CN216740654U - Outer scaffold is wall spare even - Google Patents

Outer scaffold is wall spare even Download PDF

Info

Publication number
CN216740654U
CN216740654U CN202123157926.6U CN202123157926U CN216740654U CN 216740654 U CN216740654 U CN 216740654U CN 202123157926 U CN202123157926 U CN 202123157926U CN 216740654 U CN216740654 U CN 216740654U
Authority
CN
China
Prior art keywords
connecting piece
external
section
steel pipe
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123157926.6U
Other languages
Chinese (zh)
Inventor
高文峰
邹向向
郑建平
邓伟
卢伟荣
程羽
万泽民
刘俊
余亚翔
葛荣斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongda Construction Co ltd
Original Assignee
Zhongda Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongda Construction Co ltd filed Critical Zhongda Construction Co ltd
Priority to CN202123157926.6U priority Critical patent/CN216740654U/en
Application granted granted Critical
Publication of CN216740654U publication Critical patent/CN216740654U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model discloses an outer scaffold frame is wall spare even belongs to the construction equipment field. The outer scaffold wall connecting piece is embedded in a main concrete structure through a fixing rod with a bending section, and a straight rod section with an external thread section is used for connecting a connecting piece of a welded steel pipe. This outer scaffold frame is wall spare even when using, can cup joint the steel-pipe fitting on the dead lever through connecting piece and internal thread spare, then normally is connected the steel-pipe fitting through the fastener with outer scaffold frame, when the outrigger is demolishd, only needs loosen internal thread spare, with the unnecessary part of dead lever cut off alright, and connecting piece, internal thread spare and the equal reuse of steel-pipe fitting. Utilize this kind of external scaffolding to link wall spare, can solve secondary structure construction inconvenience, need reserve entrance to a cave secondary shutoff and have difficult problems such as infiltration hidden danger.

Description

Outer scaffold is wall spare even
Technical Field
The utility model belongs to the technical field of building construction equipment technique and specifically relates to outer scaffold draws node to be convenient for demolish and the drawknot is rigid connection's device among the building construction process.
Background
At present, the external scaffold wall connecting piece for building engineering construction mainly adopts the forms of embedding common steel pipes on a floor beam, connecting the embedded steel pipes with an external scaffold through fasteners and the like. However, in the traditional method, when the secondary structure is constructed, a hole needs to be reserved in the wall, unnecessary trouble is caused to construction, the wall is easy to remove, potential safety hazards exist, and the hidden water seepage hazards still exist for the beam after the embedded steel pipe is cut off. In the prior art, the galvanized flat steel is embedded in the main structure of the building, and the galvanized flat steel is connected with the wall connecting rod through the double-cross fastener. But this kind of mode is flexonics, can satisfy outer scaffold tensile effect, can't satisfy the resistance to compression, may lead to the unstable scheduling problem of support body.
Disclosure of Invention
The utility model discloses a solve prior art's defect, reduce later stage quality hidden danger when increasing scaffold frame overall safety nature, provide an outer scaffold frame even wall spare, it is inconvenient effectively to solve secondary structure construction, needs to reserve a hole secondary shutoff and has a difficult problem such as infiltration hidden danger.
The utility model discloses realize that the technical scheme that above-mentioned purpose adopted as follows:
an external scaffold wall connecting piece comprises a fixed rod, a connecting piece, an internal thread piece and a steel pipe piece; the fixed rod is formed by connecting a vertical straight rod section and a bending section, and an external thread section is arranged on the straight rod section; the connecting piece is provided with a through hole and a welding area for welding the steel pipe; the connecting piece is sleeved on the external thread section of the straight rod section through the through hole; the internal thread piece is screwed into the external thread section and is tightly attached to the connecting piece sleeved on the external thread section to form unilateral limit on the connecting piece; one end of the steel pipe fitting is welded and fixed on the welding area of the connecting piece, and the other end of the steel pipe fitting extends in the direction far away from the fixing rod and is used for connecting and fixing a main node of an external scaffold.
Preferably, the fixing rod is an L-shaped screw.
Preferably, the connecting member is a steel plate having a through hole.
Preferably, the aperture of the through hole is slightly larger than the diameter of the straight rod section of the fixing rod, so that the connecting piece can only slide along the axial direction of the straight rod section.
Preferably, the female screw member is a nut.
Furthermore, the size of the nut is larger than that of the through hole on the connecting piece.
Preferably, the length of the steel pipe fitting is greater than the span between the external scaffold wall connecting piece and the external scaffold main node.
Preferably, the steel pipe is horizontally erected.
The utility model provides an outer scaffold frame is wall spare even, this outer scaffold frame is wall spare even through the dead lever that has the bending segment is pre-buried in main part concrete structure, and the straight pole section that has the external screw thread section then is used for connecting the connecting piece of welding steel pipe spare. This outer scaffold frame is wall spare even when using, can cup joint the steel-pipe fitting on the dead lever through connecting piece and internal thread spare, then normally is connected the steel-pipe fitting through the fastener with outer scaffold frame, when the outrigger is demolishd, only needs loosen internal thread spare, with the unnecessary part of dead lever cut off alright, and connecting piece, internal thread spare and the equal reuse of steel-pipe fitting. The outer scaffold wall connecting piece can solve the problems that secondary structure construction is inconvenient, secondary plugging of a hole needs to be reserved, water seepage hidden danger exists and the like, and the drawknot is in rigid connection, so that the potential safety hazard of construction can be avoided.
Drawings
Fig. 1 is a schematic view of the device of the external scaffolding wall connecting piece of the present invention.
Fig. 2 is an enlarged view of the connection position in fig. 1.
Fig. 3 is an organization form of the construction process of the wall connecting piece of the external scaffold in the utility model.
Reference symbol correspondence relationship: fixing rod 1, connecting piece 2, internal thread piece 3 and steel pipe piece 4
Detailed Description
The invention will be further elucidated and described with reference to the drawings and embodiments. The utility model discloses in the technical characteristics of each embodiment under the prerequisite that does not conflict each other, all can carry out corresponding combination.
In a preferred embodiment of the present invention, there is provided an external scaffolding wall connecting member for forming a rigid connection structure between a main structure and an external scaffolding, which ensures the safety of erection and construction of the external scaffolding. The main structure used for embedding the fixing piece can be a wall, a column, a beam or other main structures, and is determined according to actual needs.
As shown in fig. 1, the main structure of the external scaffolding wall connecting piece comprises four parts, namely a fixing rod 1, a connecting piece 2, an internal thread piece 3 and a steel pipe 4. The specific structure and connection form of each component will be described in detail below.
The function of dead lever 1 is pre-buried in the major structure thing, provides the drawknot position of outer scaffold frame outward. The fixed rod 1 is formed by connecting a vertical straight rod section and a bending section, and an external thread section is arranged on the straight rod section. It should be noted that, the straight rod section and the bent section may be either integrated or welded in sections, which is not limited in this respect. The effect of steel-pipe fitting 4 is used for carrying out the lock joint with the main node of outer scaffold frame fixedly, and the effect of connecting piece 2 is detachable connection steel-pipe fitting 4 and dead lever 1, wherein can realize fixing and dismantling in order to guarantee steel-pipe fitting 4, still need introduce interior screw thread spare 3 and carry on spacingly.
As shown in fig. 2, the connector 2 is provided with a through hole and a blank region as a welding region for welding the end of the steel pipe 4. The connecting piece 2 is sleeved on the external thread section of the straight rod section through a through hole arranged at the upper part. The internal thread piece 3 can be screwed into the external thread section and is closely attached to the connecting piece 2 sleeved on the same external thread section to form unilateral limit to the connecting piece 2. In order to ensure the limiting effect, the size of the internal thread member 3 should be larger than the size of the through hole formed on the connecting member 2. In addition, the other surface of the connector 2 needs to be supported to form another limit position on the main structure, except for the surface welded to the steel pipe 4. Since one end of the steel pipe 4 is welded and fixed to the welding region of the connector 2, the steel pipe 4 can be rigidly fixed to the main structure under the double-side restriction of the female screw 3 and the main structure to the connector 2. The other end of the steel pipe fitting 4 extends and overhangs in the direction far away from the fixing rod 1 and is used for connecting and fixing a main node of an external scaffold. When in actual use, can be in advance steel pipe fitting 4 and connecting piece 2 through welding be even as an organic whole, directly overlap connecting piece 2 on pre-buried dead lever 1 during the installation, rethread internal thread spare 3 with connecting piece 2 compress tightly on dead lever 1 can.
The concrete size parameters and the materials of the fixing rod 1, the connecting piece 2, the internal thread piece 3 and the steel pipe piece 4 in each outer scaffold wall connecting piece can be selected according to actual needs. In this embodiment, the fixing rod 1 is an L-shaped screw, the connecting member 2 is a steel plate with an opening, and the internal thread member 3 is a nut with an internal thread. The L-shaped screw, the steel plate and the nut all belong to common standard parts in construction, and special processing is not needed, so that the acquisition and processing cost of raw materials can be reduced. In addition, the thread parameters of the external thread section on the straight rod section of the L-shaped screw need to be matched with the nut so that the two can form thread matching. The width of the steel plate should be larger than the diameter of the welded steel pipe 4, and the length should be enough to allow a space for opening a through hole. The nut is screwed on the external thread section of the L-shaped screw and tightly presses the back of the steel plate, and the size of the nut is larger than the through hole formed in the waist of the steel plate. Through the rotation of the nut on the external thread section, the distance between the bending sections of the steel plate and the L-shaped screw rod can be adjusted, and then the steel pipe fitting 4 is fixed on the connecting piece 3. However, the L-shaped screw, the steel plate and the nut are only one implementation form of the middle fixing rod 1, the connecting member 2 and the internal thread member 3, and other alternatives can be adopted in other embodiments instead of the middle fixing rod, as long as similar functions can be realized.
In addition, in the connecting element 2, the aperture of the through hole should preferably be slightly larger than the diameter of the straight rod section of the fixing rod 1, that is, the connecting element 2 and the fixing rod 1 form a clearance fit, so that the connecting element 2 can only slide along the axial direction of the straight rod section and can not move along the radial direction, thereby improving the stability of connection and fixation between the two.
The length of the steel pipe 4 is determined according to the actual distance between the scaffold and the main structure, and since the steel pipe 4 is generally horizontally erected, the length of the steel pipe 4 should be longer than the span between the external scaffold wall coupling and the external scaffold main node. Of course, in practical applications, the steel pipe 4 may not be horizontal, and may also have a certain inclination angle, which is not limited.
This outer scaffold wall connecting piece is in the assembly use, and specific use method is as follows:
one end of the steel pipe 4 is placed at the lower part of the steel plate of the connecting piece 2 and is welded firmly by adopting a welding mode. Then embedding the bent section of the L-shaped screw into the main structure and connecting and fixing the bent section with the built-in steel bar, wherein the straight rod section is positioned outside the pouring area of the main structure, and the external thread section on the straight rod section needs to be ensured to protrude out of a side vertical face of the main structure, on which an external scaffold needs to be erected; and then after the concrete is cured, starting to set up an external scaffold, for each position of the external scaffold needing to be tied, penetrating the through hole of the connecting piece 2 into the external thread section of the fixing piece 1 and attaching the external thread section to the side surface of the main structure, and then screwing the nut so that pressing force is applied between the connecting piece 2 and the main structure, and the connecting piece and the main structure are matched with each other to be clamped and fixed on the fixing piece 1 under the limit of the steel plate. The other end of the steel pipe fitting 4 extends to the main node of the outer scaffold and is connected with the main node of the outer scaffold through a fastener.
As shown in fig. 3, in an actual construction organization, material is first purchased and entered; then, draw the node position to the first even wall, get a set of even wall spare device and install, draw the node position to every other even wall in proper order and get a set of even wall spare device and install, wait at last when the construction finishes dismantling the outer scaffolding, unscrew the nut on each L type screw rod, and then lift off steel pipe fitting 4 and connecting piece 2 and be used for the used repeatedly when the construction next time. After the construction is completed and the connector 2, the nut, and the steel pipe 4 are removed, the portion of the L-shaped screw, from which the main structure is exposed, is cut off, and then other necessary constructions can be continued on the main structure.
The above-mentioned embodiments are merely a preferred embodiment of the present invention, but it is not intended to limit the present invention. Various changes and modifications can be made by one of ordinary skill in the pertinent art without departing from the spirit and scope of the present invention. Therefore, all the technical schemes obtained by adopting the mode of equivalent replacement or equivalent transformation fall within the protection scope of the utility model.

Claims (8)

1. An external scaffold wall connecting piece is characterized by comprising a fixed rod (1), a connecting piece (2), an internal thread piece (3) and a steel pipe piece (4); the fixing rod (1) is formed by connecting a vertical straight rod section and a bending section, and an external thread section is arranged on the straight rod section; the connecting piece (2) is provided with a through hole and a welding area for welding the steel pipe fitting (4); the connecting piece (2) is sleeved on the external thread section of the straight rod section through the through hole; the internal thread piece (3) is screwed into the external thread section and is tightly attached to the connecting piece (2) sleeved on the external thread section to form unilateral limit to the connecting piece (2); one end of the steel pipe fitting (4) is welded and fixed on the welding area of the connecting piece (2), and the other end of the steel pipe fitting extends in the direction far away from the fixing rod (1) and is used for connecting and fixing a main node of an external scaffold.
2. The external scaffolding wall element according to claim 1, characterized in that the fixing rod (1) is an L-shaped screw.
3. The external scaffolding wall element according to claim 1, characterized in that the connecting element (2) is a steel plate with a through hole.
4. External scaffolding wall element according to claim 1, characterized in that the aperture of the through hole is slightly larger than the diameter of the straight pole section of the fixation pole (1) so that the connection element (2) can only slide axially along the straight pole section.
5. External scaffolding wall element according to claim 1, characterized in that the internally threaded element (3) is a nut.
6. An external scaffolding wall element according to claim 5, characterized in that the size of the nut is larger than the size of the through hole in the connector (2).
7. External scaffolding wall element according to claim 1, characterized in that the length of the steel pipe (4) should be greater than the span between the external scaffolding wall element and the external scaffolding master node.
8. External scaffolding wall element according to claim 1, characterized in that the steel pipe (4) is kept horizontally erected.
CN202123157926.6U 2021-12-14 2021-12-14 Outer scaffold is wall spare even Active CN216740654U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123157926.6U CN216740654U (en) 2021-12-14 2021-12-14 Outer scaffold is wall spare even

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123157926.6U CN216740654U (en) 2021-12-14 2021-12-14 Outer scaffold is wall spare even

Publications (1)

Publication Number Publication Date
CN216740654U true CN216740654U (en) 2022-06-14

Family

ID=81935547

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123157926.6U Active CN216740654U (en) 2021-12-14 2021-12-14 Outer scaffold is wall spare even

Country Status (1)

Country Link
CN (1) CN216740654U (en)

Similar Documents

Publication Publication Date Title
CN101892738B (en) Embedded scaffold connecting tube and construction method thereof
CN111287386B (en) Mechanical connection device and steel bar connection method for steel bar part commercialized construction
CN201254830Y (en) Convenient wall joint
CN204850414U (en) Shaped steel of encorbelmenting draws wire rope instrument formula anchor to one side
CN105569363B (en) A kind of swivel joint attachment means and application method for prefabricated components diagonal brace
CN205955173U (en) Modular link wall spare subassembly
CN209369051U (en) A kind of pre-embedded device in concrete
CN110863644A (en) Novel turnover tool type beam side connecting wall piece fixing device and method
CN216740654U (en) Outer scaffold is wall spare even
CN212224604U (en) Wall connecting assembly for connecting outer wall scaffold and wall structure
CN203795825U (en) Scaffold and wall connector and scaffold and wall connecting structure
CN210342642U (en) Scaffold wall connecting piece and scaffold
CN207073275U (en) Builder's jack fixture and builder's jack
CN114075871A (en) Triangular overhanging support base for slip form
CN210032563U (en) Outer frame wall connecting piece
CN211173042U (en) Scaffold wall connecting piece
CN209990123U (en) Adjustable wall connecting piece device
CN114182951A (en) External scaffold wall connecting piece tie method used in construction
CN112609982A (en) Method for manufacturing wall with heat-insulation plate by adopting energy-saving bolt
CN218176163U (en) Pre-buried formula connecting piece
CN219569677U (en) External-adhesion steel reinforced structure of shear wall
CN216766729U (en) Pre-buried double-bolt head of building engineering is wall spare even
CN217461418U (en) A link wall fixing device for construction
CN218758664U (en) Wall connecting assembly
CN217205271U (en) Outer scaffold frame is easily dismantled and is linked wall spare structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant