CN216613942U - Lifting support for outer wall full-penetration construction - Google Patents

Lifting support for outer wall full-penetration construction Download PDF

Info

Publication number
CN216613942U
CN216613942U CN202123041162.4U CN202123041162U CN216613942U CN 216613942 U CN216613942 U CN 216613942U CN 202123041162 U CN202123041162 U CN 202123041162U CN 216613942 U CN216613942 U CN 216613942U
Authority
CN
China
Prior art keywords
lifting
rod
assembly
fixing base
bottom plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123041162.4U
Other languages
Chinese (zh)
Inventor
吴文锋
吴国雄
刘亚东
何国生
张东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuli Construction Group Co Ltd
Original Assignee
Fuli Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuli Construction Group Co Ltd filed Critical Fuli Construction Group Co Ltd
Priority to CN202123041162.4U priority Critical patent/CN216613942U/en
Application granted granted Critical
Publication of CN216613942U publication Critical patent/CN216613942U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to the technical field of outer wall full-penetration construction supports, and discloses a lifting support for outer wall full-penetration construction, which comprises a bottom plate, a lifting assembly and a driving assembly, wherein the lifting assembly and the driving assembly are arranged on the bottom plate; the lifting component comprises a vertical rod, a lifting rod, a first fixing base, a hook, a fixing rod, a second fixing base and a pulley, the vertical rod is installed on the bottom plate, a sliding groove is formed in the side wall of the vertical rod, the lifting rod is arranged inside the sliding groove, a supporting component is installed on the side wall of the lifting rod, the first fixing base is installed at the center position of the lifting rod, the hook is installed on the first fixing base, a driving component is connected with the hook, the fixing rod is installed at the top of the vertical rod, the second fixing base is installed at the center position of the fixing rod, and the pulley is installed on the second fixing base. Through lifting unit and drive assembly's setting, can go up and down according to the work demand.

Description

Lifting support for outer wall full-penetration construction
Technical Field
The utility model relates to the technical field of supports for outer wall full-penetration construction, in particular to a lifting support for outer wall full-penetration construction.
Background
The outer wall is defined by a judgment method, A-B is taken as a wall, if the A-B wall line can cut the related building enclosure, the wall is taken as an inner wall, otherwise, the wall is taken as an outer wall. From the architectural perspective, the boundary member for enclosing a building to form an indoor space and an outdoor space is called an outer wall. It has the functions of: bear certain load, shelter from wind and rain, preserve heat and insulate heat, prevent noise, prevent fire and be safe, etc.
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, and also can be a process of changing various lines on a design drawing into a real object at a specified place, and comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like, wherein the construction operation place is called a building construction site or a construction site, and a support is required in the building construction process.
The support is used in outer wall full-penetration construction in the existing market needs further promotion in the technology, and the height of the support is used in outer wall full-penetration construction in the existing market can not be adjusted according to own requirements, so that the work efficiency is greatly influenced.
SUMMERY OF THE UTILITY MODEL
The utility model provides a lifting support for outer wall full-penetration construction, which solves the problem that the height of the support for outer wall full-penetration construction in the process of the prior art can not be adjusted according to the requirement, and the working efficiency is greatly influenced.
In order to solve the problems, the utility model adopts the following technical scheme: a lifting support for full-penetration construction of an outer wall comprises a bottom plate, a lifting assembly and a driving assembly, wherein the lifting assembly and the driving assembly are arranged on the bottom plate, the lifting assembly is connected with the driving assembly, and a supporting assembly is arranged on the lifting assembly;
the lifting assembly comprises a vertical rod, a lifting rod, a first fixing base, a hook, a fixing rod, a second fixing base and a pulley, the vertical rod is installed on the bottom plate, a sliding groove is formed in the side wall of the vertical rod, the lifting rod is arranged inside the sliding groove, the side wall of the lifting rod is installed on the supporting assembly, the central position of the lifting rod is installed on the first fixing base, the hook is installed on the first fixing base and connected with the driving assembly, the top of the vertical rod is installed on the fixing rod, the central position of the fixing rod is installed on the second fixing base, and the pulley is installed on the second fixing base.
Preferably, the driving assembly comprises a supporting block, a motor, a wire collecting wheel, a third fixing base and a rope, the supporting block is installed on the bottom plate, the motor is installed on the supporting block, the output end of the motor is connected with the wire collecting wheel, the wire collecting wheel is installed on the third fixing base, the third fixing base is installed on the bottom plate, one end of the rope is connected with the wire collecting wheel, and the other end of the rope surrounds the second fixing base and is connected with the hook.
Preferably, the support assembly comprises a support plate and a guard rail, the support plate is mounted on the side wall of the lifting rod, and the guard rail is mounted on the support plate.
Preferably, the size of the sliding groove is matched with the size of the section of the lifting rod.
Preferably, the number of the lifting assemblies is two, and the two groups of the lifting assemblies are connected through the supporting plate.
The rope collecting device has the advantages that the rope is convenient to collect through the arrangement of the motor and the rope collecting wheel, the position of the rope collecting wheel is fixed through the arrangement of the third fixing base, the lifting rod can be driven to lift in the sliding groove through the arrangement of the rope, the hook can be conveniently pulled through the rope through the arrangement of the second fixing base and the pulley, workers can be conveniently driven to lift through the arrangement of the lifting rod, the first fixing base, the hook and the supporting plate, the position of the motor is fixed through the arrangement of the supporting block, and certain protection is provided for the workers through the arrangement of the protective guard.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a schematic view of a lifting bracket for full penetration construction of an external wall according to the present invention;
fig. 2 is a schematic side view of a lifting bracket for full penetration construction of an external wall.
The reference numbers in the figures illustrate: 1. a base plate; 2. a vertical rod; 201. a chute; 3. a lifting rod; 4. a first stationary base; 5. a hook; 6. fixing the rod; 7. a second stationary base; 8. a pulley; 9. a support block; 10. a motor; 11. a wire collecting wheel; 12. a third stationary base; 13. a rope; 14. a support plate; 15. a guard rail.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-2, the lifting support for the full-penetration construction of the outer wall comprises a bottom plate 1, a lifting assembly and a driving assembly, wherein the lifting assembly and the driving assembly are arranged on the bottom plate 1, the lifting assembly is connected with the driving assembly, and a supporting assembly is arranged on the lifting assembly;
lifting unit includes montant 2, lifter 3, first unable adjustment base 4, hook 5, dead lever 6, second unable adjustment base 7 and pulley 8, install montant 2 on the bottom plate 1, spout 201 has been seted up to montant 2's lateral wall, spout 201's inside sets up lifter 3, lifter 3's lateral wall installation supporting component, lifter 3's the first unable adjustment base 4 of central point position installation, install hook 5 on the first unable adjustment base 4, driving assembly is connected to hook 5, montant 2's top installation dead lever 6, the central point of dead lever 6 puts installation second unable adjustment base 7, install pulley 8 on the second unable adjustment base 7.
Wherein, drive assembly includes supporting shoe 9, motor 10, line concentration wheel 11, third unable adjustment base 12 and rope 13, install supporting shoe 9 on the bottom plate 1, install motor 10 on the supporting shoe 9, motor 10's output and line concentration wheel 11 are connected, line concentration wheel 11 is installed on third unable adjustment base 12, third unable adjustment base 12 is installed on bottom plate 1, the one end and the line concentration wheel 11 of rope 13 are connected, the other end of rope 13 centers on second unable adjustment base 7 and is connected with hook 5, its effect is convenient for drive lifter 3 and goes up and down.
The support assembly comprises a support plate 14 and a guard rail 15, the support plate 14 is installed on the side wall of the lifting rod 3, and the guard rail 15 is installed on the support plate 14 and is used for supporting workers conveniently.
Wherein, the size of spout 201 and the cross-sectional dimension phase-match of lifter 3, its effect is that make lifter 3 go up and down more stable.
Wherein, lifting unit's quantity is two sets of, and two sets of lifting unit pass through backup pad 14 and connect, and its effect is that the better drive backup pad 14 of being convenient for rises.
Working principle;
the staff stands in backup pad 14, starter motor 10, and motor 10 output drives line concentrator 11 and rotates, and line concentrator 11 rotates and twines rope 13 and collects, and when 13 stimulations of rope, drive pulley 8 and rotate, and rope 13 drives hook 5 and upwards rises simultaneously, and hook 5 drives first unable adjustment base 4, and first unable adjustment base 4 drives lifter 3 and rises in the inside of spout 201, and lifter 3 drives backup pad 14 and rises.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the utility model, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (5)

1. The lifting support for the full-penetration construction of the outer wall is characterized by comprising a bottom plate (1), a lifting assembly and a driving assembly, wherein the lifting assembly and the driving assembly are arranged on the bottom plate (1), the lifting assembly is connected with the driving assembly, and a supporting assembly is arranged on the lifting assembly;
the lifting component comprises a vertical rod (2), a lifting rod (3), a first fixed base (4), a hook (5), a fixed rod (6), a second fixed base (7) and a pulley (8), the bottom plate (1) is provided with the vertical rod (2), the side wall of the vertical rod (2) is provided with a sliding groove (201), the lifting rod (3) is arranged in the sliding groove (201), the supporting component is arranged on the side wall of the lifting rod (3), the first fixed base (4) is arranged at the central position of the lifting rod (3), the first fixing base (4) is provided with the hook (5), the hook (5) is connected with the driving component, the top of the vertical rod (2) is provided with the fixed rod (6), the center of the fixed rod (6) is provided with the second fixed base (7), and the pulley (8) is arranged on the second fixed base (7).
2. The lifting support for the full-penetration construction of the external wall according to claim 1, wherein the driving component comprises a supporting block (9), a motor (10), a line concentration wheel (11), a third fixing base (12) and a rope (13), the supporting block (9) is installed on the bottom plate (1), the motor (10) is installed on the supporting block (9), the output end of the motor (10) is connected with the line concentration wheel (11), the line concentration wheel (11) is installed on the third fixing base (12), the third fixing base (12) is installed on the bottom plate (1), one end of the rope (13) is connected with the line concentration wheel (11), and the other end of the rope (13) surrounds the second fixing base (7) and is connected with the hook (5).
3. The lifting support for the full-penetration construction of the external wall according to claim 1, wherein the supporting assembly comprises a supporting plate (14) and a guard rail (15), the supporting plate (14) is installed on the side wall of the lifting rod (3), and the guard rail (15) is installed on the supporting plate (14).
4. The lifting support for the full-penetration construction of the external wall according to claim 3, wherein the size of the sliding groove (201) is matched with the cross-sectional size of the lifting rod (3).
5. The lifting support for the full-penetration construction of the external wall according to claim 4, wherein the number of the lifting assemblies is two, and the two lifting assemblies are connected through the supporting plate (14).
CN202123041162.4U 2021-12-06 2021-12-06 Lifting support for outer wall full-penetration construction Active CN216613942U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123041162.4U CN216613942U (en) 2021-12-06 2021-12-06 Lifting support for outer wall full-penetration construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123041162.4U CN216613942U (en) 2021-12-06 2021-12-06 Lifting support for outer wall full-penetration construction

Publications (1)

Publication Number Publication Date
CN216613942U true CN216613942U (en) 2022-05-27

Family

ID=81702111

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123041162.4U Active CN216613942U (en) 2021-12-06 2021-12-06 Lifting support for outer wall full-penetration construction

Country Status (1)

Country Link
CN (1) CN216613942U (en)

Similar Documents

Publication Publication Date Title
CN211119728U (en) Operation platform for auxiliary installation of air conditioner external unit
CN210685119U (en) Overhead assembled roof
CN216613942U (en) Lifting support for outer wall full-penetration construction
CN210563676U (en) Signal tower with high-efficiency maintenance and wind-proof stability
CN217233021U (en) A security fence for building engineering construction management
CN201460186U (en) Adhesive lifting scaffold
CN208253801U (en) A kind of air-conditioner outdoor unit displacement structure of house
CN212388834U (en) Pavilion furred ceiling wooden wall structure in gardens
CN213923842U (en) Wallboard lifting device in assembled
CN210289051U (en) Noise reduction type building construction platform
CN210049646U (en) On-spot interim facility solar protection devices
CN221119150U (en) Self-clamping type vertical shaft construction combined operation hanging frame
CN215594393U (en) Integrally assembled movable house
CN216079010U (en) Safety monitoring device for Beidou construction positioning
CN216587964U (en) Unit combined solar iron tower
CN220647518U (en) Camera convenient to it is fixed
CN211345115U (en) Portable municipal administration LED energy-saving lighting system installs testing arrangement
CN220732922U (en) Intelligent building security device
CN114183012B (en) Tower crane foundation shaping enclosure structure
CN220815121U (en) Electric power pylon convenient to overhaul
CN216190897U (en) Building carrying frame with protection function
CN218955798U (en) Environmental protection monitoring instrument bears frame
CN210286562U (en) Building engineering lifting device
CN218507353U (en) Photovoltaic flat-inclined single tracking support and assembly mounting tool
CN215443277U (en) Convenient-to-disassemble and assemble prefabricated house with heat insulation structure for construction site

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant