CN217326372U - Be used for pre-buried dismantlement of outer wall to face limit construction safety arrangement - Google Patents

Be used for pre-buried dismantlement of outer wall to face limit construction safety arrangement Download PDF

Info

Publication number
CN217326372U
CN217326372U CN202122288436.3U CN202122288436U CN217326372U CN 217326372 U CN217326372 U CN 217326372U CN 202122288436 U CN202122288436 U CN 202122288436U CN 217326372 U CN217326372 U CN 217326372U
Authority
CN
China
Prior art keywords
wall
frame
pipe
buried
pipe support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122288436.3U
Other languages
Chinese (zh)
Inventor
徐劲子
王志强
姜鹤
严修发
杨敢为
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN202122288436.3U priority Critical patent/CN217326372U/en
Application granted granted Critical
Publication of CN217326372U publication Critical patent/CN217326372U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model relates to a detachable adjacent edge construction safety protection device for outer wall pre-embedding, which comprises a pipe frame, wherein connecting plates are arranged at two ends of the pipe frame, a template for pouring an outer wall can be placed at the groove clamping positions of the two connecting plates, a pre-embedded frame is arranged at the bottom of the groove wall of the pipe frame, the other end of the pre-embedded frame extends to the position of an outer wall reinforcement cage, and the pipe frame is connected with the end of the pre-embedded frame through a nut; make the pipe support fix on the wall of outer wall under the cooperation through connecting plate and pre-buried frame, when the wall construction operation of outer wall is operated to needs, can make staff's safety belt hang in the connecting rod department between two rubber wheels, after a slice region construction is accomplished, can stimulate the safety belt and make the rubber wheel walk along the cell wall of pipe support, through can making things convenient for the staff to be under construction to the wall on the outer wall like this, reduce the construction degree of difficulty and potential safety hazard, solve the outer wall effectively and do not have safe hanging point and hang the unable problem that leads to the construction difficulty that removes of point.

Description

Be used for pre-buried dismantlement of outer wall to face limit construction safety arrangement
Technical Field
The utility model relates to a construction technical field especially relates to a be used for outer wall pre-buried can dismantle and face limit construction safety arrangement.
Background
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, also can be said to be the process of changing various lines on the design drawing into a real object in appointed places, at present, the outer wall and the eminence face the limit construction time mostly do not have the safety belt hanging point, hang the point few, hang the unable problem such as removal of point, increased the construction degree of difficulty like this, have the potential safety hazard.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to overcome prior art's defect, provide a be used for the outer wall pre-buried can dismantle and face limit construction safety arrangement, can make things convenient for the staff to be under construction to the wall on the outer wall, reduce the advantage of the construction degree of difficulty and potential safety hazard.
The technical scheme for realizing the purpose is as follows:
the utility model provides a be used for outer wall pre-buried can dismantle and face limit construction safety arrangement, including the pipe support, the connecting plate is installed at the both ends of pipe support, two the template of pouring the outer wall can be placed to the double-layered groove department of connecting plate, pre-buried frame is installed to the cell wall bottom of pipe support, just the pre-buried frame other end extends to outer wall steel reinforcement cage department, the pipe support with the end department of pre-buried frame passes through the nut and connects, the inside pipe box department of pipe support is fixed with two rubber wheels, two it is fixed through the connecting rod between the rubber wheel.
Preferably, the number of the embedded frames and the number of the nuts are several. In order to make the pipe frame fixed on the wall more firmly.
Preferably, the spacing rod is installed to the chase port department of pipe support, just the spacing rod with threaded connection between the pipe support. To avoid the rubber wheels falling off from the tube trough ports of the tube rack.
Preferably, the groove wall of the pipe frame is of a smooth structure. In order to ensure that the rubber wheel rolls more stably at the groove wall of the pipe frame.
Preferably, the embedded frame is of a T-shaped structure. In order to avoid the falling of the embedded frame.
Preferably, the pipe frame is an aluminum alloy member. To avoid corrosion damage to the pipe support.
Preferably, the length of the connecting plate is the same as the length of the pipe frame. To avoid the pipe racks protruding from both ends of the exterior wall form.
The utility model has the advantages that: the utility model discloses at the in-process that uses, make the pipe support fix on the wall of outer wall under the cooperation through connecting plate and pre-buried frame, when needs are operated the wall construction of outer wall, can make staff's safety belt hang the connecting rod department between two rubber wheels, after a slice region construction is accomplished, can stimulate the safety belt and make the rubber wheel follow the cell wall walking of pipe support, can make things convenient for the staff to be under construction to the wall on the outer wall through this, reduce the construction degree of difficulty and potential safety hazard, solve the outer wall effectively and do not have safe hanging point and hang the unable problem that leads to the construction difficulty that removes of point.
Drawings
FIG. 1 is a schematic view of the present invention;
FIG. 2 is a schematic cross-sectional view of the tube rack of FIG. 1 according to the present invention;
description of reference numerals:
1. a pipe frame; 2. a connecting plate; 3. a limiting rod; 4. pre-embedding a frame; 5. a rubber wheel; 6. a connecting rod; 7. and a nut.
Detailed Description
The invention will be further explained with reference to the drawings and the specific embodiments.
Referring to fig. 1 to 2, the utility model provides a be used for outer wall pre-buried can dismantle and face limit construction safety arrangement, including pipe support 1, the both ends welding of pipe support 1 has connecting plate 2, and the template of pouring the outer wall can be placed to the double-layered groove department of two connecting plates 2, and pre-buried frame 4 is installed to pipe support 1's cell wall bottom, and the pre-buried frame 4 other end extends to outer wall steel reinforcement cage department, and pipe support 1 passes through nut 7 with pre-buried frame 4's end department and is connected, and 1 inside pipe box department of pipe support rolls has two rubber wheels 5, fixes through connecting rod 6 between two rubber wheels 5.
In this example, make the outer wall template place the draw-in groove department at connecting plate 2, place the steel reinforcement cage department of laying at the outer wall to pre-buried frame 4, pour the outer wall after the above-mentioned operation is accomplished, the concrete solidifies the back, demolish the outer wall template, when the wall construction operation of outer wall is required, can make staff's safety belt hang in connecting rod 6 department between two rubber wheels 5, after a slice region construction is accomplished, can stimulate the safety belt and make rubber wheel 5 walk along the cell wall of pipe support 1, through can make things convenient for the staff to be under construction to the wall on the outer wall like this, reduce the advantage of the construction degree of difficulty and potential safety hazard.
Furthermore, as shown in fig. 1, the number of the embedded frames 4 and the number of the nuts 7 are several, so that the pipe frame 1 can be fixed on a wall more firmly, and the phenomenon of falling is avoided.
Further, as shown in fig. 1, a limiting rod 3 is installed at a pipe groove port of the pipe support 1, the limiting rod 3 is in threaded connection with the pipe support 1, and the rubber wheel 5 can be prevented from falling from the pipe groove port of the pipe support 1 by blocking the limiting rod 3.
Further, as shown in fig. 2, the groove wall of the pipe frame 1 is of a smooth structure, so that the rubber wheels 5 can roll more stably on the groove wall of the pipe frame 1.
Further, as shown in fig. 1, the embedded frame 4 is of a T-shaped structure, so that when the end of the embedded frame 4 is placed inside the outer wall, the end of the embedded frame can be in full contact with the concrete inside the outer wall, and the embedded frame 4 is prevented from falling off.
Further, as shown in fig. 1, the pipe frame 1 is made of aluminum alloy, and the aluminum alloy has good corrosion resistance, so that the pipe frame 1 can be prevented from being corroded and damaged in the using process.
Further, as shown in fig. 1, the length of the connecting plate 2 is the same as that of the pipe frame 1, and by making the length of the connecting plate 2 the same as that of the pipe frame 1, when the external wall formwork is placed at the clamping groove of the connecting plate 2, the pipe frame 1 is prevented from protruding from both ends of the external wall formwork.
The utility model discloses a theory of operation is: the utility model discloses in the in-process that uses, before the outer wall is pour, make the outer wall form place the draw-in groove department at connecting plate 2, place the steel reinforcement cage department of laying at the outer wall to pre-buried frame 4, pour the outer wall after the above-mentioned operation is accomplished, after the concrete solidifies, can make pre-buried frame 4 fix the inside at the outer wall, and then make pipe support 1 hug closely under the cooperation of nut 7 and fix the surface at the outer wall, then continue to demolish the template on outer wall surface, when the wall construction operation of outer wall is operated to needs, can make staff's safety belt hang in connecting rod 6 departments between two rubber wheels 5, after a slice region construction is accomplished, can stimulate the safety belt and make rubber wheel 5 follow the cell wall walking of pipe support 1, after the construction is accomplished, twist nut 7, make pipe support 1 break away from with pre-buried frame 4 can, through this can used repeatedly.
The present invention has been described in detail with reference to the embodiments shown in the drawings, and those skilled in the art can make various modifications to the present invention based on the above description. Therefore, certain details of the embodiments should not be construed as limitations of the invention, which are intended to be covered by the following claims.

Claims (7)

1. The utility model provides a be used for outer wall pre-buried can dismantle and face limit construction safety arrangement, a serial communication port, including the pipe support, the connecting plate is installed, two at the both ends of pipe support the template of pouring the outer wall can be placed to the double-layered groove department of connecting plate, pre-buried frame is installed to the cell wall bottom of pipe support, just the pre-buried frame other end extends to outer wall steel reinforcement cage department, the pipe support with the end department of pre-buried frame passes through the nut and connects, the inside pipe box department of pipe support is fixed with two rubber wheels, two it is fixed through the connecting rod between the rubber wheel.
2. The detachable edge construction safety protection device for the outer wall pre-burying according to claim 1, wherein the number of the pre-burying frames and the number of the nuts are a plurality.
3. The utility model provides a be used for outer wall pre-buried can dismantle and face limit construction safety arrangement, a serial communication port, the gag lever post is installed to the chase port department of pipe support, just the gag lever post with threaded connection between the pipe support.
4. The detachable adjacent edge construction safety protection device for the outer wall pre-burying of the claim 1, wherein the groove wall of the pipe frame is of a smooth structure.
5. The detachable adjacent edge construction safety protection device for the outer wall pre-buried structure as claimed in claim 1, wherein the pre-buried frame is of a T-shaped structure.
6. The detachable adjacent edge construction safety protection device for the embedded of the outer wall of claim 1, wherein the pipe frame is an aluminum alloy member.
7. The detachable adjacent edge construction safety protection device for the embedded of the outer wall of claim 1, wherein the length of the connecting plate is the same as that of the pipe frame.
CN202122288436.3U 2021-09-22 2021-09-22 Be used for pre-buried dismantlement of outer wall to face limit construction safety arrangement Active CN217326372U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122288436.3U CN217326372U (en) 2021-09-22 2021-09-22 Be used for pre-buried dismantlement of outer wall to face limit construction safety arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122288436.3U CN217326372U (en) 2021-09-22 2021-09-22 Be used for pre-buried dismantlement of outer wall to face limit construction safety arrangement

Publications (1)

Publication Number Publication Date
CN217326372U true CN217326372U (en) 2022-08-30

Family

ID=82944431

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122288436.3U Active CN217326372U (en) 2021-09-22 2021-09-22 Be used for pre-buried dismantlement of outer wall to face limit construction safety arrangement

Country Status (1)

Country Link
CN (1) CN217326372U (en)

Similar Documents

Publication Publication Date Title
CN204266590U (en) Sump, hoistway formwork bed die anti-floating system
CN205976410U (en) Shaped steel is encorbelmented scaffold frame and can be dismantled type of falling U screw vacuum pump
CN204174935U (en) A kind of outer wall of basement one side formwork supporting and protection structure
CN103669655A (en) Construction technology for pouring concrete of walls on two sides of deformation joint
CN203961276U (en) High-building construction steel form and handling frame Integral lifting stage apparatus
CN108222066A (en) A kind of combined steel formwork support system and its construction method
CN205777482U (en) A kind of back cord formula aluminum alloy mould plate
CN103603491A (en) Beam plate post-cast strip form plate support frame and setting up method thereof
CN217326372U (en) Be used for pre-buried dismantlement of outer wall to face limit construction safety arrangement
CN106320373A (en) Supporting system at position of post-pouring belt of underground garage roof and construction method
CN202658872U (en) Tool connecting tube of building scaffold
CN204139596U (en) Reserving hole sleeve pipe and get pipe device
CN104746521B (en) The application of oversized cross-section slope cushion layer constructing structure
CN203200719U (en) Hanging type slope pouring template device
CN203361605U (en) Anchor ring assembly
CN206267520U (en) A kind of self-supporting post-cast strip is poured with hanging mould
CN211846865U (en) Device for hoisting corrugated pipe
CN202031309U (en) Suspending operation platform for structural concrete constructions
CN211520604U (en) Movable assembly type chute
CN104912333A (en) Wall construction system and construction method
CN104674951A (en) Automatic tripping device for hoisting large reinforced concrete prefabricated columns and beams
CN207620379U (en) A kind of side mould fixing device
CN207469752U (en) A kind of venthole non-dismantling formwork
CN204174906U (en) A kind of builder's jack anchor ring
CN205063312U (en) Cantilever beam fixing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant