safety protection platform equipment suitable for construction of pier column in water
CN213572033U (en) Retaining wall supporting construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant