CN216971869U - Building material lifting device with high bearing capacity - Google Patents
Building material lifting device with high bearing capacity Download PDFInfo
- Publication number
- CN216971869U CN216971869U CN202220684282.1U CN202220684282U CN216971869U CN 216971869 U CN216971869 U CN 216971869U CN 202220684282 U CN202220684282 U CN 202220684282U CN 216971869 U CN216971869 U CN 216971869U
- Authority
- CN
- China
- Prior art keywords
- stand
- building material
- slider
- transport vechicle
- lifting device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The application discloses building material elevating gear that height bore, it includes frame, transport vechicle and is used for lifting by crane the hoisting machine of transport vechicle to construct, the frame includes the stand of two sets of relative settings, the vertical setting of stand, be provided with the slider on the stand, the length direction and the stand sliding connection of stand are followed to the slider, the transport vechicle can be dismantled with the slider and be connected. This application has the stability that improves the transport vechicle and lift by crane the in-process to reduce the possibility that the building dropped, thereby provide construction safety's effect.
Description
Technical Field
The application relates to the technical field of lifting equipment, in particular to a high-bearing building material lifting device
Background
In the construction process of buildings, various building materials such as concrete, gravel, templates and various sundries are often carried; at the existing construction site, for high-rise buildings, a tower crane is mostly adopted to carry materials. However, for some low-rise buildings, such as urban and rural self-living buildings, the tower crane equipment is expensive to use, and the overall cost of the hoisting process is high.
Therefore, the material is carried by adopting a hoisting trolley, namely, the hoisting equipment is arranged on the floor, and then the material is loaded in the trolley on the ground and then the hoisting equipment is used for hoisting the trolley. However, the cart can produce great rocking in the hoisting process, so that the possibility of falling of building materials is greatly increased, and great potential safety hazards exist. Therefore, improvements are needed.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, promote the security of material hoist and mount in-process in shallow inside, this application provides a building material elevating gear that highly bears.
The application provides a building material elevating gear that high bears adopts following technical scheme:
the utility model provides a building material elevating gear that high bears, includes frame, transport vechicle and is used for lifting by crane the hoisting machine of transport vechicle to construct, the frame includes the stand of two sets of relative settings, the vertical setting of stand, be provided with the slider on the stand, the length direction and the stand sliding connection of stand are followed to the slider, the transport vechicle can be dismantled with the slider and be connected.
By adopting the technical scheme, when the building materials are transported to the floor slab from the ground, the hoisting mechanism is arranged on the floor slab, the transport vehicle is connected with the sliding block, then the materials are loaded on the transport vehicle, and the transport vehicle is hoisted by the hoisting mechanism; when the transport vehicle moves to the height of the floor slab, a constructor standing on the floor slab unloads the materials in the transport vehicle; after unloading is finished, slowly lowering the transport vehicle by using the hoisting mechanism; because the stand all plays the effect of spacing direction at the lift by crane of transport vechicle with transfer the in-process for the transport vechicle all moves steadily with transferring the in-process, is showing the possibility that has reduced the material and dropped, has improved construction safety nature greatly.
Preferably, one side of the sliding block far away from the upright post is fixedly connected with a telescopic rod, and the side wall of the transport vehicle is fixedly connected with a connecting box for inserting the telescopic rod.
Through adopting above-mentioned technical scheme, insert the connecting box with the telescopic link, accomplish the installation of transport vechicle promptly, extract the telescopic link from the connecting box in, accomplish the dismantlement of transport vechicle promptly, easy operation is high-efficient.
Preferably, the telescopic link is including fixing the fixed box of keeping away from stand one side at the slider, it has the cutting to slide the grafting in the fixed box, fixedly connected with spring between the one end that the cutting inserted fixed box and the slider.
Through adopting above-mentioned technical scheme, under the condition that does not have exogenic action, the existence of spring for the cutting is inserted in the connecting box all the time, thereby makes the slider be connected with the transport vechicle and stabilizes, and then ensures the security of transport vechicle hoist and mount process.
Preferably, the side wall of the insert is fixedly connected with a shift lever, the side wall of the fixing box is provided with a limiting groove, the limiting groove extends along the length direction of the fixing box, and the shift lever is connected with the limiting groove in a sliding manner.
Through adopting above-mentioned technical scheme, when needs pull down the transport vechicle from the frame, stir the driving lever and can drive the cutting and remove until cutting and junction box separation towards the direction that is close to the slider, conveniently pull down the transport vechicle from the frame, can increase the frequency of transport building materials in the same time.
Preferably, one side of the fixing box, which is provided with the limiting groove, is hinged with a limiting ring, and the motion track of the limiting ring is intersected with the limiting groove.
Through adopting above-mentioned technical scheme, order about the cutting through the driving lever and remove so that cutting and junction box separation back, rotate the spacing ring and detain the driving lever until the spacing ring to the restriction spring kick-backs, only need alone can be pulled down the transport vechicle from the frame, easy operation is high-efficient.
Preferably, the hoisting mechanism comprises a winch arranged on the floor slab and an I-beam fixed at the tops of the two groups of stand columns, a fixed pulley is mounted on a cross beam of the I-beam, and a pull rope of the winch bypasses the fixed pulley and is connected with the transport vehicle.
By adopting the technical scheme, when the transport vehicle is hoisted, the transport vehicle is firstly connected with the sliding block, then the winch is installed on the constructed floor slab, the pull rope of the winch is tied with the transport vehicle after bypassing the fixed pulley, and then the transport vehicle can be hoisted by winding the pull rope through the winch; in the same way, the transport vehicle can be put down by slowly releasing the pull rope through the winch.
Drawings
FIG. 1 is a schematic overall structure of the present application;
FIG. 2 is an enlarged schematic view of A of FIG. 1 of the present application;
fig. 3 is a schematic structural view of the telescopic rod in the present application.
Description of reference numerals:
1. a transport vehicle; 2. a base plate; 3. a column; 4. a chute; 5. a slider; 6. a telescopic rod; 61. a fixing box; 62. cutting; 63. a spring; 7. a connection box; 8. a deflector rod; 9. a limiting groove; 10. a limiting ring; 11. a hoist; 12. an I-beam; 13. a fixed pulley; 14. and (7) a floor slab.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses building material lifting device with high bearing capacity. Referring to fig. 1, the lifting device comprises a frame, a transport vehicle 1 and a lifting mechanism for lifting the transport vehicle 1.
Referring to fig. 1, the frame includes a bottom plate 2 and two sets of columns 3 fixed on the bottom plate 2, the two sets of columns 3 are vertically arranged oppositely, and a gap for accommodating the transport vehicle 1 is left between the two sets of columns 3. Two stands 3 are a set of, and four stands 3 are located four edges of bottom plate 2 respectively. In order to facilitate the unloading after the transport vehicle 1 is lifted, the height of the upright column 3 is higher than that of the floor slab 14. Two sets of 3 relative one sides of stand have all been seted up spout 4 along vertical direction, and the horizontal cross-section of spout 4 is the T type setting, and it has slider 5 to slide to peg graft in spout 4, and transport vechicle 1 can dismantle the setting between four sliders 5.
Referring to fig. 1 and 2, specifically, slider 5 deviates from one side fixedly connected with telescopic link 6 of 4 tank bottoms of spout, and fixedly connected with is used with the connecting box 7 that telescopic link 6 cooperateed on transport vechicle 1, and connecting box 7 is provided with four, and four connecting boxes 7 divide into two sets ofly, and two sets of connecting box 7 set up respectively on transport vechicle 1 is close to its two sides lateral wall of handlebar, and the interval between two connecting boxes 7 of same group equals the interval between two telescopic links 6 of same group.
Referring to fig. 3, the telescopic rod 6 comprises a fixed box 61 fixedly connected with the sliding block 5, the axis of the fixed box 61 is perpendicular to the axis of the upright post 3, an inserting strip 62 is inserted in the fixed box 61 in a sliding mode, the inserting strip 62 is matched with the connecting box 7 in an inserting mode, and a spring 63 is fixedly connected between one end, inserted into the fixed box 61, of the inserting strip 62 and one side, deviated from the bottom of the sliding groove 4, of the sliding block 5. When the spring 63 is in a natural state, the insert 62 protrudes from one end of the fixed case 61 away from the slider 5.
Referring to fig. 3, a shift lever 8 is vertically and fixedly connected to the upper surface of the insert 62, a limit groove 9 for inserting the shift lever 8 is formed in the side wall of the fixing box 61 in a penetrating manner, the limit groove 9 is formed in the length direction of the fixing box 61, and the limit groove 9 penetrates through one end of the fixing box 61, which is far away from the sliding block 5. The fixing box 61 is also hinged with a limiting ring 10 at one side provided with a limiting groove 9, the limiting ring 10 is positioned between one end of the fixing box 61 connected with the sliding block 5 and the limiting groove 9, and the moving track of the limiting ring 10 is intersected with the moving track of the shifting lever 8. When the retainer ring 10 fastens the shift lever 8, the insert 62 is separated from the connection box 7.
Referring to fig. 1, when the transporter 1 is mounted on a frame, the transporter 1 is placed between two sets of uprights 3 with the handlebars of the transporter 1 facing the building for subsequent discharge. Then the position of the transport vehicle 1 is adjusted to enable the connecting box 7 to be aligned to the corresponding inserting strip 62, the limiting ring 10 of the fixing box 61 is rotated successively to release the shifting rod 8, the spring 63 rebounds to push the inserting strip 62 to be inserted into the corresponding connecting box 7, the installation of the transport vehicle 1 is completed, and then the transport vehicle 1 is lifted by the hoisting mechanism.
Referring to fig. 1, specifically, the hoisting mechanism includes a hoist 11 and an i-beam 12, the i-beam 12 is fixed on the tops of the two sets of columns 3, a fixed pulley 13 is installed on a cross beam of the i-beam 12, and a pull rope of the hoist 11 bypasses the fixed pulley 13. When the transport vehicle 1 is hoisted, the winch 11 is installed on the constructed floor slab 14, then the pull rope of the winch 11 is bound with the transport vehicle 1, and then the transport vehicle 1 can be hoisted by winding the pull rope through the winch 11. During, stand 3 plays spacing guide effect to transport vechicle 1 for transport vechicle 1 can not rock everywhere lifting by crane the in-process, thereby can not have the material to drop, provides the security of construction. After the transport vechicle 1 moved to the floor height, the constructor who stands on the floor unloaded the material in the transport vechicle 1, then reverses through hoist engine 11 in order to relax the stay cord and can slowly transfer transport vechicle 1. During which time. The upright 3 also guides the carriage 1, so that the carriage 1 remains stable during the lowering operation.
The application discloses a building material elevating gear that high bears's theory of operation does:
when the building materials are conveyed from the ground to the constructed floor 14, the transport vehicle 1 is firstly connected with the slide block 5, and then the building materials are filled in the cargo hopper of the transport vehicle 1. After the material is filled, the pull rope is wound through the winch 11 to lift the transport vehicle 1, after the transport vehicle 1 moves upwards to the height of the floor slab 14, the construction personnel lift the building materials in the transport vehicle 1 off, and then slowly lower the transport vehicle 1 through the winch 11 until the transport vehicle 1 falls back to the bottom plate 2. During the lift of transport vechicle 1, stand 3 all plays spacing guide effect to transport vechicle 1 for transport vechicle 1 remains steadily throughout at the lift in-process, makes transport vechicle 1 can not have the material to drop at last moving the in-process, has improved the construction security greatly.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.
Claims (6)
1. The utility model provides a building material elevating gear that high bears which characterized in that: including frame, transport vechicle (1) and be used for lifting by crane hoisting machine of transport vechicle (1) and construct, the frame includes stand (3) of two sets of relative settings, stand (3) vertical setting, be provided with slider (5) on stand (3), the length direction and stand (3) sliding connection of stand (3) are followed in slider (5), transport vechicle (1) can be dismantled with slider (5) and be connected.
2. A high load bearing building material lifting device according to claim 1, wherein: one side fixedly connected with telescopic link (6) of stand (3) are kept away from in slider (5), the lateral wall fixedly connected with of transport vechicle (1) supplies telescopic link (6) male connecting box (7).
3. A high load bearing building material lifting device according to claim 2, wherein: the telescopic rod (6) comprises a fixed box (61) fixed on one side, far away from the upright post (3), of the sliding block (5), an inserting strip (62) is inserted in the fixed box (61) in a sliding and inserting mode, and a spring (63) is fixedly connected between one end, inserted into the fixed box (61), of the inserting strip (62) and the sliding block (5).
4. A high load bearing building material lifting device according to claim 3, characterised in that: the side wall of the inserting strip (62) is fixedly connected with a shifting rod (8), the side wall of the fixing box (61) is provided with a limiting groove (9), the limiting groove (9) extends along the length direction of the fixing box (61), and the shifting rod (8) is connected with the limiting groove (9) in a sliding mode.
5. A high load bearing building material lifting device according to claim 4, characterised in that: one side of the fixed box (61) provided with the limiting groove (9) is hinged with a limiting ring (10), and the motion track of the limiting ring (10) is intersected with the limiting groove (9).
6. A high load bearing building material lifting device according to claim 1, wherein: the hoisting mechanism comprises a winch (11) arranged on a floor (14) and an I-shaped beam (12) fixed to the tops of the two groups of upright posts (3), a fixed pulley (13) is mounted on a cross beam of the I-shaped beam (12), and a pull rope of the winch (11) bypasses the fixed pulley (13) and is connected with the transport vehicle (1).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202220684282.1U CN216971869U (en) | 2022-03-25 | 2022-03-25 | Building material lifting device with high bearing capacity |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202220684282.1U CN216971869U (en) | 2022-03-25 | 2022-03-25 | Building material lifting device with high bearing capacity |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN216971869U true CN216971869U (en) | 2022-07-15 |
Family
ID=82339476
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202220684282.1U Active CN216971869U (en) | 2022-03-25 | 2022-03-25 | Building material lifting device with high bearing capacity |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN216971869U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115973940A (en) * | 2023-02-17 | 2023-04-18 | 浙江新曙光建设有限公司 | Building construction handling device |
-
2022
- 2022-03-25 CN CN202220684282.1U patent/CN216971869U/en active Active
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115973940A (en) * | 2023-02-17 | 2023-04-18 | 浙江新曙光建设有限公司 | Building construction handling device |
| CN115973940B (en) * | 2023-02-17 | 2023-08-29 | 浙江新曙光建设有限公司 | Building construction handling device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN201250064Y (en) | Front launching nose type bridge girder erection machine for bridge erection | |
| CN210457317U (en) | A housing construction vertical transport vehicle | |
| CN214734024U (en) | Indoor material conveying device in high-rise building construction process | |
| CN211004404U (en) | A double-column stacker | |
| CN116117984A (en) | Automatic circulating system and method for movable pedestal in precast beam field | |
| CN215439468U (en) | Liftable support for construction engineering construction | |
| CN215160594U (en) | High-rise building construction lifting device | |
| CN116357096B (en) | A suspended self-lifting material platform | |
| CN223018199U (en) | A detachable transport device and feeding system | |
| CN220432076U (en) | Conveyer of large-scale steel construction feed bin top cap construction | |
| JP2014141230A (en) | Lifting/lowering transport device of instrument for ropeway | |
| CN2672011Y (en) | Multipurpose construction hoist | |
| CN207957486U (en) | A kind of mine lift Transportation Engineering mechanical equipment | |
| CN212050449U (en) | Operation platform truck of dam panel reinforcing bar installation | |
| CN116498096B (en) | Building material transportation hoisting device | |
| CN222593222U (en) | A transport device for prefabricated concrete components | |
| CN220283359U (en) | Industrial factory building vertical hoisting device | |
| CN113859337A (en) | Civil engineering construction fragment of brick handling equipment | |
| CN216764176U (en) | Material lifting device for preparing mortar | |
| CN219823585U (en) | Lifting type construction platform for house construction engineering | |
| CN215558664U (en) | Lifting device for material transportation in vertical shaft | |
| CN221739786U (en) | A construction loading machine | |
| CN224160355U (en) | Rapid loading station liftable maintenance platform | |
| CN111943078A (en) | A hydraulic lifting system and lifting method thereof | |
| CN220565730U (en) | Guide rail type discharging device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |