CN217458479U - Integral hoisting equipment for pile foundation - Google Patents

Integral hoisting equipment for pile foundation Download PDF

Info

Publication number
CN217458479U
CN217458479U CN202123178897.1U CN202123178897U CN217458479U CN 217458479 U CN217458479 U CN 217458479U CN 202123178897 U CN202123178897 U CN 202123178897U CN 217458479 U CN217458479 U CN 217458479U
Authority
CN
China
Prior art keywords
pile foundation
wall
pentagonal
hoisting equipment
integral hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123178897.1U
Other languages
Chinese (zh)
Inventor
袁永傑
谢漫涛
李自坤
徐凯燕
邓洪钧
刘佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Communications Polytechnic
Guangdong Guanyue Highway and Bridge Co Ltd
Original Assignee
Guangdong Communications Polytechnic
Guangdong Guanyue Highway and Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Communications Polytechnic, Guangdong Guanyue Highway and Bridge Co Ltd filed Critical Guangdong Communications Polytechnic
Priority to CN202123178897.1U priority Critical patent/CN217458479U/en
Application granted granted Critical
Publication of CN217458479U publication Critical patent/CN217458479U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model relates to the technical field of pile foundations, and discloses integral hoisting equipment for pile foundations, which comprises a hoisting block, a pile foundation and a pentagonal installation block, wherein a hydraulic rod is installed on the inner wall of the hoisting block, the telescopic end of the hydraulic rod is fixedly connected with the upper surface of the pentagonal installation block, a plurality of identical grippers are placed outside the pile foundation, a plurality of identical fixing parts are installed on the outer surface of each gripper, the outer surface of each fixing part is fixedly connected with the inner wall of the pentagonal installation block, a plurality of identical rotary drums are installed on the upper surface of the pentagonal installation block, and the inner wall of each rotary drum is movably connected with a telescopic rod; the utility model discloses a hanging piece, hydraulic stem, pentagon installation piece and sucking disc cooperate, play and carry out the effect of auxiliary force when high pressure water jet equipment is circular cut to the pile foundation, realize applying the purpose of the power that upwards promotes to the pile foundation, need carry out the problem that the long time circular cut when avoiding pile foundation diameter great, are favorable to the in-process of circular cut to promote the pile foundation.

Description

Integral hoisting equipment for pile foundation
Technical Field
The utility model relates to a pile foundation technical field specifically is a whole handling equipment for pile foundation.
Background
The pile foundation is a deep foundation consisting of piles and pile bearing platforms connected with the pile tops or a single pile foundation connected with the pile foundations through piles, if the pile bodies are completely buried in the soil, the bottom surfaces of the bearing platforms are in contact with the soil body, the pile foundation is called a low bearing platform pile foundation, if the upper parts of the pile bodies are exposed out of the ground and the bottom surfaces of the bearing platforms are located above the ground, the pile foundation is called a high bearing platform pile foundation, the building pile foundation is usually a low bearing platform pile foundation, and the application of the pile foundation in high-rise buildings is wide.
When the existing pile foundation is subjected to circular cutting, a novel method for breaking concrete by using high-pressure water jet is adopted for circular cutting, the pile foundation needs to be lifted after the pile foundation is cut off, and a hoisting device of a concrete breaking device by using high-pressure water jet is matched.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
The utility model provides a not enough to prior art, the utility model provides a whole handling equipment for pile foundation possesses and assists the circular cutting to high pressure water jet device, carries out the handling advantage with the pile foundation after the circular cutting.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a whole handling equipment for pile foundation, is including hanging the piece, pile foundation and pentagon installation piece, hang the inner wall of piece and install the hydraulic stem, the flexible end of hydraulic stem and the last fixed surface of pentagon installation piece are connected, the same grabhook of a plurality of, every have been placed in the outside of pile foundation the same mounting of a plurality of, every is all installed to the surface of grabhook the same mounting of a plurality of, every the surface of mounting all with the inner wall fixed connection of pentagon installation piece, the last surface mounting of pentagon installation piece has the same rotary drum of a plurality of, every the equal swing joint of inner wall of rotary drum has the telescopic link, every the top of telescopic link all with the bottom surface fixed connection who hangs the piece, the sucking disc is installed to the bottom surface of pentagon installation piece.
Preferably, a disc is mounted on the upper surface of the hanging block, and the inner wall of the disc is fixedly connected with the outer surface of the hydraulic rod.
Preferably, the upper surface of the disc is provided with a plurality of same threaded holes, and the inner wall of each threaded hole is in threaded connection with a fixing bolt.
Preferably, the outer surface of each fixing bolt is in threaded connection with the inner wall of the hanging block, and a stabilizing plate is mounted on the outer surface of each rotating cylinder.
Preferably, the bottom surface of each stabilizing plate is fixedly connected with the upper surface of the pentagonal mounting block, and the inner wall of each stabilizing plate is in threaded connection with two groups of self-tapping screws.
Preferably, the outer surface of each group of automatic screws is in threaded connection with the inner wall of the pentagonal mounting block, and two cross beams are mounted on the outer surface of the lifting block.
Preferably, two beam plates are installed on the bottom surface of each beam, and a sliding plate is installed on the bottom surface of each beam plate.
Preferably, a track plate is placed below each beam plate, and the outer surface of each track plate is connected with the inner portion of the sliding plate in a sliding mode.
(III) advantageous effects
Compared with the prior art, the utility model provides a whole handling equipment for pile foundation possesses following beneficial effect.
1. This an integral hoisting equipment for pile foundation, through the hanging piece, the hydraulic stem, pentagon installation piece and sucking disc cooperate, can play and carry out the effect of auxiliary power when high pressure water jet equipment circumcises the pile foundation, realize exerting the purpose of the power that upwards promotes to the pile foundation, need carry out the problem that the long time circumcises when avoiding pile foundation diameter great, be favorable to promoting the pile foundation in the in-process of circumcising, through the mounting, can play the effect of fixed grabhook, avoid the grabhook to produce lax problem, be favorable to improving the security when the grabhook uses.
2. This an integral handling equipment for pile foundation through being provided with the gripper, can play the effect that carries out the centre gripping to the pile foundation that cuts off, realizes cooperating hydraulic stem and sucking disc etc. and hoist the purpose of pile foundation, avoids using loop wheel machine or rope to hoist not safe enough problem, cooperatees through telescopic link and rotary drum, can play the effect of rotating gripper and pile foundation, realizes the fixed pile foundation of rotatory gripper and the purpose of cooperation girdling.
Drawings
FIG. 1 is a schematic three-dimensional structure of a beam slab of the present invention;
fig. 2 is a three-dimensional structure schematic diagram of the gripper of the present invention;
fig. 3 is a schematic structural view of a pentagonal mounting block of the present invention;
fig. 4 is a cross-sectional view of a three-dimensional front view of the hanging block of the present invention.
In the figure: 1. a hanging block; 2. fixing the bolt; 3. a disc; 4. a cross beam; 5. a beam plate; 6. a slide plate; 7. a threaded hole; 8. a pile foundation; 9. a track plate; 10. a gripper; 11. a fixing member; 12. a hydraulic rod; 13. a rotating drum; 14. a telescopic rod; 15. a pentagonal mounting block; 16. a self-tapping screw; 17. a stabilizing plate; 18. and (4) sucking discs.
Detailed Description
In order to better understand the utility model discloses an aim at, structure and function, below combine the figure, it is right to the utility model relates to a further detailed description is made to whole handling equipment for pile foundation.
Referring to fig. 1-4, the present invention: the utility model provides a whole handling equipment for pile foundation, includes and hangs piece 1, pile foundation 8 and pentagon installation piece 15 utilizes and hangs piece 1, can fix hydraulic stem 12, for whole hoist and mount part provides the support space, through pentagon installation piece 15, can install each part, does benefit to each part and carries out the whole work, hangs the inner wall of piece 1 and installs hydraulic stem 12, utilizes hydraulic stem 12, can stretch out and draw back hoist and mount part, provides power for hoist and mount pile foundation 8.
Hang the last surface mounting of piece 1 and have disc 3, utilize disc 3 to connect hydraulic stem 12 and hang piece 1, fix hydraulic stem 12, the inner wall of disc 3 and the outer fixed surface of hydraulic stem 12 are connected, the flexible end of hydraulic stem 12 and the last fixed surface of pentagonal installation piece 15 are connected, a plurality of the same grabhook 10 has been placed in the outside of pile foundation 8, through grabhook 10, can be with the 8 centre gripping of pile foundation, conveniently promote pile foundation 8, replace loop wheel machine and rope handling form.
The same screw hole 7 of a plurality of has been seted up to the upper surface of disc 3, the equal threaded connection of the inner wall of every screw hole 7 has fixing bolt 2, cooperate through screw hole 7 and fixing bolt 2, fix disc 3, realize the purpose of fixing the stable fixing on hanging piece 1 of hydraulic stem 12, the same mounting 11 of a plurality of is all installed to the surface of every gripper 10, it is fixed to gripper 10 to utilize mounting 11, can increase the security in the use of gripper 10.
Every fixing bolt 2's surface all with the inner wall threaded connection who hangs piece 1, firm board 17 is all installed to every rotary drum 13's surface, every mounting 11's surface all with the inner wall fixed connection of pentagonal installation piece 15, every firm board 17's bottom surface all is connected with the last fixed surface of pentagonal installation piece 15, every firm board 17's the equal threaded connection of inner wall has two sets of self-tapping screw 16, cooperate through firm board 17 and self-tapping screw 16, fix rotary drum 13, increase rotary drum 13 and pentagonal installation piece 15's joint strength.
The upper surface of the pentagonal mounting block 15 is provided with a plurality of identical rotary drums 13, the rotary drums 13 are utilized to realize the purpose of rotation, the grabhook 10 can be rotated into the gap of the pile foundation 8, and the outer surface of each group of self-tapping screws 16 is in threaded connection with the inner wall of the pentagonal mounting block 15.
Hang two crossbeams 4 of the surface mounting of piece 1, the equal swing joint of the inner wall of every rotary drum 13 has telescopic link 14, utilizes telescopic link 14, can play the effect that supports and cooperate telescopically, provides power when promoting pile foundation 8, and two beam slabs 5 are all installed to the bottom surface of every crossbeam 4, utilize crossbeam 4 and beam slab 5's connection, support hoist device, are favorable to hoist device to remove simultaneously.
Slide 6 is all installed jointly to the bottom surface of every group beam slab 5, and the top of every telescopic link 14 all with the bottom surface fixed connection who hangs piece 1, track board 9 has all been placed to the below of every beam slab 5, cooperatees through slide 6 and track board 9, can remove the pile foundation 8 after cutting off for pile foundation 8 shifts out the construction site.
The outer surface of each track plate 9 is connected with the inner portion of the sliding plate 6 in a sliding mode, the bottom surface of the pentagonal mounting block 15 is provided with a sucker 18, the pile foundation 8 can be fixedly sucked through the sucker 18, a certain auxiliary circular cutting effect is achieved, and the sucker is matched with the gripper 10 to clamp the pile foundation.
The utility model discloses a theory of operation is: firstly, when a hoisting device is needed to hoist the pile foundation 8, the hydraulic rod 12 is utilized to drive the pentagonal mounting block 15 to move, the sucker 18 is further sucked on the pile foundation 8 to suck and fix the pile foundation 8, when the pile foundation 8 is circularly cut, the hydraulic rod 12 and the sucker 18 can assist in circular cutting to lift the pile foundation 8 upwards, due to upward force, high-pressure water jet equipment can more easily break the internal structure of the pile foundation 8, the sucker 18 plays a certain role in assisting circular cutting and can subsequently hoist the pile foundation 8, when the pile foundation 8 is circularly cut out of a groove capable of being clamped, the rotary drum 13 is rotated to enable the gripper 10 to enter the groove, the gripper 10 is fixed by the fixing piece 11 to avoid the condition that the gripper 10 is not safe enough, after the pile foundation 8 is cut, the telescopic rod 12 is utilized to stretch and drive the telescopic rod 14 to stretch so as to hoist the pile foundation 8, the sucking disc 18 and the gripper 10 simultaneously fix and clamp the pile foundation 8, and after the pile foundation 8 is hoisted, the sliding plate 6 is moved, the cross beam 4 and the beam plate 5 support the hoisting block 1, so that the hoisting block 1 can move the pile foundation 8 out of a construction site along with the movement of the sliding plate 6.
It is to be understood that the present invention has been described with reference to certain embodiments, and that various changes or equivalents may be substituted for elements thereof by those skilled in the art without departing from the spirit and scope of the invention. In addition, many modifications may be made to adapt a particular situation or material to the teachings of the invention without departing from the essential scope thereof. Therefore, the present invention is not limited to the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of the present application are intended to be covered by the present invention.

Claims (8)

1. The utility model provides an integral handling equipment for pile foundation, includes hanging piece (1), pile foundation (8) and pentagon installation piece (15), its characterized in that: hang the inner wall of piece (1) and install hydraulic stem (12), the flexible end of hydraulic stem (12) is connected with the last fixed surface of pentagonal installation piece (15), a plurality of the same grabhook (10) has been placed in the outside of pile foundation (8), every the surface of grabhook (10) all installs the same mounting (11) of a plurality of, every the surface of mounting (11) all with the inner wall fixed connection of pentagonal installation piece (15), the last surface mounting of pentagonal installation piece (15) has the same rotary drum (13) of a plurality of, every the equal swing joint of inner wall of rotary drum (13) has telescopic link (14), every the top of telescopic link (14) all with hang the bottom surface fixed connection of piece (1), sucking disc (18) are installed to the bottom surface of pentagonal installation piece (15).
2. The integral hoisting equipment for the pile foundation of claim 1, which is characterized in that: the upper surface of the hanging block (1) is provided with a disc (3), and the inner wall of the disc (3) is fixedly connected with the outer surface of the hydraulic rod (12).
3. The integral hoisting equipment for the pile foundation of claim 2, which is characterized in that: a plurality of same threaded holes (7) are formed in the upper surface of the disc (3), and each inner wall of each threaded hole (7) is connected with a fixing bolt (2) in a threaded mode.
4. The integral hoisting equipment for the pile foundation of claim 3, which is characterized in that: the outer surface of each fixing bolt (2) is in threaded connection with the inner wall of the hanging block (1), and a stabilizing plate (17) is mounted on the outer surface of each rotary drum (13).
5. The integral hoisting equipment for the pile foundation of claim 4, which is characterized in that: the bottom surface of each stabilizing plate (17) is fixedly connected with the upper surface of the pentagonal mounting block (15), and the inner wall of each stabilizing plate (17) is in threaded connection with two groups of self-tapping screws (16).
6. The integral hoisting equipment for the pile foundation according to claim 5, characterized in that: the outer surface of each group of self-tapping screws (16) is in threaded connection with the inner wall of the pentagonal mounting block (15), and two cross beams (4) are mounted on the outer surface of the hanging block (1).
7. The integral hoisting equipment for the pile foundation of claim 6, which is characterized in that: every two beam slabs (5) are all installed to the bottom surface of crossbeam (4), every group slide (6) are all installed jointly to the bottom surface of beam slab (5).
8. The integral hoisting equipment for the pile foundation according to claim 7, which is characterized in that: track plates (9) are placed below the beam plates (5), and the outer surface of each track plate (9) is connected with the sliding plate (6) in a sliding mode.
CN202123178897.1U 2021-12-17 2021-12-17 Integral hoisting equipment for pile foundation Active CN217458479U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123178897.1U CN217458479U (en) 2021-12-17 2021-12-17 Integral hoisting equipment for pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123178897.1U CN217458479U (en) 2021-12-17 2021-12-17 Integral hoisting equipment for pile foundation

Publications (1)

Publication Number Publication Date
CN217458479U true CN217458479U (en) 2022-09-20

Family

ID=83233140

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123178897.1U Active CN217458479U (en) 2021-12-17 2021-12-17 Integral hoisting equipment for pile foundation

Country Status (1)

Country Link
CN (1) CN217458479U (en)

Similar Documents

Publication Publication Date Title
CN201924360U (en) Multifunctional hydraulic static pile press
CN2863892Y (en) Self-lifting riprap levelling platform boat
CN210562365U (en) Underwater rock crushing device
CN217458479U (en) Integral hoisting equipment for pile foundation
CN214780221U (en) Hoisting device for steel reinforcement cage
CN212248238U (en) Pile driver is used in bridge construction
CN210595164U (en) PC post lifts by crane auxiliary device upright
CN105715028A (en) Successive lifting device and lifting scaffold with same
CN209443490U (en) A kind of reusable pin-connected panel tower crane base
CN216613852U (en) Tool for mounting high and ultrahigh ALC (autoclaved lightweight concrete) wallboard
CN202369321U (en) Vibration isolating support hoist
CN211596734U (en) Rammer compactor for construction
CN111943054A (en) Assembled hoisting equipment for building
CN110844768A (en) Culvert pipe overhead hoist for construction
CN112499486A (en) Portable transformer lifter and operation method thereof
CN215516375U (en) Manhole hoisting device for foundation reinforcement cage
CN110682418A (en) Wallboard supporting die table
CN114734404B (en) Horizontal splitting method for end plate top beam and arc beam assembly of sunken ship integral salvaging equipment
CN216332609U (en) Self-adaptive convenient channel for operation deck and jacket platform
CN214192351U (en) Tower crane davit
CN212794794U (en) Hydraulic shaft puller device
CN216892399U (en) Drilling bored concrete pile head wholly cuts off and lifts construction structures
CN216190576U (en) Hydraulic dragging lifting type double-beam structure of crane
CN212174240U (en) Culvert pipe overhead hoist for construction
CN221274981U (en) Hoisting tool capable of turning over tower drum

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant