CN217128957U CN202220904683.3U CN202220904683U CN217128957U CN 217128957 U CN217128957 U CN 217128957U CN 202220904683 U CN202220904683 U CN 202220904683U CN 217128957 U CN217128957 U CN 217128957U
Authority
CN
China
Prior art keywords
arc
wall
plate
bounding wall
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220904683.3U
Other languages
Chinese (zh)
Inventor
林其涛
刘晓勇
林联远
徐昆
夏庭俊
刘庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Urban Construction Group Co Ltd
First Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Original Assignee
China Railway Urban Construction Group Co Ltd
First Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Urban Construction Group Co Ltd, First Engineering Co Ltd of China Railway Urban Construction Group Co Ltd filed Critical China Railway Urban Construction Group Co Ltd
Priority to CN202220904683.3U priority Critical patent/CN217128957U/en
Application granted granted Critical
Publication of CN217128957U publication Critical patent/CN217128957U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model relates to an oval concrete column construction mould, first bounding wall and second bounding wall including a pair of symmetry, four arcs of outer wall fixedly connected with of first bounding wall and second bounding wall, the arc is connected first bounding wall and second bounding wall for an inside oval-shaped pouring basin that becomes, first bounding wall includes straight board, the first connecting pin of both ends difference fixedly connected with and the second connecting pin of straight board. First bounding wall and second bounding wall carry out the closed loop ground through four arcs and connect, just so can form with oval-shaped casting box in its inside, through pouring concrete in this casting box, will let the concrete solidify the shaping in the casting box, first connecting pin and the second connecting pin that sets up in the both sides of first bounding wall can the joint in the butt joint inslot of arc, just so first bounding wall and arc just are difficult to break away from for the structure is more stable.

Description

Elliptical concrete column construction mould
Technical Field
The utility model relates to a concrete technical field specifically indicates oval concrete column construction mould.
Background
In the construction operation, the post is very common structure, and the template that traditional mode adopted the regularization mostly is under construction, but in order to guarantee the holistic rigidity of template and intensity, the structure of this kind of template is complicated, weight is heavier, uses, transports and all comparatively inconvenient.
The traditional concrete mold is an oval mold, and a common wooden template is easy to warp at a curved surface, so that the template needs to be customized in advance to avoid the warp of the subsequent bent template, and the template is required to have good combination capability.
SUMMERY OF THE UTILITY MODEL
To the above-mentioned problem that prior art exists, the to-be-solved technical problem of the utility model is: the curved surface of the template is prevented from warping and the template is convenient to mount.
In order to solve the technical problem, the utility model adopts the following technical scheme: oval concrete column construction mould, including first bounding wall and the second bounding wall of a pair of symmetry, four arcs of outer wall fixedly connected with of first bounding wall and second bounding wall, the arc is connected first bounding wall and second bounding wall for an inside oval-shaped casting trough that becomes.
First bounding wall includes straight board, the both ends of straight board are first connecting pin of fixedly connected with and second connecting pin respectively, the straight board is kept away from the first fixed ear of one side fixedly connected with and the fixed ear of second of pouring gate, and the fixed ear symmetry of first fixed ear and second sets up the position that is close to both ends in straight board side, the arc includes the right angle board, the interior angle department fixedly connected with arc panel of right angle board, butt joint groove has been seted up to the inner wall of a straight flange of right angle board, should butt joint groove and the fixed ear sliding connection of adjacent first fixed ear or adjacent second, the ground needle that ground can be inserted to the bottom outer wall fixedly connected with of arc, the connecting hole that can insert the ground needle is seted up at the inner wall top of arc, the outside of first bounding wall is provided with the scaffold frame.
The first enclosing plate and the second enclosing plate are connected in a closed loop mode through the four arc-shaped plates, so that an oval pouring groove can be formed in the first enclosing plate, concrete can be solidified and formed in the pouring groove by pouring concrete in the pouring groove, the first connecting pin and the second connecting pin which are arranged on two sides of the first enclosing plate can be clamped in the butt joint grooves of the arc-shaped plates, so that the first enclosing plate and the arc-shaped plates are not easy to separate, the structure is more stable, meanwhile, the arc-shaped plates are also plastic plates of the upper arc surfaces of the oval concrete columns, the curve-shaped plates prefabricated in advance can prevent the curved-surface templates from warping, the arc-shaped plates can be inserted into the ground through ground pins at the bottoms of the arc-shaped plates, the stability of the molds on the ground can be improved, when the two groups of molds are accumulated together to increase the shaping height of the molds, the ground pins are required to be inserted into the connecting holes, and the ground pins are limited through the connecting holes, the degree of agreeing with of two moulds can be improved, can keep concrete column and ground perpendicular simultaneously.
Preferably, the outer wall of one straight side of the right-angle plate is fixedly connected with a first connecting lug, and the outer wall of the other straight side of the right-angle plate is fixedly connected with a second connecting lug. The assembling combination of the internal mold can be realized through the first connecting lug and the second connecting lug.
Preferably, the ground needle comprises a cylinder, and a conical needle head is fixedly connected to one end of the cylinder. The needle head increases the pressure intensity by reducing the area, so that the column body can be inserted into the ground more conveniently.
Preferably, the scaffold is arranged on the outer side of the first enclosing plate and comprises a plurality of vertical rods, a plurality of cross rods, a plurality of longitudinal rods and a plurality of fixing pieces for fixing the vertical rods, the cross rods and the longitudinal rods.
The scaffold is wholly cubic, and wherein montant, horizontal pole and vertical pole have constituted the limit of scaffold, and these limits are connected through the hole on the mounting in its respective summit department, and these holes are non-intersect in the space, need install fastening screw when fixed and ensure the stability of montant, horizontal pole and vertical pole to horizontal pole and vertical pole can block between two first engaging lugs and two second engaging lugs, thereby strengthen the firmness to inside mould.
Preferably, the outer wall of the cross rod is attached to the outer wall of the arc-shaped plate, and the outer wall of the longitudinal rod is attached to the outer wall of the arc-shaped plate. Let vertical pole and horizontal pole laminating mould, just make scaffold frame to the structural connection of assembling die inseparabler, never let the mould not hard up.
Preferably, the first enclosing plate is connected with the arc-shaped plate through a bolt. The two arc plates are connected through bolts. The integral structure of the die is fixed through the bolts, subsequent dismantling can be facilitated, and if the die is connected in a welding mode, all devices of the die cannot be recycled, so that the die can become a disposable product.
As preferred, the inside of first bounding wall is equipped with detection mechanism, detection mechanism includes stretching plate, fixed cover, hardness detector, thread bush, transmission line and threaded rod, open the upper surface of first bounding wall has the recess, stretching plate movable mounting is in the inside of recess, fixed cover fixed mounting is in the inside of first bounding wall, thread bush and fixed cover fixed connection, thread bush and threaded rod threaded connection, hardness detector movable mounting is in the inside of thread bush, and hardness detector's top and threaded rod swing joint, hardness detector's last fixed surface installs transmission line and activity through threaded rod, extends to the outside of threaded rod.
Preferably, the outer wall of one side of each of the first enclosing plate and the second enclosing plate is provided with a limiting mechanism, each limiting mechanism comprises a screw rod, a threaded cylinder, a limiting lug, a movable plate, an anti-skidding sleeve and a telescopic rod, the limiting lugs are fixedly arranged on the outer walls of the first enclosing plate and the second enclosing plate, the telescopic rods are movably connected inside the limiting lugs, the telescopic rods are movably connected with the first fixing lugs and the first connecting lugs, one end of each telescopic rod is fixedly connected with the movable plate, one side of the movable plate is movably connected with the screw rod through a bearing, the screw rod is in threaded connection with the threaded cylinders, and the anti-skidding sleeves are fixedly arranged on the outer side surfaces of the threaded cylinders.
Compared with the prior art, the utility model discloses at least, following advantage has:
the technical effects must be elaborated in conjunction with the technical solutions. The following modes are adopted:
1. the first enclosing plate and the second enclosing plate are connected in a closed loop mode through the four arc-shaped plates, so that an oval pouring groove can be formed in the first enclosing plate, concrete can be solidified and formed in the pouring groove by pouring concrete in the pouring groove, the first connecting pin and the second connecting pin which are arranged on two sides of the first enclosing plate can be clamped in the butt joint grooves of the arc-shaped plates, so that the first enclosing plate and the arc-shaped plates are not easy to separate, the structure is more stable, meanwhile, the arc-shaped plates are also plastic plates of the upper arc surfaces of the oval concrete columns, the curve-shaped plates prefabricated in advance can prevent the curved-surface templates from warping, the arc-shaped plates can be inserted into the ground through ground pins at the bottoms of the arc-shaped plates, the stability of the molds on the ground can be improved, when the two groups of molds are accumulated together to increase the shaping height of the molds, the ground pins are required to be inserted into the connecting holes, and the ground pins are limited through the connecting holes, the degree of agreeing with of two moulds can be improved, can keep concrete column and ground perpendicular simultaneously.
2. Just can strengthen the intensity of equipment back mould through the scaffold, the scaffold wholly is the cube, wherein montant, horizontal pole and vertical pole have constituted the limit of scaffold, these limits are connected through the hole on the mounting in its respective summit department, these holes are non-intersect in the space, need install fastening screw to ensure the stability of montant, horizontal pole and vertical pole when fixed, and horizontal pole and vertical pole can block between two first engaging lugs and two second engaging lugs, thereby strengthen the firmness to inside mould.
3. After the concrete is poured in the pouring groove, the tensile plate is taken out to the accessible to the threaded rod is rotated, and then drives the hardness detector and removes, makes the hardness detector contact with the concrete that the pouring was accomplished, and then the hardness detector is opened to the external controller of accessible, carries out hardness detection to the concrete that the pouring was accomplished, can check whether the concrete that the pouring was accomplished reaches qualified standard, is convenient for judge whether the concrete can be put into use, and then improves concrete shaping quality.
4. First bounding wall and second bounding wall when the installation, need fix engaging lug and fixed ear to it and insert the connecting pin, at this moment need keep first bounding wall and second bounding wall fixed, the accessible rotates a screw section of thick bamboo and then drives the lead screw and rotate, make the movable plate drive the telescopic link and remove, and telescopic link and fixed ear and engaging lug contact, alright make first bounding wall and second bounding wall carry out relatively fixed, need not the manual work at this moment and fix first bounding wall and second bounding wall, the material resources of using manpower sparingly, the operation is simple, convenient to use, and the work efficiency is improved, be convenient for install the quick of first bounding wall and second bounding wall.
Drawings
Fig. 1 is a schematic view showing the overall structure of an oval concrete column-working mold according to examples 1 to 3.
Fig. 2 is a schematic structural view of the first enclosing plate structure of embodiment 1.
Fig. 3 is a schematic structural view of an arc-shaped plate structure of embodiment 1.
Fig. 4 is a schematic structural view of a mold assembly structure of embodiment 2.
Fig. 5 is a schematic sectional view of the hardness detection mechanism according to embodiment 2.
Fig. 6 is an enlarged schematic view of a portion a in fig. 5.
Fig. 7 is a schematic sectional view of the limiting mechanism.
In the figure, a first enclosing plate-1, a second enclosing plate-2, an arc-shaped plate-3, a ground pin-4, a connecting hole-5, a scaffold-6, a straight plate-100, a first connecting pin-101, a second connecting pin-102, a first fixing lug-103, a second fixing lug-104, a right-angle plate-300, an arc-shaped plate-301, an abutting groove-302, a first connecting lug-303, a second connecting lug-304, a column-400, a needle-401, a vertical rod-600, a transverse rod-601, a longitudinal rod-602, a fixing piece-603, a hardness detection mechanism-7, a stretching plate-71, a fixing sleeve-72, a hardness detection instrument-73, a threaded sleeve-74, a transmission line-75, a threaded rod-76, a limiting mechanism-8, a screw rod-81, a threaded cylinder-82, a limiting lug-83, a moving plate-84, an anti-slip sleeve-85 and a telescopic rod-86.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1-7, the oval concrete column construction mold comprises a pair of symmetrical first enclosing plate 1 and second enclosing plate 2, four arc-shaped plates 3 are fixedly connected to the outer walls of the first enclosing plate 1 and the second enclosing plate 2, and the first enclosing plate 1 and the second enclosing plate 2 are connected into a pouring groove with an oval inner part through the arc-shaped plates 3.
First bounding wall 1 includes straight board 100, the first connecting pin 101 of one side fixedly connected with and second connecting pin 102 of straight board 100 respectively, straight board 100 is kept away from the first fixed ear 103 of one side fixedly connected with and the fixed ear 104 of second of pouring gate, first fixed ear 103 and the fixed ear 104 symmetry of second set up the position that is close to both ends in straight board 100 side, arc 3 includes right-angle plate 300, interior angle department fixedly connected with arc panel 301 of right-angle plate 300, butt joint groove 302 has been seted up to the inner wall of a straight flange of right-angle plate 300, this butt joint groove 302 and the fixed ear 104 sliding connection of adjacent first fixed ear 103 or adjacent second, ground needle 4 that ground can be inserted to the bottom outer wall fixedly connected with of arc 3, connecting hole 5 that can insert ground needle 4 is seted up at the inner wall top of arc 3, the outside of first bounding wall 1 is provided with scaffold 6.
The first enclosing plate 1 and the second enclosing plate 2 are connected in a closed loop mode through the four arc-shaped plates 3, so that an oval pouring groove can be formed in the first enclosing plate 1, concrete can be solidified and formed in the pouring groove by pouring the concrete in the pouring groove, the first connecting pin 101 and the second connecting pin 102 which are arranged on two sides of the first enclosing plate 1 can be clamped in the butt joint groove 302 of the arc-shaped plates 3, so that the first enclosing plate 1 and the arc-shaped plates 3 are not easy to separate, the structure is more stable, meanwhile, the arc-shaped plates 3 are also plastic plates of the cambered surfaces on oval concrete columns, the curved surface templates can be prevented from warping through the arc-shaped plates 3 prefabricated in advance, the arc-shaped plates 3 can be inserted underground through the ground pins 4 at the bottoms of the arc-shaped plates 3, the stability of the die on the ground can be improved, when two groups of dies are accumulated together to increase the molding height of the die, need insert ground needle 4 in the connecting hole 5, come to carry on spacingly to ground needle 4 through connecting hole 5, can improve the degree of agreeing with of two moulds, can keep concrete column and ground vertical simultaneously.
The outer wall fixedly connected with of a straight flange of right-angle plate 300 first engaging lug 303, the outer wall fixedly connected with second engaging lug 304 of another straight flange of right-angle plate 300, ground needle 4 includes cylinder 400, the conical syringe needle 401 of one end fixedly connected with of cylinder 400, still including setting up the scaffold frame 6 in the outside of first bounding wall 1, scaffold frame 6 includes a plurality of montants 600, a plurality of horizontal poles 601, a plurality of vertical poles 602 and a plurality of mounting 603 that are used for fixed three, the outer wall of horizontal pole 601 and the outer wall laminating of arc 3, the outer wall of vertical pole 602 and the outer wall laminating of arc 3.
The strength of the assembled mold can be enhanced by the scaffold 6, the scaffold 6 is integrally cubic, wherein the vertical bars 600, the horizontal bars 601 and the vertical bars 602 form the edges of the scaffold 6, the edges are connected at the respective vertexes thereof through the holes in the fixing members 603, the holes are not intersected in space, fastening screws are required to be installed to ensure the stability of the vertical bars 600, the horizontal bars 601 and the vertical bars 602 when the scaffold is fixed, and the horizontal bars 601 and the vertical bars 602 are clamped between the two first connecting lugs 303 and the two second connecting lugs 304, so that the firmness of the inner mold is enhanced.
First bounding wall 1 passes through bolted connection with arc 3, passes through bolted connection between two arcs 3. The integral structure of the die is fixed through the bolts, subsequent dismantling can be facilitated, and if the die is connected in a welding mode, all devices of the die cannot be recycled, so that the die can become a disposable product.
Detection mechanism 7 is equipped with in the inside of first bounding wall 1, detection mechanism 7 includes stretching plate 71, fixed cover 72, hardness detector 73, thread bush 74, transmission line 75 and threaded rod 76, open flutedly on the upper surface of first bounding wall 1, stretching plate 71 movable mounting is in the inside of recess, fixed cover 72 fixed mounting is in the inside of first bounding wall 1, thread bush 74 and fixed cover 72 fixed connection, thread bush 74 and threaded rod 76 threaded connection, hardness detector 73 movable mounting is in the inside of thread bush 74, and the top and the threaded rod 76 movable connection of hardness detector 73, the last fixed surface of hardness detector 73 installs the transmission line and the activity runs through threaded rod 76, extend to the outside of threaded rod 76.
After the concrete is poured in the pouring groove, the tensile plate 71 can be drawn out, the threaded rod 76 is rotated, the hardness detector 73 is driven to move, the hardness detector 73 is made to be in contact with the concrete after pouring, the hardness detector 73 can be opened through an external controller, the concrete after pouring is subjected to hardness detection, whether the concrete after pouring meets the qualified standard or not can be checked, whether the concrete can be put into use or not can be judged conveniently, and the concrete forming quality can be improved.
One side outer wall of first bounding wall 1 and second bounding wall 2 all is equipped with stop gear 8, stop gear 8 includes lead screw 81, a screw thread section of thick bamboo 82, spacing ear 83, movable plate 84, anti-skidding cover 85 and telescopic link 86, spacing ear 83 fixed mounting is at the outer wall of first bounding wall 1 and second bounding wall 2, the inside swing joint of spacing ear 83 has the telescopic link, telescopic link 86 and first fixed ear 103 and first connection ear 303 swing joint, the one end and the movable plate 84 fixed connection of telescopic link 86, bearing and lead screw 81 swing joint are passed through to one side of movable plate 84, lead screw 81 and screw thread section of thick bamboo 82 threaded connection, anti-skidding cover 85 fixed mounting is on the outside surface of a screw thread section of thick bamboo 82.
First bounding wall 1 and second bounding wall 2 when the installation, need fix engaging lug and fixed ear to it and insert the connecting pin, at this moment need keep first bounding wall 1 and second bounding wall 2 fixed, the accessible rotates screw thread section of thick bamboo 82 and then drives lead screw 81 and rotate, make movable plate 84 drive telescopic link 86 and remove, and telescopic link 86 and fixed ear and engaging lug contact, alright make first bounding wall 1 and second bounding wall 2 carry out the relatively fixed, need not the manual work at this moment and fix first bounding wall 1 and second bounding wall 2, the material resources of using manpower sparingly, the operation is thus simple, and convenient to use is realized, the work efficiency is improved, be convenient for install first bounding wall 1 and second bounding wall 2 fast.
Finally, although the present invention has been described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that the present invention can be modified or replaced by other means without departing from the spirit and scope of the present invention, which should be construed as limited only by the appended claims.

Claims (5)

1. Oval concrete column construction mould, its characterized in that: the pouring trough comprises a pair of symmetrical first enclosing plate (1) and second enclosing plate (2), wherein the outer walls of the first enclosing plate (1) and the second enclosing plate (2) are fixedly connected with four arc-shaped plates (3), and the first enclosing plate (1) and the second enclosing plate (2) are connected into a pouring trough with an oval inner part through the arc-shaped plates (3);
the first enclosing plate (1) comprises a straight plate (100), two ends of the straight plate (100) are fixedly connected with a first connecting pin (101) and a second connecting pin (102) respectively, one side, far away from a pouring groove, of the straight plate (100) is fixedly connected with a first fixing lug (103) and a second fixing lug (104), the first fixing lug (103) and the second fixing lug (104) are symmetrically arranged at positions, close to two ends, of the side face of the straight plate (100), the arc plate (3) comprises a right-angle plate (300), an arc panel (301) is fixedly connected to an inner angle of the right-angle plate (300), a butt joint groove (302) is formed in the inner wall of one straight edge of the right-angle plate (300), and the butt joint groove (302) is in sliding connection with the adjacent first fixing lug (103) or the adjacent second fixing lug (104);
the bottom outer wall fixedly connected with of arc (3) can insert ground needle (4) on ground, connecting hole (5) that can insert ground needle (4) are seted up at the inner wall top of arc (3), the outside of first bounding wall (1) is provided with scaffold frame (6).
2. The elliptical concrete column working mold according to claim 1, characterized in that: the outer wall of one straight side of the right-angle plate (300) is fixedly connected with a first connecting lug (303), and the outer wall of the other straight side of the right-angle plate (300) is fixedly connected with a second connecting lug (304).
3. The elliptical concrete column construction mold of claim 2, wherein: the ground needle (4) comprises a cylinder (400), and one end of the cylinder (400) is fixedly connected with a conical needle head (401).
4. The elliptical concrete column construction mold of claim 2, wherein: still including setting up scaffold (6) in the outside of first bounding wall (1), scaffold (6) include a plurality of montants (600), a plurality of horizontal pole (601), a plurality of vertical pole (602) and a plurality of mounting (603) that are used for fixed three.
5. The elliptical concrete column working mold according to claim 4, wherein: the outer wall of horizontal pole (601) and the outer wall laminating of arc (3), the outer wall laminating of outer wall and the arc (3) of vertical pole (602).
CN202220904683.3U 2022-04-19 2022-04-19 Elliptical concrete column construction mould Active CN217128957U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220904683.3U CN217128957U (en) 2022-04-19 2022-04-19 Elliptical concrete column construction mould

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220904683.3U CN217128957U (en) 2022-04-19 2022-04-19 Elliptical concrete column construction mould

Publications (1)

Publication Number Publication Date
CN217128957U true CN217128957U (en) 2022-08-05

Family

ID=82649987

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220904683.3U Active CN217128957U (en) 2022-04-19 2022-04-19 Elliptical concrete column construction mould

Country Status (1)

Country Link
CN (1) CN217128957U (en)

Similar Documents

Publication Publication Date Title
CN217128957U (en) Elliptical concrete column construction mould
CN216427858U (en) Linear adjusting template device for post-cast section of curved track beam
WO2022116585A1 (en) Push-pull-type disassembling and assembling device and disassembling and assembling method for top mold of double-t-beam pouring mold
CN214925429U (en) Prefabricated steel mould of brickwork
CN110344333B (en) Internal mold splicing module, variable integral-disassembly type internal mold and construction process of internal mold splicing module
CN210850741U (en) Prefabricated window production mould that wafts
CN209742366U (en) Supporting system for integral lifting in cylinder
CN210414970U (en) Prefabricated trench mould system of assembled
CN109826437B (en) Supporting system for integrally lifting in cylinder
CN112895087A (en) Integral tunnel inverted arch block die
CN111251423A (en) Mould for producing prefabricated reinforced concrete hollow template with cross holes therein
CN219410570U (en) Assembly type box inner die for municipal construction
CN111283852A (en) Production device for prefabricated hollow template with crossed holes inside
CN219132682U (en) Egg-shaped groove die
CN221271506U (en) Prefabricated component mould
CN210282673U (en) Stair prefabricating mold
CN220389783U (en) Prefabricated concrete cover plate steel wood assembling die with adjustable
CN220389788U (en) Prefabricated bay window die
CN218519066U (en) New energy automobile skylight four-side edge strip injection molding combination mold
TWI588342B (en) A compound assembly moldboard applied to construction.
CN215549636U (en) Rapid demoulding's building engineering room is built and is used prefabricated wall body mould
CN215564441U (en) Building assembled construction mould
CN212193599U (en) Production device for prefabricated hollow template with crossed holes inside
CN218535402U (en) Injection molding machine clamping head plate convenient to replace