CN217685574U - Refrigeration air supply arrangement for industrial factory building - Google Patents

Refrigeration air supply arrangement for industrial factory building Download PDF

Info

Publication number
CN217685574U
CN217685574U CN202221423556.8U CN202221423556U CN217685574U CN 217685574 U CN217685574 U CN 217685574U CN 202221423556 U CN202221423556 U CN 202221423556U CN 217685574 U CN217685574 U CN 217685574U
Authority
CN
China
Prior art keywords
air
factory building
dryer
blower body
industrial factory
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221423556.8U
Other languages
Chinese (zh)
Inventor
张军
张浩昀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Lvshi Refrigeration Engineering Co ltd
Original Assignee
Shanghai Lvshi Refrigeration Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Lvshi Refrigeration Engineering Co ltd filed Critical Shanghai Lvshi Refrigeration Engineering Co ltd
Priority to CN202221423556.8U priority Critical patent/CN217685574U/en
Application granted granted Critical
Publication of CN217685574U publication Critical patent/CN217685574U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Air-Conditioning Room Units, And Self-Contained Units In General (AREA)

Abstract

The utility model discloses an industry refrigeration technology field's an industry factory building is with refrigeration air supply arrangement, including the forced draught blower body, the top of forced draught blower body is connected with the holding plate, and department is fixed with the jib in the middle of the top of holding plate, central dryer and reposition of redundant personnel dryer are installed to the bottom of forced draught blower body, and the connection of the bottom fixedly connected with symmetry of forced draught blower body is followed, connects along setting up with the axle center with the reposition of redundant personnel dryer, connects the bottom on edge and is fixed with the retainer plate, and threaded hole has been seted up to the bottom of retainer plate. The utility model discloses a reposition of redundant personnel dryer cooperation guide way is used for the multi-angle to carry air conditioning, and gaseous entering guide way is interior to see off through the hold in the end, and the accessible accelerates the air current velocity of flow and reduces the air current temperature on the one hand of the end to offset the heat that the air extractor during operation produced, the device can distribute fast inside the factory building with single wind direction air current more evenly through setting up many multi-direction guide ways.

Description

Refrigeration air supply arrangement for industrial factory building
Technical Field
The utility model relates to an industry refrigeration technology field specifically is a refrigeration air supply arrangement for industrial factory building.
Background
The industrial factory building refers to various houses which are directly used for production or matched for production, and comprises a main workshop, an auxiliary house and an auxiliary facility house. In order to adjust the temperature of the plant, the interior of the plant is often required to be refrigerated and supplied with air.
But current refrigeration air supply arrangement is because lack the drainage subassembly, and cold air circulation intensity is poor in leading to the factory building, based on this, the utility model discloses an industry is refrigeration air supply arrangement for factory building to solve above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an industrial factory building is with refrigeration air supply arrangement to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides an industrial factory building is with refrigeration air supply arrangement, includes the forced draught blower body, and the top of forced draught blower body is connected with the holding plate, and department is fixed with the jib in the middle of the top of holding plate, central dryer and reposition of redundant personnel dryer are installed to the bottom of forced draught blower body, and the connection of the bottom fixedly connected with symmetry of forced draught blower body is followed, connects along setting up with the same axle center of reposition of redundant personnel dryer, connects the bottom on edge and is fixed with the retainer plate, and the threaded hole is seted up to the bottom of retainer plate, and the bottom detachable connection of retainer plate has the collar, and the bottom fixedly connected with guide way of retainer plate, guide way's side is connected with the application of force pole, and guide way's one end is fixed with the finish, and the opening part of finish is connected with the position circle, and the inside of position circle runs through there is the air extractor.
Preferably, four corners of the top of the blower body are respectively connected with a tension reinforcing rod, and expansion bolts penetrate through internal threads of the tension reinforcing rod.
Preferably, the bottom of the blower body is connected with a central guide pipe, and the central guide pipe and the central air duct are coaxial.
Preferably, the contact end is clamped on the inner wall of the connecting edge in a tangent manner.
Preferably, the contact end is a hollow hard tube, and the inner diameter of the contact end is not less than the diameter of the split air duct.
Preferably, the closing end is a hollow conical tube, and the end of the closing end, which is far away from the guide channel, is a contraction opening.
Preferably, the input end of the air pump is electrically connected with an external power supply.
Compared with the prior art, the beneficial effects of the utility model are that:
(1) The utility model discloses a reposition of redundant personnel dryer cooperates the guide way and is used for the multi-angle to carry air conditioning, and gas passes through the closing end and sees off in getting into the guide way, and the closing end can reduce the air current temperature through accelerating the air current velocity on the one hand to offset the heat that the air extractor during operation produced, the device can distribute single wind direction air current inside the factory building more evenly fast through setting up many multi-direction guide ways, thereby promote the circulation intensity of air current in the factory building;
(2) The utility model discloses a pulling force stiffener is used for strengthening the fixed of jib, promotes the installation stability of forced draught blower body, and through setting up central honeycomb duct and central dryer with the axle center, can avoid central honeycomb duct to cause the central dryer to shelter from, has guaranteed the smooth circulation of air current.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is an exploded view of the three-dimensional structure of the refrigerating and air-supplying device for industrial plants;
FIG. 2 is a bottom view of the refrigerating and air-supplying apparatus for industrial factory building;
fig. 3 is the utility model discloses industry factory building is with refrigeration air supply arrangement's reposition of redundant personnel dryer structure chart.
In the drawings, the components represented by the respective reference numerals are listed below:
1. a blower body; 2. a holding plate; 3. a tension reinforcement bar; 4. a central air duct; 5. a boom; 6. a split air duct; 7. a connecting edge; 8. a fixed ring; 9. a threaded hole; 10. a contact end; 11. a mounting ring; 12. a guide channel; 13. a force application rod; 14. a closing end; 15. positioning rings; 16. an air extractor; 17. a central flow guide pipe.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person skilled in the art without making creative efforts belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: a refrigeration air supply device for an industrial factory building comprises an air supply device body 1, wherein the top of the air supply device body 1 is connected with a retaining plate 2, a suspender 5 is fixed in the middle of the top of the retaining plate 2, a central air duct 4 and a shunt air duct 6 are installed at the bottom of the air supply device body 1, the bottom of the air supply device body 1 is fixedly connected with a symmetrical connecting edge 7, a contact end 10 is tangentially clamped on the inner wall of the connecting edge 7, the connecting edge 7 and the shunt air duct 6 are coaxially arranged, a fixing ring 8 is fixed at the bottom of the connecting edge 7, a threaded hole 9 is formed in the bottom of the fixing ring 8, a mounting ring 11 is detachably connected at the bottom of the fixing ring 8, a guide channel 12 is fixedly connected at the bottom of the mounting ring 11, a force applying rod 13 is connected to the side surface of the guide channel 12, a closing end 14 is fixed at one end of the guide channel 12, a positioning ring 15 is connected at the opening of the closing end 14, an air extractor 16 penetrates through the inside of the positioning ring 15, the input end of the air extractor 16 is electrically connected with an external power supply, and the bottom of the air supply device body 1 is connected with a central guide pipe 17;
wherein, the forced draught blower body 1 is used for supplying air, central honeycomb duct 17 is used for the air current that vertical drainage center dryer 4 blew out, reposition of redundant personnel dryer 6 cooperation guiding channel 12 is used for multi-angle air conditioning of carrying simultaneously, during the connection, contact jaw 10 is tangent with the inner wall of connecting along 7, surround completely to the side of reposition of redundant personnel dryer 6, prevent gas leakage, gaseous entering guiding channel 12 is interior to send out through the hold end 14, hold end 14 accessible on the one hand accelerates the air current velocity of flow and reduces the air current temperature, thereby offset the heat that air extractor 16 during operation produced, the device is through setting up many multi-direction guiding channel 12, can distribute fast inside the factory building with single wind direction air current more evenly.
Referring to fig. 1-3, four corners of the top of the blower body 1 are respectively connected with a tension reinforcing rod 3, an expansion bolt penetrates through an internal thread of the tension reinforcing rod 3, the central duct 17 and the central duct 4 are coaxial, the contact end 10 is a hollow hard pipe, the inner diameter of the contact end 10 is not smaller than the diameter of the splitter duct 6, the closing end 14 is a hollow conical pipe, and one end of the closing end 14, which is far away from the guide channel 12, is a contraction port;
wherein, the tensile force stiffener 3 is used for strengthening the fixed of jib 5, promotes the installation stability of forced draught blower body 1, through setting up central honeycomb duct 17 and central dryer 4 coaxial center, can avoid central honeycomb duct 17 to lead to the fact to shelter from central dryer 4, has guaranteed the smooth circulation of air current.
The holistic theory of operation does, and during the use, contact tip 10 is tangent with the inner wall of connecting along 7, surrounds the side of reposition of redundant personnel dryer 6 entirely, prevents gas leakage, and gas gets into in the guide way 12 and sends out through the throat end 14, and the throat end 14 accessible accelerates the air current velocity of flow on the one hand and reduces the air current temperature to offset the heat that air extractor 16 during operation produced.
In the description herein, references to the description of "one embodiment," "an example," "a specific example," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The preferred embodiments of the present invention disclosed above are intended to aid in the description of the invention. The preferred embodiments are not intended to be exhaustive or to limit the invention to the precise forms disclosed. Obviously, many modifications and variations are possible in light of the above teaching. The embodiments were chosen and described in order to best explain the principles of the invention and its practical applications, to thereby enable others skilled in the art to best understand the invention for and utilize the invention. The present invention is limited only by the claims and their full scope and equivalents.

Claims (7)

1. The utility model provides an industry factory building is with refrigeration air supply arrangement, includes blower body (1), and the top of blower body (1) is connected with keeper plate (2), and department is fixed with jib (5), its characterized in that in the middle of the top of keeper plate (2): center dryer (4) and reposition of redundant personnel dryer (6) are installed to the bottom of forced draught blower body (1), the connection of the bottom fixedly connected with symmetry of forced draught blower body (1) is along (7), connect and set up with the axle center along (7) and reposition of redundant personnel dryer (6), the bottom of connecting along (7) is fixed with retainer plate (8), threaded hole (9) have been seted up to the bottom of retainer plate (8), the bottom detachable connection of retainer plate (8) has collar (11), the bottom fixedly connected with guide way (12) of collar (11), the side of guide way (12) is connected with application of force pole (13), the one end of guide way (12) is fixed with the end of ending (14), the opening part of end of ending (14) is connected with position circle (15), the inside of position circle (15) is run through there is air extractor (16).
2. The cooling air supply device for the industrial factory building according to claim 1, characterized in that: four corners of the top of the blower body (1) are respectively connected with a tension reinforcing rod (3), and expansion bolts penetrate through internal threads of the tension reinforcing rod (3).
3. The refrigerating and air-supplying device for the industrial factory building, as claimed in claim 1, is characterized in that: the bottom of the air feeder body (1) is connected with a central guide pipe (17), and the central guide pipe (17) and the central air duct (4) are coaxial.
4. The refrigerating and air-supplying device for the industrial factory building, as claimed in claim 1, is characterized in that: the inner wall of the connecting edge (7) is tangentially clamped with a contact end (10).
5. The cooling air supply device for the industrial factory building according to claim 4, characterized in that: the contact end (10) is a hollow hard tube, and the inner diameter of the contact end (10) is not smaller than the diameter of the split air cylinder (6).
6. The refrigerating and air-supplying device for the industrial factory building, as claimed in claim 1, is characterized in that: the closing end (14) is a hollow conical tube, and one end of the closing end (14) far away from the guide channel (12) is a closing opening.
7. The refrigerating and air-supplying device for the industrial factory building, as claimed in claim 1, is characterized in that: the input end of the air pump (16) is electrically connected with an external power supply.
CN202221423556.8U 2022-06-08 2022-06-08 Refrigeration air supply arrangement for industrial factory building Active CN217685574U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221423556.8U CN217685574U (en) 2022-06-08 2022-06-08 Refrigeration air supply arrangement for industrial factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221423556.8U CN217685574U (en) 2022-06-08 2022-06-08 Refrigeration air supply arrangement for industrial factory building

Publications (1)

Publication Number Publication Date
CN217685574U true CN217685574U (en) 2022-10-28

Family

ID=83708008

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221423556.8U Active CN217685574U (en) 2022-06-08 2022-06-08 Refrigeration air supply arrangement for industrial factory building

Country Status (1)

Country Link
CN (1) CN217685574U (en)

Similar Documents

Publication Publication Date Title
CN217685574U (en) Refrigeration air supply arrangement for industrial factory building
CN108716023A (en) A kind of meltblown beam prepared for nanofiber
CN109972329A (en) A kind of dedicated production tooling of high-strength carbon fiber
CN216109837U (en) Concrete automatic spray curing means suitable for aluminum alloy template construction technology
CN108953795B (en) Quick joint for sprinkling irrigation
CN2195814Y (en) Automatic cable clamp
WO2014205758A1 (en) Multi-cleaning media-switching valve
CN201329319Y (en) Injector with inspection window
CN211451468U (en) Air conditioner refrigerant distributor
CN214579483U (en) Easy-to-assemble pipeline connector for ventilation of clean room
CN206439991U (en) Spherical air port and the attachment means of steel pipe
CN208920821U (en) A kind of blowing dryer
CN207237137U (en) A kind of sprinkler connecting bend
CN218175219U (en) Bidirectional air locking device of spandex spinning channel
CN216382941U (en) Portable air duct structure for fan
CN206244944U (en) Improved ring blowing device wind pushing mechanism
CN216199915U (en) Plain type bearing rapid cooling device
CN2826117Y (en) Connecting tube adapter structure for indoor unit and outdoor unit of air conditioner
CN218627712U (en) Tunnel cave high temperature formation of image viewing device
CN219570943U (en) Energy storage liquid cooling pipeline seven-way valve assembly
CN219943250U (en) Air blowing nozzle and air blowing device
CN215380391U (en) One-machine multi-shed flower mushroom planting system
CN220755359U (en) Integrated cooling integrated block with atomization function
CN215302584U (en) Auxiliary device for garden machinery insecticide spraying
CN210637649U (en) Temperature-resistant and corrosion-resistant non-metal flexible connector

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant