CN217232487U CN202220385833.4U CN202220385833U CN217232487U CN 217232487 U CN217232487 U CN 217232487U CN 202220385833 U CN202220385833 U CN 202220385833U CN 217232487 U CN217232487 U CN 217232487U
Authority
CN
China
Prior art keywords
steel pipe
steelframe
jack
fixing bolt
slip casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220385833.4U
Other languages
Chinese (zh)
Inventor
李金磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202220385833.4U priority Critical patent/CN217232487U/en
Application granted granted Critical
Publication of CN217232487U publication Critical patent/CN217232487U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses an office space steel pipe concrete cylinder project organization, including the cylinder structural layer, the fixed surface of cylinder structural layer installs connection steelframe, a plurality of connection steelframe end to end connection constitutes the annular, two the slip casting steel pipe is installed to connection steelframe's junction, connection steelframe's surface mounting has the decoration PLASTIC LAMINATED, the surface mounting who decorates the PLASTIC LAMINATED has fixing bolt, fixing bolt's tail end is located the inside of slip casting steel pipe, the inside injection concrete of slip casting steel pipe. A official working space steel pipe concrete cylinder project organization, through the picture peg of a plurality of connection steelframes that set up and the concatenation of butt joint groove head and the tail be the loop configuration to the position of the No. two jacks of the connection steelframe of front side corresponds with the position of the No. one jack of the connection steelframe of rear side, the concatenation of slip casting steel pipe and connection steelframe is accomplished to a jack and No. two jacks that insert the slip casting steel pipe on the same vertical line.

Description

Concrete filled steel tube column body design structure for office space
Technical Field
The utility model relates to an architectural decoration field, in particular to office space steel pipe concrete cylinder design structure field.
Background
The steel tube concrete column is a member formed by filling concrete in a steel tube, the existing column body design structure mainly combines a vertical steel tube and a circular steel tube in a welding mode, the surface of the steel frame is easy to be damaged in a welding connection mode, so that the steel frame is easy to be repaired, rotten and unsuitable for long-term use, the structure is used through a preset steel ring, for some existing column bodies, the construction can not be carried out by the engineering of thickening the column bodies, the size and the specification of the existing column bodies are not adjustable, the existing column body and the steel tube are customized in advance, meanwhile, the steel frame body and the steel tube are used for a long time, rust can easily occur, so that the steel frame body and the steel tube are connected and loosened, meanwhile, a decorative plate fixed on the steel frame through bolts is easy to fall off, and accordingly, the office space steel tube concrete column body design structure is provided.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a main aim at provides an office space steel pipe concrete column body project organization, can effectively solve the problem in the background art.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides an office space steel pipe concrete column body project organization, includes the cylinder structural layer, the outer fixed surface of cylinder structural layer installs the connection steelframe, a plurality of the connection steelframe end to end connection constitutes the annular, two the slip casting steel pipe is installed to the junction of connecting steelframe, the surface mounting of connecting steelframe has the decoration PLASTIC LAMINATED, the surface mounting who decorates the PLASTIC LAMINATED has fixing bolt, fixing bolt's tail end is located the inside of slip casting steel pipe, the inside injection concrete of slip casting steel pipe, during fixing bolt's tail end inserts the screw like this, the concrete solidifies fixing bolt's tail end in the inside of slip casting steel pipe to it is not hard up to take place after avoiding fixing bolt to go up rust.
The utility model discloses a further improvement lies in, the front end fixed mounting who connects the steelframe has the picture peg, connect the afterbody of steelframe and seted up the butt joint groove, be located the front side and connect the steelframe butt joint groove with be located the rear side and connect the steelframe the picture peg is pegged graft, and picture peg and the butt joint groove head and the tail concatenation of a plurality of connection steelframes through setting up like this can splice into the not loop configuration of equidimension for loop configuration.
The utility model discloses a further improvement lies in, a jack has been seted up at the middle part of picture peg No. two jacks have been seted up to the afterbody of connecting the steelframe, is located the front side and connects the steelframe No. two jacks with be located the rear side and connect the steelframe No. one the jack position corresponds, the slip casting steel pipe is pegged graft with a jack and No. two jacks and is fixed to two connecting the steelframes, and the picture peg and the end-to-end concatenation of butt joint groove through a plurality of connecting the steelframes that set up are ring structure like this to the position of No. two jacks of the connecting the steelframe of front side corresponds with the position of a jack of the connecting the steelframe of rear side, inserts a jack and No. two jacks completion slip casting steel pipe and the concatenation of connecting the steelframe on the same vertical line with the slip casting steel pipe.
The utility model discloses a further improvement lies in, the set screw hole has been seted up to the side of picture peg, the interior edge of set screw hole installs the inflation thread bush, fixing bolt's middle part and set screw hole threaded connection use fixing bolt to decorate the PLASTIC LAMINATED when fixing on connecting the steelframe like this, and fixing bolt's tail end makes screw, connection steelframe and decorates the PLASTIC LAMINATED fixed in inserting the screw, and fixing bolt's middle part and the inboard inflation thread bush of set screw hole are connected and are made inflation thread bush inflation and the preceding butt joint inslot edge contact of connecting the steelframe, increase two fixed effects of connecting between the steelframe.
The utility model discloses a further improvement lies in, the screw has been seted up on the surface of slip casting steel pipe, the position and the set screw hole of screw correspond, fixing bolt's afterbody and screw threaded connection, the lateral groove has been seted up on the surface of slip casting steel pipe and the both sides that are located the screw, there is the axis of rotation along fixed mounting in the lateral groove, the bottom of axis of rotation is rotated and is connected with the rotor plate.
The utility model discloses a further improvement lies in, the entrance of side channel seals and is connected with the elastic sleeve, the surface and the rotor plate of elastic sleeve are fixed, the fixed surface of rotor plate installs outer anti-skidding sawtooth, the position and No. two jacks of rotor plate correspond, and concrete promotion rotor plate rotates around the axis of rotation when pouring into concrete to the slip casting steel pipe is inside like this, and the effect that sets up the elastic sleeve is for preventing that the concrete from leaking from the slip casting steel pipe, makes the contact of following in the outer anti-skidding sawtooth and No. two jacks of rotor plate side to increase the fixed effect of slip casting steel pipe and connection steelframe.
Compared with the prior art, the utility model discloses following beneficial effect has:
1. the picture peg and the butt joint groove of a plurality of connection steelframes through setting up splice for loop configuration end to end, and the position of the No. two jacks of the connection steelframe of front side corresponds with the position of the No. one jack of the connection steelframe of rear side, insert the concatenation of slip casting steel pipe and connection steelframe with a jack and No. two jacks completion slip casting steel pipe on the same vertical line with the slip casting steel pipe, and when using fixing bolt will decorate the PLASTIC LAMINATED and fix on connecting the steelframe, fixing bolt's tail end makes the screw in inserting the screw, it is fixed to connect the steelframe and decorate the PLASTIC LAMINATED, fixing bolt's middle part and the inboard inflation thread bush of set screw hole are connected and are made inflation steelframe thread bush inflation and the contact along the butt joint inslot of the previous connection, increase two fixed effects of connecting between the steelframe.
2. Concrete promotes the rotor plate and rotates around the axis of rotation when to the inside injection concrete of injected steel pipe, makes the contact along in outer anti-skidding sawtooth and the No. two jacks of rotor plate side to increase the fixed effect of injected steel pipe and connection steelframe, during fixing bolt's tail end inserted screw simultaneously, the concrete solidifies fixing bolt's tail end in the inside of injected steel pipe, takes place to become flexible after avoiding fixing bolt to go up the rust.
Drawings
Fig. 1 is the utility model relates to an overall structure schematic diagram of office space steel pipe concrete column body project organization.
Fig. 2 is the utility model relates to a slip casting steel pipe structure schematic diagram of office space steel pipe concrete cylinder project organization.
Fig. 3 is the utility model relates to an office space steel pipe concrete column body project organization's connection steelframe's overall structure's schematic diagram.
Figure 4 is the utility model relates to a slip casting steel pipe schematic drawing of section of office space steel pipe concrete cylinder project organization.
In the figure: 1. a column structural layer; 2. connecting a steel frame; 3. grouting the steel pipe; 4. positioning a screw hole; 5. decorating the fire-proof plate; 6. fixing the bolt; 7. a rotating plate; 8. a screw hole; 9. expanding the threaded sleeve; 10. inserting plates; 11. a first jack; 12. a butt joint groove; 13. a second jack; 14. a side groove; 15. outer anti-slip saw teeth; 16. an elastic sleeve; 17. and rotating the shaft.
Detailed Description
In order to make the technical means, the creative features, the achievement purposes and the functions of the present invention easy to understand, in the description of the present invention, it is to be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. indicate the orientation or the positional relationship based on the orientation or the positional relationship shown in the drawings, only for the convenience of describing the present invention and simplifying the description, but not for indicating or implying that the indicated device or element must have a specific orientation, be constructed and operated in a specific orientation, and thus, cannot be understood as limiting the present invention. Furthermore, the terms "a," "an," "two," and "three" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance. The present invention will be further described with reference to the following detailed description.
Example 1
As shown in fig. 1-4, a concrete-filled steel tube column design structure for office space comprises a column structure layer 1, wherein a plurality of connecting steel frames 2 are fixedly mounted on the outer surface of the column structure layer 1, the connecting steel frames 2 are connected end to form a ring shape, a grouting steel tube 3 is mounted at the joint of the two connecting steel frames 2, a decorative fireproof plate 5 is mounted on the surface of the connecting steel frame 2, a fixing bolt 6 is mounted on the surface of the decorative fireproof plate 5, the tail end of the fixing bolt 6 is located inside the grouting steel tube 3, and concrete is poured into the grouting steel tube 3; an inserting plate 10 is fixedly installed at the front end of the connecting steel frame 2, a butt joint groove 12 is formed in the tail of the connecting steel frame 2, and the butt joint groove 12 located in the front side connecting steel frame 2 is inserted into the inserting plate 10 located in the rear side connecting steel frame 2; the middle part of the plug board 10 is provided with a first jack 11, the tail part of the connecting steel frame 2 is provided with a second jack 13, the second jack 13 positioned on the front side connecting steel frame 2 corresponds to the first jack 11 positioned on the rear side connecting steel frame 2, and the grouting steel pipe 3 is inserted into the first jack 11 and the second jack 13 to fix the two connecting steel frames 2; the side of the inserting plate 10 is provided with a positioning screw hole 4, the inner edge of the positioning screw hole 4 is provided with an expansion threaded sleeve 9, and the middle part of the fixing bolt 6 is in threaded connection with the positioning screw hole 4.
The embodiment can realize that: through the picture peg 10 and the butt joint groove 12 end to end concatenation of a plurality of connection steelframe 2 that set up as loop configuration, and the position of the jack 13 No. two of the connection steelframe 2 of front side corresponds with the position of the jack 11 No. one of the connection steelframe 2 of rear side, accomplish the concatenation of grout steel pipe 3 and connection steelframe 2 with a jack 11 and No. two jacks 13 that insert the grout steel pipe 3 on the same vertical line, and when using fixing bolt 6 to fix the decoration PLASTIC LAMINATED 5 on connecting steelframe 2, the tail end of fixing bolt 6 inserts makes screw hole 8 in the screw hole 8, it is fixed with decoration PLASTIC LAMINATED 5 to connect steelframe 2, the middle part of fixing bolt 6 is connected with the inboard inflation thread bush 9 of set screw hole 4 and makes inflation thread bush 9 inflation contact with the butt joint inslot 12 of the preceding connection steelframe 2, increase two fixed effects between the connection steelframe 2.
Example 2
As shown in fig. 1-4, an office space steel pipe concrete column design structure comprises a column structure layer 1, a connecting steel frame 2 is fixedly installed on the outer surface of the column structure layer 1, a plurality of connecting steel frames 2 are connected end to form a ring shape, a grouting steel pipe 3 is installed at the joint of the two connecting steel frames 2, a decorative fireproof plate 5 is installed on the surface of the connecting steel frame 2, a fixing bolt 6 is installed on the surface of the decorative fireproof plate 5, the tail end of the fixing bolt 6 is located inside the grouting steel pipe 3, and concrete is injected into the grouting steel pipe 3; an inserting plate 10 is fixedly installed at the front end of the connecting steel frame 2, a butt joint groove 12 is formed in the tail of the connecting steel frame 2, and the butt joint groove 12 located in the front side connecting steel frame 2 is inserted into the inserting plate 10 located in the rear side connecting steel frame 2; the middle part of the plug board 10 is provided with a first jack 11, the tail part of the connecting steel frame 2 is provided with a second jack 13, the second jack 13 positioned on the front side connecting steel frame 2 corresponds to the first jack 11 positioned on the rear side connecting steel frame 2, and the grouting steel pipe 3 is inserted into the first jack 11 and the second jack 13 to fix the two connecting steel frames 2; a positioning screw hole 4 is formed in the side face of the inserting plate 10, an expansion threaded sleeve 9 is mounted on the inner edge of the positioning screw hole 4, and the middle of the fixing bolt 6 is in threaded connection with the positioning screw hole 4; the surface of the grouting steel pipe 3 is provided with a screw hole 8, the position of the screw hole 8 corresponds to the position screw hole 4, the tail part of the fixing bolt 6 is in threaded connection with the screw hole 8, side grooves 14 are formed in the surface of the grouting steel pipe 3 and positioned on two sides of the screw hole 8, a rotating shaft 17 is fixedly installed on the inner edge of each side groove 14, and the bottom of each rotating shaft 17 is rotatably connected with a rotating plate 7; an elastic sleeve 16 is connected to an inlet of the side groove 14 in a sealing mode, the outer surface of the elastic sleeve 16 is fixed to the rotating plate 7, outer anti-skidding sawteeth 15 are fixedly installed on the outer surface of the rotating plate 7, and the position of the rotating plate 7 corresponds to the second jack 13.
The embodiment can realize that: concrete promotion rotor plate 7 rotates around axis of rotation 17 when to 3 inside injection concretes of injected steel pipe, along the contact in 15 and No. two jacks 13 of outer anti-skidding sawtooth of rotor plate 7 side, thereby increase injected steel pipe 3 and linking steel frame 2's fixed effect, simultaneously during fixing bolt 6's tail end inserts screw 8, the concrete solidifies fixing bolt 6's tail end in injected steel pipe 3's inside, take place to become flexible after avoiding fixing bolt 6 to go up the rust.
It should be noted that, the utility model relates to a design structure of office space steel pipe concrete column, when in use, firstly, the inserting plates 10 and the butt-joint grooves 12 of a plurality of connecting steel frames 2 are spliced end to form an annular structure and fixed outside the column structure layer 1, and the position of the second jack 13 of the connecting steel frame 2 at the front side corresponds to the position of the first jack 11 of the connecting steel frame 2 at the rear side, the grouting steel pipe 3 is inserted into the first jack 11 and the second jack 13 on the same vertical line to complete the splicing of the grouting steel pipe 3 and the connecting steel frame 2, when the fixing bolt 6 is used to fix the decorative fireproof plate 5 on the connecting steel frame 2, the tail end of the fixing bolt 6 is inserted into the screw hole 8 to fix the screw hole 8, the connecting steel frame 2 and the decorative fireproof plate 5, the middle part of the fixing bolt 6 is connected with the expansion thread sleeve 9 at the inner side of the positioning screw hole 4 to expand the expansion thread sleeve 9 to contact with the inner edge of the butt-joint groove 12 of the previous connecting steel frame 2, concrete promotion rotor plate 7 rotates around axis of rotation 17 when to 3 inside injection concretes of injected steel pipe, along the contact in 15 and No. two jacks 13 of outer anti-skidding sawtooth of rotor plate 7 side, thereby increase injected steel pipe 3 and linking steel frame 2's fixed effect, simultaneously during fixing bolt 6's tail end inserts screw 8, the concrete solidifies fixing bolt 6's tail end in injected steel pipe 3's inside, take place to become flexible after avoiding fixing bolt 6 to go up the rust.
The foregoing shows and describes the basic principles and principal features of the invention, together with the advantages thereof. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only illustrative of the principles of the present invention, and that various changes and modifications may be made without departing from the spirit and scope of the present invention, and all such changes and modifications fall within the scope of the present invention as claimed. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides an office space concrete filled steel tube cylinder project organization, includes cylinder structural layer (1), its characterized in that: the utility model discloses a concrete grouting structure, including cylinder structural layer (1), connecting steel frame (2), a plurality of, connecting steel frame (2) end to end connection constitutes the annular, two the junction of connecting steel frame (2) installs grouting steel pipe (3), the surface mounting of connecting steel frame (2) has decoration PLASTIC LAMINATED (5), the surface mounting who decorates PLASTIC LAMINATED (5) has fixing bolt (6), the tail end of fixing bolt (6) is located the inside of grouting steel pipe (3), the inside injection concrete of grouting steel pipe (3).
2. The office space concrete filled steel tube column design structure of claim 1, wherein: the front end fixed mounting who connects steelframe (2) has picture peg (10), butt joint groove (12) have been seted up to the afterbody of connecting steelframe (2), are located the front side and connect steelframe (2) butt joint groove (12) with be located rear side and connect steelframe (2) picture peg (10) are pegged graft.
3. The concrete filled steel tube column design structure for office space according to claim 2, wherein: jack (11) have been seted up at the middle part of picture peg (10) No. two jack (13) have been seted up to the afterbody of connecting steelframe (2), are located front side connecting steelframe (2) No. two jack (13) with be located rear side connecting steelframe (2) jack (11) position corresponds, slip casting steel pipe (3) are pegged graft with jack (11) and No. two jack (13) and are fixed two connecting steelframe (2).
4. The concrete filled steel tube column design structure for office space according to claim 2, wherein: the side of the inserting plate (10) is provided with a positioning screw hole (4), an expansion thread sleeve (9) is installed on the inner edge of the positioning screw hole (4), and the middle of the fixing bolt (6) is in threaded connection with the positioning screw hole (4).
5. The concrete filled steel tube column design structure for office space according to claim 3, wherein: screw (8) have been seted up on the surface of slip casting steel pipe (3), the position and the set screw hole (4) of screw (8) correspond, the afterbody and screw (8) threaded connection of fixing bolt (6), lateral groove (14) have been seted up on the surface of slip casting steel pipe (3) and the both sides that are located screw (8), there is axis of rotation (17) interior edge fixed mounting of lateral groove (14), the bottom rotation of axis of rotation (17) is connected with rotor plate (7).
6. The concrete-filled steel tube column design structure for the office space according to claim 5, wherein: the entrance of side channel (14) seals and is connected with elastic sleeve (16), the surface and the rotor plate (7) of elastic sleeve (16) are fixed, the fixed surface of rotor plate (7) installs outer anti-skidding sawtooth (15), the position and No. two jack (13) of rotor plate (7) correspond.
CN202220385833.4U 2022-02-25 2022-02-25 Concrete filled steel tube column body design structure for office space Active CN217232487U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220385833.4U CN217232487U (en) 2022-02-25 2022-02-25 Concrete filled steel tube column body design structure for office space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220385833.4U CN217232487U (en) 2022-02-25 2022-02-25 Concrete filled steel tube column body design structure for office space

Publications (1)

Publication Number Publication Date
CN217232487U true CN217232487U (en) 2022-08-19

Family

ID=82836217

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220385833.4U Active CN217232487U (en) 2022-02-25 2022-02-25 Concrete filled steel tube column body design structure for office space

Country Status (1)

Country Link
CN (1) CN217232487U (en)

Similar Documents

Publication Publication Date Title
WO2021057388A1 (en) Apparatus for fabricating concrete shaft wellbore model and usage method
CN217232487U (en) Concrete filled steel tube column body design structure for office space
CN204826423U (en) Prefabricated assembled is reinforcing bar sleeve grout connecting piece for concrete member
CN108442681B (en) Building outer wall scaffold connecting structure and mounting method
CN111305871A (en) Telescopic grouting filling type shield segment soil supporting device and construction method
CN214576913U (en) Tunnel lateral wall drilling extension mould
CN210032718U (en) Anchor rod supporting device for connecting existing masonry wall and new masonry structure
CN210316231U (en) Assembled construction grout sleeve
CN110284705B (en) Sectional type formwork system for reinforcing concrete cylinder
CN210459234U (en) Steel supporting structure and supporting system
CN114215228A (en) Seamless installation and construction process for fair-faced concrete
CN113832985A (en) Foundation pit structure and construction method thereof
CN112012243A (en) Prefabricated integrated reinforced concrete inspection well and construction method thereof
CN219431841U (en) Steel template suitable for small-section tunnel
CN111927377A (en) Energy-saving tunnel advanced small guide pipe quick-assembling grout stopping structure
CN215718791U (en) Tunnel supporting structure of underpass solution cavity
CN212380915U (en) Assembled cable trench
CN110905199A (en) Construction method of aluminum alloy formwork diagonal bracing device
CN216891988U (en) Make things convenient for anchor extension sleeve deeply that buries of mud jacking
CN210368500U (en) Airport cement concrete pavement free end dowel bar fixing device
CN109779252A (en) Building template fixed structure and its screw rod locating sleeve through walls and construction method
CN216196630U (en) Quick filling device for template fixing hole
CN204152205U (en) Decoration exposed concrete construction method split bolt punch die used
CN219909935U (en) Upper formwork grouting equipment of filling wall
CN218030219U (en) Two lining end moulds in country rock profile self-adaptation tunnel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant