CN217051320U - A jib structure for hoisting piping lane - Google Patents
A jib structure for hoisting piping lane Download PDFInfo
- Publication number
- CN217051320U CN217051320U CN202123091452.XU CN202123091452U CN217051320U CN 217051320 U CN217051320 U CN 217051320U CN 202123091452 U CN202123091452 U CN 202123091452U CN 217051320 U CN217051320 U CN 217051320U
- Authority
- CN
- China
- Prior art keywords
- connecting plate
- hoisting
- mounting hole
- boom
- jib
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model relates to a building technical field provides a jib structure for hoisting piping lane, include: the first suspender is used for being connected with the main beam of the lifting appliance; the top of the universal seat is connected with the first suspender; the top of second jib with universal seat is connected, and the bottom is used for connecting the piping lane. The utility model provides a boom structure for hoisting piping lane, through setting up first jib, universal seat and second jib, not only the second jib can realize multi-direction swing, and holistic jib is shorter among the relative prior art of the length of second jib moreover, and it is downthehole that many-sided make the second jib insert the piping lane hole of hoist more easily, has reduced the installation coefficient who hoists the piping lane, has also reduced the requirement to the position accuracy of piping lane hole of hoist simultaneously.
Description
Technical Field
The utility model relates to a building technical field especially relates to a jib structure for hoisting piping lane.
Background
Pipe corridor, i.e. corridor of pipes. A plurality of pipelines in chemical industry and related factories are gathered together and arranged along the outside of a device or a factory building, generally in the air, and are supported by a bracket to form a similar appearance with a corridor; there are also a few pipe galleries located underground.
A jib structure that is used for hoist and mount piping lane among the prior art is integrative mostly, and when hoist and mount piping lane, the piping lane hoisting point is many, is provided with a plurality of hoistways on it, and the jib size is long, and the clearance between jib and the piping lane hoist and mount hole is less, in wanting that the jib inserts the hoist and mount hole completely smoothly, the degree of difficulty coefficient is great, hardly guarantees that all piping lane hoist and mount hole positions all satisfy the demands. Moreover, when the hoist rod inserts the hole for hoist, individual hoist rod can't inject the hole for hoist smoothly, need to cut into the hole for hoist with the hoist rod by force, will cause the piping lane impaired like this, and serious person can lead to the piping lane to scrap, brings very big inconvenience for the hoist and mount of piping lane.
SUMMERY OF THE UTILITY MODEL
The utility model provides a jib structure for hoisting piping lane for solve among the prior art hoist and mount piping lane installation degree of difficulty and the easy impaired defect of piping lane, realize having reduced the piping lane and hoist the installation degree of difficulty, and improved the accuracy.
The utility model provides a jib structure for hoisting piping lane, include:
the first suspender is used for being connected with the main beam of the lifting appliance;
the top of the universal seat is connected with the first suspender;
the top of second jib with universal seat is connected, and the bottom is used for connecting the piping lane.
According to the utility model provides a jib structure for hoisting pipe gallery, the universal seat includes upper seat and lower seat, the top of upper seat is connected with the first jib, the bottom with the lower seat articulated; the bottom of the lower seat is connected with the second suspender.
According to the utility model provides a jib structure for hoisting pipe gallery, the upper seat comprises a fixed part and a first connecting part, the fixed part and the first connecting part are connected integrally;
the fixed part is provided with a first mounting hole; the first hanging rod penetrates through the first mounting hole and is detachably connected with the fixing part;
the first connecting portion comprises a first connecting plate and a second connecting plate, the first connecting plate and the second connecting plate are arranged oppositely and vertically arranged at the bottom of the fixing portion, and second mounting holes are formed in the first connecting plate and the second connecting plate along the horizontal direction.
According to the utility model provides a jib structure for hoisting pipe gallery, the lower seat includes second connecting portion, main part and third connecting portion, the second connecting portion and the third connecting portion are connected as an organic whole;
the second connecting part comprises a third connecting plate and a fourth connecting plate, the third connecting plate and the fourth connecting plate are arranged oppositely and are vertically arranged on the top of the main body part, and third mounting holes are formed in the third connecting plate and the fourth connecting plate; the third mounting hole corresponds to the second mounting hole;
the third connecting part comprises a fifth connecting plate and a sixth connecting plate, the fifth connecting plate and the sixth connecting plate are arranged oppositely and are vertically arranged at the bottom of the main body part, and fourth mounting holes are formed in the fifth connecting plate and the sixth connecting plate;
the axis of the fourth mounting hole is perpendicular to the axis of the third mounting hole;
and the first pin shaft penetrates through the second mounting hole and the third mounting hole at the same time so as to enable the upper seat and the lower seat to be hinged.
According to the utility model provides a boom structure for hoisting pipe gallery, the second boom is provided with a fifth mounting hole, and a second pin shaft penetrates through the fifth mounting hole and the fourth mounting hole simultaneously, so that the lower seat is connected with the second boom; the first pin shaft is perpendicular to the second pin shaft.
According to the utility model provides a pair of a jib structure for hoisting piping lane, first jib with connect through the nut between the fixed part.
According to the utility model provides a pair of a jib structure for hoisting piping lane, the top periphery of first jib is provided with the external screw thread, first jib pass through the nut with the hoist girder is connected.
According to the utility model provides a pair of a jib structure for hoisting piping lane, the universal seat is the stainless steel universal seat.
According to the utility model provides a boom structure for hoisting pipe gallery, the second boom includes annular portion and pull rod portion, the middle part of annular portion sets up as the fifth mounting hole; the pull rod part is arranged at the bottom of the annular part and is used for connecting a pipe gallery.
According to the utility model provides a pair of a boom structure for hoisting piping lane, the thickness of annular portion is greater than pull rod portion.
The utility model provides a boom structure for hoisting piping lane, through setting up boom structure into the components of a whole that can function independently structure, set up to first jib, universal seat and second jib, not only multi-direction swing can be realized to the second jib, holistic jib is shorter among the relative prior art of length of second jib moreover, it is downthehole that many-sided make the second jib insert the piping lane hole of hoist more easily, the installation coefficient of hoist and mount piping lane has been reduced, the requirement to the position accuracy of piping lane hole of hoist has also been reduced simultaneously.
Drawings
In order to more clearly illustrate the technical solutions of the present invention or the prior art, the following briefly introduces the drawings required for the embodiments or the prior art descriptions, and obviously, the drawings in the following description are some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
Fig. 1 is a first installation schematic diagram of a boom structure for hoisting a pipe gallery provided by the present invention;
fig. 2 is an enlarged view of a point a in fig. 1 provided by the present invention;
fig. 3 is a second schematic view illustrating the installation of the boom structure for hoisting a pipe gallery provided by the present invention;
fig. 4 is an enlarged view of fig. 3 at B provided by the present invention;
fig. 5 is a first schematic structural diagram of the universal base provided by the present invention; .
Fig. 6 is a schematic structural diagram ii of the universal base provided by the present invention;
fig. 7 is a first schematic structural view of a second suspension rod provided by the present invention;
fig. 8 is a second schematic structural view of a second suspension rod provided by the present invention;
reference numerals:
1: a first boom; 2: a universal base; 3: a second boom;
4: a hanger main beam; 5: a pipe gallery; 6: a first pin shaft;
7: a second pin shaft; 21: an upper seat; 22: a lower seat;
211: a fixed part; 212: a connecting portion; 2121: a first connecting plate;
2122: a second connecting plate; 221: a second connecting portion; 222: a third connecting portion;
2211: a third connecting plate; 2212: a fourth connecting plate; 213: a second mounting hole;
223: a third mounting hole; 224: a fourth mounting hole; 31: an annular portion;
32: a pull rod part; 33: a fifth mounting hole; 2213: a fifth connecting plate;
2214: and a sixth connecting plate.
Detailed Description
To make the objects, technical solutions and advantages of the present invention clearer, the drawings in the present invention will be combined to clearly and completely describe the technical solutions of the present invention, and obviously, the described embodiments are some, but not all embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
The boom structure for hoisting a pipe gallery disclosed by the invention is described below with reference to fig. 1-4, and comprises a first boom 1, wherein the first boom 1 is used for being connected with a main beam 4 of a lifting appliance; the top of the universal seat 2 is connected with the first suspender 1; the top of second jib 3, second jib 3 is connected with universal seat 2, and the bottom is used for connecting pipe gallery 5.
An embodiment of the utility model provides a boom structure for hoisting piping lane, through setting up boom structure into the components of a whole that can function independently, set up to first jib 1, universal seat 2 and second jib 3, not only second jib 3 can realize multi-direction swing, and second jib 3's length is holistic jib shorter among the prior art relatively, it is downthehole to make second jib 3 insert the piping lane hoist and mount more easily in the two aspects, the installation coefficient of hoist and mount piping lane has been reduced, the requirement to the position accuracy of piping lane hoist and mount hole has also been reduced simultaneously.
In one embodiment of the present invention, the universal base 2 comprises an upper base 21 and a lower base 22, the top of the upper base 21 is connected with the first suspension rod 1, and the bottom is hinged with the lower base 22; the bottom of the lower seat 22 is connected to the second boom 3.
In this embodiment, upper seat 21 and lower seat 22 are articulated, can realize that lower seat 22 swings along a plurality of directions, and then because second jib 3 is connected in lower seat 22's bottom, then second jib 3 also can swing along a plurality of directions for second jib 3 matches with the piping lane mounting hole more easily, reduces piping lane hoist and mount coefficient.
More specifically, as shown in fig. 5 and 6, the upper seat 21 includes a fixing portion 211 and a first connecting portion 212, the fixing portion 211 and the first connecting portion 212 being integrally connected; alternatively, the fixing portion 211 and the first connecting portion 212 are fixedly connected; the integral connection can reinforce the stability of the structure.
The fixing portion 211 is provided with a first mounting hole (not shown); the first suspender 2 passes through the first mounting hole and is detachably connected with the fixing part 211; the first hanger bar 2 may be connected to the fixing portion 211 by a fastening member such as a nut.
The first connecting portion 212 includes a first connecting plate 2121 and a second connecting plate 2122, the first connecting plate 2121 and the second connecting plate 2122 are disposed opposite to each other and vertically disposed at the bottom of the fixing portion 211, and second mounting holes 213 are disposed on the first connecting plate 2121 and the second connecting plate 2122 along a horizontal direction, and the second mounting holes 213 are used for providing a mounting structure for connecting the upper seat 21 and the lower seat 22.
As shown in fig. 5 and 6, the lower seat 22 includes a second connecting portion 221, a main body portion (not shown in the drawings), and a third connecting portion 222, the second connecting portion 221, the main body portion, and the third connecting portion 222 being integrally connected; the integrated connection is simple in process and can also enhance the stability of the overall structure of the lower seat.
The second connecting portion 221 includes a third connecting plate 2211 and a fourth connecting plate 2212, the third connecting plate 2211 and the fourth connecting plate 2212 are disposed oppositely and vertically on the top of the main body, and third mounting holes 223 are formed in the third connecting plate 2211 and the fourth connecting plate 2212; the third mounting hole 223 is adapted to cooperate with the second mounting hole 213 to provide a mounting structure for the connection of the upper and lower seats 21 and 22. The first pin 6 penetrates both the second mounting hole 213 and the third mounting hole 223 to hinge the upper seat 21 and the lower seat 22.
As shown in fig. 5, the third connecting portion 222 includes a fifth connecting plate 2213 and a sixth connecting plate 2214, the fifth connecting plate 2213 and the sixth connecting plate 2214 are disposed oppositely and vertically on the bottom of the main body, and fourth mounting holes 224 are opened on the fifth connecting plate 2213 and the sixth connecting plate 2214; the axis of the fourth mounting hole is vertical to the axis of the third mounting hole; the fourth mounting hole 224 is used to provide a mounting structure for the connection between the third connecting portion 222 and the second boom 3.
Furthermore, as shown in fig. 7, a fifth mounting hole 33 is formed on the second suspension rod 3, and the second pin 7 simultaneously penetrates through the fifth mounting hole 33 and the fourth mounting hole 224, so that the lower seat 22 is connected with the second suspension rod 3, and the first pin 6 is perpendicular to the second pin 7.
It should be noted that the first pin 6 penetrates through the second mounting hole 213 and the third mounting hole 223 at the same time to hinge the upper seat 21 and the lower seat 22; the lower seat 22 can swing along the radial direction of the first pin shaft 6; the second pin 7 simultaneously penetrates through the fifth mounting hole 33 and the fourth mounting hole 224 to connect the lower seat 22 and the second suspension rod 3, so that the second suspension rod 3 can swing along the radial direction of the second pin 7. Because the second suspender 3 is connected with the lower seat 22, the second suspender 3 can swing in multiple directions and is matched with a pipe gallery hoisting hole through proper swing, so that the difficulty coefficient of hoisting the pipe gallery is reduced; meanwhile, the requirement on the position accuracy of the mounting hole of the corridor is also reduced.
In addition, the top periphery of first jib 1 is provided with the external screw thread, and is connected with hoist girder 4 through the nut. As shown in fig. 1, a plurality of through holes are arranged on the main beam 4 of the lifting appliance, the top of the first suspender 1 penetrates through the through holes and is connected with the top of the main beam 4 of the lifting appliance through nuts, so that the first suspender 1 is basically arranged inside the main beam 4 of the lifting appliance, the overall height of the lifting structure is reduced, the space distance is reduced, and the installation space is saved.
In order to further optimize the technical scheme, the universal seat 2 is a stainless steel universal seat.
More specifically, as shown in fig. 8, the second hanger bar 3 includes a ring portion 31 and a tie bar portion 32, a middle portion of the ring portion 31 is provided as a fifth mounting hole 33, and the tie bar portion 32 is provided at a bottom portion of the ring portion 31 and is used for connecting a pipe gallery. The thickness of annular portion 31 is greater than pull rod portion 32, and the purpose is to guarantee that annular portion 31 has sufficient intensity, prevents annular portion 31 hoist and mount pipe gallery after deformation.
The utility model discloses an installation for hoisting boom structure of piping lane does:
firstly, a first suspender 1 is penetrated into a through hole of a main beam 4 of a lifting appliance, and the top of the first suspender 1 is fixed on the top of the main beam 4 of the lifting appliance through a nut;
secondly, the bottom of the first suspender 1 penetrates through a first mounting hole of the fixing part 211, and the bottom of the first suspender 1 is connected with the fixing part 211 through a nut;
thirdly, the second hanger rod 3 is connected to the bottom of the third connecting portion 222 by the second pin 7 penetrating through the fourth mounting hole 224 and the fifth mounting hole 33;
and finally, inserting the second suspender 3 into the pipe gallery hoisting hole to complete the pipe gallery hoisting.
The universal base 2 can be assembled in advance, that is, the upper base 21 and the lower base 22 are hinged together only by penetrating the first pin shaft 6 through the second mounting hole 213 and the third mounting hole 223; after the first suspension rod 1 is connected with the upper seat 21, the upper seat 21 and the lower seat 22 can be hinged together, the installation sequence is not limited, and the operation can be freely carried out according to the habit of a user.
The utility model discloses a jib structure for hoisting pipe gallery has not only reduced the degree of difficulty of hoist and mount pipe gallery, has reduced hoist and mount overall height moreover, has reduced spatial distance, has brought very big facility for the pipe gallery hoist and mount, avoids the pipe gallery to arouse simultaneously to scrap because of the hoist and mount problem.
Finally, it should be noted that: the above embodiments are only used to illustrate the technical solution of the present invention, and not to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, it should be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; such modifications and substitutions do not depart from the spirit and scope of the present invention in its corresponding aspects.
Claims (10)
1. A boom structure for hoisting a pipe gallery, comprising:
the first suspender is used for being connected with the main beam of the lifting appliance;
the top of the universal seat is connected with the first suspender;
the top of second jib with universal seat is connected, and the bottom is used for connecting the piping lane.
2. The boom structure for hoisting a pipe gallery according to claim 1, wherein the universal base comprises an upper base and a lower base, the upper base being connected at a top to the first boom and at a bottom to the lower base; the bottom of the lower seat is connected with the second suspender.
3. Boom structure for hoisting a pipe rack according to claim 2, wherein the upper seat comprises a fixing part and a first connecting part, the fixing part and the first connecting part being integrally connected;
the fixed part is provided with a first mounting hole; the first hanging rod penetrates through the first mounting hole and is detachably connected with the fixing part;
the first connecting portion comprises a first connecting plate and a second connecting plate, the first connecting plate and the second connecting plate are arranged oppositely and vertically arranged at the bottom of the fixing portion, and second mounting holes are formed in the first connecting plate and the second connecting plate along the horizontal direction.
4. A boom structure for hoisting a pipe rack according to claim 3, wherein the lower seat comprises a second connecting part, a main body part and a third connecting part which are integrally connected;
the second connection portion includes: the third connecting plate and the fourth connecting plate are arranged oppositely and are vertically arranged at the top of the main body part, and third mounting holes corresponding to the second mounting holes are formed in the third connecting plate and the fourth connecting plate;
the third connection portion includes: the fifth connecting plate and the sixth connecting plate are arranged oppositely and are vertically arranged at the bottom of the main body part, and fourth mounting holes are formed in the fifth connecting plate and the sixth connecting plate;
the axis of the fourth mounting hole is perpendicular to the axis of the third mounting hole;
and the first pin shaft simultaneously penetrates through the second mounting hole and the third mounting hole so as to hinge the upper seat and the lower seat.
5. The boom structure for hoisting a pipe gallery according to claim 4, wherein a fifth mounting hole is formed on the second boom, and a second pin shaft penetrates through the fifth mounting hole and the fourth mounting hole at the same time, so that the lower seat is connected with the second boom; the first pin shaft is perpendicular to the second pin shaft.
6. A boom structure for hoisting a pipe rack according to claim 3, characterized in that the first boom is connected with the fixing part by a nut.
7. The boom structure for hoisting a pipe gallery according to claim 6, wherein the first boom is provided with an external thread on its top periphery and is connected to the spreader main beam by a nut.
8. A boom construction for hoisting a pipe rack according to any of the claims 1-7, characterized in that the gimbal table is a stainless steel gimbal table.
9. Boom structure for hoisting a pipe corridor according to claim 5, wherein the second boom comprises a ring part and a drawbar part, the middle part of the ring part being provided as the fifth mounting hole; the pull rod part is arranged at the bottom of the annular part and is used for connecting a pipe gallery.
10. A boom construction for hoisting a pipe rack according to claim 9, characterized in that the thickness of the ring part is larger than the pull rod part.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202123091452.XU CN217051320U (en) | 2021-12-10 | 2021-12-10 | A jib structure for hoisting piping lane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202123091452.XU CN217051320U (en) | 2021-12-10 | 2021-12-10 | A jib structure for hoisting piping lane |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217051320U true CN217051320U (en) | 2022-07-26 |
Family
ID=82477723
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202123091452.XU Active CN217051320U (en) | 2021-12-10 | 2021-12-10 | A jib structure for hoisting piping lane |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217051320U (en) |
-
2021
- 2021-12-10 CN CN202123091452.XU patent/CN217051320U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108249275A (en) | A kind of prefabricated part hanging tool and lifting attitude-adjusting method | |
CN217051320U (en) | A jib structure for hoisting piping lane | |
CN209891528U (en) | Steel frame conversion layer assembled mounting structure of ultrahigh space ceiling | |
CN206156567U (en) | Thin cylinder body hoist | |
CN205114843U (en) | Prefabricated post hoist device with unhook function | |
CN105804416B (en) | The attachment structure of prefabrication tower crane | |
CN210064895U (en) | Installation hoist of prefabricated unit in space | |
CN204299180U (en) | Balcony forming panel | |
CN106121259A (en) | The hanging apparatus of embedded integrated outer wall plate and hanging method thereof | |
CN207314630U (en) | A kind of band damping rope suspension arrangement | |
CN106044564A (en) | Installation method for blind penetrating installation guide structure | |
CN205688778U (en) | A kind of elevating scaffold special over sling structure | |
CN205367540U (en) | Prevent tower crane of empting | |
CN106049971A (en) | Installation method of non-contact-point lifting appliance for towering noble metal tower mast | |
CN204355947U (en) | Large-scale without eye plate lifting beam device | |
CN201334785Y (en) | Homogenization warehouse factory building structure | |
CN205855781U (en) | The lower flange of guide | |
CN205857889U (en) | The towering contactless suspender of noble metal tower mast | |
CN217894980U (en) | Large-span ALC slat wall crossbeam promotes installation device | |
CN205709351U (en) | Building hoist remote installing type attachment device | |
CN206705563U (en) | A kind of novel pile formula crane | |
CN205935718U (en) | Hoist device of embedded integral side fascia | |
CN219344213U (en) | Connection structure and shaft tower | |
CN211056457U (en) | Building structure reinforcing apparatus | |
CN202864667U (en) | Auxiliary device for lifting beam body |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |