CN216765468U CN202122227376.4U CN202122227376U CN216765468U CN 216765468 U CN216765468 U CN 216765468U CN 202122227376 U CN202122227376 U CN 202122227376U CN 216765468 U CN216765468 U CN 216765468U
Authority
CN
China
Prior art keywords
rapid trough
prefabricated
opening
highway
prefabricated section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122227376.4U
Other languages
Chinese (zh)
Inventor
宋鑫
舒晓锐
江健宏
宋军
谢波
钟立昌
徐松
赵东亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Provincial Communications Planning and Design Institute Group Co Ltd
Original Assignee
Shandong Provincial Communications Planning and Design Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Provincial Communications Planning and Design Institute Group Co Ltd filed Critical Shandong Provincial Communications Planning and Design Institute Group Co Ltd
Priority to CN202122227376.4U priority Critical patent/CN216765468U/en
Application granted granted Critical
Publication of CN216765468U publication Critical patent/CN216765468U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model relates to the technical field of highway drainage, and particularly provides a highway rapid trough prefabricated structure. Set up the rapid trough on the side slope of road surface both sides, set up the infiltration ditch bottom the median, ponding flows in the transverse drainage pipe in the infiltration ditch, the transverse drainage pipe export is located the rapid trough, the rapid trough comprises opening prefabricated section and ordinary prefabricated section, ordinary prefabricated section is both sides arch, middle sunken groove structure, and the opening prefabricated section is middle open-ended prefabricated section, opening prefabricated section opening corresponds with the outlet of transverse drainage pipe. The problem of carry ponding in can't discharging through the prefabricated section rapid trough in the highway engineering that adopts the prefabricated section rapid trough is solved.

Description

Highway rapid trough prefabricated construction
Technical Field
The utility model relates to the technical field of highway drainage, and particularly provides a highway rapid trough prefabricated structure.
Background
The statements herein merely provide background information related to the present disclosure and may not necessarily constitute prior art.
With the development of urbanization and the increasing travel demand of people, roads are widely constructed. In a road fill section, a side ditch is usually arranged outside a slope toe of an embankment side slope and used for discharging accumulated water in the boundary range of the road, wherein the accumulated water in the road range usually flows into the side ditch through the embankment side slope. In the prior art, in order to prevent the slope from being damaged by scouring, rapid troughs are usually built on the slope at intervals, and the water in the road area is collected and discharged in a centralized manner. In the road engineering provided with the central dividing strip, in order to discharge the accumulated water of the central dividing strip, an infiltration ditch is usually arranged at the bottom of the central dividing strip, and a transverse drainage pipe is arranged at intervals for discharging the water collected by the infiltration ditch. The prefabricated assembled rapid trough has the characteristics of attractive appearance, convenience in construction and the like, and is more and more applied to highway engineering in recent years.
However, the inventor finds that in the highway engineering adopting the prefabricated assembled torrent tank, if the outlet of the transverse drain pipe is arranged at the torrent tank, accumulated water in the central separation zone cannot be drained due to the shielding of the precast block; if the transverse drain pipe is arranged on a common soil slope, the slope is scoured and damaged.
SUMMERY OF THE UTILITY MODEL
The problem of the ponding of zonation in can't discharging through prefabricated section rapid trough in the highway engineering that adopts the prefabricated section rapid trough is solved.
In one or more embodiments of the present disclosure, a highway rapid trough precast block is provided, which sets up a rapid trough on the side slopes of both sides of the road surface, and sets up an infiltration ditch at the bottom of the central separation strip, accumulated water in the infiltration ditch flows into the horizontal drainage pipe, the horizontal drainage pipe outlet is located on the rapid trough, the rapid trough is composed of an opening precast block and a common precast block, the common precast block is a groove structure with two convex sides and a concave middle part, the opening precast block is a middle open-ended precast block, and the opening of the opening precast block corresponds to the horizontal drainage pipe outlet.
One of the above technical solutions has the following advantages or beneficial effects:
1) in the prior art, the accumulated water in the central separation zone is generally discharged through the transverse drainage pipe, but in the highway using the precast block torrent tank, the accumulated water is usually directly discharged onto the side slope, so that the side slope is scoured and damaged. The reasonable discharge of accumulated water in the central road separation zone is realized by matching the seepage ditch with the transverse drainage pipe and the rapid trough precast block.
2) In the prior art, a cast-in-place groove body is reserved at the position, where the precast block covers the outlet of the drain pipe, to prevent the side slope from being washed away, but the side slope is not attractive and the construction process is complex. And this disclosure uses the prefabricated section, and the construction is simple when comparatively pleasing to the eye.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this disclosure, illustrate embodiments of the disclosure and, together with the description, serve to explain the disclosure and not to limit the disclosure.
FIG. 1 is a schematic diagram of a rapid trough preform block according to example 1.
Fig. 2 is a sectional view of a drainage structure for roads according to embodiment 1.
Fig. 3 is a top view of the drainage structure of the road according to embodiment 1.
Wherein, 1, longitudinal infiltration is conducted; 2. a transverse drain pipe; 3. opening the prefabricated block; 4. a common precast block, 5, opening the precast block; 6. a central separator; 7. a road surface.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments of the present invention without making any creative effort, shall fall within the protection scope of the present invention.
The problem that accumulated water in a central separation zone cannot be discharged through the precast block torrent tank in highway engineering adopting the precast block torrent tank is solved.
In one or more embodiments of the present disclosure, a highway rapid trough precast block is provided, which sets up a rapid trough on the side slopes of both sides of the road surface, and sets up an infiltration ditch at the bottom of the central separation strip, accumulated water in the infiltration ditch flows into the horizontal drainage pipe, the horizontal drainage pipe outlet is located on the rapid trough, the rapid trough is composed of an opening precast block and a common precast block, the common precast block is a groove structure with two convex sides and a concave middle part, the opening precast block is a middle open-ended precast block, and the opening of the opening precast block corresponds to the horizontal drainage pipe outlet.
Furthermore, the road surface is in a cross section form with a high middle part and low two sides. This cross section form is the common cross section form on highway road surface, and this structure itself is favorable to the drainage on road surface, and surface gathered water flows to the relatively low road surface both sides of elevation easily promptly, and then flows to the rapid trough, realizes the drainage.
Further, the prefabricated section rapid trough sets up on road surface both sides side slope.
Further, the rapid trough is composed of prefabricated blocks. The rapid trough prefabricated section is for cast in situ labour saving and time saving, only need pour required prefabricated section in advance in the mould, with prefabricated section transportation to job site, the installation can.
Still further, the rapid trough groove body comprises opening prefabricated section and ordinary prefabricated section, and ordinary prefabricated section is the recess form, and there is the opening for ordinary prefabricated section groove body bottom in the opening prefabricated section, opening prefabricated section opening corresponds with horizontal drain pipe export.
Furthermore, the common precast block and the opening precast block can be manufactured by a die casting method in the prior art.
Furthermore, the opening precast block is positioned in the middle of the rapid trough. Corresponding to the transverse drainage pipe, does not affect the water collection at the upper part of the rapid trough and the drainage at the lower part.
Furthermore, the opening of the precast block is slightly larger than the transverse drain pipe, so that the installation is convenient, the precast block opening and the transverse drain pipe are plugged by adopting plugging materials such as cement mortar and the like, and the precast block opening and the transverse drain pipe are relatively sealed, so that accumulated water in the transverse drain pipe is conveniently discharged outside, and the accumulated water is prevented from permeating into the side slope.
Further, the road surface edge sets up the curb, the curb sets up loudspeaker form opening with rapid trough junction and is convenient for concentrate the collection road surface catchment.
Further, the infiltration ditch is a longitudinal infiltration ditch. Used for collecting middle zone accumulated water.
Furthermore, the infiltration ditch is communicated with the transverse drainage pipe to form a whole set of drainage system.
Furthermore, the transverse drainage pipe connecting the longitudinal seepage ditch of the central separation belt and the torrent tank has a certain transverse gradient. The accumulated water can flow from high to low position.
In the highway engineering adopting the precast block torrent tank, the length of the precast block is determined according to the convenience of manual carrying and installation, and is generally about 50 cm. Because the size of the rapid trough precast block is a fixed value, but the length of the side slope is not a fixed value, the cutting of the precast block cannot be avoided in the installation process of the rapid trough precast block. If the rapid trough precast block with the opening is adopted, the opening position of the precast block with the opening needs to correspond to the outlet of the transverse drain pipe, and the upper side and the lower side of the precast block need to be provided with the common precast block without the opening, so that the upper side and the lower side of the rapid trough can be respectively cut in the installation process of the rapid trough. Because the vertical distance between the outlet of the transverse drain pipe and the top surface of the roadbed is a fixed value, the length of the side slope at the upper part of the outlet of the transverse drain pipe is also a fixed value, the size of the prefabricated block of the rapid trough is determined according to the fixed value, so that the cutting of the prefabricated block of the rapid trough at the upper part of the prefabricated block with the opening can be avoided, and the cutting work of each rapid trough can be reduced.
Example 1
The embodiment provides a prefabricated structure of a highway rapid trough, which comprises a road surface 7, wherein rapid troughs are arranged on slopes on two sides of the road surface 7, as shown in fig. 2. The inner side of the pavement is provided with a central dividing strip 6, the bottom of the central dividing strip 6 is provided with a longitudinal infiltration ditch 1, the longitudinal infiltration ditch 1 is connected with a transverse drainage pipe 2, and the outlet of the transverse drainage pipe 2 is positioned on a rapid trough.
In order to discharge the accumulated water at the bottom of the central separator, in the prior art, the bottom of the central separator 6 is provided with a longitudinal infiltration ditch 1 which is connected with a transverse drain pipe 2, and the longitudinal infiltration ditch and the transverse drain pipe are matched to discharge the accumulated water in the central separator 6 to a rapid trough positioned on a road slope, so that the problem of the accumulated water in the central separator 6 is solved. However, in the road engineering adopting the precast block torrent tank, the accumulated water of the transverse drain pipe 2 cannot be discharged through the torrent tank due to the shielding of the precast block.
The road surface 7 is of a structure with a high middle part and low two sides. The central separator 6 is located at the highest point of the road surface. The transverse drainage pipes are obliquely arranged from the central separation belt to two sides of the road surface. The accumulated water can flow from high to low position.
The rapid trough is composed of precast blocks. The precast block is prepared in advance, and only needs to be installed on site in the actual construction process, so that the requirement of rapid installation is met, and a cast-in-place rapid trough is avoided.
As shown in fig. 1, the rapid trough is composed of an opening precast block 3 and a common precast block 4, the opening precast block 3 is a precast block with an opening in the middle, and a precast block opening 5 of the opening precast block 3 corresponds to an outlet of the transverse drain pipe 2. If the rapid trough does not have the opening, then 2 exports of horizontal drain pipe can be blocked by the rapid trough, and unable drainage realizes that horizontal drain pipe 2 smoothly drains at prefabricated section upper shed.
As shown in fig. 3, the two side edges of the road surface 7 are provided with kerbs, and the kerbs extend from the side edges of the road surface to the inlet of the rapid trough. The collection and the discharge of the accumulated water on the road surface 7 are convenient. The intersection of the kerbstone and the rapid trough is of a horn mouth structure. Further improving the effect of collecting and discharging the accumulated water at the 7-position of the road surface.
The above disclosure is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the scope of the present invention, therefore, the present invention is not limited by the appended claims.

Claims (9)

1. The utility model provides a highway rapid trough prefabricated construction, its characterized in that sets up the rapid trough on the side slope of road surface both sides, sets up the infiltration ditch bottom the median, during ponding flowed in the transverse drainage pipe in the infiltration ditch, the transverse drainage pipe export is located the rapid trough, the rapid trough comprises opening prefabricated section and ordinary prefabricated section, ordinary prefabricated section is both sides arch, middle sunken groove structure, and the opening prefabricated section is middle open-ended prefabricated section, opening prefabricated section opening corresponds with the transverse drainage pipe export.
2. The prefabricated structure of a highway chute as set forth in claim 1 wherein said roadway is in the form of a cross section with a high middle and low sides.
3. The precast structure of highway chutes of claim 2 wherein the precast block chutes are provided on slopes on both sides of the road surface.
4. The highway chute preform structure of claim 1, wherein the opening preform block is located in the middle of the chute.
5. The prefabricated structure of a highway rapid trough according to claim 1, wherein the opening of the prefabricated block is slightly larger than the transverse drainage pipe.
6. The prefabricated structure for a road chute of claim 1 wherein said road surface has kerbs at both side edges thereof, said kerbs extending from the side edges of the road surface up to the inlet of the chute.
7. The prefabricated structure of a highway rapid trough according to claim 1, wherein the junction of the curbstone and the rapid trough is in a bell mouth-shaped structure.
8. The prefabricated structure for a road rapid trough according to claim 1, wherein the seepage groove is a longitudinal seepage groove.
9. The prefabricated structure of a highway chute of claim 1 wherein the transverse drainage pipe connecting the longitudinal seepage channel of the central divider to the chute has a transverse slope.
CN202122227376.4U 2021-09-14 2021-09-14 Highway rapid trough prefabricated construction Active CN216765468U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122227376.4U CN216765468U (en) 2021-09-14 2021-09-14 Highway rapid trough prefabricated construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122227376.4U CN216765468U (en) 2021-09-14 2021-09-14 Highway rapid trough prefabricated construction

Publications (1)

Publication Number Publication Date
CN216765468U true CN216765468U (en) 2022-06-17

Family

ID=81953917

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122227376.4U Active CN216765468U (en) 2021-09-14 2021-09-14 Highway rapid trough prefabricated construction

Country Status (1)

Country Link
CN (1) CN216765468U (en)

Similar Documents

Publication Publication Date Title
CN100422443C (en) Kerbstone with drainage hole
CN103233433A (en) Urban road pavement rainwater collection and utilization system
CN109024146A (en) Expressway slope discharge structure
CN217053410U (en) Water seepage and drainage structure for green belt at edge of urban road
CN109797839A (en) A kind of efficient pollution cutting device of urban road inlet for stom water and cut dirty operating method
CN106087648B (en) A kind of special Quick drainage of urban road and irrigation system
CN212956842U (en) Drainage system of highway median
CN109024673A (en) A kind of sponge road surface-underground pipe gallery system and construction technology
CN216765468U (en) Highway rapid trough prefabricated construction
CN210395028U (en) Road shoulder drainage water-collecting device
CN217439127U (en) A sponge type side ditch structure for urban road
CN210507029U (en) Road drainage structure
JP2002061105A (en) Boundary water introducing groove block and waste water treatment structure in road
CN212224121U (en) Road structure with surface type water collecting function
CN114922277A (en) A sponge type side ditch structure for urban road
CN105839771B (en) One kind is dammed type rain perforaled strainer
CN210049366U (en) Road rainwater leading opening prefabricated concrete and road rainwater leading opening prefabricated concrete unit body
CN211522695U (en) Multifunctional sponge road structure
CN208884688U (en) A kind of highway water-break slot
CN110005043B (en) Prefabricated concrete for road rainwater guide opening and preparation method and application thereof
CN107060054A (en) A kind of functional rain well for adapting to rainfall
CN216765471U (en) Highway superelevation section rapid trough prefabricated construction
CN217869796U (en) Curb structure beside road
CN213508766U (en) Water drainage structure for road of cross-sluiceway road section
CN216006487U (en) Multistage bridge and culvert drainage device

Legal Events