CN217600645U - Stable heat recovery coke oven vault structure of easily constructing - Google Patents

Stable heat recovery coke oven vault structure of easily constructing Download PDF

Info

Publication number
CN217600645U
CN217600645U CN202221213480.6U CN202221213480U CN217600645U CN 217600645 U CN217600645 U CN 217600645U CN 202221213480 U CN202221213480 U CN 202221213480U CN 217600645 U CN217600645 U CN 217600645U
Authority
CN
China
Prior art keywords
brick
bricks
vault
main wall
heat recovery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221213480.6U
Other languages
Chinese (zh)
Inventor
耿宁
郑彭
牛聪
赵殿辉
李鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Acre Coking and Refractory Engineering Consulting Corp MCC
Original Assignee
Acre Coking and Refractory Engineering Consulting Corp MCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Acre Coking and Refractory Engineering Consulting Corp MCC filed Critical Acre Coking and Refractory Engineering Consulting Corp MCC
Priority to CN202221213480.6U priority Critical patent/CN217600645U/en
Application granted granted Critical
Publication of CN217600645U publication Critical patent/CN217600645U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P20/00Technologies relating to chemical industry
    • Y02P20/10Process efficiency
    • Y02P20/129Energy recovery, e.g. by cogeneration, H2recovery or pressure recovery turbines

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The utility model relates to a heat recovery coke oven technical field especially relates to a stabilize heat recovery coke oven vault structure of easy construction. The main wall and the vault are built by main wall leather bricks, arch foot bricks, roof spanning bricks, arch roof bricks and positioning bricks; the main wall and vault combining position set up double-deck concave-convex cooperation locking structure, and main wall skin brick passes through concave-convex structure interlock locking with striding the crown brick, and the location brick between two hunch foot bricks passes through concave-convex structure interlock locking with striding the crown brick. Greatly increased the stability of furnace roof structure, and the locating brick makes the hunch foot brick fixed by the main wall in the horizontal direction, when building single carbomorphism room hunch crown brick, the position of hunch foot brick can not take place to slide and skew yet, and convenient construction has saved a large amount of manpower and materials.

Description

Stable heat recovery coke oven vault structure of easily constructing
Technical Field
The utility model relates to a heat recovery coke oven technical field especially relates to a stabilize heat recovery coke oven vault structure of easy construction.
Background
The current heat recovery coke oven is generally composed of a furnace bottom, a multi-connected flame path, a main wall, a carbonization chamber and a furnace top. The coking process of the heat recovery coke oven comprises direct heating and indirect heating, coal materials are pyrolyzed in a coking chamber to generate combustible gas, part of the combustible gas is mixed with air entering from the top of the coking chamber and then is combusted, the coal materials are directly heated, and the residual combustible gas which is not fully combusted enters a descending channel in a main wall through holes in the upper part of the main wall, flows from top to bottom, flows out of the descending channel through holes in the lower part of the main wall and flows into a multi-connected flame path in the lower part of the coal materials. In the multi-connected flame path, combustible gas and air entering from the sealing wall are mixed and then fully combusted, heat is transferred to coal materials through the bottom of the carbonization chamber, combusted waste gas enters an ascending channel in the main wall through a hole in the lower part of the main wall, and finally flows out of the heat recovery coke oven body and enters a flue gas pipeline through an ascending pipe in the top of the coke oven.
The top of the carbonization chamber is of a large-span arch structure, the arch foot bricks are positioned on the upper part of the main wall, and the gravity of the arch head bricks and the refractory materials on the upper part of the arch crown is converted into horizontal lateral thrust and vertical downward pressure at the arch foot bricks. When the vault of the heat recovery coke oven with one hole is built, if arch foot bricks slide and shift unstably, arch foot bricks collapse, and the elevation of the vault is difficult to control, so that the traditional heat recovery coke oven building method is that arch foot bricks are built in all carbonization chambers of a group of coke ovens simultaneously, so that the gravity components (horizontal lateral thrust) borne by the arch foot bricks of the adjacent carbonization chambers can be mutually offset, the stability of the arch foot bricks is ensured, but a group of coke ovens usually consists of 10-20 carbonization chambers, a large amount of manpower and material resources are consumed in construction, the control difficulty is increased, and the quality and safety control in the construction process are not facilitated.
SUMMERY OF THE UTILITY MODEL
In order to overcome the defects of the prior art, the utility model provides a stable and easy-to-construct heat recovery coke oven vault structure, which increases the stability of the main wall and the oven top, and is convenient for construction and saves a large amount of manpower and material resources when the vault of the carbonization chamber is built.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a stable and easily constructed heat recovery coke oven vault structure comprises a main wall and a vault, wherein the main wall and the vault are built by main wall leather bricks, arch foot bricks, roof spanning bricks, arch roof bricks and positioning bricks; the main wall and vault combining position set up double-deck concave-convex cooperation locking structure, and main wall skin brick passes through concave-convex structure interlock locking with striding the crown brick, and the location brick between two hunch foot bricks passes through concave-convex structure interlock locking with striding the crown brick.
The upper layer and the lower layer of the main wall skin brick are occluded through the groove tongue.
The main wall upper portion wall leather brick is the overhanging type structure.
And a groove tongue is arranged between the positioning brick and the top-crossing brick.
The vault is built by wedge vault bricks with a big top and a small bottom, and the side surfaces between the vault bricks are matched by a ditch tongue.
Compared with the prior art, the beneficial effects of the utility model are that:
1) The utility model discloses main wall leather brick and stride the crown block and pass through concave-convex structure interlock locking, the positioning brick between the arch foot brick with stride the crown block and pass through concave-convex structure interlock locking once more, greatly increased furnace roof structure's stability, and the positioning brick makes the arch foot brick fixed by the main wall at the horizontal direction, when building single carbomorphism room arch crown block by laying bricks or stones, the position of arch foot brick can not take place to slide and squint yet, convenient construction has saved a large amount of manpower and materials.
2) The utility model discloses through the interlock of ditch tongue between the upper and lower floor of main wall skin brick, be favorable to the overall stability of main wall.
3) The utility model discloses main wall upper portion wall leather brick is the formula structure of encorbelmenting, plays fine supporting role to the hunch foot brick, is favorable to the overall stability of vault.
4) The utility model discloses the location brick with stride between the roof brick, through the mode of addding the ditch tongue between the brick layer, increase the stability of main wall and vault structure.
5) The utility model discloses the vault adopts wedge vault brick big-end-up to build by laying bricks or stones and forms, and the side between the vault brick adds establishes the cooperation of ditch tongue, increases the stability of vault.
Drawings
FIG. 1 is a schematic cross-sectional view of the structure of a main wall and a vault of a prior art heat recovery coke oven;
FIG. 2 is a schematic cross-sectional view of the structure of the main wall and the vault of the heat recovery coke oven of the present invention;
fig. 3 is a partially enlarged view of fig. 2.
In the figure: 1-main wall skin brick 2-arch springing brick 3-span top brick 4-arch top brick 5-positioning brick
Detailed Description
The following description of the embodiments of the present invention will be made with reference to the accompanying drawings:
as shown in figure 1, in the main wall and the vault of the existing heat recovery coke oven, no interlayer matching structure exists between the brick skin on the upper part of the main wall and the roof-spanning brick, and between the roof-spanning brick and the arch foot brick, so that the sliding and the deviation are easy to occur, the brick joint of the arch roof brick is not uniform, the vault sinks, the elevation is not easy to control, and the construction quality can not be ensured.
As shown in fig. 2 and 3, the main wall leather bricks 1 and the roof-spanning bricks 3 are locked by the concave-convex structure in an engaged manner, the positioning bricks 5 between the arch foot bricks 2 and the roof-spanning bricks 3 are locked by the concave-convex structure in an engaged manner again, the stability of the furnace roof structure is greatly improved, the positioning bricks 5 enable the arch foot bricks 2 to be fixed by the main wall in the horizontal direction, and when the single carbonization chamber arch top brick 4 is built, the position of the arch foot bricks 2 cannot slide or shift.
The upper layer and the lower layer of the main wall skin brick 1 are occluded by the grooves and the tongues, which is favorable for the integral stability of the main wall.
The main wall leather bricks 1 on the upper part of the main wall are of an overhanging type structure, play a good supporting role for the arch foot bricks 2 and are beneficial to the overall stability of the arch crown.
Between the positioning brick 5 and the roof-spanning brick 3, the stability of the main wall and the vault structure can be improved by additionally arranging a groove tongue between brick layers.
The vault is built by arch top bricks 4 with large top and small bottom, and the side surfaces between the arch top bricks 4 can be additionally provided with ditch tongues for matching, so that the stability of the vault is improved. The structure is convenient to construct, and a large amount of manpower and material resources are saved.
The utility model discloses increased the stability of main wall and furnace roof, when building by laying bricks or stones the carbomorphism room vault, convenient construction has saved a large amount of manpower and materials.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (5)

1. A stable and easily constructed heat recovery coke oven vault structure comprises a main wall and a vault, wherein the main wall and the vault are built by main wall leather bricks, arch foot bricks, roof spanning bricks, arch roof bricks and positioning bricks; the method is characterized in that: the main wall and vault combining position set up double-deck concave-convex cooperation locking structure, and main wall skin brick passes through concave-convex structure interlock locking with striding the crown brick, and the location brick between two hunch foot bricks passes through concave-convex structure interlock locking with striding the crown brick.
2. The stable, easily constructed heat recovery coke oven vault structure of claim 1 wherein: the upper layer and the lower layer of the main wall skin brick are meshed through the grooves and the tongues.
3. The stable, easily constructed heat recovery coke oven vault structure of claim 1, wherein: the main wall upper portion wall leather brick is the overhanging type structure.
4. The stable, easily constructed heat recovery coke oven vault structure of claim 1, wherein: and a groove tongue is arranged between the positioning brick and the top spanning brick.
5. The stable, easily constructed heat recovery coke oven vault structure of claim 1 wherein: the vault is built by wedge vault bricks with a big top and a small bottom, and the side surfaces between the vault bricks are matched by a ditch tongue.
CN202221213480.6U 2022-05-20 2022-05-20 Stable heat recovery coke oven vault structure of easily constructing Active CN217600645U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221213480.6U CN217600645U (en) 2022-05-20 2022-05-20 Stable heat recovery coke oven vault structure of easily constructing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221213480.6U CN217600645U (en) 2022-05-20 2022-05-20 Stable heat recovery coke oven vault structure of easily constructing

Publications (1)

Publication Number Publication Date
CN217600645U true CN217600645U (en) 2022-10-18

Family

ID=83568411

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221213480.6U Active CN217600645U (en) 2022-05-20 2022-05-20 Stable heat recovery coke oven vault structure of easily constructing

Country Status (1)

Country Link
CN (1) CN217600645U (en)

Similar Documents

Publication Publication Date Title
US11795400B2 (en) Coke ovens having monolith component construction
AU2019284030B2 (en) Horizontal heat recovery coke ovens having monolith crowns
US9193915B2 (en) Horizontal heat recovery coke ovens having monolith crowns
CN217600645U (en) Stable heat recovery coke oven vault structure of easily constructing
CN209508137U (en) A kind of oven top structure for coke oven that air-tightness is strong
CN115161041A (en) Stable heat recovery coke oven vault structure of easily constructing
CN105089604B (en) Underground coal gasification furnace and gasification process
CN2926230Y (en) Coal oven firebox-carbonizing chamber unit
CN218025924U (en) Coke oven roof structure
CN219861195U (en) Heat recovery coke oven vault structure
CN209906703U (en) Masonry structure of coal charging hole, smoke guide hole or ascending pipe hole
CN217600644U (en) Heat recovery coke oven carbonization chamber bottom structure
CN116463130A (en) Heat recovery coke oven vault structure
CN102747177B (en) Blast furnace hot blast stove and construction method thereof
CN216688005U (en) Environment-friendly coke oven top
CN115161038A (en) Heat recovery coke oven carbonization chamber bottom structure
CN1560195A (en) Production method of formed coke using coking powder as row-material and special formed coke furnace
CN109401761A (en) A kind of oven top structure for coke oven that air-tightness is strong and its construction method
CN218842045U (en) Dividing wall structure of coke oven regenerator
CN217230612U (en) Heat recovery coke oven main wall structure
CN117603710A (en) Double-deck vault structure of heat recovery coke oven
CN115353894A (en) Coke oven roof structure
CN115948170A (en) Dividing wall structure of coke oven regenerator
CN114656979A (en) Heat recovery coke oven main wall structure
GB191501738A (en) Improved Tile and Method of Setting same to be employed in the Construction of that Portion known as the Regenerator Chamber in Gas Making or Carbonising Plants.

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant