CN217268935U - Explorator suitable for side wall steel reinforcement framework - Google Patents

Explorator suitable for side wall steel reinforcement framework Download PDF

Info

Publication number
CN217268935U
CN217268935U CN202220107066.0U CN202220107066U CN217268935U CN 217268935 U CN217268935 U CN 217268935U CN 202220107066 U CN202220107066 U CN 202220107066U CN 217268935 U CN217268935 U CN 217268935U
Authority
CN
China
Prior art keywords
steel reinforcement
side wall
operation platform
transverse
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220107066.0U
Other languages
Chinese (zh)
Inventor
刘晓阳
张宏伟
张涛
陈志扬
朱旭红
童侨
孙军汉
张浩民
匡志军
郭秀
佘国生
徐建新
李金伦
朱小金
代高健
叶川语
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 7 Co Ltd
PowerChina South Construction Investment Co Ltd
PowerChina Chengdu Concrete Products Co Ltd
PowerChina South Construction Technology Co Ltd
Original Assignee
Sinohydro Bureau 7 Co Ltd
PowerChina South Construction Investment Co Ltd
PowerChina Chengdu Concrete Products Co Ltd
PowerChina South Construction Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 7 Co Ltd, PowerChina South Construction Investment Co Ltd, PowerChina Chengdu Concrete Products Co Ltd, PowerChina South Construction Technology Co Ltd filed Critical Sinohydro Bureau 7 Co Ltd
Priority to CN202220107066.0U priority Critical patent/CN217268935U/en
Application granted granted Critical
Publication of CN217268935U publication Critical patent/CN217268935U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a profiling suitable for side wall framework of steel reinforcement, including mould base and reinforcement auxiliary component, the mould base includes anterior segment operation platform district and back end operation platform district, and reinforcement auxiliary component includes vertical bar location cardboard and arc location cardboard, and vertical bar location cardboard and arc location cardboard all are equipped with the draw-in groove that is used for fixed bar, links up at the juncture in front end operation platform district and back end operation platform district, vertical bar location cardboard and arc location cardboard. The utility model discloses set up the operation platform district of two sections differences on same profiling tool, including the anterior segment operation platform district that is equipped with straight strip location cardboard and the back end operation platform district that is equipped with arc location cardboard, accomplish one step when realizing the preparation of side wall framework of steel reinforcement for fashioned framework of steel reinforcement is of high quality, can obtain better shaping effect of pouring, has improved the efficiency of construction greatly.

Description

Explorator suitable for side wall steel reinforcement framework
Technical Field
The utility model relates to a framework for steel reinforcement technical field, specific theory relates to a profiling suitable for side wall framework for steel reinforcement.
Background
The steel bar framework is formed by welding and binding a plurality of steel bars together to form a complete net rack which is used for restraining concrete and improving the integrity of a concrete member; some steel reinforcement frameworks are bound in advance, which are often used in brick-concrete construction, such as constructional columns, cantilever beams and the like, and an integral hoisting mode is adopted during construction; and the other steel bar frameworks are in a field binding mode, so that the mode is more flexible and the adaptability is better.
The side wall of the subway tunnel comprises a plane section and an arc-surface section, in order to be more flexible to process, the steel reinforcement frameworks are mostly bound on site and are separately processed, and then the two sections of formed steel reinforcement frameworks are welded, so that the forming quality of the steel reinforcement frameworks is easily influenced by the operation, for example, the connection degree of the steel reinforcement frameworks is poor, and the height difference exists on the plane of the poured side wall; and if the steel bar spacing of the steel bar framework has larger deviation, and the like.
The defects seriously affect the construction efficiency and are to be solved.
Disclosure of Invention
In order to overcome prior art's problem, the utility model provides a profiling suitable for side wall framework of steel reinforcement.
The utility model discloses technical scheme as follows:
the utility model provides a profiling suitable for side wall framework of steel reinforcement, includes the mould base and locates the reinforcement auxiliary component of mould base top, the mould base includes anterior segment operation platform district and back end operation platform district, reinforcement auxiliary component includes vertical bar location cardboard and arc location cardboard, the vertical bar location cardboard is located the upper surface of mould base, the vertical bar location cardboard with the arc location cardboard all is equipped with the draw-in groove that is used for fixed bar, the vertical bar location cardboard is located anterior segment operation platform district, the arc location cardboard is located the back end operation platform district department of mould base, and anterior segment operation platform district with the juncture in back end operation platform district the vertical bar location cardboard with the arc location cardboard is connected.
According to the above scheme the utility model discloses, a serial communication port, the mould base is banding rectangle underframe, and this rectangle underframe includes a plurality of horizontal channel-section steels and a plurality of vertical channel-section steels, horizontal channel-section steel with vertical channel-section steel is connected perpendicularly, two horizontal channel-section steel is a set of, and locates the both sides of mould base, with a set of two horizontal channel-section steel is parallel from top to bottom, two of same height evenly be equipped with many between the horizontal channel-section steel vertical channel-section steel.
Furthermore, the upper transverse channel steel and the lower transverse channel steel in the same group are connected through short struts.
Furthermore, the longitudinal channel steel at the position and above the front section operation platform area is aligned with the longitudinal channel steel at the lower part one by one.
Furthermore, the opening directions of all the longitudinal channel steel are the same.
According to above scheme the utility model discloses, a serial communication port, the vertical bar location cardboard includes longitudinal positioning cardboard and transverse orientation cardboard, above longitudinal channel-section steel department, every interval longitudinal channel-section steel are equipped with one the longitudinal positioning cardboard, adjacent two at least be equipped with the transverse orientation cardboard of two parallels between the longitudinal positioning cardboard.
According to above-mentioned scheme the utility model discloses, a serial communication port, reinforcement auxiliary member is still including being located the end of anterior segment operation platform district keeps off the piece and is located the end tail of back end operation platform district keeps off the piece, the end keep off with the end tail keeps off the piece and all is equipped with the stores pylon, and the stores pylon of two sets up in opposite directions.
Furthermore, the end stopper comprises end angle steel and an end transverse groove which are vertically connected, a plurality of end hangers are arranged on the outer side surface of the end angle steel, and rectangular end hanging rings are arranged on the lower surface of the end transverse groove.
Furthermore, the two end angle steels are symmetrically arranged at the top angles at two sides of the mould base.
Furthermore, the end transverse groove comprises parallel long channel steel and short channel steel, the long channel steel is located above the short channel steel, and the upper surface of the long channel steel is provided with an end clamping interface with an opening facing upwards.
Furthermore, the end-tail stopper comprises end-tail angle steel, and an end-tail hanging rack of the end-tail stopper is arranged on the inner side surface of the end-tail angle steel.
According to the above scheme the utility model discloses, a serial communication port, reinforcement auxiliary component still includes a plurality of stingers, the stinger evenly locates on the horizontal channel-section steel of mould base both sides top, the trailing flank of stinger is equipped with a plurality of brackets.
Further, the front side of the stinger is provided with an accessory fixing seat, the accessory fixing seat is tightly attached to the stinger, one side, away from the stinger, of the accessory fixing seat is provided with a circular hanging ring, and the circular hanging rings on the two sides of the mould base are aligned.
According to above scheme the utility model discloses, its characterized in that, reinforcement auxiliary component still includes a plurality of sides and keeps off the piece, the side keeps off to be located on the horizontal channel-section steel of mould base both sides top, just the side that anterior segment operation platform district keeps off the number of pieces quantity and is more than the side that back end operation platform district keeps off the number of pieces quantity.
According to the above scheme the utility model discloses, a serial communication port, the intermediate position bottom of mould base is equipped with the main muscle backup pad, and is equipped with C type channel-section steel in the main muscle backup pad.
According to the above scheme the utility model discloses, a serial communication port, an at least lateral surface of mould base is equipped with the extension channel-section steel, the extension channel-section steel is connected with neighbouring horizontal channel-section steel, and is on a parallel with horizontal channel-section steel.
Further, the extension channel steel is aligned with the transverse channel steel.
According to the above scheme the utility model discloses, its beneficial effect lies in:
the utility model provides a profiling suitable for side wall steel reinforcement framework sets up two sections different operation platform districts on same profiling tool, including the anterior segment operation platform district that is equipped with straight strip location cardboard and the back end operation platform district that is equipped with arc location cardboard, accomplish one step when realizing the preparation of side wall steel reinforcement framework for fashioned steel reinforcement framework is of high quality, can obtain better pouring shaping effect, has improved the efficiency of construction greatly.
Drawings
FIG. 1 is a front view of the present invention;
fig. 2 is a partial schematic view of a top view of the present invention;
FIG. 3 is an enlarged view of portion A of FIG. 1;
FIG. 4 is an enlarged view of portion B of FIG. 1;
fig. 5 is an enlarged view of portion C of fig. 1.
In the figure, 1, a mould base; 101. a front-stage operating platform area; 102. a back-end work area; 11. longitudinal channel steel; 12. transverse channel steel; 13. a short strut; 14. a main reinforcement support plate; 15. c-shaped channel steel;
2. positioning a clamping plate; 201. a longitudinal positioning clamping plate; 202. transversely positioning a clamping plate; 203. an arc-shaped positioning clamping plate; 21. A card slot; 22. a support bar;
3. an end stop; 31. end angle steel; 32. a transverse groove at the end head; 33. an end hanger; 34. an end head hoisting ring;
4. a stinger; 41. a bracket;
5. an accessory fixing seat; 51. a circular ring;
6. a side stopper;
7. an end stop; 71. end tail angle steel; 72. an end-to-end hanger;
8. and (4) extending the channel steel.
Detailed Description
For better understanding of the objects, technical solutions and technical effects of the present invention, the present invention will be further explained with reference to the accompanying drawings and embodiments. It is to be noted that the following examples are only for explaining the present invention and are not intended to limit the present invention.
It will be understood that when an element is referred to as being "secured to" or "disposed on" another element, it can be directly on the other element or intervening elements may also be present, and when an element is referred to as being "connected" to another element, it can be directly connected to the other element or intervening elements may also be present.
The terms "upper", "lower", "left", "right", "top", "bottom", "inner", "outer", and the like indicate orientations or positions based on the orientations or positions shown in the drawings, and are for convenience of description only and should not be construed as limiting the technical solution.
The meaning of "a number" is two or more unless specifically defined otherwise. The terms "first", "second" and "first" are used merely for descriptive purposes and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features.
As shown in fig. 1 and 2, a profiling suitable for a side wall steel reinforcement framework comprises a mould base 1 and a steel reinforcement binding auxiliary component arranged above the mould base 1, wherein the mould base 1 comprises a longitudinal channel steel 11 and transverse channel steel 12, four transverse channel steels 12 are provided, two transverse channel steels are in a group and are arranged at two sides of the mould base 1, and the two transverse channel steels 12 of each group are vertically parallel and are connected and fixed through short struts 13; evenly be equipped with the longitudinal channel-section steel 11 of a plurality of parallels between two horizontal channel-section steels 12 of front segment operation platform district 101 department, same height, upper and lower two-layer longitudinal channel-section steel 11 one-to-one, the position is the same promptly, quantity is also the same to make mould base 1 form a stable in structure's rectangular base.
In this embodiment, two ends of the longitudinal channel 11 are welded to the inner side surfaces of the transverse channel 12, and the directions of the notches of all the longitudinal channels 11 are the same. The reinforcement auxiliary component comprises a positioning clamping plate 2, a clamping groove 21 is uniformly formed in the positioning clamping plate 2, and the clamping groove 21 is used for clamping a reinforcement bar to complete positioning. Specifically, the positioning clamping plates comprise a longitudinal positioning clamping plate 201 and a transverse positioning clamping plate 202, the longitudinal positioning clamping plate 201 and the transverse positioning clamping plate 202 are straight positioning clamping plates, the straight positioning clamping plates are arranged at the top of the clamping fixture base, one longitudinal positioning clamping plate 201 is arranged at the upper longitudinal channel steel 11 at intervals of one longitudinal channel steel 11, and the longitudinal positioning clamping plate 201 is aligned with the lower longitudinal channel steel 11; be equipped with the horizontal positioning cardboard 202 of two piece at least parallels between two adjacent longitudinal register cardboard 201, the quantity of the horizontal positioning cardboard 202 between two adjacent longitudinal register cardboard 201 can be set for according to framework of steel reinforcement's actual need. The longitudinal positioning clamping plate 201 and the transverse positioning clamping plate 202 form a front-section operating platform area 101 of the mould base 1, and a leveling and positioning operating platform is provided for binding and manufacturing of a side wall steel reinforcement framework. The mould base 1 further comprises a rear section operation platform area 102, and an operation platform for bending and positioning is provided for binding and manufacturing the side wall steel reinforcement framework.
The utility model discloses realize setting up two sections different operation platform district on same profiling tool, the side wall framework of steel reinforcement makes one step when makeeing for pour fashioned side wall face roughness and improve greatly, thereby improved the efficiency of construction.
As shown in fig. 3, in this embodiment, the reinforcement auxiliary member further includes end stoppers 3, an accessory fixing seat 5, a stinger 4 and side stoppers 6, the two end stoppers 3 are disposed at the front end of the front-section workbench, the end stoppers 3 include end angle steels 31 and end transverse grooves 32, and the two end angle steels 31 are symmetrically disposed on the transverse channel steels 12 at the two sides of the mold base 1; a plurality of end hangers 33 are arranged on the outer side surfaces of the end angle steels 31, and the end hangers 33 are used for placing and fixing supporting pieces (not shown in the figure, the same applies below) at the end parts of the steel reinforcement framework; the end transverse groove 32 is vertically arranged on the end angle steel 31, the lower surface of the end transverse groove 32 is provided with a rectangular end lifting ring 34, and the end lifting rings 34 on the end stoppers 3 at two sides are used for connecting in series with a positioning rod for binding steel bars; the end transverse groove 32 comprises a long channel steel and a short channel steel, the long channel steel is arranged above the short channel steel, an end clamping interface with an upward opening is further arranged on the upper surface of the long channel steel, and the end clamping interface is used for installing a fixed pressing plate.
In the embodiment, a plurality of stingers 4 are arranged above the mould base 1, the stingers 4 are vertically arranged on the transverse channel steels 12 at two sides, and are uniformly distributed on the transverse channel steels 12; the trailing flank of stinger 4 is equipped with a plurality of brackets 41, and bracket 41 is used for placing the support piece at fixed framework of steel reinforcement middle part, realizes the location to the framework of steel reinforcement ligature process, further ensures the dimensional requirement, the rib regularity requirement etc. of framework of steel reinforcement ligature process to promote framework of steel reinforcement's quality.
At the leading flank of stinger 4, be equipped with accessory fixing base 5, the stinger 4 is hugged closely to accessory fixing base 5, and one side that stinger 4 was kept away from to accessory fixing base 5 is equipped with circular rings 51, and the circular rings 51 of 1 both sides of mould base align to realize that circular rings 51 can alternate the dead lever, the dead lever crosses steel reinforcement framework, firmly fixes its main muscle spare on the profiling, is convenient for carry out the ligature, is favorable to the lifting efficiency. In the present embodiment, a total of three accessory holders 5 are provided, respectively at the front end, the middle end, and the rear end of the tire base 1.
In this embodiment, mould base 1 top is equipped with a plurality of sides and keeps off piece 6, and side fender piece 6 sets up perpendicularly on horizontal channel-section steel 12, and the side of mould base 1 front end keeps off 6 distribution quantity of piece and is more intensive than the side of mould base 1 rear end keeps off 6 distribution quantity, is favorable to earlier stage operation to framework of steel reinforcement's design.
As shown in fig. 4, in the present embodiment, the reinforcement auxiliary member further includes an end-to-end stopper 7, and the end-to-end stopper 7 is disposed at the tail end of the rear working platform area 102 of the fixture base 1. Specifically, the end-to-end stopper 7 includes an end-to-end angle iron 71, and a plurality of end-to-end hangers 72 are disposed on an inner side surface of the end-to-end angle iron 71, and are also used for placing supporting members, so that the constructors can fix and bind the end sections of the side walls.
In this embodiment, in the rear-section working platform area 102 of the clamping fixture base 1, the auxiliary reinforcing steel bar binding component further includes an arc-shaped positioning clamping plate 203, and a clamping groove 21 is also arranged on the arc-shaped positioning clamping plate 203 and used for clamping reinforcing steel bars for accurate positioning; the juncture, the vertical bar location cardboard and the arc location cardboard of anterior segment operation platform district and back end operation platform district are connected, and are more smooth and easy when more doing benefit to the preparation of side wall framework of steel reinforcement, can improve the quality of pouring the back side wall.
The below of arc location cardboard 203 is equipped with bracing piece 22, and a plurality of bracing pieces 22 highly reduce gradually from front end to rear end to accord with the structure that arc location cardboard 203 rear end portion is bent down, realize that bracing piece 22 provides powerful support for arc location cardboard 203.
As shown in fig. 5, in this embodiment, a main rib supporting plate 14 is disposed at the bottom of the middle position of the mold base 1, the main rib supporting plate 14 connects two short pillars 13, and a C-shaped channel 15 is disposed on the main rib supporting plate 14 for increasing the structural strength of the middle section of the mold base 1.
As shown in fig. 2, an extension channel steel 8 is additionally arranged on at least one outer side surface of the mould base 1, the extension channel steel 8 is connected with a transverse channel steel 12 on the side and is parallel to the transverse channel steel 12, the length of the extension channel steel 8 is equal to that of the transverse channel steel 12, and the extension channel steel 8 is aligned with the transverse channel steel 12; the extension channel steel 8 is the same as the transverse channel steel 12, and two extension channel steels are arranged in parallel up and down. The extension channel steel 8 is used for increasing the contact area of the mould base 1 and the bottom surface, so that the stability of the mould base 1 is improved, and the shaking in the construction process is prevented.
To sum up, the straight positioning clamping plate and the arc positioning clamping plate of the utility model can provide positioning and fixing for the main reinforcement binding process of the steel reinforcement framework, reduce errors and ensure the overall quality of the steel reinforcement framework; the end stopper, the end-tail stopper, the side stopper and the stinger further provide accurate positioning and spacing requirements for the binding process of the steel reinforcement framework, improve the regularity of the ribs and reduce the deviation of the intervals of the ribs.
All possible combinations of the technical features in the above embodiments may not be described for the sake of brevity, but should be considered as being within the scope of the present disclosure as long as there is no contradiction between the combinations of the technical features.
The above examples only represent some embodiments of the present invention, and the description thereof is more specific and detailed, but not to be construed as limiting the scope of the present invention. It should be noted that, for those skilled in the art, without departing from the spirit of the present invention, several variations and modifications can be made, which are within the scope of the present invention. Therefore, the protection scope of the present invention should be subject to the appended claims.

Claims (10)

1. A profiling suitable for a side wall steel reinforcement framework is characterized by comprising a clamping fixture base and a steel reinforcement binding auxiliary component arranged above the clamping fixture base, wherein the clamping fixture base comprises a front section operation platform area and a rear section operation platform area, the steel reinforcement binding auxiliary component comprises a straight strip positioning clamping plate and an arc-shaped positioning clamping plate, the straight strip positioning clamping plate is positioned on the upper surface of the clamping fixture base, the straight strip positioning clamping plate and the arc-shaped positioning clamping plate are both provided with clamping grooves used for fixing steel reinforcement bars,
the straight strip positioning clamping plate is arranged in the front section operation platform area, the arc positioning clamping plate is arranged in the rear section operation platform area, and the straight strip positioning clamping plate is connected with the arc positioning clamping plate at the junction of the front section operation platform area and the rear section operation platform area.
2. The profiling die for the side wall steel reinforcement framework as claimed in claim 1, wherein said die base is an elongated rectangular bottom frame, said rectangular bottom frame comprises a plurality of transverse channels and a plurality of longitudinal channels, said transverse channels and said longitudinal channels are vertically connected, two of said transverse channels are in one group and are arranged on two sides of said die base, two of said transverse channels in the same group are vertically parallel, and a plurality of said longitudinal channels are uniformly arranged between two of said transverse channels at the same height.
3. The profiling mold for the side wall steel reinforcement framework as claimed in claim 2, wherein the two transverse channel steels in the same group are connected through short struts.
4. The explorator suitable for the side wall steel reinforcement framework as claimed in claim 1, wherein the straight bar positioning snap-gauge comprises a longitudinal positioning snap-gauge and a transverse positioning snap-gauge, one longitudinal positioning snap-gauge is provided at every other longitudinal channel at the upper longitudinal channel, and at least two parallel transverse positioning snap-gauges are provided between two adjacent longitudinal positioning snap-gauges.
5. The profile modeling suitable for the side wall steel reinforcement framework according to claim 1, wherein the reinforcement binding auxiliary component further comprises an end stopper and an end-to-end stopper, the end stopper is disposed in the front working area, the end-to-end stopper is disposed in the rear working area, both the end stopper and the end-to-end stopper are provided with hanging racks, and the hanging racks at the two positions are disposed in opposite directions.
6. The profile modeling for the side wall steel reinforcement framework, according to claim 5, wherein the end stopper comprises vertically connected end angle steel and an end transverse groove, the outer side surface of the end angle steel is provided with a plurality of end hangers, and the lower surface of the end transverse groove is provided with a rectangular end hanging ring.
7. The profiling mold for the side wall steel reinforcement framework as claimed in claim 1, wherein the steel reinforcement binding auxiliary member further comprises a plurality of stingers, the stingers are uniformly arranged on the transverse channel steel above two sides of the mold base, and a plurality of brackets are arranged on the rear side surfaces of the stingers.
8. The profiling suitable for the side wall steel reinforcement framework as claimed in claim 7, wherein an accessory fixing seat is arranged on the front side face of the stinger, the accessory fixing seat is tightly attached to the stinger, a circular hanging ring is arranged on one side, away from the stinger, of the accessory fixing seat, and the circular hanging rings on two sides of the mould base are aligned.
9. The profile modeling for the side wall steel reinforcement framework according to claim 1, wherein the steel reinforcement binding auxiliary component further comprises a plurality of side stoppers, the side stoppers are arranged on the transverse channel steel above two sides of the mould base, and the number of the side stoppers in the front section working platform area is greater than that of the side stoppers in the rear section working platform area.
10. The profiling mold for the side wall steel reinforcement framework as claimed in claim 1, wherein at least one outer side surface of the mold base is provided with an extension channel steel, and the extension channel steel is connected with an adjacent transverse channel steel and is parallel to the transverse channel steel.
CN202220107066.0U 2022-01-14 2022-01-14 Explorator suitable for side wall steel reinforcement framework Active CN217268935U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220107066.0U CN217268935U (en) 2022-01-14 2022-01-14 Explorator suitable for side wall steel reinforcement framework

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220107066.0U CN217268935U (en) 2022-01-14 2022-01-14 Explorator suitable for side wall steel reinforcement framework

Publications (1)

Publication Number Publication Date
CN217268935U true CN217268935U (en) 2022-08-23

Family

ID=82897619

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220107066.0U Active CN217268935U (en) 2022-01-14 2022-01-14 Explorator suitable for side wall steel reinforcement framework

Country Status (1)

Country Link
CN (1) CN217268935U (en)

Similar Documents

Publication Publication Date Title
CN217268935U (en) Explorator suitable for side wall steel reinforcement framework
CN209261237U (en) A kind of prefabricated panel clamping device
CN206186089U (en) Case roof beam reinforcement bed -jig
CN210475352U (en) Be applied to standard bed-jig of empty core plate reinforcement
CN110700490B (en) Transfer floor large-span steel reinforced concrete beam and construction method
CN204552774U (en) A kind of monolithic inverted arch mould bases of locating longitudinal waterstop
CN211622612U (en) Arc corner building system
CN217871200U (en) Multi-cavity steel plate shear wall steel bar truss
CN216298427U (en) Reinforcing bar interfacing apparatus that building engineering technique was used
CN213793999U (en) Prefabricated box girder bed-jig
CN114108499A (en) Suspended casting beam reference section hinged type triangular bracket combined hanging basket integrated device and construction method thereof
CN210530084U (en) Open type steel reinforced concrete composite truss floor
CN210615626U (en) Grid bow member processing bed-jig
CN209163439U (en) Tool-typed formwork installs structure at a kind of structure drop plate
CN210013093U (en) Novel concrete road side form template reinforcing device
CN217270233U (en) Roof framework of steel reinforcement profiling
CN214190859U (en) Beam-ends mould strorage device
CN217292807U (en) Accurate longeron framework of steel reinforcement profiling fixes a position
CN216881505U (en) Stand column framework installation jig frame device
CN214168791U (en) Prefabricated arch box construction system of box type arch bridge
CN214981832U (en) Precast beam reinforcing bar design die carrier device
CN217174396U (en) Pier stud tray reinforcement rack
CN212052374U (en) Rhombus truss assembly
CN218779948U (en) Side form reinforced structure of high-low span beam
CN217897388U (en) Supporting structure for overhanging cornice formwork on reinforcing steel bar net rack

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant