CN216863590U - Hoisting equipment for building construction - Google Patents

Hoisting equipment for building construction Download PDF

Info

Publication number
CN216863590U
CN216863590U CN202220693838.3U CN202220693838U CN216863590U CN 216863590 U CN216863590 U CN 216863590U CN 202220693838 U CN202220693838 U CN 202220693838U CN 216863590 U CN216863590 U CN 216863590U
Authority
CN
China
Prior art keywords
pipe
lever
vertical pipe
welded
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220693838.3U
Other languages
Chinese (zh)
Inventor
张龙龙
王云松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin Institute Of Architectural Science And Design
Original Assignee
Jilin Institute Of Architectural Science And Design
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin Institute Of Architectural Science And Design filed Critical Jilin Institute Of Architectural Science And Design
Priority to CN202220693838.3U priority Critical patent/CN216863590U/en
Application granted granted Critical
Publication of CN216863590U publication Critical patent/CN216863590U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model belongs to the technical field of building equipment, and particularly relates to hoisting equipment for building construction, which comprises a lever, a hanging bracket, a vertical pipe, a cross-shaped base and 4 bottom plates, wherein the lever is arranged on the hanging bracket; a lifting rope is tied at the front end of the lever, a lifting hook is tied at the bottom end of the lifting rope, a lifting ring is welded at the rear end of the lifting rope, a pulling rope is tied on the lifting ring, a hanging rope is tied at the front part of the lever, and a hook is tied at the top end of the hanging rope; the hanger is formed by vertically welding a horizontal pipe and a vertical pipe, a supporting plate is welded between the horizontal pipe and the vertical pipe, a hanging ring is welded at the outer end of the horizontal pipe, and a retaining ring is welded at the lower part of the vertical pipe; the cross-shaped base is formed by welding 4 square tubes and an insertion tube, and a rib plate is welded between the insertion tube and the square tubes; the bottom cartridge of riser is in the intubate, and 4 bottom plates cartridge respectively are in the square hole of square pipe, and the bottom cartridge of riser is at the top of riser, and the couple is hung on the link. The hoisting equipment hoists bagged materials to the high position of the car hopper from the ground through the lever, so that high-rise stacking loading of the bagged materials is realized. Simple operation, time saving and labor saving.

Description

Hoisting equipment for building construction
Technical Field
The utility model belongs to the technical field of building equipment, and particularly relates to hoisting equipment for building construction.
Background
In the process of building construction, bagged materials such as sand, cement or construction waste need to be loaded on the car, and the bags on the bottom layer of the car hopper are labor-saving to load, and are low in height. When the bags are stacked higher than two layers, due to the fact that the loading height is increased, a loader needs to firstly carry the bags on the shoulders and then stack the bags on a car hopper, and a person standing on the car hopper needs to cooperate with a person under the car to stack and load the car. After the stacking height continues to increase, two people are required under the truck to lift the bag over the top to complete loading. The mode of loading bagged materials by high stacking is time-consuming and labor-consuming, the loading efficiency is low, and potential safety hazards exist. Therefore, design a can improve pile up neatly and load lifting device for construction of efficiency.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide lifting equipment for building construction, which can improve stacking loading efficiency. The automatic feeding device is simple and convenient to operate, time-saving, labor-saving, safe, reliable, simple in structure, reasonable in design, low in manufacturing cost, economical, applicable, and easy to popularize and use on a large scale.
The technical scheme adopted by the utility model is as follows: the hoisting equipment for building construction comprises a lever, a hoisting frame, a vertical pipe, a cross-shaped base and 4 bottom plates; a lifting rope is tied at the front end of the lever, a lifting hook is tied at the bottom end of the lifting rope, a lifting ring is welded at the rear end of the lifting rope, a pulling rope is tied on the lifting ring, a hanging rope is tied at the front part of the lever, and a hook is tied at the top end of the hanging rope; the hanger is formed by vertically welding a horizontal pipe and a vertical pipe, a supporting plate is welded between the horizontal pipe and the vertical pipe, a hanging ring is welded at the outer end of the horizontal pipe, and a retaining ring is welded at the lower part of the vertical pipe; the cross-shaped base is formed by welding 4 square tubes and an insertion tube, and rib plates are welded between the insertion tube and the square tubes; the bottom end of the vertical pipe is inserted in the insertion pipe, the 4 bottom plates are respectively inserted in the square holes of the square pipes, the bottom end of the vertical pipe is inserted in the top of the vertical pipe, and the hook is hung on the hanging ring.
Furthermore, the lever is a thin-wall steel pipe or an aluminum alloy pipe, and the lever is provided with a ring groove for binding the lifting rope and the hanging rope.
Furthermore, the horizontal pipe, the vertical pipe and the vertical pipe are steel pipes or aluminum alloy pipes.
Furthermore, the bottom plate is an aluminum alloy thin plate or a wood plate, and the length of the bottom plate is not less than 1.5 m.
Further, the height of the stand pipe is not less than 2.5 meters, and the length of the lever is not less than 3 meters.
The utility model has the beneficial effects that: the utility model provides a can improve pile up neatly and load lifting device for efficiency of construction, this lifting device utilizes lever principle to hoist bagged materials to the eminence of car hopper from ground, realizes the high-rise pile up neatly of bagged materials and loads. The automatic feeding device is simple and convenient to operate, time-saving, labor-saving, safe, reliable, simple in structure, reasonable in design, low in manufacturing cost, economical, applicable, and easy to popularize and use on a large scale.
Drawings
FIG. 1 is a schematic structural diagram of the first embodiment;
FIG. 2 is a schematic structural diagram of a lever according to the first embodiment;
FIG. 3 is a schematic view of a hanger according to an embodiment;
FIG. 4 is a schematic structural view of a cross-shaped base according to an embodiment;
FIG. 5 is a top view of FIG. 4;
FIG. 6 is a schematic diagram of an embodiment.
Detailed Description
Example one
Referring to the figures, the hoisting equipment for building construction comprises a lever 1, a hoisting frame 2, a vertical pipe 3, a cross-shaped base 4 and 4 bottom plates 5; a lifting rope 15 is bound at the front end of the lever 1, a lifting hook 16 is bound at the bottom end of the lifting rope 15, a lifting ring 12 is welded at the rear end of the lifting rope, a pull rope 11 is bound on the lifting ring 12, a hanging rope 14 is bound at the front part of the lever 1, and a hook 13 is bound at the top end of the hanging rope 14; the hanger 2 is formed by vertically welding a horizontal pipe 21 and a vertical pipe 22, a supporting plate 24 is welded between the horizontal pipe 21 and the vertical pipe 22, a hanging ring 25 is welded at the outer end of the horizontal pipe 21, and a retaining ring 23 is welded at the lower part of the vertical pipe 22; the cruciform base 4 is formed by welding 4 square tubes 43 and an insertion tube 41, and a rib plate 42 is welded between the insertion tube 41 and the square tube 43; the bottom end of the vertical pipe 3 is inserted into the insertion pipe 41, the 4 bottom plates 5 are respectively inserted into the square holes 44 of the square pipes 43, the bottom end of the vertical pipe 22 is inserted into the top of the vertical pipe 3, and the hook 13 is hung on the hanging ring 25; the lever 1 is a thin-wall steel pipe or an aluminum alloy pipe, and annular grooves for binding the lifting ropes 15 and the hanging ropes 14 are formed in the lever 1; the horizontal pipe 21, the vertical pipe 22 and the vertical pipe 3 are steel pipes or aluminum alloy pipes; the bottom plate 5 is an aluminum alloy thin plate or a wood plate, and the length of the bottom plate 5 is not less than 1.5 m; the height of the stand pipe 3 is not less than 2.5 meters, and the length of the lever 1 is not less than 3 meters.
The hoisting equipment for building construction is assembled before bagged material multilayer palletizing and loading, the cross flower base is placed beside a car hopper on one side of a ground material bag, 4 bottom plates are inserted on the square tubes, and the bottoms of the vertical tubes are inserted in the vertical tubes at the top of the vertical tubes. When the high needs of pile up neatly hoist and mount material bag, with the lifting hook of lever front end on can the pocket bag rope, pocket bag net or the pocket bag area of embracing the sack, pull down the stay cord with strength after the material bag is unsettled and raise, rotatory lever makes the material bag of being lifted arrange car hopper pile up neatly bag top in, and the loading workman who stands on the pile up neatly bag draws pocket bag area and continues the pile up neatly with the sack, and hoist and mount labour saving and time saving has improved loading efficiency. And the large-size parts of the hoisting equipment for the whole building construction are detachably designed, so that the occupied space is small, and the hoisting equipment is convenient to store or transport.

Claims (5)

1. The utility model provides a lifting device for construction which characterized in that: the hoisting equipment comprises a lever (1), a hanging bracket (2), a vertical pipe (3), a cross flower base (4) and 4 bottom plates (5); a lifting rope (15) is bound at the front end of the lever (1), a lifting hook (16) is bound at the bottom end of the lifting rope (15), a lifting ring (12) is welded at the rear end of the lifting rope (15), a pull rope (11) is bound on the lifting ring (12), a hanging rope (14) is bound at the front part of the lever (1), and a hook (13) is bound at the top end of the hanging rope (14); the hanging bracket (2) is formed by vertically welding a transverse pipe (21) and a vertical pipe (22), a supporting plate (24) is welded between the transverse pipe (21) and the vertical pipe (22), a hanging ring (25) is welded at the outer end of the transverse pipe (21), and a retaining ring (23) is welded at the lower part of the vertical pipe (22); the cruciform base (4) is formed by welding 4 square tubes (43) and an insertion tube (41), and a rib plate (42) is welded between the insertion tube (41) and the square tube (43); the bottom end of the vertical pipe (3) is inserted in the insertion pipe (41), the 4 bottom plates (5) are respectively inserted in the square holes (44) of the square pipes (43), the bottom end of the vertical pipe (22) is inserted in the top of the vertical pipe (3), and the hook (13) is hung on the hanging ring (25).
2. The hoisting equipment for building construction according to claim 1, characterized in that: the lever (1) is a thin-wall steel pipe or an aluminum alloy pipe, and annular grooves for binding the lifting rope (15) and the hanging rope (14) are formed in the lever (1).
3. The hoisting equipment for building construction according to claim 1, characterized in that: the transverse pipe (21), the vertical pipe (22) and the vertical pipe (3) are steel pipes or aluminum alloy pipes.
4. The hoisting equipment for building construction according to claim 1, characterized in that: the bottom plate (5) is an aluminum alloy thin plate or a wood plate, and the length of the bottom plate (5) is not less than 1.5 m.
5. The hoisting equipment for building construction according to claim 1, characterized in that: the height of the stand pipe (3) is not less than 2.5 meters, and the length of the lever (1) is not less than 3 meters.
CN202220693838.3U 2022-03-29 2022-03-29 Hoisting equipment for building construction Active CN216863590U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220693838.3U CN216863590U (en) 2022-03-29 2022-03-29 Hoisting equipment for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220693838.3U CN216863590U (en) 2022-03-29 2022-03-29 Hoisting equipment for building construction

Publications (1)

Publication Number Publication Date
CN216863590U true CN216863590U (en) 2022-07-01

Family

ID=82124532

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220693838.3U Active CN216863590U (en) 2022-03-29 2022-03-29 Hoisting equipment for building construction

Country Status (1)

Country Link
CN (1) CN216863590U (en)

Similar Documents

Publication Publication Date Title
CN203486726U (en) Brick and building block hoisting device
CN206502579U (en) Power pole hoisting device
CN106241165B (en) A kind of mechanical steel bar storage rack and mechanical steel bar deposit method
CN209066902U (en) A kind of fabricated PC prefabricated components superimposed sheet pile hoisting transportation frame
CN216863590U (en) Hoisting equipment for building construction
CN204899247U (en) Building site stirrup shipment hanging flower basket device
CN211034964U (en) Hoisting mechanism of steel reinforcement cage
CN204401395U (en) A kind of subgrade case
CN216971869U (en) Building material lifting device with high bearing capacity
CN206767435U (en) A kind of fragment of brick hanging apparatus for building
CN214692858U (en) Floor transportation frock
CN205973429U (en) Coil of strip class goods hoist
CN213085199U (en) Block brick hoisting device
CN210852542U (en) Automatic transportation equipment for solid fermented feed
CN114590697A (en) High-span concrete support dismantling method based on reserved lifting hook for closed space
CN202022651U (en) Steel bar hoisting device
CN206529213U (en) A kind of quick handling apparatus of building block
CN205892490U (en) A special lifting device for concrete pipe pile hoist and mount
CN220815137U (en) Multifunctional suspension cage suitable for chimney construction
CN217323021U (en) Building block brick hoisting device for construction
CN219279250U (en) Cage for scattered articles
CN212953848U (en) Handling frock of bundle stock
CN105908982B (en) A kind of overhanging unloading platform tool-type limit for tonnage support
CN203667871U (en) Grain warehouse conveying equipment
CN211444209U (en) Mechanical grabbing device of automatic stacking system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant