CN217106146U - Template device for rapidly constructing arc beam - Google Patents

Template device for rapidly constructing arc beam Download PDF

Info

Publication number
CN217106146U
CN217106146U CN202220617556.5U CN202220617556U CN217106146U CN 217106146 U CN217106146 U CN 217106146U CN 202220617556 U CN202220617556 U CN 202220617556U CN 217106146 U CN217106146 U CN 217106146U
Authority
CN
China
Prior art keywords
template
plate
formwork
rod
arc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220617556.5U
Other languages
Chinese (zh)
Inventor
郭旭
芦晨
黄崇武
伍琦
路迪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No6 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
No6 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No6 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical No6 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority to CN202220617556.5U priority Critical patent/CN217106146U/en
Application granted granted Critical
Publication of CN217106146U publication Critical patent/CN217106146U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a template device of rapid construction arc beam relates to building engineering technical field. The utility model discloses a first template, the second template, the horizontal pole, branch and baffle, first template and second template are through outside bolted connection, the both ends of first template and second template are connected with the baffle jointly, the both sides of first template and second template can be dismantled and are connected with branch, the overlap joint has the horizontal pole on the branch, the jack runs through and sets up on the plate body, the equidistant bottom at the plate body of fixing of backing plate and engaging lug, branch includes the extension board, the hanging piece, the body of rod and bottom plate, the upper portion at the body of rod inboard is fixed to the extension board, the hanging piece joint is at the top of the body of rod, the bottom plate welding is in the bottom of the body of rod. The utility model discloses a be connected with branch in first template and the second template, the terminal surface of first template and second template is connected with the baffle, has solved current arc beam template, and the person of not being convenient for is under construction fast and current arc beam template, does not have the problem of better firm effect.

Description

Template device for rapidly constructing arc beam
Technical Field
The utility model belongs to the technical field of building engineering, especially, relate to a template device of rapid construction arc beam.
Background
Building engineering often can meet curved concrete beam at the in-process of construction, and concrete beam need use the arc roof beam template when putting up, but the following drawback still exists in the in-service use of current arc roof beam template:
1. the existing arc-shaped beam template is inconvenient for a user to construct quickly, and the user has inconvenience in actual use;
2. the existing arc-shaped beam template does not have a good stabilizing effect, and great hidden dangers exist in the construction process.
Therefore, the existing arc beam formwork cannot meet the requirements in practical use, so that an improved technology is urgently needed in the market to solve the problems.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a template device of rapid construction arc beam is connected with branch through first template and second template, and the terminal surface of first template and second template is connected with the baffle, has solved current arc beam template, and the quick construction of person of not being convenient for and current arc beam template do not have the problem of better firm effect.
In order to solve the technical problem, the utility model discloses a realize through following technical scheme:
the utility model relates to a template device for quickly constructing an arc beam, which comprises a first template, a second template, a cross bar, a support bar and a baffle plate, wherein the first template and the second template are connected through an external bolt, the two ends of the first template and the second template are connected with the baffle plate together, the external bolt can lead the first template and the second template to be matched with the baffle plate to form a pouring cavity, the two sides of the first template and the second template are detachably connected with the support bar, the cross bar is lapped on the support bar, the support bar can stably support the first template and the second template when in use, the first template comprises a jack, a backing plate, a connecting lug and a plate body, the jack is arranged on the plate body in a penetrating way, after the first template and the second template form the pouring cavity, a user inserts a steel bar in the jack, on one hand, the connecting strength of the first template and the second template can be improved, on the other hand, the strength of the arc beam can be improved, the base plate and the connecting lugs are fixed at the bottom of the plate body at equal intervals, the supporting rod comprises a supporting plate, a hanging block, a rod body and a bottom plate, the supporting plate is fixed at the upper part of the inner side of the rod body, the hanging block is clamped at the top of the rod body, and the bottom plate is welded at the bottom of the rod body.
Further, the baffle is connected with the first template and the second template through external bolts, and the baffle is of a sheet structure.
Further, the plate body is arc-shaped, and the end face of the plate body is Z-shaped.
Furthermore, the hanging block is in a bent plate shape, and the connecting end of the hanging block is fixed with the second template.
Furthermore, the top of the support plate is abutted to the base plate, and a round hole matched with the cross rod is formed in the rod body.
Furthermore, the first template and the second template have the same structure, and the first template is also connected with a hanging block.
The utility model discloses following beneficial effect has:
1. the utility model discloses when using, the user is connected with the building after with first template and second template equipment, the user pours the concrete into a mould in the inner chamber that first template and second template are constituteed simultaneously, can make arc roof beam casting shaping, first template and second template pass through branch support, can make the arc roof beam template firm the connection on building, hanger block and first template and second template welding simultaneously, the body of rod and hanger block joint, can be convenient for follow-up body of rod and first template and second template are dismantled, first template and second template pass through bolted connection, the baffle passes through the bolt and is connected with first template and second template, can the person of facilitating the use will the utility model discloses dismantle with the arc roof beam, current arc roof beam template has been solved, the quick problem of being under construction of the person of being not convenient for.
2. When the utility model is used, the supporting rods connected with the first template and the second template are connected through the cross rods, so that the supporting rods have better stabilizing effect, meanwhile, the jack is arranged on the plate body, a user inserts the reinforcing steel bar into the inner cavity formed by the first template and the second template, on one hand, the poured arc-shaped beam is convenient to connect with the building, on the other hand, the first template and the second template are not easy to separate from the arc-shaped beam, the stabilizing effect of the utility model can be improved, the first template and the second template can be conveniently disassembled by a user, the supporting rod is convenient to be detached during the use process, the body of rod and extension board support first template and second template, can further promote the firm effect of first template and second template, can make first template and second template difficult and arc roof beam break away from, have solved current arc roof beam template, do not have the problem of better firm effect.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural diagram of a first template according to the present invention;
fig. 3 is a connection structure diagram of the middle cross bar and the support bar of the present invention.
In the drawings, the components represented by the respective reference numerals are listed below:
1. a first template; 11. a jack; 12. a base plate; 13. connecting lugs; 14. a plate body; 2. a second template; 3. a cross bar; 4. a strut; 41. a support plate; 42. hanging blocks; 43. a rod body; 44. a base plate; 5. and a baffle plate.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
Referring to fig. 1-3, the utility model relates to a template device for fast constructing arc beam, comprising a first template 1, a second template 2, a cross bar 3, a support bar 4 and a baffle 5, wherein the first template 1 and the second template 2 are connected by external bolts, the two ends of the first template 1 and the second template 2 are connected with the baffle 5 together, the first template 1 and the second template 2 have the same structure, the first template 1 is also connected with a hanging block 42, the two sides of the first template 1 and the second template 2 are detachably connected with the support bar 4, the cross bar 3 is lapped on the support bar 4, the cross bar 3 and the support bar 4 are detachably connected, meanwhile, the cross bar 3 can not be separated from the support bar 4 under the conventional state, the baffle 5 is connected with the first template 1 and the second template 2 by external bolts, the baffle 5 is of a sheet structure, when the utility model is used, a user connects the first template 1 and the second template 2 by external bolts, baffle 5 is connected with first template 1 and second template 2 through outside bolt, can make first template 1 and second template 2 and baffle 5 constitute the pouring cavity, the user connects first template 1 and second template 2 on building afterwards, can the person of facilitating the use with arc roof beam casting shaping, branch 4 is when using, the user is connected branch 4 with first template 1 and second template 2, first template 1 and second template 2 receive the support of branch 4, can make first template 1 and second template 2 firm the connection on outside building, horizontal pole 3 is when using, can make branch 4 of being connected more firm on first template 1 and the second template 2, avoid branch 4 to the unstable support of first template 1 and second template 2.
As shown in fig. 1-2, the first formwork 1 includes an insertion hole 11, a backing plate 12, a connection lug 13 and a plate body 14, the insertion hole 11 penetrates through the plate body 14, the backing plate 12 and the connection lug 13 are fixed at the bottom of the plate body 14 at equal intervals, the plate body 14 is arc-shaped, the end face of the plate body 14 is Z-shaped, when the first formwork 1 is used, the insertion hole 11 can facilitate a user to insert a steel bar, when the steel bar is connected with concrete, the connection strength between the first formwork 1 and the arc-shaped beam and between the second formwork 2 and the arc-shaped beam can be increased, meanwhile, the arc-shaped beam can be connected with a building conveniently, when the connection lug 13 is used, the first formwork 1 and the second formwork 2 can be connected through an external bolt conveniently, and therefore a pouring cavity is formed by matching with the baffle 5.
As shown in fig. 1 and 3, the supporting rod 4 includes a supporting plate 41, a hanging block 42, a rod body 43 and a bottom plate 44, the supporting plate 41 is fixed on the upper portion of the inner side of the rod body 43, the top of the supporting plate 41 is abutted against the backing plate 12, a round hole matched with the cross rod 3 is formed in the rod body 43, the hanging block 42 is clamped on the top of the rod body 43, the hanging block 42 is in a bent plate shape, the connecting end of the hanging block 42 is fixed with the second template 2, the bottom plate 44 is welded on the bottom of the rod body 43, when the supporting rod 4 is used, a user assembles the supporting rod 4, the user welds the hanging block 42 on the first template 1 and the second template 2, the rod body 43 is clamped with the hanging block 42, the bottom of the bottom plate 44 is connected with the ground, the supporting plate 41 is abutted against the first template 1 and the second template 2, the supporting rod 4 can support the first template 1 and the second template 2, and the supporting rod 4 is connected with the cross rod 3 together by the user during the supporting process, can increase the supporting strength of the supporting rod 4, realize the utility model discloses a firm use.
One specific application of this embodiment is: first step, the user passes through outside bolted connection with first template 1 and second template 2, first template 1 and second template 2 are connected with the building simultaneously, when first template 1 and 2 cooperation baffles of second template 5 simultaneously, can constitute the concrete placement cavity, the second step, the user is connected branch 4 with first template 1 and second template 2, can make branch 4 support first template 1 and second template 2, improve the joint strength of first template 1 and second template 2 and building, the third step, the user is with grafting reinforcing bar on first template 1 and the second template 2, horizontal pole 3 is connected branch 4 on first template 1 and the second template 2 simultaneously, can make the utility model discloses stabilize the use.
The above is only the preferred embodiment of the present invention, and the present invention is not limited thereto, any technical solutions recorded in the foregoing embodiments are modified, and some technical features thereof are replaced with equivalent ones, and any modification, equivalent replacement, and improvement made thereby all belong to the protection scope of the present invention.

Claims (6)

1. The utility model provides a template device of rapid construction arc beam, includes first template (1), second template (2), horizontal pole (3), branch (4) and baffle (5), its characterized in that: the first template (1) is connected with the second template (2) through an external bolt, two ends of the first template (1) and two ends of the second template (2) are connected with a baffle (5) together, two sides of the first template (1) and two sides of the second template (2) are detachably connected with supporting rods (4), and cross rods (3) are lapped on the supporting rods (4);
the first template (1) comprises insertion holes (11), a base plate (12), connecting lugs (13) and a plate body (14), wherein the insertion holes (11) are formed in the plate body (14) in a penetrating mode, and the base plate (12) and the connecting lugs (13) are fixed to the bottom of the plate body (14) at equal intervals;
the supporting rod (4) comprises a supporting plate (41), a hanging block (42), a rod body (43) and a bottom plate (44), the supporting plate (41) is fixed on the upper portion of the inner side of the rod body (43), the hanging block (42) is clamped at the top of the rod body (43), and the bottom plate (44) is welded at the bottom of the rod body (43).
2. The formwork arrangement for rapidly constructing an arc beam according to claim 1, wherein the barrier (5) is connected to the first formwork (1) and the second formwork (2) by external bolts, the barrier (5) being of a sheet structure.
3. The formwork apparatus for rapidly constructing an arc beam according to claim 1, wherein the plate body (14) is arc-shaped, and the end surface of the plate body (14) is Z-shaped.
4. The formwork apparatus for rapidly constructing an arc beam according to claim 1, wherein the hanging block (42) is formed in a bent plate shape, and the connecting end of the hanging block (42) is fixed to the second formwork (2).
5. The template device for rapidly constructing the arc-shaped beam according to claim 1, wherein the top of the support plate (41) is abutted against the base plate (12), and a circular hole matched with the cross rod (3) is formed in the rod body (43).
6. The formwork arrangement for a rapid construction of an arc beam according to claim 1, wherein the first formwork (1) and the second formwork (2) are identical in structure, and the first formwork (1) is also connected with a hanging block (42).
CN202220617556.5U 2022-03-18 2022-03-18 Template device for rapidly constructing arc beam Active CN217106146U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220617556.5U CN217106146U (en) 2022-03-18 2022-03-18 Template device for rapidly constructing arc beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220617556.5U CN217106146U (en) 2022-03-18 2022-03-18 Template device for rapidly constructing arc beam

Publications (1)

Publication Number Publication Date
CN217106146U true CN217106146U (en) 2022-08-02

Family

ID=82603043

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220617556.5U Active CN217106146U (en) 2022-03-18 2022-03-18 Template device for rapidly constructing arc beam

Country Status (1)

Country Link
CN (1) CN217106146U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117803177A (en) * 2023-12-05 2024-04-02 中铁五局集团华南工程有限责任公司 Adjustable arc beam formwork device and application method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117803177A (en) * 2023-12-05 2024-04-02 中铁五局集团华南工程有限责任公司 Adjustable arc beam formwork device and application method thereof

Similar Documents

Publication Publication Date Title
CN217106146U (en) Template device for rapidly constructing arc beam
CN110512865B (en) Beam formwork support frame, support structure and construction method
CN210563446U (en) Novel inside pouring of strength steel concrete post device
CN209723016U (en) Foundation structure for tower crane
CN211369536U (en) Cast-in-place box girder template system
CN212453572U (en) Embedded bolt wall connecting piece device
CN210828318U (en) Be applied to super thick vertical concrete structure template system interior angle reinforced structure
CN207863567U (en) Non-prestressed flange assembles electric pole special flange disk
CN213868910U (en) Internal corner connecting piece of aluminum alloy template
CN212743365U (en) Mould hanging device convenient for hoisting caisson type toilet construction template
CN214996320U (en) Arch crown channel can have enough to meet need regularization support frame
CN215631623U (en) Flexible template structure for casting concrete cylinder
CN210482242U (en) Cylindrical tail water surge chamber impedance plate concrete pouring combined supporting system
CN109235921B (en) Construction method for reforming and reinforcing upright post of concrete chimney and application thereof
CN110905220A (en) Installation and construction method of anti-buckling energy dissipation brace of reinforced concrete structure
CN211172626U (en) Strengthening and supporting device in profiled steel sheet and concrete combined floor slab
CN218346780U (en) Vertical rod fixing device for overhanging scaffold
CN110485633A (en) A kind of steel core concrete column fast joint structure and method
CN217871020U (en) Steel structure embedded part for arc beam
CN215907394U (en) Stable form steel bar truss floor carrier plate that anti performance of cracking is high
CN214942358U (en) Triangular form hangs mould strutting arrangement
CN216973392U (en) Shaping template
CN220953358U (en) High-strength prestressed concrete pipe pile
CN215977737U (en) Connection structure of high district building carrier plate and low district building carrier plate
CN218234014U (en) Ultra-long concrete building structure provided with connector prestressed tendons

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant