CN217272333U - Municipal administration gas pipeline butt joint construction equipment - Google Patents

Municipal administration gas pipeline butt joint construction equipment Download PDF

Info

Publication number
CN217272333U
CN217272333U CN202220401191.2U CN202220401191U CN217272333U CN 217272333 U CN217272333 U CN 217272333U CN 202220401191 U CN202220401191 U CN 202220401191U CN 217272333 U CN217272333 U CN 217272333U
Authority
CN
China
Prior art keywords
fixedly connected
plate
gas pipeline
butt joint
clamping block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202220401191.2U
Other languages
Chinese (zh)
Inventor
田建军
王佳佳
金鑫
金鑫民
吴凤龙
唐国旺
娄丽伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202220401191.2U priority Critical patent/CN217272333U/en
Application granted granted Critical
Publication of CN217272333U publication Critical patent/CN217272333U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model provides a municipal administration gas pipeline butt joint construction equipment, this municipal administration gas pipeline butt joint construction equipment, the on-line screen storage device comprises a base, the top fixedly connected with box of base, the inner wall sliding connection of box has the lifter plate, one side fixedly connected with connecting plate of lifter plate, the equal fixedly connected with fixed plate in both sides of connecting plate, the top of fixed plate is provided with fixed subassembly. The utility model provides a municipal administration gas pipeline butt joint construction equipment has solved current gas pipeline and has laid and adopt to bury underground the installation when in the city usually, lays the gas pipeline underground, at laying the in-process, need lift by crane the pipeline with the help of lifting device and splice, and lifting device often receives the restriction of ground space and can't use to the fixed mode to the gas pipeline is comparatively simple, the pipeline takes place to rotate easily when lifting by crane and drops even, lead to taking place the incident, give people and bring very big inconvenient problem.

Description

Municipal administration gas pipeline butt joint construction equipment
Technical Field
The utility model relates to a gas pipeline technical field especially relates to a municipal administration gas pipeline butt joint construction equipment.
Background
The gas pipeline is a pipeline for conveying natural gas, including associated gas produced in oil fields, from a mining place or a treatment plant to an urban gas distribution center or an industrial enterprise user, and is also called a gas conveying pipeline.
The pipeline hoisting device has the advantages of low transportation cost, small occupied area, quick construction, large oil and gas transportation amount, high safety performance, less transportation loss, no three-waste emission, small leakage risk, small environmental pollution, small adverse weather influence, small equipment maintenance amount, convenient management, easy realization of remote centralized monitoring and the like, in the prior art, the pipeline hoisting device is usually buried and installed when being laid in a city, the pipeline hoisting device is laid underground, the pipeline hoisting device is required to be spliced in the laying process, the hoisting device is usually limited by the ground space and cannot be used, the fixing mode of the gas pipeline is simple, the pipeline is easy to rotate or even fall when being hoisted, safety accidents are caused, and inconvenience is brought to people.
Therefore, a new municipal gas pipeline butt joint construction device is needed to solve the technical problems.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model provides a municipal gas pipeline butt joint construction equipment with simple, the convenient to use of design, fixed effectual and improvement construction security.
The utility model provides a municipal administration gas pipeline butt joint construction equipment, the on-line screen storage device comprises a base, the top fixedly connected with box of base, the inner wall sliding connection of box has the lifter plate, one side fixedly connected with connecting plate of lifter plate, the equal fixedly connected with fixed plate in both sides of connecting plate, the top of fixed plate is provided with fixed subassembly.
In order to reach the effect of fixing the gas pipeline, as the utility model provides a municipal administration gas pipeline butt joint construction equipment, it is preferred, fixed subassembly includes first clamp splice, second clamp splice, mounting panel, first fixing bolt and slipmat, the top of fixed plate is provided with first clamp splice, the top of first clamp splice is provided with the second clamp splice, the equal fixedly connected with mounting panel in both sides of first clamp splice and second clamp splice, the inside of mounting panel is provided with first fixing bolt, the inner wall of first clamp splice and second clamp splice all is provided with the slipmat.
In order to reach and install fixed effect to first clamp splice and second clamp splice, conduct the utility model provides a municipal administration gas pipeline butt joint construction equipment, it is preferred, threaded hole is seted up to the inside of mounting panel, the inner wall of screw hole and first fixing bolt's outside threaded connection.
In order to reach and install fixed effect to the splint, as the utility model provides a municipal administration gas pipeline butt joint construction equipment, it is preferred, the top fixedly connected with cardboard of fixed plate, the bottom fixedly connected with splint of first clamp splice.
In order to reach and install fixed effect to first clamp splice, conduct the utility model provides a municipal administration gas pipeline butt joint construction equipment, it is preferred, one side of splint is provided with second fixing bolt, first mounting hole and the second mounting hole that uses with the cooperation of second fixing bolt are seted up respectively to the inside of cardboard and splint.
In order to reach and support fixed effect to the motor, as the utility model provides a municipal administration gas pipeline butt joint construction equipment, it is preferred, the bottom fixedly connected with dead lever of box inner chamber, the top fixedly connected with fixing base of dead lever.
In order to reach the effect that drives the fly leaf and go up and down, conduct the utility model provides a municipal administration gas pipeline butt joint construction equipment, it is preferred, the top fixedly connected with motor of fixing base, the output fixedly connected with threaded rod of motor.
In order to reach the effect that drives the lifter plate and go up and down, as the utility model provides a municipal administration gas pipeline butt joint construction equipment, it is preferred, the outside threaded connection of threaded rod has the fly leaf, one side of fly leaf and one side fixed connection of lifter plate.
In order to reach the effect that supports the fly leaf, conduct the utility model provides a municipal administration gas pipeline butt joint construction equipment, it is preferred, the inner wall sliding connection of fly leaf has the bracing piece, the bottom of bracing piece and the bottom fixed connection of box inner chamber.
In order to reach and support fixed effect to the fixed plate, as the utility model provides a municipal administration gas pipeline butt joint construction equipment, it is preferred, the solid fixed cylinder of top fixedly connected with of base, the bottom fixedly connected with supporting seat of solid fixed cylinder inner chamber, the top welding of supporting seat has the spring, the top fixedly connected with support column of spring, the top of support column and the bottom fixed connection of fixed plate.
Compared with the prior art, the beneficial effects of the utility model are that:
the municipal gas pipeline butt joint construction device comprises a base, a box body is fixedly connected to the top of the base, a lifting plate is connected to the inner wall of the box body in a sliding mode, a connecting plate is fixedly connected to one side of the lifting plate, fixing plates are fixedly connected to the two sides of the connecting plate, a gas pipeline is placed on the top of a first clamping block, a second clamping block is placed on the top of the first clamping block and is in threaded connection with a mounting plate through a first fixing bolt, the second clamping block is fixed to the top of the first clamping block, the gas pipeline is clamped and fixed, an anti-slip mat effectively prevents the gas pipeline from moving, stability is greatly improved, the height of the gas pipeline is adjusted through lifting of the lifting plate, a constructor can conveniently butt joint the gas pipeline, the problem that the existing gas pipeline is usually buried and installed when being laid in a city is solved, the gas pipeline is laid underground is solved, in the laying process, the pipeline is required to be spliced by means of hoisting equipment, the hoisting equipment is often limited by the ground space and cannot be used, the fixing mode of the gas pipeline is simple, the pipeline is easy to rotate and even drop when being hoisted, safety accidents are caused, and inconvenience is brought to people.
Drawings
Fig. 1 is a schematic structural view of a preferred embodiment of the municipal gas pipeline docking construction device provided by the present invention;
fig. 2 is a schematic structural view of the fixing assembly of the present invention;
FIG. 3 is a schematic structural view of the clamping plate and the clamping plate of the present invention;
fig. 4 is a schematic view of the internal structure of the box body of the present invention;
fig. 5 is a schematic view of the internal structure of the fixing cylinder of the present invention.
Reference numbers in the figures: 1. a base; 2. a box body; 3. a lifting plate; 4. a connecting plate; 5. a fixing plate; 6. a fixing assembly; 61. a first clamping block; 62. a second clamp block; 63. mounting a plate; 64. a first fixing bolt; 65. a non-slip mat; 7. a threaded hole; 8. clamping a plate; 9. a splint; 10. a second fixing bolt; 11. a first mounting hole; 12. a second mounting hole; 13. fixing the rod; 14. a fixed seat; 15. a motor; 16. a threaded rod; 17. a movable plate; 18. a support bar; 19. a fixed cylinder; 20. a supporting base; 21. a spring; 22. and (7) supporting the column.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and embodiments.
Please refer to fig. 1, fig. 2, fig. 3, fig. 4 and fig. 5 in combination, in which fig. 1 is a schematic structural diagram of a preferred embodiment of the municipal gas pipeline docking construction device according to the present invention; fig. 2 is a schematic structural view of the fixing assembly of the present invention; FIG. 3 is a schematic structural view of the clamping plate and the clamping plate of the present invention; fig. 4 is a schematic view of the internal structure of the box body of the present invention; fig. 5 is a schematic view of the internal structure of the fixing cylinder of the present invention. A municipal administration gas pipeline butt joint construction equipment, includes base 1.
In the specific implementation process, as shown in fig. 1, fig. 2, fig. 3 and fig. 4, the top of the base 1 is fixedly connected with a box body 2, the inner wall of the box body 2 is connected with a lifting plate 3 in a sliding manner, one side of the lifting plate 3 is fixedly connected with a connecting plate 4, two sides of the connecting plate 4 are fixedly connected with fixing plates 5, and a fixing component 6 is arranged above the fixing plates 5.
The fixing assembly 6 comprises a first clamping block 61, a second clamping block 62, a mounting plate 63, a first fixing bolt 64 and a non-slip mat 65, the first clamping block 61 is arranged above the fixing plate 5, the second clamping block 62 is arranged at the top of the first clamping block 61, the mounting plate 63 is fixedly connected to the two sides of the first clamping block 61 and the two sides of the second clamping block 62, the first fixing bolt 64 is arranged inside the mounting plate 63, and the non-slip mat 65 is arranged on the inner walls of the first clamping block 61 and the second clamping block 62.
The mounting plate 63 is provided with a threaded hole 7 therein, and the inner wall of the threaded hole 7 is in threaded connection with the outer side of the first fixing bolt 64.
The top of the fixed plate 5 is fixedly connected with a clamping plate 8, and the bottom of the first clamping block 61 is fixedly connected with a clamping plate 9.
A second fixing bolt 10 is arranged on one side of the clamping plate 9, and a first mounting hole 11 and a second mounting hole 12 matched with the second fixing bolt 10 are respectively formed in the clamping plate 8 and the clamping plate 9.
It should be noted that: by arranging the base 1, the box body 2 is fixedly connected to the top of the base 1, the inner wall of the box body 2 is connected with the lifting plate 3 in a sliding manner, one side of the lifting plate 3 is fixedly connected with the connecting plate 4, two sides of the connecting plate 4 are fixedly connected with the fixing plates 5, the top of the fixing plates 5 is fixedly connected with the clamping plates 8, the bottom of the first clamping block 61 is fixedly connected with the clamping plates 9, the clamping plates 9 are clamped with the clamping plates 8, then the clamping plates 9 are in threaded connection with the first mounting holes 11 and the second mounting holes 12 through the second fixing bolts 10, the clamping plates 9 and the clamping plates 8 are fixed, so that the first clamping block 61 is fixedly arranged at the top of the fixing plate 5, then a gas pipeline is placed at the top of the first clamping block 61, then the second clamping block 62 is placed at the top of the first clamping block 61, and is in threaded connection with the threaded hole 7 in the mounting plate 63 through the first fixing bolt 64, so that the second clamping block 62 is fixed at the top of the first clamping block 61, thereby press from both sides tight fixedly to the gas pipeline, the effectual gas pipeline that prevents of slipmat 65 takes place the activity, has improved stability greatly, comes highly to adjust the gas pipeline through the lift of lifter plate 3 after that, makes things convenient for constructor to carry out butt joint operation to the gas pipeline.
Referring to fig. 1, 4 and 5, a fixing rod 13 is fixedly connected to the bottom of the inner cavity of the box body 2, and a fixing seat 14 is fixedly connected to the top of the fixing rod 13.
The top of fixing base 14 is fixedly connected with motor 15, and the output fixedly connected with threaded rod 16 of motor 15.
The outer side of the threaded rod 16 is connected with a movable plate 17 through threads, and one side of the movable plate 17 is fixedly connected with one side of the lifting plate 3.
The inner wall of the movable plate 17 is connected with a support bar 18 in a sliding manner, and the bottom of the support bar 18 is fixedly connected with the bottom of the inner cavity of the box body 2.
The fixed section of thick bamboo 19 of base 1's top fixedly connected with, the bottom fixedly connected with supporting seat 20 of the 19 inner chambers of fixed section of thick bamboo, the top welding of supporting seat 20 has spring 21, spring 21's top fixedly connected with support column 22, the top of support column 22 and the bottom fixed connection of fixed plate 5.
It should be noted that: the bottom of the inner cavity of the box body 2 is fixedly connected with a fixed rod 13, the top of the fixed rod 13 is fixedly connected with a fixed seat 14, the top of the fixed seat 14 is fixedly connected with a motor 15, the motor 15 drives a threaded rod 16 to rotate, the threaded rod 16 rotates to drive a movable plate 17 to move up and down, thereby adjusting the height of the lifting plate 3 and greatly improving convenience, the movable plate 17 is slidably connected with a support rod 18, support fixed to fly leaf 17, make fly leaf 17 more stable at the lift in-process, the fixed section of thick bamboo 19 of top fixedly connected with of base 1, the bottom fixedly connected with supporting seat 20 of the 19 inner chambers of fixed section of thick bamboo, the top fixedly connected with spring 21 of supporting seat 20, the top fixedly connected with support column 22 of spring 21, support column 22 supports fixed plate 5 fixedly, makes fixed plate 5 more stable when reciprocating, can not take place to rock.
The utility model provides a pair of municipal administration gas pipeline butt joint construction equipment's theory of operation as follows:
when in use, by arranging the base 1, the box body 2 is fixedly connected to the top of the base 1, the inner wall of the box body 2 is connected with the lifting plate 3 in a sliding manner, one side of the lifting plate 3 is fixedly connected with the connecting plate 4, two sides of the connecting plate 4 are fixedly connected with the fixing plates 5, the top of the fixing plate 5 is fixedly connected with the clamping plate 8, the bottom of the first clamping block 61 is fixedly connected with the clamping plate 9, the clamping plate 9 is clamped with the clamping plate 8, then the clamping plate 9 is in threaded connection with the first mounting hole 11 and the second mounting hole 12 through the second fixing bolt 10, the clamping plate 9 and the clamping plate 8 are fixed, so that the first clamping block 61 is fixedly arranged at the top of the fixing plate 5, then the gas pipeline is placed at the top of the first clamping block 61, then the second clamping block 62 is placed at the top of the first clamping block 61, and is in threaded connection with the threaded hole 7 in the mounting plate 63 through the first fixing bolt 64, thereby fixing the second clamping block 62 on the top of the first clamping block 61, thereby clamping and fixing the gas pipeline, the anti-slip mat 65 effectively prevents the gas pipeline from moving, greatly improving the stability, then adjusting the height of the gas pipeline through the lifting of the lifting plate 3, facilitating the butt joint operation of constructors on the gas pipeline, the bottom of the inner cavity of the box body 2 is fixedly connected with the fixed rod 13, the top of the fixed rod 13 is fixedly connected with the fixed seat 14, the top of the fixed seat 14 is fixedly connected with the motor 15, the motor 15 drives the threaded rod 16 to rotate, the threaded rod 16 rotates to drive the movable plate 17 to move up and down, thereby adjusting the height of the lifting plate 3, greatly improving the convenience, the inside of the movable plate 17 is slidably connected with the supporting rod 18, supporting and fixing the movable plate 17, and making the movable plate 17 more stable in the lifting process, the fixed 19 of the top fixedly connected with of base 1, the bottom fixedly connected with supporting seat 20 of the 19 inner chambers of the fixed cylinder, the top fixedly connected with spring 21 of supporting seat 20, the top fixedly connected with support column 22 of spring 21, support column 22 support fixed plate 5, make fixed plate 5 more stable when reciprocating, can not take place to rock.
The above only is the embodiment of the present invention, not limiting the scope of the present invention, all the equivalent structures or equivalent processes of the present invention are used in the specification and the attached drawings, or directly or indirectly applied to other related technical fields, and the same principle is included in the protection scope of the present invention.

Claims (10)

1. The utility model provides a municipal administration gas pipeline butt joint construction equipment, its characterized in that, includes base (1), top fixedly connected with box (2) of base (1), the inner wall sliding connection of box (2) has lifter plate (3), one side fixedly connected with connecting plate (4) of lifter plate (3), the equal fixedly connected with fixed plate (5) in both sides of connecting plate (4), the top of fixed plate (5) is provided with fixed subassembly (6).
2. The municipal gas pipeline butt joint construction device according to claim 1, wherein the fixing assembly (6) comprises a first clamping block (61), a second clamping block (62), a mounting plate (63), a first fixing bolt (64) and a non-slip mat (65), the first clamping block (61) is arranged above the fixing plate (5), the second clamping block (62) is arranged at the top of the first clamping block (61), the mounting plate (63) is fixedly connected to both sides of the first clamping block (61) and the second clamping block (62), the first fixing bolt (64) is arranged inside the mounting plate (63), and the non-slip mat (65) is arranged on the inner walls of the first clamping block (61) and the second clamping block (62).
3. The municipal gas pipeline butt joint construction device according to claim 2, wherein the mounting plate (63) is internally provided with a threaded hole (7), and the inner wall of the threaded hole (7) is in threaded connection with the outer side of the first fixing bolt (64).
4. The municipal gas pipeline butt joint construction device according to claim 2, wherein a clamping plate (8) is fixedly connected to the top of the fixing plate (5), and a clamping plate (9) is fixedly connected to the bottom of the first clamping block (61).
5. The municipal gas pipeline butt joint construction device according to claim 4, wherein a second fixing bolt (10) is arranged on one side of the clamping plate (9), and a first mounting hole (11) and a second mounting hole (12) matched with the second fixing bolt (10) are respectively formed in the clamping plate (8) and the clamping plate (9).
6. The municipal gas pipeline butt joint construction device according to claim 1, wherein a fixing rod (13) is fixedly connected to the bottom of the inner cavity of the box body (2), and a fixing seat (14) is fixedly connected to the top of the fixing rod (13).
7. The municipal gas pipeline butt joint construction device according to claim 6, wherein a motor (15) is fixedly connected to the top of the fixed seat (14), and a threaded rod (16) is fixedly connected to the output end of the motor (15).
8. The municipal gas pipeline butting construction device according to claim 7, wherein a movable plate (17) is screwed to the outer side of the threaded rod (16), and one side of the movable plate (17) is fixedly connected with one side of the lifting plate (3).
9. The municipal gas pipeline butting construction device according to claim 8, wherein a supporting rod (18) is slidably connected to the inner wall of the movable plate (17), and the bottom of the supporting rod (18) is fixedly connected with the bottom of the inner cavity of the box body (2).
10. The municipal gas pipeline butt joint construction device according to claim 1, wherein a fixed cylinder (19) is fixedly connected to the top of the base (1), a supporting seat (20) is fixedly connected to the bottom of an inner cavity of the fixed cylinder (19), a spring (21) is welded to the top of the supporting seat (20), a supporting column (22) is fixedly connected to the top of the spring (21), and the top of the supporting column (22) is fixedly connected to the bottom of the fixed plate (5).
CN202220401191.2U 2022-02-25 2022-02-25 Municipal administration gas pipeline butt joint construction equipment Expired - Fee Related CN217272333U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220401191.2U CN217272333U (en) 2022-02-25 2022-02-25 Municipal administration gas pipeline butt joint construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220401191.2U CN217272333U (en) 2022-02-25 2022-02-25 Municipal administration gas pipeline butt joint construction equipment

Publications (1)

Publication Number Publication Date
CN217272333U true CN217272333U (en) 2022-08-23

Family

ID=82858957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220401191.2U Expired - Fee Related CN217272333U (en) 2022-02-25 2022-02-25 Municipal administration gas pipeline butt joint construction equipment

Country Status (1)

Country Link
CN (1) CN217272333U (en)

Similar Documents

Publication Publication Date Title
CN111747286A (en) Civil engineering pipeline handling device
CN210529715U (en) Detachable deep foundation pit excavation braced system
CN217272333U (en) Municipal administration gas pipeline butt joint construction equipment
CN205444948U (en) Guarantee assembled regulator of steel column installation accuracy
CN202519621U (en) Steel hoop used for suspending support system
CN208039624U (en) A kind of easy-to-dismount steel column
CN106499188B (en) The hydraulic material distributing machine of floor inner climbing type is climbed support system
CN213418456U (en) Building scaffold wall connecting piece
CN215291569U (en) Be used for steel construction to reform transform centre sill reinforcement hoisting device
CN212503725U (en) Windproof fixing structure of tower crane for building
CN213359489U (en) Adjustable reinforcing device for supporting construction elevator on basement roof
CN210483127U (en) Rack installation strutting arrangement
CN211472177U (en) Single tensioning device of steel strand inhaul cable system with suspension locking structure
CN212104759U (en) House building steel constructs beam structure
CN114411754A (en) Foundation pit steel shotcrete prestressing force compensation arrangement
CN210366509U (en) Construction elevator capable of being integrally hoisted and installed
CN208056592U (en) A kind of tool-type inspection platform
CN108951720B (en) Reference pile and reference beam for static load test
CN220953519U (en) Prefabricated step basis is assembled fast
CN217734019U (en) Pile extension positioning device for soft geological prestressed concrete pile
CN211897873U (en) Operating platform device for bridge pipeline installation
CN217947352U (en) Steel column hoisting device
CN217377134U (en) Integral type hoist mounting structure of rig soon
CN211735874U (en) Integral installation cylinder type damper
CN217498442U (en) Positioning fixture for steel beam supporting rod

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220823